The Cinderella of Sustainable Building Projects

STRIDE TREGLOWN ARCHITECTS

Page 3: Tristan Rhodes LCBB Slides

STRIDE TREGLOWN ARCHITECTS

Political Background

Page 4: Tristan Rhodes LCBB Slides

Regulatory Reform

STRIDE TREGLOWN ARCHITECTS

Page 5: Tristan Rhodes LCBB Slides

Occupier Demand

STRIDE TREGLOWN ARCHITECTS

Page 6: Tristan Rhodes LCBB Slides

Occupier Demand

STRIDE TREGLOWN ARCHITECTS

Page 7: Tristan Rhodes LCBB Slides

Occupier Demand

STRIDE TREGLOWN ARCHITECTS

Page 8: Tristan Rhodes LCBB Slides

Occupier Demand

STRIDE TREGLOWN ARCHITECTS

Page 9: Tristan Rhodes LCBB Slides

STRIDE TREGLOWN ARCHITECTS

20 Manvers Street, Bath

• Complete refurbishment with significant structural remodelling,

building rebranded with new identity

• Net area increased by 18%

• Planning risk and construction programme reduced through

refurbishment

• Speculatively started and fully let prior to completion

• Bath headline rental of £31sq.ft

• Largest private array of PV’s in Bath

• EPC B

Page 10: Tristan Rhodes LCBB Slides

STRIDE TREGLOWN ARCHITECTS

20 Manvers Street, Bath

• Complete refurbishment with significant structural remodelling,

building rebranded with new identity

• Net area increased by 18%

• Planning risk and construction programme reduced through

refurbishment

• Speculatively started and fully let prior to completion

• Bath headline rental of £31sq.ft

• Largest private array of PV’s in Bath

• EPC B

Page 11: Tristan Rhodes LCBB Slides

STRIDE TREGLOWN ARCHITECTS

County Hall, Trowbridge

• 40% reduction in carbon emissions

• BREEAM Excellent

• Reuse of 1920’s and 1970’s buildings to create light and airy

public space and offices for the Council

• Improvements in airtightness and thermal performance of the

existing buildings.

Page 12: Tristan Rhodes LCBB Slides

740 Aztec West, Bristol

STRIDE TREGLOWN ARCHITECTS

• L&G fund requirement for 10% improvement over current

building regulations

• EPC D to EPC A, achieved through significant work on air

tightness as well as on site renewables

• Shift of rental from £12 - £21sq.ft, headline rental in Aztec West

• Increase in net area of 9%

• Agent brief to ‘rebrand and reposition’

• Speculatively started and fully let prior to completion

Page 13: Tristan Rhodes LCBB Slides

STRIDE TREGLOWN ARCHITECTS

740 Aztec West, Bristol

• L&G fund requirement for 10% improvement over current

building regulations

• EPC D to EPC A, achieved through significant work on air

tightness as well as on site renewables

• Shift of rental from £12 - £21sq.ft, headline rental in Aztec West

• Increase in net area of 9%

• Agent brief to ‘rebrand and reposition’

• Speculatively started and fully let prior to completion

Page 14: Tristan Rhodes LCBB Slides

STRIDE TREGLOWN ARCHITECTS

740 Aztec West, Bristol

• L&G fund requirement for 10% improvement over current

building regulations

• EPC D to EPC A, achieved through significant work on air

tightness as well as on site renewables

• Shift of rental from £12 - £21sq.ft, headline rental in Aztec West

• Increase in net area of 9%

• Agent brief to ‘rebrand and reposition’

• Speculatively started and fully let prior to completion

Page 15: Tristan Rhodes LCBB Slides

STRIDE TREGLOWN ARCHITECTS

740 Aztec West, Bristol

• L&G fund requirement for 10% improvement over current

building regulations

• EPC D to EPC A, achieved through significant work on air

tightness as well as on site renewables

• Shift of rental from £12 - £21sq.ft, headline rental in Aztec West

• Increase in net area of 9%

• Agent brief to ‘rebrand and reposition’