The State Hospitals Board for Scotland - PAMS... · (P)AMS and associated assets annually through...
Transcript of The State Hospitals Board for Scotland - PAMS... · (P)AMS and associated assets annually through...
The State Hospitals Board for Scotland
Property and Asset Management Strategy 2015 – 2020
Page 2
Contents:
1 Executive Summary
1.1 The Purpose of the State Hospital Property and Asset Management Strategy (P)AMS
1.2 The State Hospitals Board for Scotland
1.3 Other Assets and Investment
1.4 The State Hospital (P)AMS
1.5 Organisational Strategies
1.6 Governance and Performance Management
1.7 Current Status and Issues
2 Where are we?
2.1 Strategic context & The State Hospital Property and Asset Management Strategy
2.2 The State Hospitals Board for Scotland
2.3 Property and Asset Management Structures and Governance
2.3.1 Accountability Arrangements 2.3.2 (P)AMS Production Process
2.3.3 Information systems
2.3.4 Assurance Statement
2.4 The assets and the issues
2.4.1 Land
2.4.2 Buildings and property
2.4.3 Site layout
2.4.3.1 Office Accommodation
2.4.3.2 Service changes
2.4.4 Vehicles
2.4.5 Security Equipment
2.4.6 eHealth and IM&T 2.4.7 Medical Equipment
2.4.8 Total Assets
2.4.9 Backlog Maintenance
2.4.10 Changes to SCART (Statutory Compliance and Risk Tool)
2.4.11 Planned Preventative Maintenance (PPM) and Reactive Maintenance 2.4.12 Sustainability, Energy and the Environment
2.4.13 Fire Risk Assessments and Emergency Preparedness
2.4.14 Workforce plan
3 Where do we want to be?
3.1 Significant National or Local plans, Key targets and Deliverables
3.2 Possible changes to need or to associated services
3.3 Consultation and Engagement
3.4 Risks and Challenges
4 How do we get there?
4.1 Projects and plans; costs, procurement, benefits, project lead and risks.
4.1.1 Minor planned or possible investment (to be managed within normal capital / revenue allocation):
4.1.2 Significant planned or possible investment (requiring additional funding):
4.1.3 Other Work Streams
4.2 Affordability
5 Appendices
Appendix 1: National Asset and Facilities Performance Framework
Appendix 2: Estates and Asset Management System high level Board report
Page 3
1 Executive Summary
1.1 The purpose of the State Hospital’s Property and Asset Management Strategy ((P)AMS) The NHSS requires that each Health Board submit an annually reviewed Property and Asset Management Strategy covering the coming 5 – 10 years. The (P)AMS should meet defined criteria demonstrating that investments are:
Carefully considered and planned
Contributing to organisational aims
Used effectively and efficiently
Monitored and maintained appropriately
Decommissioned, disposed of & replaced effectively and efficiently 1.2 The State Hospitals Board for Scotland The State Hospitals Board for Scotland is a special health board proving high security mental
health care for Scotland and Northern Ireland. It occupies a single site of approximately 65Ha. It
has 140 beds and approximately 700 staff. A major rebuild of The State Hospital completed in
2012; 90% of the site is less than 7 years old, with the remaining 10% refurbished.
Its buildings include patient accommodation, off ward therapy areas, offices, carer’s facilities,
security buildings and estates buildings. In addition its other assets include IM&T, Estates and
Security equipment and infrastructure. The value of the organisations assets is £63m.
1.3 Other Assets and Investment
Uniquely, a high proportion of the hospitals assets are related to security; the majority of the
security equipment and infrastructure was replaced or refurbished over the process of
rebuilding. IT is also a significant element of the organisation’s assets. Both areas may require
significant investment over the life of this (P)AMS as high value assets approach end of life.
Work is underway to scope the extent of the requirements.
