Transformer on Load

download Transformer on Load

of 14

Transcript of Transformer on Load

  • 8/14/2019 Transformer on Load

    1/14

    Transformer on Load

    V1

    I0

    I 2

    Load

    2

    2

    2

    Fig. 4

  • 8/14/2019 Transformer on Load

    2/14

    Phasor diagram for Transformer on Load

    E2

    V1

    I2'

    I2

    I0

    I1

    Load I2 is

    resistive

    K=1

    0

    E2

    V1

    I2

    '

    I 2

    I0

    I1

    Load I2

    is

    inductive

    K=1

    01

    2

    Fig. 5

    1

  • 8/14/2019 Transformer on Load

    3/14

    Actual transformer:

    Winding resistance & magnetic leakage

    R1

    X1 I 1

    E1

    V1

    R2

    X2

    I2

    V2

    E2

    2

    1

    2

    11XRZ +=

    R1 & R2 : resistances of primary & secondary windings respectively.

    X1 & X2 : leakage reactances of primary & secondary windings respectively.

    2

    2

    2

    22 XRZ +=

  • 8/14/2019 Transformer on Load

    4/14

    Phasor diagram of actual transformer

    a) I2 is resistive b) I2 is inductive c) I2 is capacitive

  • 8/14/2019 Transformer on Load

    5/14

    Transfer of resistances & reactances to any

    side

    The Cu loss by I2 in secondary = I22 R2. If is the

    equivalent resistance in the primary which wouldhave caused the same loss as R2 in the secondary,

    then

    Similarly, equivalent primary resistance as referredto secondary is

    2

    2

    2

    2

    1

    2

    2

    22

    122

    2

    k

    R

    I

    I

    RRor,

    RIRI

    =

    =

    =

    1

    2

    1RkR =

    2

    R

  • 8/14/2019 Transformer on Load

    6/14

    Leakage reactances can also be transferred

    from one winding to other ;

    Total resistance referred to primary is

    Total reactance referred to primary is

    Total impedance of transformer referred to

    primary is

    2

    2

    2kXX =

    1

    2

    1 XkX =

    +=2101

    RRR

    += 2101 XXX

    2

    01

    2

    0101XRZ +=

  • 8/14/2019 Transformer on Load

    7/14

    Similarly, total resistance referred to secondary is

    Similarly, total reactance referred to secondary is

    Similarly, total impedance of transformer

    referred to secondary is

    +=

    1202

    RRR

    += 1202 XXX

    2

    02

    2

    0202 XRZ +=

  • 8/14/2019 Transformer on Load

    8/14

    R02

    X02

    Impedance referred to secondary

    Z02

  • 8/14/2019 Transformer on Load

    9/14

    Equivalent circuit of Transformer

    I1

    E1

    V1

    I2

    V2

    E2

    R 1 X 1 I 1

    I0

    I2

    '

    V 1 E 1 E 2

    R 2 X 2

    R 0 X 0

    I2

    Z LV 2

    A) Circuit

    B) Equivalent circuit of transformer

    Iw I

  • 8/14/2019 Transformer on Load

    10/14

    Equivalent circuit of Transformer referred to

    primaryR1 X1 I1

    I0

    I2'

    V1 E2'= E1

    R2' X2'

    R0 X0 ZL'V2

    '

    I2'

    I1

    E2' = E2/K, R2' = R2/K

    2, X2' = X2/K2, V2' =V2/K, ZL =ZL/K

    2

    E2/E1 = I1/I2 = K

    R1 X1I1

    I0

    I2'

    V1 E2'= E1

    R2' X2'

    ZL'

    I2'

    I1

    R0 X0

    V2'

    D) Approximate equivalent circuit

    Iw

    Iw

    I

    I

    C) Equivalent circuit with secondary impedances transferred to primary

  • 8/14/2019 Transformer on Load

    11/14

    = R1 X01= X1I1

    I0

    I2'

    V1

    +R2' + X2'

    ZL'

    I2'

    I1

    R0 X0

    V2'

    R01

    Approximate Equivalent circuit with secondary impedances

    transferred to primary

  • 8/14/2019 Transformer on Load

    12/14

    Transformer tests

    The performance of a transformer can be calculated on the basis of its

    equivalent circuit which contains the 4 main parameters:

    1. Equivalent resistance R01(or R02)

    2. Equivalent leakage reactance X01 (or X02)

    3. Core loss resistance R0

    4. Magnetizing reactance X0.

    These parameters are determined from the following tests:

    a) Open circuit test

    b) Short circuit test

  • 8/14/2019 Transformer on Load

    13/14

  • 8/14/2019 Transformer on Load

    14/14

    Short Circuit test

    This test is conducted to determine:1. Full-load copper loss

    2. Equivalent resistance & reactance referred to metering side.

    LV

    supply

    V

    AW

    Low Voltage windingHigh Voltage winding

    A low voltage (5 -10% of normal primary voltage) at correct frequency is applied

    to the primary winding & is continuously increased till full load currents flow both

    in primary & secondary. Since applied voltage is small, flux linking with core is

    very small & hence, iron loss can be neglected & reading of wattmeter givestotal copper losses at full load.

    If Vsc is the voltage required to circulate rated load currents, then

    2

    01

    2

    010101

    2

    01 ; RZXRIWI

    VZ

    sc

    sc

    sc===