T.M.Jayasekera B Sc. Eng, C Eng, MBA,FIE,FIM,FCIWEM,MICE,MSLIM,MSLITAD National Consultant
description
Transcript of T.M.Jayasekera B Sc. Eng, C Eng, MBA,FIE,FIM,FCIWEM,MICE,MSLIM,MSLITAD National Consultant
T.M.Jayasekera T.M.Jayasekera B Sc. Eng, C Eng, B Sc. Eng, C Eng, MBA,FIE,FIM,FCIWEM,MICE,MSLIM,MSLITADMBA,FIE,FIM,FCIWEM,MICE,MSLIM,MSLITAD
National Consultant National Consultant
UNDP TA on Strengthening Plan UNDP TA on Strengthening Plan Implementation CapabilityImplementation Capability
Ministry of Plan Implementation .Ministry of Plan Implementation .
Results Based Results Based Monitoring and Monitoring and
Evaluation SystemEvaluation System
Challenges Confronting Society in 21st Century
Development Challenges
Alternatives Programmes designed
to attack the problems
Social Challenges
Poverty, Hunger, Mal-nutrition, Child Mortality,
Maternal Mortality, Degrading Environment
Braking families increasing crimes Drug abuse,
child and spouse abuse, teenage pregnancy
Scarce Resource – Tough Choices :- Cancel some programmes to continue others
Programmes Evaluation
What is Working
Poorly
What is more
effective
What is Working
Well
What is less
effective
Traditional Project Monitoring System to Traditional Project Monitoring System to speed-up Implementationspeed-up Implementation
Implementation Implementation Failures Failures Low Foreign Aid DisbursementLow Foreign Aid Disbursement
Disbursement RatioDisbursement Ratio Sri LankaSri Lanka 13.12%13.12% (Target 20%)(Target 20%) China China 29.82%29.82% ThailandThailand 37.14%37.14% VietnamVietnam 17.87% (ADB 2004)17.87% (ADB 2004)
Sick Projects/Sick Projects/ Problems ProjectsProblems Projects Time OverrunTime Overrun Loan Cancellations Loan Cancellations
Monitorable Work Plan with Financial / Physical targetMonitorable Work Plan with Financial / Physical target Monitor Financial and Physical Progress (formats)Monitor Financial and Physical Progress (formats) Identify short falls / Gaps – issues – Remedial Action.Identify short falls / Gaps – issues – Remedial Action. Early warning Signal – AlertsEarly warning Signal – Alerts M&E Mechanism – LM Meetings – Back to Office Report – PMCM&E Mechanism – LM Meetings – Back to Office Report – PMC Foreign Aid Utilization – 2003 – 14%Foreign Aid Utilization – 2003 – 14% 2004 – 20%2004 – 20%
Implementation Progress Implementation Progress alone not sufficient:alone not sufficient:
Project Failures and Project Failures and Declining “Results”Declining “Results”
PS47%
GS44%
US9%
US PS GS
ADB Projects 2004
Concept of RBME Concept of RBME Tracks performance of a Tracks performance of a
projects based onprojects based onImplementation Progress Implementation Progress
(Physical / financial)(Physical / financial)Development Objectives Development Objectives
(Benefits / effects and Impacts)(Benefits / effects and Impacts)
Implementation ProgressImplementation Progress may may not necessarily lead to not necessarily lead to satisfactory achievement of satisfactory achievement of development objectives development objectives
Results Management CultureResults Management Culture
Input Outputs ImpactEffect
The Logical FrameworkThe Logical FrameworkLFA is an analytical tool forLFA is an analytical tool for objective oriented project objective oriented project planning and managementplanning and management including Monitoring and including Monitoring and Evaluation. It is a way of structuring the main elements of Evaluation. It is a way of structuring the main elements of a project, highlighting logical linkages between inputs, a project, highlighting logical linkages between inputs, planned activities and expected results. In the planned activities and expected results. In the development processdevelopment processIf the inputs are available then activities will take place.If the inputs are available then activities will take place.If activities take place then the outputs would be If activities take place then the outputs would be produced. produced. If the outputs are produced then the purpose will be If the outputs are produced then the purpose will be achieved.achieved.If purpose is achieved, it will contribute to the fulfillment If purpose is achieved, it will contribute to the fulfillment of goal.of goal.
