Thermal GEM assumptions Erwan Hemery 12 May 2009.
-
Upload
karin-murphy -
Category
Documents
-
view
217 -
download
0
Transcript of Thermal GEM assumptions Erwan Hemery 12 May 2009.
Thermal GEM assumptions
Erwan Hemery
12 May 2009
Number of peakers available• Before: 15 peakers - 10 diesel and 5 gas, total capacity = 2500 MW• Now: 37 peakers - 24 diesel and 13 gas, total capacity = 2960 MW
Engine capex and HR• The capex decreases with the installed capacity and the capex increases with the efficiency – intercool system 15-20% more expensive
Turbine OCGT
y = 2235.3x-0.2882
R2 = 0.9907
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0 50 100 150 200 250 300MW
US
$/kW
Reference: GTW handbook 2009
Heatrate OCGT
y = -20.051x + 9875.2
R2 = 0.6193
y = -4.5392x + 9849.3
R2 = 0.8103
4000
5000
6000
7000
8000
9000
10000
11000
0 50 100 150 200MW
HR
(G
J/G
Wh)
Peakers details
Gas peakers
Diesel peakers
• Assumptions: 80 % of the total cost is exposed to foreign currency• e.g. LMS100 US$709/kW at exchange of 0.8 = NZ$886/kW + 20% for local cost = NZ$1063/kW
at exchange of 0.5 = NZ$1418/kW + 20% for local cost = NZ$1701/kW
Name GE frame 6BCapacity (MW) 40Heatrate (GJ/GWh) 9667F. costs (US$/kW) 772
Name GE LM6000 PC SprintCapacity (MW) 50Heatrate (GJ/GWh) 8872F. costs (US$/kW) 866
Name LMS100Capacity (MW) 100Heatrate (GJ/GWh) 7870F. costs (US$/kW) 709
Name SGT5 2000ECapacity (MW) 160Heatrate (GJ/GWh) 10366F. costs (US$/kW) 518
Location: Marsden, Otahuhu, Huntly, Port Maunganui, Whirinaki, New Plymouth, Gracefield and Islington.
Location: Stratford, Southdown, Otahuhu, and Huntly.
Peakers O&M costs
Variable ($/MWh) Fixed ($/kW)BeforeDiesel 4.25 40Gas 40 50NowDiesel 12 14Gas 7 13
• Average is presented above but fixed and variable O&M would differ between engine size and type (decrease vs capacity and more expensive for diesel engine)• For the gas engine an extra $2/GJ is added on the top of the gas price to reflect gas flexibility
CCGT
Turbine CCGT
y = 1933.6x-0.1968
R2 = 0.9985
0
200
400
600
800
1000
1200
0 200 400 600 800 1000MW
US
$/kW
Heatrate CCGT
y = -0.7923x + 6846.6
R2 = 0.2128y = -1.4259x + 6747.4
R2 = 0.5774
4000
5000
6000
7000
8000
0 200 400 600 800 1000 1200MW
HR
(G
J/G
Wh)
Reference: GTW handbook 2009 and GE website
CCGT details
Name S206FACapacity (MW) 240Heatrate (GJ/GWh) 6400F. costs (US$/kW) 660
Name MS9001FACapacity (MW) 380Heatrate (GJ/GWh) 6200F. costs (US$/kW) 600
Name SCC5-4000FCapacity (MW) 420Heatrate (GJ/GWh) 6150F. costs (US$/kW) 590
• Assumptions: 80 % of the total cost is exposed to foreign currency• e.g. US$600/kW at exchange of 0.5 = NZ$1200/kW + 20% for local cost = NZ$1440/kW
Coal
O&M costs
0
20
40
60
80
100
120
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Plant #
US
$/kW
CCGT
Coal
Average CCGT
Average Coal
Current GEM ass. Gas
Current GEM ass. Coal
Assuming exchange rate of 0.6 for the triangles
• O&M coal should be ~$100/kW instead of $40/kW• Adjust Coal/Lignite capex price as the CCGT capex has been changed : roughly 2.33 times more expensive than CCGT (~ $NZ 3300/kW)
Coal and Lignite HR
• HR values in GEM average at 10,000 GJ/GWh (36 %)…this is true for existing subcritical (180 bar, 540 oC)• New subcritical coal plant with conventional environmental controls operate closer to 39% efficiency• Supercrital steam-cycle (240 bar, 570 oC) have become the system of choice in Europe and USA and have efficiency in the range of 42% to 45%.• IGCC and ultra-supercritical plants could have 50% efficiency
Coal HR in GEM: 8600 GJ/GWh (42 %)Lignite HR in GEM: 9300 GJ/GWh (39 %)
CCS
• Before we had a gain in efficiency but that’s the opposite there is a loss in efficiency caused by the capturing ~ 10% less then a standard Coal• CCS cost has been set to twice the price of standard coal (IEA,2006) – cheaper in the future?• Calculation shows that CCS break even with Coal at a carbon charge of $110/t (good agreement with IEA).• IEA says in the future break even could be at ~$NZ 90/t roughly equivalent to a 10% decrease of capex• …in the base case ($75/t) we need to drop the capex by 25% to built CCS instead of Coal or set the carbon charge higher (do we want Coal generation in the TTER base case?)• CCS has been set to $US 2800/kW
Pipeline costs
• Rough calculation to add an extra concost to the gas fired station depending on their location (steady state isothermal gas flow model)• Sfd and Hly no gas concost• Swn, Ota and hpi required gas concost• Set all the potential CCGT and OCGT to max offtake and remove the constraint – get the diameter and the total cost (based on ITL costs estimate)• Need to extent the Maui pipeline (750 mm) to Ota.• Split the total cost (fraction of the volume used for each power station) for the 1st 80 km• For hpi an extra 40 km of 350 mm pipeline is required and half of the cost goes to 240 MW Rodney 1 and 240 MW Rodney 2.
CCCT $m 20-30OCGT $m 8-15