Detailed Report on Manufacturing of Turbo Generators at BHEL Haridwar
Turbo Generators
-
Upload
jayson-cartagena-jueco -
Category
Documents
-
view
108 -
download
8
description
Transcript of Turbo Generators
“OPERATION AND MAINTENANCEOF LARGE TURBOGENERATORS”
By: Nejarine Tio Torred
What is Turbo Generator?
steam and gas turbine-driven generators
Ratings: from few Megawatts (MW) up to 1900 MW
Two- and four pole design employing round rotors
What is Turbo Generator?
Rotational operating speed: 3600 and 1800 rpm ( North America, Japan, Asia)
3000 and 1500 rpm (Europe, Africa, Australia, Asia, and South America)
Synchronous machine with frequency of 60 or 50 Hz
Stator Core
Made up of thin sheets of electrical grade, 3% to 4% silicon or grain oriented, and 0.014 inch (0.355 mm) or 0.019 inch (0.483 mm) thick steel.
Stator CoreLamination is insulated on both sides with an organic (varnish) or inorganic (layer of oxidation) compound.
Hydrogen gas: coolant of the core
Stator Core
Note:Generators with a small outer core diameter (four pole) are usually lower fluxed machines while a large diameter (two-pole) are generally high flux machines.
Stator Frame
To provide support for the stator core and to act as a pressure vessel for the hydrogen cooling gas.
Stator Frame
Note:Ensure that the natural frequencies of the core and the frame are not near 60/50 Hz or 120/100 Hz.
Weight of the largest stator can reach up to 500 tons.
Stator WindingMade up of
insulated copper conductor bars that are distributed around the inside diameter of the stator core, called the stator bore, in equally spaced slots to ensure symmetrical flux linkage.
Stator Winding
OIndirectly cooled machines: strands are all solid
ODirectly gas-cooled machines: cooling ducts are insulated from the copper strands.
ODirect water-cooled: the strands are constructed as hollow, to carry liquid cooling, rectangular in shape and are insulated from each other.
Rotor Winding
OInstalled in the slots machined in the forging main body and is distributed symmetrically around the rotor between the poles.
Rotor WindingField voltage is
dc and can reach as high as 700V.
Rotor winding slot wedges are made of
aluminum or brass and do not usually sit tight in the slots to provide
thermal expansion during operation.
Retaining-Rings
Most highly
stressed componen
t
Hold the end-winding copper of the rotor winding
against centrifugal load during operation
Designed with a safety
factor of 150% up to 20%
overspeed.
Rotor Turning Gear
ORequired to slowly roll the rotor when the generator is taken off line.
Rotor Turning Gear
OFor two pole: 80 or 90 tons.
OFour pole: as much as 150 tons
Rotor Fans
For cooling gas circulation
Hydrogen CoolersHeat exchangers
mounted inside the generator in the
enclosed atmosphere
Generator Auxiliary Systems
Lubricating oil system
Hydrogen cooling system
Seal oil system Stator cooling
water system Excitation system
Lube Oil System
Generator Auxiliary Systems
provides oil for all the turbine and generator bearings the source of seal oil
Lube Oil System
Components:i. Main lube oil tankii. Pumpsiii. Heat exchangersiv. Filters and strainersv. Centrifuge or purifiervi. Vapor extractorvii. Check valves and
instrumentation
Hydrogen Cooling System
Reasons:O inherently better heat
transfer characteristics ( approx. 14 times)
O better the heat transfer with higher hydrogen pressure
O less windage and friction losses than air
Hydrogen Cooling System
Reasons:O suppression of partial discharges
with increased hydrogen pressureO significant increases of the
breakdown voltage of generator components
Hydrogen Cooling System
Control:O pressure regulators (below 500
cubic feet per day losses)O gas purity (maintained above 97%)O dew-point monitors (maintained
below -10 degree Celsius and not allowed to rise above 0 degree Celsius
Hydrogen Cooling System
Control:OC02
requirement
Since the explosive range of hydrogen/oxygen mixture is 4 to 75% hydrogen in air.
