TPC meeting, CERN, 29-30 April 2002Børge Svane Nielsen, NBI1 Status of laser system TPC meeting,...
-
Upload
martha-sexton -
Category
Documents
-
view
212 -
download
0
Transcript of TPC meeting, CERN, 29-30 April 2002Børge Svane Nielsen, NBI1 Status of laser system TPC meeting,...
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 1
Status of laser systemStatus of laser system
TPC meeting, CERN, 29-30 April 2002B.S.Nielsen, J. Westergaard
Niels Bohr Institute
Micro-mirror production status New support of micro-mirrors in rods Micro-mirror z positions New beam transport to muon arm side NBI lab tests:
• 1 mm beam profiles• preliminary high voltage tests
Absolute versus relative calibrations
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 2
TPC Laser principleTPC Laser principle
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 3
Laser tracks in TPCLaser tracks in TPC
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 4
Micro-mirror productionMicro-mirror production
A.Ridiger, Moscow: all fibres cut, polished, coated and tested 43 of 60 mirror bundles produced angle measurements about to start
micro-mirror bundle
brass cup
protection cap
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 5
Laser rod with mirrorsLaser rod with mirrorsdrawing shown in December 2001
New: Alu ring design changed & mirror support integrated with rings
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 6
Mirror support ringsMirror support rings
New: mirror support integrated with Alu rings:
Prototype produced at NBI
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 7
Rod gluingRod gluing
normal gas rod Alu ring:
normal gas rod macrolon piece:
mirror support ring:
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 8
Micro-mirror z positions (1)Micro-mirror z positions (1)
4 micro-mirrors per rod, at about (0, 1/3, 2/3, 1) length vary z positions slightly between odd/even rod
Principle of choosing z positions:
Normal gas rod consists of sections: 180+10210+180 mmwith alu rings inbetween.In laser rod:
cut first and last section in two and insert laser ring replace 2 normal rings with laser rings in odd rods cut 2 middle sections and insert laser rings in even rods
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 9
Micro-mirror z positions (2)Micro-mirror z positions (2)
108 rods 1415 mm = 210 mm
24 rods 415 mm = 60 mm
24 rods 615 mm = 90 mm
12 rods 815 mm = 120 mm
12 rods 1015 mm = 150 mm
120 rods 1415 mm = 210 mm
24 rods 1215 mm = 180 mm
12 normal gas rods:
12 laser rods(full TPC):
Suggestion:All mirror support rings glued to short rods and6 long rods at NBI. Full rods glued at CERN.
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 10
New muon arm side beam transport
New muon arm side beam transport
possible new layout
limited space between TPC and space frame move beam transport 10º from vertical plane adds 2 mirrors on sharf side + modifies beam transport on muon side
hope to attach 50 mm pipe on outside of TPC permanently
special prismnew placement
alternatives
special prism
beam transport as foreseen
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 11
Laser lab at NBILaser lab at NBI
power supply
1064 nm laser
doubler
532 nm
quadrupler
266 nm
expandingtelescope
amplifier
rod with micro-mirrors
CCD camera
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 12
Reflected 1 mm beamReflected 1 mm beam
FWHM=.93mm
z=31cm z=200cm
FWHM=.95mm
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 13
Reflected 1 mm beams (2)Reflected 1 mm beams (2)z=13 cm 16 cm
47 cm
1.00mmFWHM=1.00mm
1.17mm
0.93mm
19 cm
1.01mm
23 cm
1.10mm
31 cm
0.93mm
100cm 150cm
0.79mm
200cm
0.95mm
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 14
Preliminary HV testsPreliminary HV tests
200 M 10200 Mtotal L=2.10 m
70-80 kV40 A @ 80 kV
in air
laser off/on: no change in current (1 A)
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 15
Laser system objectives(P. Glässel)
• Electronics testing• Sector alignment• Drift velocity monitoring
– Pressure, temperature– Temperature gradients (stratification?)– ExB effects, space charge
• Two possible approaches:– Relative measurements, rely only on time stability of laser
ray position– Absolute measurements, requires knowledge of absolute
position of laser ray. More ambitious
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 16
Stability of laser and beamsStability of laser and beams
We are trying to assure the best possible mechanical stability in the construction and to make position measurements during installation.
But: we cannot assure laser system position stability better than the tolerances and movements of the support structure (rods and cylinders).
System with micro-mirrors laser ray positions determined by the mirror positions and angles, not by the main laser beam.
Mechanical stability of the TPC is good enough for precise (100 m) relative measurements once the TPC is installed.
During installation, the TPC will undergo stresses due to handling (turning on end) and change of loads (ROCs, cables etc). ’Absolute’ positions must refer to something that it stable or measuredrelative to something else well-known: ROCs, central electrode... ?
This should make the system better than most previous ones.
TPC meeting, CERN, 29-30 April 2002 Børge Svane Nielsen, NBI 17
How obtain ’absolute’ positions?How obtain ’absolute’ positions?
What is known precisely and ’absolutely’? (100-200 m ?) central electrode z position pad plane z and gating wire z and x/y position special effort: measure beams near inner cylinder for beams close to end-plate with TPC in horizontal position before installation of IROCs
Well measured relative to each other (100 m, 0.05 mrad): internal angles in micro-mirror bundles micro-mirror bundles in support rings bundle support rings in uninstalled rods
Probably needs ’internal alignment’ and iterations: precise position and angles of beams far from end-plates everything that may move due to twists of cylinders, rods etc.
Less well measured or prone to move (500 m, 0.2 mrad): rod positions relative to ROCs, central electrode and ALICE x,y,z