Page 4
1.4 The State Hospital (P)AMS
The State Hospital (P)AMS includes consideration of assets in the following categories:
Land
Buildings
Security Equipment and Infrastructure
Medical Equipment
Estates Equipment and Infrastructure
IM&T Hardware and Infrastructure
Vehicles
And gives further consideration of
Service Changes
Sustainability
Backlog maintenance requirements
1.5 Organisational Strategies The Hospital’s strategy is described by The State Hospitals Local Delivery Plan (LDP). The LDP is the State Hospital’s description of how it will achieve the key deliverables of the Route Map to the 2020 Vision for Health and Social Care. Through compliance with The Asset Management Policy for NHSScotland, the State Hospital (P)AMS will in turn ensure that the strategic aims are supported by the performance management, maintenance and replacement of assets as required. 1.6 Governance & Performance Management The condition & performance of the hospitals assets is undertaken through a range of information systems including the Estates Asset Management System (EAMS) and the regularly updated asset register. As of this year the Health Facilities Scotland KPI dashboard will be regularly reported to the hospital’s Senior Management Team. Property and asset performance is considered annually by the Boards Audit Committee, and the Annual (P)AMS is reviewed and approved by the State Hospital’s Board.
Page 5
1.7 Current Status and Issues
The majority of the organisation’s asset base is its buildings, all of which have been
replaced or refurbished within the last seven years.
The demand for high security beds remains stable and is likely to continue to remain so,
though the hospital has been able to operate across 11 of its 12 wards for part of the
year.
The national work streams around integration and shared services may have some
impact for the organisation, but is unlikely to impact significantly on assets.
This means that the (P)AMS is primarily focussed on monitoring and maintaining the
condition and performance of those new assets and maintaining or replacing other, more
minor, assets. A range of other important pieces of work are required to support the strategy;
amongst these some key issues are:
Monitoring the assets for changes in the speed of deterioration and the backlog maintenance requirement
Reviewing the future use of the Occupational Health and Management Centre buildings
Setting realistic energy and carbon reduction targets
Monitoring for long term change in demand for beds at The State Hospital and across the Network
Concluding and implementing reviews of vehicles & workforce
Concluding reviews of the secure perimeter and the IM&T network and planning investment and implementation
Continuing to engage with national work on Health and Social Care integration and shared services and monitoring for impact
Taking the opportunity to implement the wind turbine energy project should funding become available
Page 6
2 Where are we now?
2.1 Strategic context & The State Hospital Property and Asset Management Strategy
The National Health Service in Scotland holds assets worth in excess of £5 billion. In order to
ensure effective use and governance of these assets each health board produces and submits
an annual Property and Asset Management Strategy covering the coming 5 – 10 years.
The State Hospital (P)AMS describes how the organisation uses its assets efficiently, safely and
in a way that contributes to health improvement as articulated in the Scottish Governments
2020 vision for high quality health. The (P)AMS does this by examining Where we are now,
looks ahead to Where we want to be and takes cognisance of risks, opportunities and potential
barriers to achieving these aims in How we will get there.
The strategic agenda for healthcare services in Scotland is set by The Healthcare Quality
Strategy for NHSScotland. The Local delivery Plan for The State Hospital details how the
organisation intends to meet the requirements of this strategy and other key strategies.
The strategic aims of the hospital align with the “HEAT” targets of
Health Improvement
Efficiency and Governance Improvements
Access to Services
Treatment appropriate to individuals
And are set within the overall context of the Quality ambitions set out in the NHSScotland
Quality strategy;
Person centred
Safe
Effective
The Asset Management Policy for NHSScotland establishes the policy environment and key
performance indicators for asset management, which include the submission to the Scottish
Government of annually updated asset management strategies. The policy provides a
framework against which the planning, delivery, management and disposal of assets is
undertaken. The framework (The National Asset and Facilities Performance Framework),
provides quality outcomes for assets and facilities that align with the 2020 vision through the
quality outcomes of the quality strategy. The performance framework includes consideration of
the physical environment, statutory compliance, costs, and the (P)AMS. The framework is
shown in full at Appendix 1.
Page 7
2.2 The State Hospitals Board for Scotland
The State Hospitals Board for Scotland is the sole provider of high security mental health care
for adult males in Scotland, also providing the same service for Northern Ireland. It is a Special
Health Board and provides 140 beds, with approximately 700 staff. It occupies a single site in
South Lanarkshire. The hospital was almost totally rebuilt over recent years, with building work
beginning in 2007 and progressing through 3 phases to completion in 2011.