Seal Oil System
a portion of the lube oil, had its own pumps, motors, hydrogen detraining, and controls to regulate the pressure and flow
Maintained about 15 psi to stop hydrogen from leaking past the seals.
Stator Cooling Water System
To provide source of demineralized water to the generator stator winding for direct cooling
used in machines rated or above 300 MVA
Stator Cooling Water System
System Components:
O Pumps (ac motor driven pumps used to deliver the cooling water, dc motor driven pump used for emergency shutdown)
O Heat exchangers ( for heat removal)
Stator Cooling Water System
System Components:
O Filters and Strainers (removal of debris)
O De-Ionizing Subsystem ( maintained low conductivity)
O Makeup tank ( to hold sufficient makeup water as required)
OGas collection and venting required (venting off other gases like oxygen)
Exciter System
Types:O Rotating: motor or shaft driven,
self-excitedO Static: external source of powerO Brushless: consists of high-
frequency ac generator with a rotating fused diode assembly
Operation and Control
Machine Rating:O Gas turbine Gen.: 400 MVAO Steam turbine Gen.: 1600 – 2000
MVAPower factor: 0.85 to 0.90, lagging
Operation and Control
Speed:O 60 Hz: 3600 rpm for 2-poles
gen: 1800 rpm for 4-
poles genO 50 Hz : 3000 rpm for 2-poles
gen: 1500 rpm for 4-
poles gen
Hydrogen Pressure: 75 psi (518 Kpa)
Operation and Control
Hydrogen Temperature:O max allowable cold gas: 46 ºCO cold gas operating set point: 30-40
ºCO hot and cold hydrogen gas at full
load condition: 15 – 25 ºC
Operation and Control
Overloading:O 10% overload condition will
increase the heat in the conductor by about 20%
O expected life of insulation: approx. halved for every 8 to 10 ºC increase in temperature
Operation and Control
Overspeed: rotors of turbogenerators are
designed to withstand a 120% spin test
Shutdown Operation
The turbine should be tripped before the generator.
Make sure the generator does not motor the turbine.
Attain electrical separation by following clearly established safe routines.
Place the unit on turning gear as deemed necessary.
Generator Maintenance and Testing
Type of Maintenance Breakdown maintenance
- employed for short termeconomic gains with little regard to the future of the specific piece ofequipment.
- applied to smaller components,where repair is more costly than replacement
Generator Maintenance and Testing
Type of Maintenance
Planned maintenance- entails the predetermined
maintenance schedules.- based on experience
acquired during many years of operation, onthe reliability of the equipment, as well as on load demands, weather, personnel availability, coordination with other plants of the same utility
Generator Maintenance and Testing
Type of Maintenance Predictive maintenance
- schedule is based mainly on statistical calculations.
- age of the insulation components, type of insulation, load cycles, and abnormal operation events.
Generator Maintenance and Testing
Type of Maintenance
Condition-Based maintenance
- determining whento inspect, maintain, and refurbish a generator and other plant equipment
-applied when equipment is monitored by a number of on-line, real-time sensors, as well as off-line periodic testing routines.
Generator Maintenance and Testing
Stator Core Mechanical Tests
Core Tightness- is done by
inserting a thin, tapered, and hardened steel knife blade between laminations to determine the degree of looseness in the stator ring.
01
Generator Maintenance and Testing
Stator Core Mechanical Tests
Core and Frame Vibration Testing
- is done by online testing, where vibration transducers are mounted on the core and frame internal to the machine.
01
Generator Maintenance and Testing
Core and Frame Vibration Testing
Note:The maximum vibration of the stator core and core frame should be less than 50µm peak to peak, with no natural resonance within the frequency ranges of 50 – 75 Hz and 100 – 140 Hz for 60 Hz systems, and about 40 -65 Hz and 80 – 120 Hz for 50 Hz systems
Generator Maintenance and Testing
Stator Core Electrical Tests
EL-CID Testing- (Electromagnetic-Core
Imperfection Detector)- The heat produced is detected
and quantified using established infrared techniques.
