14th Australian Tunnelling Conference
Tim Parker | Project Director City & Southwest | Sydney Metro
![Page 2: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/2.jpg)
Overview
1. Introduction and Context
2. Sydney Metro Overview
3. Northwest update
4. City & Southwest tunnelling
5. Q&A
![Page 3: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/3.jpg)
More than 65 km
31 metro railway stations
Two stages
Northwest 15 km new twin
tunnel
City & Southwest 16 km new
twin tunnel
![Page 4: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/4.jpg)
Sydney Metro Benefits
![Page 5: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/5.jpg)
Customer Experience
![Page 6: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/6.jpg)
Sydney Metro
Stage 1 – 36km
Open first half of 2019
8 new stations; 5 upgraded
4,000 car spaces
![Page 7: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/7.jpg)
Cudgegong
Tunnels & Station Civil (TSC)
Design & construct Driven tunnels, station excavation,
ground support
Surface/Viaduct Civil (SVC)
Epping Bella Vista Cudgegong
Epping Bella Vista Chatswood
Design & construct Surface civil infrastructure (including viaduct), Bella
Vista to Cudgegong
Epping to Chatswood Rail Link (ECRL) existing infrastructure interface
Operations, Trains & Systems (OTS) PPP Partially privately financed (with substantial State contribution)
Deliver railway systems (new and upgraded), trains, stations & precincts Operate services & stations, maintain all assets
Early Civil Works by TfNSW
Chatswood
Epping to Chatswood Rail Link (ECRL) enabling works by TfNSW
Integration Activities by TfNSW
Sydney Metro Northwest delivery
![Page 8: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/8.jpg)
Sydney Metro Northwest
Industry participants – sectors and countries
![Page 9: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/9.jpg)
Tunnelling (TSC)
![Page 10: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/10.jpg)
Tunnelling
More than 2.5 million tonnes of rock excavated
100% crushed rock recycled
98,184 concrete segments
![Page 11: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/11.jpg)
98,184 concrete segments
16,290 waterproof rings
More than 3,600 tonnes of cement
18 months, 635,000 working hours
Tunnelling (TSC) – Pre-cast Facility
Site was demobilised as of March 2016
![Page 12: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/12.jpg)
State of the art launch gantries
from Dubai
Gantries to lift segments into
place – enabling main arterial
roads to remain open during
construction
121 piers
1,200 segments
124 spans
Skytrain - SVC
![Page 13: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/13.jpg)
![Page 14: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/14.jpg)
Sydney Metro: City & Southwest
Chatswood to Sydenham EIS exhibition Q2
2016
Start construction 2017
Start major contract procurement Q3- Q4 2016
Sydenham to Bankstown EIS exhibition 2017
First TBM 2018
Operations 2024
![Page 15: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/15.jpg)
Metro Alignment Design - Theoretical
Stations equally spaced
Slight vertical between each station
Tunnels are in parallel
Straight alignment – no curves
If curves – long radius
![Page 16: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/16.jpg)
Metro Alignment Design - Reality
Natural constraints
– Geotechnical condition
– Land levels
Station locations
– Customer based
– Land availability
![Page 17: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/17.jpg)
Natural Constraints
Geotechnical Investigation
Harbour Crossing
Other tunnels
![Page 18: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/18.jpg)
Ground Investigation CBD
Stage 1
– 26 Land boreholes
– 22 Marine boreholes
– 30 Cone Penetration Testing (CPT)
Stage 2
City
– 29 Boreholes
– 13 CPT
– 10 test pits
Southwest
– 128 investigation holes
![Page 19: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/19.jpg)
Ground Investigation Harbor
Planned
• Geophysics
• Diamond coring + Standard Penetration Test (SPT)
• In-situ stress testing
Additional
• CPT testing
• Denison Sediment sampling
• Upper sediment testing
• Further Geophysics
• Seismic
• Borehole tomography
• Resistivity
![Page 20: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/20.jpg)
Natural Constraints
![Page 21: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/21.jpg)
Geology
![Page 22: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/22.jpg)
Underground Constraints
Other tunnels
Maximum gradients
Underground stations – Passenger focused
Utilities
Rock anchors
![Page 23: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/23.jpg)
Artist’s impression of Martin Place Interchange
![Page 24: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/24.jpg)
![Page 25: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/25.jpg)
Harbour Crossing Alignment
Option 1 – Rock TBM
Deep sediments
Option 2 – Soft ground TBM
Option 3 – Shallow IMT
![Page 26: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/26.jpg)
Harbour Crossing Alignment
![Page 27: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/27.jpg)
Metro Alignment Design Reality
![Page 28: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/28.jpg)
Metro Alignment Design Reality
![Page 29: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/29.jpg)
Contracting strategy – City & Southwest
![Page 30: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/30.jpg)
Reference
Tunnelling
Strategy
![Page 31: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/31.jpg)
Harbour – Ground Treatment
![Page 32: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/32.jpg)
TSE Procurement Strategy
• Progressive Industry Engagement
• Early Release of Design and Investigation Results
• Expression of Interest to respond to Technical Aspects
• Intensive Interactive Tender Process
![Page 33: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/33.jpg)
TSE
Currently out to tender
Two consortia shortlisted and invited to tender
– The John Holland CPB Ghella Joint Venture, made up of John
Holland Pty Ltd, CPB Contractors Pty Ltd and Ghella Pty Ltd
&
– The Ferrovial, Acciona Ltd and BAM Joint Venture, made up of
Ferrovial Agroman (Australia) Pty Ltd, Acciona Infrastructure
Australia Pty Ltd and BAM International Australia Pty Ltd
Tender closes at the end of the year
Tender will be awarded in mid 2017
![Page 34: Tim Parker - Transport for NSW](https://reader031.fdocuments.in/reader031/viewer/2022012313/58a458bd1a28ab55068b671d/html5/thumbnails/34.jpg)
Thank you