![Page 1: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/1.jpg)
Twin Ports Interchange Reconstruction Project
Monthly Update MeetingMarch 26, 2018
![Page 2: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/2.jpg)
Project Layout
North
![Page 3: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/3.jpg)
Concept C – Recommended
Signal relocated to an expected location Maintains all
traffic movements Minimizes
bridge structure
![Page 4: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/4.jpg)
US 53 Fill Option
Need for alley opening?No fill between Superior and
Michigan Street Parking Issues?Other areas?
![Page 5: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/5.jpg)
US 53 Bridge Visualization
Preliminary – Subject to Change
![Page 6: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/6.jpg)
US 53 Bridge Visualization
Preliminary – Subject to Change
![Page 7: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/7.jpg)
US 53 Bridge Visualization
Preliminary – Subject to Change
![Page 8: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/8.jpg)
US 53 Bridge Visualization
Preliminary – Subject to Change
![Page 9: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/9.jpg)
US 53 Ramp to 21st Ave
![Page 10: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/10.jpg)
Coffee Creek (Trout Stream) and Tunnel
![Page 11: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/11.jpg)
Project Map – I-535/GarfieldInterchange
Goals Reduced footprint Remove sharp curves Standardize interchange Possible rehab of existing
bridge
Minor work needed on Bridge 69810
![Page 12: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/12.jpg)
Garfield / I-535 Interchange Concept 1
Preliminary – Subject to Change
![Page 13: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/13.jpg)
Garfield / I-535 Interchange Concept 2
Preliminary – Subject to Change
![Page 14: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/14.jpg)
Railroad Street Connection Option 1
![Page 15: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/15.jpg)
Railroad Street Connection at Michigan Street-Option 1
Preliminary –Subject to Change
![Page 16: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/16.jpg)
Rendering of Bend Tec Bridge for Lakeshore Drive in Chicago
![Page 17: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/17.jpg)
Railroad Street Option 2
![Page 18: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/18.jpg)
Railroad Street Option 3
![Page 19: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/19.jpg)
Mesaba Avenue Improvements
Planned for construction in 2018
![Page 20: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/20.jpg)
Mesaba Avenue Ramp Additional Lane
![Page 21: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/21.jpg)
One-Way Pair Option for Temporary Traffic Mitigation
Preliminary
![Page 22: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/22.jpg)
Temporary Mitigation Options
One way pairs Lower Michigan Street EB Superior Street or First Street WB
Railroad Street and Garfield Avenue turn lanes Paving of Railroad Street Truck stopping lanes at rail crossings on Railroad Street Signalizing 27th Avenue West ramps Turn lane on 27th Avenue WestMesaba Avenue ramp – additional lane Others
![Page 23: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/23.jpg)
Tentative Project Schedule
![Page 24: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/24.jpg)
High Level Estimate Range
Project Component Low (millions) High (millions)
TPI Interchange $140 $165
US 53 Bridges $60 $75
Garfield/I-535 Interchange $30 $40
27th Avenue W Bridge $3 $5
Railroad Street Connection $7 $15
TOTAL $240 $300
![Page 25: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/25.jpg)
Next Meeting
Monday, April 30 11:30-12:30 6:00 – 7:00 pm
How can we disseminate information better?What other information can we provide?
![Page 26: Twin Ports Interchange Reconstruction ProjectTwin Ports Interchange Reconstruction Project Monthly Update Meeting March 26, 2018. Project Layout North. Concept C – Recommended Signal](https://reader034.fdocuments.in/reader034/viewer/2022042200/5ea088104c9ed373c01913b1/html5/thumbnails/26.jpg)
Thank You!
Questions/Comments