02
Generator Maintenance and Testing
Stator Core Electrical Tests
EL-CID TestingHow this will work?• A 120 or 230V with current capacity
of 15 to 20 A• The winding is energized
approximately 3 to 4% or 5V per meter.
• EL-CID detect fault in mA.
+-100mA( core has damage)
02
Generator Maintenance and Testing
Stator Core Electrical Tests
Rated Flux Test with Infrared Scan
- used to check the integrity of the insulation between the laminations in the stator core.
02
Generator Maintenance and Testing
Stator Core Electrical Tests
Core Loss Test- always
determined at the factory by the manufacturer, and is not a test that is generally done at site.
02
Generator Maintenance and Testing
Stator Core Electrical Tests Through-Bolt
Insulation Resistance
- to ensure that the through-bolts do not create any short circuits across the stator core laminations.
- meggering at 500V dc. Good reading: hundreds of MΩ range.
02
Generator Maintenance and Testing
Stator Core Electrical Tests Insulation
Resistance of Flux Screens
- to ensure that no additional circulating currents flow between the core and the flux screens.
- meggering at 500V dc. Good reading: hundreds of MO range.
02
Generator Maintenance and Testing
Stator Winding Mechanical Tests
Wedge Tightness
- is done by tapping with a suitable hammer and recording the degree of looseness on a chart.
03
Generator Maintenance and Testing
Wedge TightnessRe-wedging is required if:
• Less than 75% of the wedges are tight in the slot.
• Three or more adjacent wedges are fully loose.
• Fully loose end-wedges must be re-tightened.
Generator Maintenance and Testing
Stator Winding Mechanical Tests Stator End-Winding Vibration
- “bump test” (temporary vibration transducers mounted on the end-winding and a calibrated hammer to measure the vibration signatures.
03
Generator Maintenance and Testing
Water-Cooled Stator Winding Tests
Air Pressure Decay
- “pressurizing the stator winding to about 30 psi and watching that the drop in pressure does not exceed 0.1 psi over a 6 hour period.
04
Generator Maintenance and Testing
Water-Cooled Stator Winding Tests Tracer Gases- “pressurizing
the stator winding with helium.
- used to “sniff” over the external surfaces of the exposed portions of the stator winding.
04
Generator Maintenance and Testing
Water-Cooled Stator Winding Tests Vacuum Decay
- determine the leak sensitivity of the entire winding.
- by pulling vacuum to 29 in. of mercury, and watching gauge does not drop by more than 0.2 in Hg over 6 hours.
04
Generator Maintenance and Testing
Water-Cooled Stator Winding Tests
Pressure Drop
- to estimate the stator cooling water flow rate in each bar.
04
Generator Maintenance and Testing
Water-Cooled Stator Winding Tests
Flow Testing- to
determine if there are restrictions in the cooling water path and it is done by water.
04
Generator Maintenance and Testing
Water-Cooled Stator Winding Tests Capacitance
Mapping- to identify the
presence of moisture in the ground-wall insulation from stator winding leaks.+-2 S.D. (good)+ 3 S.D. (suspect)+ 5 S.D. (wet)
04
Generator Maintenance and Testing
Stator Winding Electrical Tests
Pre-testing Requirements• Completely dried• Three phases must be isolated• Generator CT windings should
be shorted• Consult vendor/pertinent
standards
05
Generator Maintenance and Testing
Stator Winding Electrical Tests
Series Winding Resistance
- to measure the ohms resistance of the copper in each phase.
- to detect shorted turns, bad connections, and open circuits.Accepted test: 0.5% error from the average
05
Generator Maintenance and Testing
Stator Winding Electrical Tests Insulation Resistance (IR)
- to measure the ohmic resistance between conductors in each of the three phases and the ground.
- from 500 to 5000V in 1 min.Accept: (VLL in KV + 1) MΩ.
