TRACK RECORD PIPELINE MAINTENANCE & REPAIR Page 1 of 3 DATE CLIENT SCOPE OF WORK 26.05.2006 Bumifocus Emergency work- Protection for exposed pipe at Jalan Johan Setia, Klang, Banting Selangor. 27.12.2007 Petronas Gas Excavation at NPS24 Lumut Lateral. 31.12.2007 Petronas Gas Excavation and soil stability at PGU 3 S2. 18.11.2009 Petronas Gas Pipeline repair at Shah Alam, Sitiawan and Gurun regional offices - crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes. 25.03.2010 Petronas Gas Line pipe preservation (PHASE I) for Pasir Gudang and Kuantan Regional Office.- crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes. 27.03.2010 Petronas Gas Line pipe preservation (PHASE I) program for Sitiawan Regional Office.- crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes. 27.03.2010 Petronas Gas Line pipe preservation (PHASE I) for Shah Alam Regional Office.- crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes. 27.03.2010 Petronas Gas Line pipe preservation (PHASE I) for Gurun Regional Office.-. crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes. 13.08.2010 Petronas Gas Line pipe preservation (PHASE II) for Kuantan Regional Office.- crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes. 13.08.2010 Petronas Gas Line pipe preservation (PHASE II) for Pasir Gudang regional office.- crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes. 31.10.2010 Petronas Gas Line Pipe Inspection (PHASE II) for Gurun, Pasir Gudang, Sitiawan and Shah Alam Regional Offices – Crane Rental. 18.11.2010 Petronas Gas Pipeline repair at Shah Alam, Sitiawan and Gurun regional offices - crane rental, visual inspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes.

description

RECORD

Transcript of Track Record -Pipeline Maintenance Repair

  • TRACK RECORD PIPELINE MAINTENANCE & REPAIR

    Page 1 of 3

    DATE CLIENT SCOPE OF WORK

    26.05.2006 Bumifocus Emergency work- Protection for exposed pipe at Jalan Johan Setia, Klang, Banting Selangor.

    27.12.2007 Petronas Gas Excavation at NPS24 Lumut Lateral.

    31.12.2007 Petronas Gas Excavation and soil stability at PGU 3 S2.

    18.11.2009 Petronas Gas Pipeline repair at Shah Alam, Sitiawan and Gurun regional offices - crane rental, visual inspection, holiday test,adhesion test, coating thickness measurement, handling of line pipes.

    25.03.2010 Petronas Gas Line pipe preservation (PHASE I) for Pasir Gudang and Kuantan Regional Office.- crane rental, visualinspection, holiday test, adhesion test, coating thickness measurement, handling of line pipes.

    27.03.2010 Petronas Gas Line pipe preservation (PHASE I) program for Sitiawan Regional Office.- crane rental, visual inspection, holidaytest, adhesion test, coating thickness measurement, handling of line pipes.

    27.03.2010 Petronas Gas Line pipe preservation (PHASE I) for Shah Alam Regional Office.- crane rental, visual inspection, holiday test,adhesion test, coating thickness measurement, handling of line pipes.

    27.03.2010 Petronas Gas Line pipe preservation (PHASE I) for Gurun Regional Office.-. crane rental, visual inspection, holiday test,adhesion test, coating thickness measurement, handling of line pipes.

    13.08.2010 Petronas Gas Line pipe preservation (PHASE II) for Kuantan Regional Office.- crane rental, visual inspection, holiday test,adhesion test, coating thickness measurement, handling of line pipes.

    13.08.2010 Petronas Gas Line pipe preservation (PHASE II) for Pasir Gudang regional office.- crane rental, visual inspection, holidaytest, adhesion test, coating thickness measurement, handling of line pipes.

    31.10.2010 Petronas Gas Line Pipe Inspection (PHASE II) for Gurun, Pasir Gudang, Sitiawan and Shah Alam Regional Offices CraneRental.

    18.11.2010 Petronas Gas Pipeline repair at Shah Alam, Sitiawan and Gurun regional offices - crane rental, visual inspection, holiday test,adhesion test, coating thickness measurement, handling of line pipes.

  • TRACK RECORD PIPELINE MAINTENANCE & REPAIR

    Page 2 of 3

    DATE CLIENT SCOPE OF WORK

    19.01.2011 Petronas Gas Line pipe preservation programme (PHASE III) for Gurun, Sitiawan, Shah Alam, Seremban Pasir Gudang,Kuantan, Gudang and Segamat Regional Office.- crane rental, visual inspection, holiday test, adhesion test,coating thickness measurement, handling of line pipes.

    29.05.2012 Petronas Gas Provision of 45 ton crane and manpower to relocate line pipes at Shah Alam Regional Office.

    11.10.2012 Petronas Gas Verify gas leak at Perwaja Metering Station, Kemaman.

    1.11.2012 Petronas Gas Access road repair & excavator rental.

    14.11.2012 Petronas Gas Provision of manpower, materials, consumables & equipment to undertake verification dig-up, pit-depthmeasurement, coating inspection, STOPAQ application for NPS 24 PD Lateral.

    26.11.2012 Petronas Gas Provision of manpower, materials, consumables & equipment to undertake verification dig-up, pit-depthmeasurement, coating inspection, STOPAQ application for NPS24 Prai Lateral.

    29.11.2012 Petronas Gas Provision of manpower, materials, consumables & equipment to undertake verification dig-up, pit-depthmeasurement, coating inspection, STOPAQ application for NPS36 PGU 3 Sector 1 Sitiawan.

    10.12.2012 Petronas Gas Provision of 45 ton crane and manpower to relocate line pipes at Shah Alam Regional Office.

    11.12.2012 Petronas Gas Provision of manpower, materials, consumables & equipment to undertake verification dig-up, pit-depthmeasurement, coating inspection, STOPAQ application for NPS 36 PGU3 Sector 1.

    14.12.2012 Petronas Gas Provision of manpower, materials, consumables & equipment to undertake magnetic particle inspection (MPI)for NPS 24 Port Dickson Lateral.

    29.04.2013 Petronas Ammonia Provision of manpower & materials to do temporary STOP IT Pipe Repair Clamp at Vessel V3-1203 forPetronas Chemicals Ammonia Sdn Bhd.

    25.09.2013 Petronas Gas Provision of manpower, materials, consumables & equipments to undertake verification dig-up, pit-depthmeasurement, soil sampling & coating repair for NPS 36 PGU 2 Sector 1, Kuantan.

  • TRACK RECORD PIPELINE MAINTENANCE & REPAIR

    Page 3 of 3

    DATE CLIENT SCOPE OF WORK

    7.10.2013 Petronas Gas Provision of manpower, materials, consumables & equipments to undertake verification dig-up, pit-depthmeasurement, soil sampling & Clock Spring Enhancement composite repair & STOPAQ for NPS 4 TioxideLateral, NPS 12 Optimal, NPS 4 ET & NPS 20 YTL, Terengganu.

    11.12.2013 Petronas Gas Provision of manpower, materials, consumables & equipments to undertake verification dig-up, pit-depthmeasurement, NDT & Clock Spring Enhancement composite repair for NPS 36 PGU 2 Sector 1 Pipeline,Johor.