Given that the patients do not have access to other services or communities, the Hospital
redevelopment addressed the clinical model aspiration of ensuring the site, as far as possible,
meets all of the patients needs (e.g. therapeutic, vocational, social, spiritual and physical
wellbeing) via a range of therapeutic, educational, diversional, health and recreational services.
The site configuration and security features mean that the majority of patients are able to access
the grounds and attend therapy departments without requiring escorting staff.
A post project review of the rebuild project has been undertaken this year and concludes that
the rebuild met its overarching targets of cost, time and quality and meets the aspirations of the
organisations clinical model. Positive feedback was received across all areas of the strategic
review, which included clinical effectiveness, safety and security, physical environment, staff,
patients, carers and finance. As would be expected the review identified some lessons to be
learnt with regard to future projects, operational and management matters.
All assets are located at the State Hospitals site (See Figure 1). Figure 1: The State Hospital Location
Page 8
2.3 Property and Asset Management Structures and Governance
The (P)AMS supports the delivery of the clinical and corporate strategies and is approved at Board level. In order to ensure an effective link between the Hospital’s operational activities, planned objectives and national strategy, the (P)AMS Board lead is the Security Director.
The performance of assets is seen as critical by the State Hospitals Board. For the hospital to meet its strategic objectives it is essential that existing and planned investment is targeted and effectively utilised. The Board considers the contribution and performance and risks of the (P)AMS and associated assets annually through reporting to the Board’s Audit Committee and the (P)AMS is approved by The State Hospital’s Board. This includes consideration of the NHSS asset KPIs (Appendix 1). 2.3.1 Accountability Arrangements Operational Management of asset management systems is overseen by The Security Director and relevant stakeholders, particularly the Facilities department. An organisational chart demonstrating accountability arrangements and information systems within the facilities department is at fig 2; Information systems are further explained at section 2.3.2. In addition the Security Director is responsible to the Board for resilience issues and Health and Safety which results in regular informal and formal discussion taking place regarding the state of all assets. The Head of Estates and Facilities attends the Business Continuity Group, Health Safety and Welfare Committee and Infection Control Committee. A full facilities operational organisational chart is at fig 3. Fig 2: Accountability Arrangements
Security Director
Head of Estates & Facilities
Estates Officer Estates Co-ordinator
Responsibilities
3i Estate Asset Management System (EAMS)
3i Fire & Risk Manager
VFA Capital Planning Tool
Statutory Compliance Audit and Risk Tool (SCART)
Corporate Greencode -Environmental Management System (EMS)
Energy Monitoring and Reporting Tool (EMART)
NHS National Services Scotland – Health Facilities Scotland – Estates & Facilities Benchmarking KPI’s
Ofgem – Ongoing Compliance with Renewable Heat Incentive (RHI) and Feed-In Tariff (FiT) obligations
Estates Maintenance Management System, including Planned Preventative Maintenance
Estates elements of Property and Asset Management Strategy ((P)AMS)
All maintenance contracts for the hospital
Control of Contractors
TSH Board
Page 9
Fig 3: Facilities Organisational Chart
Security Director
Head of Estates &
Facilities
Estates Co-
ordinator
(Operational)
Housekeeping &
Linen Services
Manager
Catering Services
Manager
Estates Staff:
Porters (6)
Maintenance Assistants
(7)
Electricians (3)
Fitters (2)
Joiner / Locksmith (1)
Linen & Sewing
Staff (3) Housekeeping
Staff:
Supervisors (3)
Housekeepers (65)
Catering Staff:
Food Production
Supervisor (1)
Cooks (6)
Catering Assistants (8)
Hard FM Soft FM
Estates Officer
(Projects)
Estates
Administrator
Estates Admin
Assistant /
Telephonist
Telephonist / Admin
Assistant (2)
Page 10
2.3.2 (P)AMS Production Process
The (P)AMS is ultimately approved by the State Hospitals Board prior to submission to Scottish
Government via HFS. Prior to Board approval it is scrutinised and approved for submission to
the Board by the Senior Management Team (SMT) of the hospital. The SMT is chaired by the
Chief Executive and includes membership from all clinical and non clinical areas of the hospital.
