Tracker Progress
-
Upload
virginia-boyer -
Category
Documents
-
view
26 -
download
0
description
Transcript of Tracker Progress
1G.Barber Tracker Update, Berkeley 10 Feb 2005
Tracker Progress
Contents:-
Station
Space Frame
Patch Panel / Vacuum Seal
Light Guide Map
Position of Degrader/Support
2G.Barber Tracker Update, Berkeley 10 Feb 2005
Station
The bare carbon fibre station machined and ready to accept the scintillating fibre planes.
3G.Barber Tracker Update, Berkeley 10 Feb 2005
Station ‘Connectorisation’
Each station has a total of 30 connectors, 10 per view. Each connector has 22 holes instead of the previous 18 but all of these are not used in every connector. All 3 planes are aligned and glued before the ‘connectorisation’ can begin. This is one of the main areas where a rigid QA system will need to be implemented. The photograph shows Roger Hare fitting connectors to the 4th prototype station at Imperial on Monday.
4G.Barber Tracker Update, Berkeley 10 Feb 2005
Space Frame
Components All of the components that make
the space frame assemblies have been or are in the process of being manufactured.
Tooling The jigs that align the space frames are all manufactured.
One further development?
5G.Barber Tracker Update, Berkeley 10 Feb 2005
Connector Map
126 Way
126 Way
128 Way
128 Way
125 Way
View ‘W’211 Channels
View ‘V’211 Channels
View ‘X’211 Channels
This is the connector map created for the KEK Test beam prototype. It will be updated for the final detector and will be a more uniform layout.
6G.Barber Tracker Update, Berkeley 10 Feb 2005
Connector 1
View ‘V’
18 Way
Bundles2 – 19
To Bulkhead Connector - 1
Station connectorViewed from thepolished face
2
6 4
8
5
7
3
91011
12
14 13151617
19 18xx
x x
7G.Barber Tracker Update, Berkeley 10 Feb 2005
Bulkhead Connector 1
View ‘V’
126 Way
Bundles2 – 127 in ‘V’
From ConnectorsC1 – C6
Station connectorViewed from thepolished face
2 64 85 73 9 10 11 12 13
x
14 1816 20 22 2415 1917 21 23 25
26 3028 32 34 3627 3129 33 35 37
39 4341 45 47 4938 4240 44 46 48
50 5452 56 59 61
63 6765 69 71 73
74 7876 80 83 85
87 9189 93 95 97
98 102100 104 107 109
111 115113 117 119 121
51 5553 57
62 6664 68
75 7977 81
99 103101 105
86 9088 92
110 114112 116
122 126124123 127125
70
94
118
58
82
106
72
96
120
60
84
108
x
8G.Barber Tracker Update, Berkeley 10 Feb 2005
Lead Diffuser
The lead diffuser will sit inside the bore of the cryostat at a position of Z = -6015 This is 238mm from the tracker plane. It will be supported on a spider that is fixed to the patch panel and can be put into position in ‘thin slices’. This gives 2 advantages:- it can be put into position in manageable pieces (weight) and the thickness/position can easily be changed.Extended guide studs also give more security during the installation.
9G.Barber Tracker Update, Berkeley 10 Feb 2005
Conclusions
There is still a great deal to design and detail and a few outstanding problems to solve but overall the design should be pretty much as for the prototype.
So once the prototype is completed in the next few weeks and assuming we find no major problems with the construction philosophy we can then concentrate on the final detailed design.