Input Activities Output Purpose Goal
Input Outputs GoalPurpose
MenMaternalMoneyManagement
Rehabilitation of Tanks, canals, Sluice gates and distribution channels
Functional Irrigation Scheme
Increased AcreageCropping IntensifyAccess to water
Increased ProductionIncreased EmploymentImproved Living standard
Activities
Implementation Results
Project LogicProject Logic
The model describes as to how these The model describes as to how these activities could conceivably achieve activities could conceivably achieve the stated goals and objectives the stated goals and objectives (Results Chain)(Results Chain)
A specification of what must be done A specification of what must be done to achieve the desired goals.to achieve the desired goals.
Programme model conveys the Programme model conveys the linkages between program goals and linkages between program goals and objectives and progrmme action. i.e. objectives and progrmme action. i.e. establishes the link between the establishes the link between the problem and the programme.problem and the programme.
Programme Theory
Input Outputs ImpactsOutcome
Water pipesTaps Advice etc.
Installation of pipes. training, involving women community management
20 water taps installed; 10000 safe gallons p.a.
Water borne diseases reducedLess diarrheaMore time available to women
Improved living conditions to womenImproved health situation
Activities
Water Supply Project
Programme TheoryProgramme Theory
Log Frame Matrix IntroductionLog Frame Matrix Introduction
The Log Frame provides a one-page summary of:The Log Frame provides a one-page summary of:
WHYWHY a project is carried outa project is carried out
WHATWHAT the project is expected to achievethe project is expected to achieve
HOWHOW the project is going to achieve these resultsthe project is going to achieve these results
WHICHWHICH external factors are crucial for the success of the external factors are crucial for the success of the projectproject
HOWHOW we can assess the success of the projectwe can assess the success of the project
WHEREWHERE we find the data required to assess the success we find the data required to assess the success of the projectof the project
WHATWHAT the project will costthe project will cost
THE LOGICAL FRAMEWORKTHE LOGICAL FRAMEWORK
- Tool for better Project Cycle Management- Tool for better Project Cycle Management
EVALUATIONDESIGN/
APPRAISALLOG FRAME
IMPLEMENTATION AND MONITORING
IDENTIFICATION
Goal Purpose
Outputs Activities
Outputs Activities
Goal Purpose
Project Planning Matrix / Logical Framework MatrixProject Planning Matrix / Logical Framework Matrix
Note 1 : Emphasis on developing performance indicators
Note 2 : The Project Management should be able to guarantee the project outputs. The immediate objective is beyond their direct control
Hierarchy of Objective
Verifiable Indicators
Means of Verification
Important Assumptions
GOAL Measuring the achievement of the GOAL
PURPOSE Measuring the achievement of the PURPOSE
OUTPUTS Measuring the achievement of the OUTPUTS
INPUTS Summary of the project inputs: COSTS AND RESOURCES
Definition and TerminologyDefinition and Terminology
Input - Resources (Men, Material, Money, Management)
Output - Physical accomplishment that the project management should be able to guarantee.
Purpose - The immediate objective or effect which is expected to be achieved as the result of the project
Goal - The ultimate (long term) overall objective of the project
OVI - Set of criteria's, indicators or measures to verify achievement of objectives at different levels.
This includes direct or proxy (indirect) indicators. Objectively verifiable means, different independent observers would come to the same conclusion as to the status of achievement.
LFA Contd..LFA Contd..
MOV - The means, methods and sources which permit OVI to be measured in precise term.
