TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion...
Transcript of TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion...
![Page 1: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/1.jpg)
1
TransCanada’s Napanee Generating Station (NGS)
Presentation to the Community Liaison Committee Wednesday, September 17, 2015
![Page 2: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/2.jpg)
2
1. Project Updates
1. E.S. Fox
2. Matrix NAC
2. Transfer of Combustion Turbine Generator parts from Pickering to Taylor
Kidd Warehouse
3. Delivery of Duct Work from Cambridge
4. Piping Shipments from Toronto
5. Heat Recovery Steam Generator (HRSG) Component Delivery - Overseas
6. Condenser Delivery from US
7. Combustion Turbine Generator (CTG) Foundation Concrete Pours
8. Combustion Turbine Delivery Japan and Savannah, Georgia
Introductions & Agenda
![Page 3: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/3.jpg)
3
OBL – Project Status/Activities/Look Ahead
E.S. Fox Ltd.
![Page 4: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/4.jpg)
4
E.S. Fox – Project Status/Activities/Look Ahead
![Page 5: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/5.jpg)
E.S. Fox – Project Status/Activities/Look Ahead
5
Q3 Activities
• Complete civil earth works by the end of September
• Completed installation of the duct bank and raw water service pipe into the Lennox GS pumphouse
• Installed and backfilled sanitary sewer line
• Cooling water discharge
pipe installed to Lennox GS discharge channel
(complete by Sept.30)
![Page 6: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/6.jpg)
E.S. Fox – Project Status/Activities/Look Ahead
6
Q3 Activities
• Station to station grounding is nearing completion
• Final pavement and curb replacement will be completed in October
• Installed and backfilled sanitary sewer line
• Cooling water discharge
pipe into Lennox GS channel
(complete by Sept.30)
![Page 7: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/7.jpg)
E.S. Fox – Project Status/Activities/Look Ahead
7
Q4 Look Ahead
• Current staffing approximately 15
• Plan to demobilize in mid-November
• Return in spring 2016 to install pumping equipment
![Page 8: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/8.jpg)
8
Project Status/Activities/Look Ahead
Matrix NAC
![Page 9: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/9.jpg)
Matrix – Project Status/Activities/Look Ahead
Q3 Activities
• Installed temporary construction and permanent site entrances including traffic lights at temporary entrance
9
![Page 10: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/10.jpg)
Matrix – Project Status/Activities/Look Ahead
Q3 Activities
• Focus has been and remains the installation of buried services, equipment and building foundations (E.g. HRSG pours)
• Completion of Storm Water Management System
10
![Page 11: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/11.jpg)
Matrix – Project Status/Activities/Look Ahead
Q4 Look Ahead
• Major equipment deliveries – details to follow
• Focus will continue on civil work including additional large
concrete pours for:
• Combustion Turbine Generator foundation & pedestal
• Steam Turbine Generator foundations
(pours of approximately less than 1,000 cu metres)
• Completion of landscaping berms
• planting will take place as early as possible in 2016
11
![Page 12: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/12.jpg)
Matrix – Project Status/Activities/Look Ahead
Q4 Look Ahead
• Recently introduced a second shift
• Current manpower is approximately 300
• Anticipated manpower during Q4 – approximately 450
12
![Page 13: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/13.jpg)
13
TransCanada’s Napanee Generating Station (NGS)
Heavy Haul Activities
![Page 14: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/14.jpg)
14
• This activity involves approximately 250-300 truck loads of
material to be moved from a warehouse in Pickering, Ontario
to Matrix’s rental warehouse space on Taylor Kidd Road
(Bombardier).
• Includes 12 oversized or permitted loads.
• Shipping route should include Highway 401, County Road 4
and Taylor Kidd Road. (confirm)
• These shipments have started and will continue at a rate of
approximately 2 trucks per day.
• Shipments complete by October 31.
Transfer of CTG Parts from Pickering
![Page 15: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/15.jpg)
15
• This activity involves a total of 48 shipments from
Cambridge, Ontario including 36 oversized or permitted
loads.
• At present 1 permitted truck per day but could go to as many
as 3 trucks/day.
• Shipping route will include Highway 401 to County Road 4 to
Highway 33 to the NGS site
• Scheduled to be complete by mid-September
Delivery of Duct Work from Cambridge
![Page 16: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/16.jpg)
16
• Initially 6 trucks/week at Taylor Kidd warehouse and 10
trucks/week at site
• 31 trucks scheduled over the next two weeks
• Shipping route will include Highway 401 to County Road 4 to
Highway 33 to the NGS site.