05
Generator Maintenance and Testing
Stator Winding Electrical Tests
Polarization Index (PI)- done on a per phase basis
at the same voltage as the IR test, 40°C.PI values:Class A insulation: 1.5Class B and F insulation: 2.0
05
Generator Maintenance and Testing
Stator Winding Electrical Tests dc Hi-Pot- if the
winding is capable of sustaining the required rated voltage levels, capability to withstand overvoltages and transients, and maintain acceptable insulation life.
05
New windings: [(2*VLL + 1000) * 1.7] KV dc Field testing and maintenance: 125 to 150% of (VLL * 1.7) KV dc
Generator Maintenance and Testing
Stator Winding Electrical Tests ac Hi-Pot- if the
winding is capable of sustaining the required rated voltage levels, capability to withstand overvoltages and transients, and maintain acceptable insulation life.
05
New windings: (2*VLL + 1000) KV ac Field testing and maintenance: 125 to 150% of VLL KV ac
Generator Maintenance and Testing
Stator Winding Electrical Tests
Dissipation/Power Factor Testing
- ac test used to measure the bulk quality of the ground-wall insulation, by measuring the dielectric loss per unit volume of the insulation.
05
Generator Maintenance and Testing
Rotor Mechanical Testing
Rotor Vibration
06
MACHINE SPPED MAXIMUM AMPLITUDE
O-999 rpm 3 mils
1000-1499 rpm 2.5 mils
1500-2999 rpm 2 mils
3000 rpm & above 1 mil
Generator Maintenance and Testing
Rotor Mechanical Testing
Visual Inspection- applicable to surface
defects. It’s low cost, simple, and quick but the inspector must be knowledgeable and thorough.
06
Generator Maintenance and Testing
Rotor Mechanical Testing
Radiographic- done by
commercial X-ray or gamma units for welds, castings, and forgings. It can detects cracks, porosity, and poor welds.
06
Generator Maintenance and Testing
Rotor Mechanical Testing
Magnetic Particle
- for surface flaws in the range of 200 to 2000 amps. Magnetic powders are in dry or wet form and may be fluorescent for viewing under ultraviolet rays.
06
Generator Maintenance and Testing
Rotor Mechanical Testing
Liquid Penetrant
- primarily used for retaining-ring inspection, have greater sensitivity, and a cost-effective method.
06
Generator Maintenance and Testing
Rotor Mechanical Testing
Ultrasonic- able to detect surface and
subsurface flaws of about 2 to 3 mm
06
Generator Maintenance and Testing
Rotor Mechanical Testing
Eddy- able to
detect surface and near-surface defects, de-lamination of multi-layered components, and inclusions.
06
Generator Maintenance and Testing
Rotor Electrical Testing
Insulation Resistance (IR)
- to measure the ohmic resistance between the total rotor winding insulation and ground.
- from 500 to 1000V in 1 min.Accept: (Vf in KV + 1) MΩ.
07
Generator Maintenance and Testing
Rotor Electrical Testing
Polarization Index (PI)- to determine how clean
and dry the winding is.PI values:Class B insulation: 2.0Class F insulation: 2.0
07
Generator Maintenance and Testing
Rotor Electrical Testing
dc Hi-Pot- if the
winding is capable of sustaining the required rated voltage levels, capability to withstand overvoltages and transients, and maintain acceptable insulation life.
07
done between 1500 V up to 10 times the rated field voltage.
Generator Maintenance and Testing
Rotor Electrical Testing
ac Hi-Pot- if the
winding is capable of sustaining the required rated voltage levels, capability to withstand overvoltages and transients, and maintain acceptable insulation life.
07
Done at 10 times the rated field voltage at line frequency of 60 Hz.
Generator Maintenance and Testing
Rotor Electrical Testing Shorted turns
Detection- to detect rotor
winding shorted turns that can occur from electrical breakdown of insulation and mechanical damage.
07
Generator Maintenance and Testing
Hydrogen Seals
Liquid Penetrant- primarily used to determine
cracks, and other surface damage.
08