Assumption- These are important events, conditions decisions that must exist if the project is to succeed but which are
outside the direct control of the project management. These are linked to different levels in the project planning matrix
Log Frame : Vertical LogicLog Frame : Vertical Logic
Overall Overall GoalGoal
AssumptioAssumptionsns
Vertical Vertical LogicLogic
Project Project PurposePurpose
AssumptioAssumptionsns
Results/ Results/ OutputsOutputs
AssumptioAssumptionsns
ActivitieActivities/ s/ InputsInputs
AssumptioAssumptionsns
Log Frame : Horizontal LogicLog Frame : Horizontal Logic
Overall Overall
GoalGoalIndicatorIndicator Means of Means of
verificationverification
Horizontal Horizontal LogicLogic
Project Project PurposePurpose
IndicatorIndicator Means of Means of verificationverification
Results/ Results/ OutputsOutputs
IndicatorIndicator Means of Means of verificationverification
Activities/ Activities/ InputsInputs
Specification of inputsSpecification of inputs
Basic StructureBasic Structurea.a. Vertical LogicVertical Logicb.b. Horizontal LogicHorizontal Logic
Vertical LogicVertical Logic This identifies what project intends to do, clarifies the logical This identifies what project intends to do, clarifies the logical linkages between means and ends, and specifies uncertainties linkages between means and ends, and specifies uncertainties concerning the project. The elements of vertical logic areconcerning the project. The elements of vertical logic are
1.1. Hierarchy of project objectives:Hierarchy of project objectives:Input, output and purpose are specific to project, while Input, output and purpose are specific to project, while higher level-Goal-relates the project to the programme higher level-Goal-relates the project to the programme
of which project is a partof which project is a part
2.2. Casual linkages within the hierarchy:Casual linkages within the hierarchy:Means-end relationship.Means-end relationship.IF inputs are provided THEN output will be IF inputs are provided THEN output will be
produced……..produced……..
3.3. Important Assumptions:Important Assumptions:
-- Assumption at each level are linked to different levels Assumption at each level are linked to different levels in the in the LFM.LFM.
““IFIF the planed outputs are proceed the planed outputs are proceed and IFand IF the the important assumptions are valid important assumptions are valid THEN THEN
the project the project purpose will be achieved”purpose will be achieved”
-- Assumptions are weighted according to importance Assumptions are weighted according to importance and and probability.probability.
4.4. The notion of hypothesis:The notion of hypothesis:
-- Success at each lower level of vertical logic does not Success at each lower level of vertical logic does not guarantee success at ultimate Goal level. guarantee success at ultimate Goal level.
THE LOGICAL FRAMEWORKTHE LOGICAL FRAMEWORKImportant Assumptions:Important Assumptions:
Describe the external risks to the Describe the external risks to the projectproject
Key points:Key points: Both the criticality and probability of assumptions Both the criticality and probability of assumptions
should be assessed.should be assessed. Risks should, as far as possible be ‘internalized’ by Risks should, as far as possible be ‘internalized’ by
redesigning the project. This leads to stronger projects.redesigning the project. This leads to stronger projects.
Narrative Summary
Verifiable Indicators
Means of Verification
Important Assumptions
GOAL Assumptions about external factors for sustaining the benefits of the project.
PURPOSE Assumptions about external factors for achieving the GOAL.
OUTPUTS Assumptions about external factors for achieving the PURPOSE.
ACTIVITIES Assumptions about external factors for achieving the OUTPUTS
The Logical FrameworkThe Logical Framework
CAUSE AND EFFECT RELATIONSHIPSCAUSE AND EFFECT RELATIONSHIPS
Goal
Purpose
Outputs .
Activities
.
Assumptions
Assumptions
.
Assumptions
.
1 4
Assessment of AssumptionsAssessment of Assumptions1st Questions: “Is the assumption important1st Questions: “Is the assumption important
Yes No Don’t include this oneDon’t include this one
2nd Question: “How likely will it occur”2nd Question: “How likely will it occur”
Not likely
Almost certain
Quite likely
Don’t include this one eitherDon’t include this one either
Put this assumption into your Project Planning MatrixPut this assumption into your Project Planning Matrix
Project Management mustProject Management mustmonitor it andmonitor it andif possible influence itif possible influence it
3rd Questions: “Can the project be re-designed”3rd Questions: “Can the project be re-designed”
Yes
No
Redesign project!Redesign project!
Plan activities to influence assumptionsPlan activities to influence assumptions
Killer assumption!Killer assumption!
Warn decision makers!Warn decision makers!
Stop!Stop!