The Security Director is responsible for production of the PAMS, assisted by Facilities and
Estates staff. The diagram below at figure 4 shows how the (P)AMS is created and approved
with appropriate engagement and inclusion.
Figure 4: (P)AMS creation
SMT &
Board
eHealth Finance
Monitoring &
Performance
Information
Facilities &
Estates
Staff
Draft
(P)AMS
Infection
Control
Comm.
HFS
Security
Director
Staff
Partnership
Forum
Finance
Director
Groups & Committees
Sustainability
Patient Partnership
Health, Safety & Welfare
Business Continuity
Page 11
2.3.3 Information systems
A range of information systems exist to monitor performance and compliance across the estate.
As the amount of data required by these systems increases demands on the Facilities staff also
increase. This is considered further within the Workforce plan section of this document.
Information systems include:
Statutory Compliance and Risk Tool (SCART), Estates and Asset Management
System (EAMS) and Capital Planning Tool
The SCART is a high level tool measuring risk and statutory compliance across all areas
of operations.
The EAMS examines the “6 facets”, which are the recognised standard measurements
for building performance;
Building
Engineering
Statutory compliance
Energy performance
Space utilisation
Quality
And produces a high level report summarising conditions across all of the Boards
buildings (Appendix 2)
An additional EAMS module (Fire and Risk Manager) is now mandatory for Boards and
reports on fire risk management.
The Capital Planning Tool assists with long term planning, considers lifecycle
information, is informed by EAMS data, allows change modelling & must be used to
support any business case.
Environmental Management System (EMS) and Energy Monitoring and Reporting
Tool (EMART)
The Environmental Management System links operations to legislation in order to allow
identification and assessment of risk.
The EMART system monitors weather corrected energy consumption and calculates
carbon emissions against our baseline and highlights variance.
Page 12
Facilities Monitoring System (FMS) and Maintenance Management System (MMS)
The FMS and MMS monitor cleanliness standards and Healthcare Environmental
Inspection issues and how they are being addressed.
Information from these systems populates a Scottish Government NHSS Estates and Facilities
KPIs dashboard. As of the start of 2015 – 2016 this information is also going to be provided to
The State Hospital Management Team. Benchmarking from this information is challenging due
to the unique nature of the State Hospital, but as other organisations refine their information we
may be able to compare our performance with Medium Secure Units or other mental health
facilities.
2.3.4 Assurance Statement
The accountability arrangements and organisational structure ensure that:
Information, control and governance systems are in place
All appropriate authorisation systems are complied with
All relevant legislation is identified, assessed and complied with
All statutory and mandatory policies are in place and complied with
All relevant information is reported through the Boards systems
All of which are regularly assessed and monitored through relevant groups and committees
reporting to the Senior Management Team and Board as appropriate.
2.4 The Assets and the issues
The size of the State Hospital coupled with its function mean that it holds no high value assets
other than the buildings, IT systems and Security systems. Full details of asset values are at
table 8. The hospital also operates a small vehicle fleet. Medical equipment forms an almost
negligible part of the asset base.
The hospital’s major redevelopment project means that 90% of the buildings on site are less
than 7 years old, with remaining buildings refurbished within the same timescale.
The State Hospital holds assets worth approximately £63m. These assets include:
Page 13
2.4.1 Land
The State Hospital owns approximately 69Ha. 35Ha of operational land is contained within the
secure perimeter; another 3Ha of operational land is outside of the secure perimeter and
consists mainly of land immediately adjacent to the secure perimeter and car parking. The
remaining 31Ha has been declared non operational and is the process of being trawled through
Scottish Government for alternative use as part of the process of disposal.
There is no backlog maintenance associated with the surplus land, therefore there will be no
reduction in backlog maintenance once disposal is completed.
Land values are included at table 1.
Table 1: Land values
Asset Description Net Book Value Replacement Cost
East Wing Land – Plot A £164,883 £164,883
East Wind Land – Plot B £52,150 £52,150
East Wing Land – Plot C £3,274 £3,274
East Wing Land – Plot D £35,600 £35,600
East Wing Land – Plot E £18,217 £18,217
West Wing Land Operational £640,625 £640,625
Total £914,749 £914,947
2.4.2 Buildings and property
The hospital occupies 11 buildings, 9 of which are within the secure perimeter.
