The views expressed during this presentation do not necessarily reflect the views of KYTC.

This message is intended only for the use of the individual or entity to which it is addressed and may contain confidential information that is legally privileged and exempt from disclosure under applicable law.  If the reader of this message is not the intended recipient, you are notified that any dissemination, distribution or copying of this communication is strictly prohibited.  If you have received this communication in error, please notify this office by telephone and return this message to the original sender.  Under Kentucky Rule of Evidence 503 this communication is confidential and not intended to be disclosed to third persons other than those to whom disclosure is made in furtherance of the rendition of professional legal services to the client, Kentucky Transportation Cabinet.  

Legal Disclaimer

Page 3: Things to look for and remember while preparing FD05 Estimates.

Go to the Maintenance Intranet page

http://transportation.ky.gov/Maintenance/Pages/Intranet/Roadway-Preservation.aspx

Drive the Project

Where to Start

Page 4: Things to look for and remember while preparing FD05 Estimates.

Print out a copy of the estimate sheet and summary sheets (most current version).

Make sure you have a measuring wheel.

Take your updated Route Log.

Has your DMI been calibrated recently?

Before You Hit the Road

Page 5: Things to look for and remember while preparing FD05 Estimates.

Measure the width in several locations per mile.

Don’t measure in curves, at mailboxes, or at entrances.

Note changes in Typical Section.

Drive the Project

Page 6: Things to look for and remember while preparing FD05 Estimates.

Is there striping? Centerline, Edgelines, etc.

Are there manholes, and who are the owners?

Are there pavement markers to be removed?Only replace on Interstates, Parkways, and

TWLTL’s

Are there bridges or culverts?Check with bridge section.

Things to look for

Page 7: Things to look for and remember while preparing FD05 Estimates.

What types of shoulders are there?Are there drop-off that need correctingCan it be paved monolithic or separate

pavement wedge?

Is there curb and gutter?

Are there any RR Crossings?

Are there ADA compliant sidewalk ramps?

Things to look for

Page 8: Things to look for and remember while preparing FD05 Estimates.

Does the project have thermo to be replaced?Include quantities on summary sheets.

Are there traffic or planning loops affected?Include quantities on summary sheets.

Are there base failures that need repaired?Include quantities on summary sheets.

Things to look for

Page 9: Things to look for and remember while preparing FD05 Estimates.

How do you know if it’s a base failure?

Deep crackingRutting / pumpingWater / mud coming out of cracksUsually located near edge of pavement

Base Failures

Page 10: Things to look for and remember while preparing FD05 Estimates.

Used to correct out of section pavement.Correcting cross slopes, dips, etc.

Not a Scratch Course.

How much do you need?

Level and Wedging

Page 11: Things to look for and remember while preparing FD05 Estimates.

Ride the project

Visual survey

Usually calculated as a percentage of surface quantity.

Calculating Leveling and Wedging

Page 12: Things to look for and remember while preparing FD05 Estimates.

If the route needs more than 50% leveling and wedging, consider milling the entire route.

Helps to reduce pavement edge drop-offs.

Corrects existing rutting.

Re-defines pavement section.

How much is too much

Page 13: Things to look for and remember while preparing FD05 Estimates.

At Bridge ends and RR crossings.Usually 100 feet per 1 inch.

Curb and Gutter sections

Alternative to leveling and wedging.

Make sure milling depth is appropriate.

Milling

Page 14: Things to look for and remember while preparing FD05 Estimates.

Check intersections to see if needed.

Not for commercial entrances.

Include all bid items.

Is it technically feasible?If not, include documentation and pictures.

Sidewalk / Handicap Ramps

Page 15: Things to look for and remember while preparing FD05 Estimates.

Input project data into estimate program.

Check all quantities for errors.

Verify pavement type against Warrants.

Pavement depth1.0”, 1.25” or 1.5” (District 1, 2, 3 only or SMA)

Back in the Office

Page 16: Things to look for and remember while preparing FD05 Estimates.

Complete typical sectionsOne typical for each pavement section.Use common sense.

Show detailsPavement typeDepthType of shouldersMilling if required

Typical Section

Page 17: Things to look for and remember while preparing FD05 Estimates.

What type is needed for this project?

Will night work or restricted hours be needed?

Are there dates where no lane closures will be allowed?Holidays, festivals, etc.

Will it be a significant project?Include Public Information Plan.Complete documents for TMP.

Traffic Control Plan

Page 18: Things to look for and remember while preparing FD05 Estimates.

Check Wheeler’s “commonly made mistakes” email.Did you need flashing arrows or message

boards?

Did you include Fuel and Asphalt adjustments?

Use comments section.

Don’t forget!

Page 19: Things to look for and remember while preparing FD05 Estimates.

Use Traffic Engineer to help with Thermo and Loop quantities and locations.

Check with Permits, Project Development, and HSIP Coordinator for conflicting projects.

Check with Bridge section if bridges are on the project.

Did you include all applicable notes?

Things to Remember

Page 20: Things to look for and remember while preparing FD05 Estimates.

Did you miss anything?

See it from a contractor’s view?

What will the inspector see?

Is there anything unexpected that you may have missed?

Drive the project again

Page 21: Things to look for and remember while preparing FD05 Estimates.

Questions???