• Currently being affected by a strike
Delivery of Piping from Toronto
![Page 17: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/17.jpg)
17
• 2 large concrete pours (approximately 1,000 sq.
metres/pour) to form the foundations for the Heat Recovery
Steam Generators.
• Completed on September 8 and 14
Heat Recovery Steam Generator Foundation Pours
![Page 18: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/18.jpg)
18
• Delivery of 24 large HRSG components and 6 steam drums
will be via ship to Lafarge (heaviest module 232,036 kg)
• Component will be carried to site on 18-axle trailers
(goldhofer)
• Trip from Lafarge to site is expected to take 15 minutes
• 2 shipments per day between 7:00 a.m. and 7:30 p.m.
• Commitment to avoid school busing times 8-8:30 a.m. and 3:30-4:00 p.m.
• OPP escort required in front and behind each shipment- can
order convoy to stop to reduce traffic congestion
• Schedule – ship currently expected to arrive September 27
or 28
• 8 days of deliveries
Heat Recovery Steam Generator (HRSG) Component Delivery
![Page 19: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/19.jpg)
19
• Delivery will stand down any time Lafarge need their dock
• Other Requirements:
• Approximately 8 residential electrical services will have to
be raised prior to the first delivery
• Goldhofer stored on NGS site at night
• Message signs to be installed prior to shipments
Heat Recovery Steam Generator Component Delivery
![Page 20: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/20.jpg)
20
• Delivery of condenser from supplier in US will be by barge to
Lafarge
• One 12-line hydraulic platform trailer making two deliveries
per day over two days between Lafarge and site
• Size requires either full road closure or escort (TBD)
• Schedule : Barge scheduled to arrive October 13
Condenser Delivery
![Page 21: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/21.jpg)
21
• Large concrete pours (approximately 800 to 1,000 cu
metres/pour) to form the foundations and pedestals for the
Combustion Turbine Generators. And the Steam Turbine
Generator
• Similar to HRSG pours - will involve one concrete truck
arriving and leaving the site every 5 minutes beginning at
7:00 a.m. for 8-10 hours.
• Main batch plant will be the CBM plant set up at the
Cruickshank Quarry location on Taylor Kidd Road.
• Backup will come from CBM Kingston and then Belleville
batch plant.
• Currently determining schedule for these pours.
Combustion Turbine & Steam Turbine Foundation Concrete Pours
![Page 22: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/22.jpg)
22
• Delivery will be via ship from Japan and Savannah, Georgia
to Lafarge
• 4 shipments to NGS site expected to take approximately 15
minutes
• Road closure and/or OPP escort required
• Target delivery date is early November
Combustion Turbine Generator Delivery
![Page 23: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/23.jpg)
23
Newspaper Ad and Direct Mail Flyer
![Page 24: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/24.jpg)
24
NGS Calendar - September
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
31 August 1 September 2 3 4 5 6
Pickering Warehouse
Duct Work Deliveries
HRSG Foundation
Transfer
36 permitted loads
Piping Container
Bell Fiber
(250-300 loads)
Shipments
Cabinet Installation
7 8 9 10 11 12 13
Start of School
Duct Work
Bell Fiber
Pickering Warehouse
Deliveries
Piping Container
HRSG Foundation
Transfer
Shipments (40 loads)
Bike Tour (30-40
riders)
14 15 16 17 18 19 20
Piping Container
Lafarge
Shipments
Algoma Delivery
Pickering Warehouse
Transfer
21 22 23 24 25 26 27
Pickering Warehouse
Transfer
Amherst Island
Ship Arrives at Lafarge
HRSG Component
Dry Stone Wall
Deliveries
Festival
28 29 30
Pickering Warehouse
Transfer (on-going)
HRSG Component
Deliveries
24 modules, 6 steam
drums & associated
equipment
![Page 25: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/25.jpg)
25
NGS Calendar - October
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
1 2 3 4
Pickering Warehouse Transfer
HRSG Component
Deliveries
5 6 7 8 9 10 11
Pickering
HRSG Component
Warehouse Transfer
Deliveries
(Starting at noon)
MTO-Permitted Load
Restrictions
12 13 14 15 16 17 18
MTO Permitted Load
Restrictions
Pickering
Lafarge Petcoke
Condenser Delivery
Warehouse Transfer
Unloading
19 20 21 22 23 24 25
Pickering
Warehouse Transfer
26 27 28 29 30 31
Pickering
Warehouse Transfer
![Page 26: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship](https://reader030.fdocuments.in/reader030/viewer/2022013120/5af66bf47f8b9a954690c017/html5/thumbnails/26.jpg)
26
NGS Calendar - November
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
1
2 3 4 5 6 7 8
Combustion
Turbine Delivery
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29