90% of the buildings have been built and 10% refurbished within the last 7 years. Buildings
include:
Patient Accommodation in 4 blocks, each containing 3 units of 12 beds. (Arran, Iona, Lewis and Mull) The blocks have clinical team space adjacent to patient accommodation and are configured around multi-disciplinary teams
The Skye Centre, containing a range of therapeutic and recreational facilities, psychological treatments and a Primary Care facility
Reception (Security building and Family Visiting facility)
Estates and Facilities buildings (Essential Services block A and B)
A refurbished 1990s built ward now converted to office space (Harris)
Refurbished community hall providing training and conference facilities (Islay)
Modular build office accommodation (Management Centre)
Modular build Occupational Health Service (OHS) building (Outside of secure perimeter)
Electrical Substation (Outside of secure perimeter)
Building values are below at table 2.
Page 14
Table 2: building values
Asset Description
Net book value (000’s)
Replacement cost (000’s)
Arran Hub £7,314 £7,919
Iona Hub £7,329 £7,935
Lewis Hub £7,315 £7,919
Mull Hub £7,316 £7,919
Skye Centre £7,427 £8,119
Essential Services Block 1 £1,027 £1,131
Essential Services Block 2 £1,838 £2,035
Essential Services Block 3 £1,775 £1,937
Reception Building £2,800 £3,023
Family Centre £748 £812
Management Centre £385 £514
Islay £629 £761
Harris £2,372 £2,833
Occupational Health £269 £360
Electrical Sub Station £118 £125
Total £48,662 £53,342
2.4.3 Site layout
The aerial photograph at fig 5 shows the site layout, with more detailed information on the
statutory facets shown at table 3.
Fig 5: Site plan
Page 15
Table 3: Statutory Compliance Chart
The measures of building condition included in this (P)AMS are:
Physical Condition A=Excellent, B=Satisfactory, C=Not satisfactory, D=Unacceptable
Statutory Compliance (SCART) %
Environmental Assessment % change of energy use and carbon production against baseline
Functional Suitability A - D
Quality A - D
Space Utilisation E=Empty, U=Underutilised, F=Fully Utilised, O=Overcrowded B
uild
ing
De
sc
riptio
n
Bu
ild Y
ea
r
Flo
or A
rea
GIA
(M2
)
Ph
ys
ical
Co
nd
ition
Environmental
Assessment
Qu
ality
Fu
nc
tion
al
Su
itab
ility
Space Utilisation
Sta
tuto
ry
Co
mp
lian
ce
(SC
AR
T S
co
re)
Fully
Used
Under
Used
Empty
Site N/A N/A N/A
2014 / 2015 Q3
HEAT Target Report
shows a 25.98%
saving on energy,
and an 69.66%
saving on CO2 (in
comparison to the
baseline year of 2009
/ 2010 for the same
period)
N/A N/A N/A N/A N/A N/A
Essential Services
Block C (Estates
& Facilities) 2009 978.16 B B A 98.53% 0% 1.47% 93.56%
Essential Services
Block B (Catering
& Procurement) 2009 1203.2 B B A 100% 0% 0% 94.89%
Essential Services
Block A (Boiler
house) 2009 324.5 B B A 100% 0% 0% 97.30%
Skye Centre 2009 3862.3 B B A 99.67% 0% 0.33% 94.19%
Management
Centre 2004 465.72 B B B 100% 0% 0% 92.33%
Islay 1937 429.79 B B B 100% 0% 0% 93.56%
Arran 2011 3270 B B A 68.17% 8.12% 23.71% 95.56%
Iona 2011 3290 B B A 84.94% 9.84% 5.22% 94.66%
Lewis 2011 3270 B B A 87.43% 8.29% 4.28% 94.86%
Mull 2011 3270 B B A 85.15% 10.08% 4.77% 94.71%
Harris 1995 1433.73 B B B 93.32% 6.68% 0% 97.07%
Family Centre 2011 223.34 B A A 41.04% 58.96% 0% 98.10%
Reception 2011 1304.77 B B A 94.85% 5.14% 0% 97.45%
Occupational
Health 2005 200.92 B B B 91.05% 8.95% 0% 95.24%
External Land N/A 32.47 ha N/A N/A N/A N/A N/A N/A N/A
Railway Bridge 1950 N/A B N/A N/A N/A N/A N/A N/A
Main Intake
Substation 2009 75.99 B B B 100% 0% 0% 97.08%
Essential Services
Compound Area 92.68%
Average
SCART
score 95.20%
Heated Volume
(m3) 60,726.19
Page 16
2.4.3.1 Office Accommodation
The Scottish Futures Trust, working on behalf of HFS, undertook a review of office
accommodation across NHSScotland in 2013. The review reports average office space per user
as approx 11m2, with a 2020 target of 10 m2. The State Hospital average amount per user was
significantly in excess of this figure.