Horizontal LogicHorizontal Logic“ “ The objective of the horizontal logic is the The objective of the horizontal logic is the MEASUREMENT of the resources and results of a project, MEASUREMENT of the resources and results of a project, through OVI and MOV” (CIDA)through OVI and MOV” (CIDA)
1.1. Objectively Verifiable IndicatorObjectively Verifiable Indicator-- Measures (direct or Indirect) to verify to what extent Measures (direct or Indirect) to verify to what extent Input, Input, Output, Purpose and Goal is achieved. (Input Output, Purpose and Goal is achieved. (Input indicators, Output indicators, Purpose indicators, Goal indicators, Output indicators, Purpose indicators, Goal indicators) indicators)
-- Measurement can beMeasurement can beQuantitative (e.g. Km of road rehabilitation)Quantitative (e.g. Km of road rehabilitation)Qualitative (e.g. Farmers cooperative functioning Qualitative (e.g. Farmers cooperative functioning
effectively)effectively)Behavioral (e.g Increased use of sanitary facilities)Behavioral (e.g Increased use of sanitary facilities)
Qualitative indicators should be made measurable.Qualitative indicators should be made measurable.
-- Direct indicators should be supplemented Direct indicators should be supplemented by by indirect (proxy) indicators (e.g. indirect indirect (proxy) indicators (e.g. indirect wealth wealth indicator may be indicator may be quality of house quality of house construction construction materials, ownership of materials, ownership of bicycles/radio)bicycles/radio)
-- Properties of Goal indicatorProperties of Goal indicator
Specific Specific Measurable Measurable AchievableAchievableRealisticRealisticTime-boundTime-bound
2. Means of Verification (MOV)2. Means of Verification (MOV)
Secondary Education Improvement Secondary Education Improvement ProjectProject
Goal (Impact)
Purpose (Effect)
Outputs .
Inputs .Imp
lem
enta
tion
Res
ult
s
• Improved literacy rate• Employable workforce -
Absorption rate by Industries
• Increased enrolment rate• Less Dropout rate• Improved quality of teaching –
students pass rate
• No of teachers trained• No of text books supplied• Curriculum Development – No of
modules completed• No. of school buildings constructed • Facilities (computers, drinking
water, toilets, electricity)
• Funds spent
Key Performance Key Performance IndicatorsIndicators
QualitiesQualities S – Specific S – Specific M – MeasurableM – Measurable A – Achievable A – Achievable R – RealisticR – Realistic T – Time boundT – Time bound
Setting KPIs Setting KPIs
Baseline Indicator
Level
Desired Level of Improvement (Intervention)
Target Performance
Benchmark =
Issues and ChallengesIssues and Challenges
LFA be incorporated into design stage of the Project
Unintended effects and impacts not covered in the LFA
Highly optimistic performance target setting is dangerous as it would finally lead to rating of a good project as a failure
Indicators developed may necessitate the conduct of field surveys which are time consuming and costly.
Hierarchy of Hierarchy of ObjectivesObjectives
ObjectivelyObjectively
Verifiable IndicatorsVerifiable IndicatorsKey Key
AssumptionsAssumptions
GoalsGoals Reduce poverty in Reduce poverty in
rural area rural area Reduce pressure on Reduce pressure on
coastal fisheries coastal fisheries
ResourcesResources
8000 beneficiaries should increase 8000 beneficiaries should increase
income above poverty line.income above poverty line. Percentage of borrowers below Percentage of borrowers below
poverty line declined from 30% to poverty line declined from 30% to
19%19% No of new off-shore employmentNo of new off-shore employment
Supportive Supportive Government Government policy policy EnvironmentEnvironment
PurposePurpose Promote non-Promote non-fishing fishing
income generating income generating
activities and activities and
establishment of establishment of
entrepreneurial entrepreneurial culture culture
Number of viable micro-Number of viable micro-enterprises enterprises
established established Recovery RateRecovery Rate Number of additional workers Number of additional workers
employed per enterprises employed per enterprises Cost per job generated Cost per job generated
Fishermen are Fishermen are willing to give willing to give up traditional up traditional fishing fishing activitiesactivities
Availability of Availability of extension extension servicesservices
OutputOutput Provision of credit Provision of credit of of
Rs.400 ml to 8000 Rs.400 ml to 8000
micro enterprises micro enterprises
through PCIs and through PCIs and
accredited NGOsaccredited NGOs
Number of micro enterprises Number of micro enterprises financed financed Sector- wise and PCI wise loan Sector- wise and PCI wise loan
disbursement disbursement Average sub-loan size per PCI and Average sub-loan size per PCI and
male female participationmale female participation Percentage of borrowers without Percentage of borrowers without
previous borrowing experience previous borrowing experience
Banks are Banks are flexible to flexible to grant loans on grant loans on character character reference reference rather than rather than collateral’s collateral’s
Logical Framework Analysis