The SFT has worked with The State Hospital to identify opportunities for introducing smarter
ways of working and the following contributing factors, opportunities and constraints have been
identified:
Clinical Model
An essential part of the clinical model is co-locating the clinicians working with patients.
The four patient accommodation areas have office accommodation immediately above
them, allowing this co-location. The most efficient use of office accommodation would
potentially disrupt this model.
Managing demand
The State Hospital is the sole provider of high secure mental health care for Scotland and
Northern Ireland. The nature of its business means that this care cannot be provided by
another site. The accommodation for staff and patients needs to be able to absorb any
increase in demand.
Design of new hospital
The design for the new hospital included an allocation per office user of approximately
12m2. Although some offices are of a size that means occupancy could be increased,
many are not.
Split site working
A number of State Hospital staff work between The State Hospital and other sites and,
due to the nature of their work, require a single office.
Difficulties in use by others
Many organisations are able to flexibly sell, lease or lend their excess capacity to other
organisations. Due to the secure nature of The State Hospital this is not possible.
Page 17
Opportunities; Management Centre and Occupational Health buildings
The management centre and occupational health buildings are modular and could be
dismantled with relative ease. Although this produces a financial saving there are potential
issues that need to be explored more fully:
Management Centre
There are significant benefits to the co-location of the executive team in one
building. The impact of this change would need to be carefully considered. In
addition, the management centre hosts one of the hospitals 2 data centres, and
demolition of the building would then create a need for major change to the
hospitals data network. This change may be necessary in approximately 2 years
as the data centre approaches the end of its life and network changes may be
required; potential changes to the data network are currently being considered.
This provides a logical timescale for further consideration of the future of the
building.
Occupational Health
The Occupational Health service provides an essential service to staff and is an
important part of the response of The State Hospital to staff absence. Any plans
to remove this building will require to be considered very carefully for potential
impact in partnership with staff. The OHS contract will be reviewed over the
coming year and consideration of the location of the service will take place as
part of that review.
2.4.3.2 Service changes
It is important to note that the nature of a high secure service and site means that, by definition,
patients who require that service cannot be housed elsewhere. As the State Hospital is the sole
provider of high secure mental health care in Scotland and Northern Ireland any peaks in
service demand must be met by the hospital and services and assets must retain sufficient
capacity to be able to absorb any such peak.
The State Hospital has a capacity of 140 beds, though there are 144 useable rooms. The
additional 4 rooms provides contingencies for both the whole site and locally within each
accommodation area. Some changes have taken place in the way that the service has been
delivered over the last year; the occupied beds at the hospital have remained at or around 120
for long enough that we have been able to retract and operate across 11 of the 12 wards. This
has allowed the 12th ward to be closed for maintenance and decorating. Our plan is for the ward
to be used as a decant ward over coming years, enabling longer term planning for maintenance
and refurbishment.
Page 18
The apparent reduction in demand for high secure beds is not of sufficient volume or duration to
allow permanent change; the change to operation across 11 wards is something that can be
reversed quickly if necessary. It is also important to note that the bed numbers at the State
Hospital are complicated by the fact that 1 ward is specifically for patients with a learning
disability, with the remaining beds for patients with a mental illness. This means that an increase
in mental illness patient numbers of just 8 (at time of writing) would mean that we would need to
consider reopening the ward.
The change in occupancy level occurred in concert with the opening of more medium secure
beds at the Rohallion Clinic in Perth. The regular needs assessment for forensic services
conducted by the Forensic Managed care Network confirms that the Medium Secure estate is
now the right size. Historically, The State Hospital has admitted patients that require medium
security under an exceptional circumstances clause, but this has not been necessary since the
Rohallion Clinic opened. Despite capacity across the medium secure estate being addressed
by this, there are concerns that the configuration and location of beds could improve. Should
any changes take place the likely impact on The State Hospital would be that a small number of
learning disabled patients may be able to move, though the single ward service model for
patients with Learning Disability means there would be little opportunity to reconfigure services
on site.
Occupied bed numbers over 2010 – 2015 are detailed below in table 4.
Table 4: Occupied bed numbers 2010 – 2015
Month 2010/11 2011/12 2012/13 2013/14 2014/15
June 132 136 134 134 126
September 134 133 133 129 122
December 132 132 139 129 122
March 135 134 130 128 120
2.4.4 Vehicles
The State Hospital has a fleet of 16 vehicles. The vehicles are all owned by The State Hospital.
The table below (table 5) gives a high level summary of the split by type and their current net book value. In 2013 – 2014 part of the fleet used for patient transport was replaced and the fleet size reduced. Although some of the remaining fleet have a moderate or high risk assessment score, which would normally indicate replacement is required within the next 1-2 years, they are all low mileage and well maintained so the risk associated with their age is mitigated.
With the exception of 1 forklift (Electric) and a Quad Bike (Petrol), the fleet are 100% diesel; the older vehicles have poor emission ratings. Monitoring of usage has improved through the year with individual journey mileage being recorded.
Further review of The State Hospital fleet took place in March 2015 and the recommendations of
that review are currently being considered. Opportunities exist to improve fleet size and
efficiency through replacement of single purpose vehicles with more flexible multi functional
vehicles and by improving journey planning and logistics.
Page 19
Nationally, a shared services review of transport and fleet management is underway and we will
continue to engage with that review and await the outcome.
Table 5: Asset values of vehicles
Vehicle Descriptions Number Net book value
Replacement Cost
Cars 1
Vans 5
Buses / People Carriers 4
Others 6
Total 16 £57,692 £313,625
2.4.5 Security Equipment
The security of the hospital is paramount for the safety of the patients, staff and public. As part
of the redevelopment of the hospital security equipment was updated in the following areas:
Specialised locks
Staff alarm and communication systems
Perimeter: Fences, Electronic detection and observation equipment Locks The locks will be of good condition, functionally suitable, fully utilised and low risk for at least the next 5 years. Staff alarm and communication systems The alarm and communication systems will continue to require regular investment to ensure that they remain effective, but with that investment should be good condition, functionally suitable, fully utilised and low risk for at least the next 5 years. Perimeter Like other technology, security technology is developing at an increasing rate, and much of the specialised security equipment has the potential to reach obsolescence whilst still retaining an asset value. Contact with suppliers suggests that equipment support will be available for the immediate future, but a full replacement programme will be required to ensure that our standard is maintained beyond that timescale. Security technology is beginning to move from analogue systems to digital, and at some point a critical mass will be reached leading to a requirement to migrate to newer systems to ensure support. The fences, observation and detection systems have previously been identified as impending backlog within the EAMS system and are currently subject of a total review of efficiency and likely life in line with a projection for major capital investment in 2017 – 2018; an outline business case will be prepared for 2016 – 2017. The asset value of security equipment is below at table 6.
Page 20
Table 6: Security equipment asset value
Asset Description Net book value Replacement cost
Access & Egress Equip £405,557 £552,396
Staff safety systems £2,871,894 £3,487,546
Perimeter & Site security £2,462,778 £3,594,019
Public Safety systems £4,042 £96,157
Total £5,744,271 £7,730,118
2.4.6 eHealth IM&T Hardware; Network . There are 3 key elements to the hospitals physical IT infrastructure;
Servers: The Blade servers installed in April 2012 are just over half way through the projected life span of 5 years.
Fibre: The fibre network replaced during the hospital redevelopment programme now has a projected life of 6 - 9 years (depending on date of replacement).
Switches: Some of the network switches are now at or past end of life. There are spare switches held in on site storage to mitigate any failures. We are working in partnership with external agencies to plan the replacement and upgrading of older switches. Support arrangements need to be considered to ensure future resilience of the networks components.
In order to ensure we continue to have resilient hospitals systems, the IT infrastructure was recently audited. The outcome of these audits have identified further areas were the upgrading and replacement of equipment may be required. Additional work is being undertaken to identify and prioritise this upgrading to ensure that the Infrastructure continues to be resilient.
(Projected life of IT equipment is based on industry standards of how long products are
supported by the manufacturer.)
Hardware; Personal Computers
PC stock is, on average, about 70% through its operational life, and the ongoing replacement
programme will maintain this standard.
Software and Systems Further developments are being explored for the Electronic Patient Record (EPR). This system is now the integral to the hospital as its main clinical records system and has become a significant dependency for the organisation. Software and licences are still a major element of IT expenditure. Spend will need to continue for this requirement to ensure the support and compliance of applications and systems over coming years.
Page 21
IM&T assets and values are detailed below at table 7 Table 7: IM&T Asset values
Asset Description Net book value Replacement cost
Clinical & Business Systems
£105,577 £661,307
Server & Network Infrastructure
£545,517 £1,454,093
Software Licenses £54,663 £158,859
Desktop & Client Hardware
£169,952 £569,743
Control Room & mailing £937,683 £1,120,105
Telephone System £0 £38,671
Total £1,813,392 £4,002,778
2.4.7 Medical Equipment
The State Hospital requires very little medical equipment. The total value is approximately £31k and is an immaterial part of the asset base. The equipment we have is mainly situated in the Health Centre (a small primary care facility within The Skye Centre) and is made up of dental, ophthalmic and other primary care equipment. We also have a small quantity of medical equipment (e.g. defibrillators) situated in various locations around the site.
2.4.8 Total Assets
Table 8: Total Assets
State Hospital Assets
Asset Description Net book value
NBV % Replacement cost
Buildings £48,661,908 77.68% £53,342,347
Land £914,749 1.46% £914,749
Vehicles £57,692 0.09% £313,625
Security Equipment £5,744,271 9.17% £7,730,118
IT £1,813,392 2.90% £4,002,778
Medical equipment £31,365 0.05% £74,494
Furniture £868,001 1.39% £1,346,987
Site Services £3,064,607 4.89% £3,313,323
Assets Under Construction
£65,092 0.10% £65,092
Other £1,419,796 2.27% £1,990,476
Total £62,640,973 100% £73,093,989
Page 22
2.4.9 Backlog Maintenance
Backlog maintenance includes any work required to bring the estate back to an acceptable
condition. The backlog maintenance requirement for the hospital remains low at £334k, though it
has increased over the last year, primarily due to inflation. Detail of the Clinical / Non Clinical
split is below at table 9. The condition and depreciation of the estate and assets is closely
monitored to ensure accurate identification of any backlog maintenance requirement and to
identify any change in the pace of expected depreciation.
As depreciation has taken place as expected the majority of the estate is now at condition “B”
and will require relatively minor investment to remain at that level over the period of this (P)AMS.
A few areas remain at Condition “A”; no areas are at Condition “C” or “D”. Other than carpets
and decor requiring some attention, significant projects are:
New telephone system, previously identified within the EAMS system. Required as the
existing system becomes more challenging to maintain. Estimated cost of £80k.
The Secure Perimeter, also identified within the EAMS system as impending backlog with a
notional budget of £5m, planned for 2017 – 2018 with business case preparation beginning
this year.
Table 9: Clinical and non clinical backlog maintenance
Site
Code
Site Name Use Low Moderate Significant High Unreported Total
D101H The State
Hospitals
Board
for Scotland
Clinical 0.00 202,383.00 91,191.00 0.00 0.00 293,574.00
D101H The State
Hospitals
Board
for Scotland
Non
Clinical
1,130.00 4,520.00 34,444.00 0.00 0.00 40,094.00
TOTALS 1,130.00 206,903.00 125,635.00 0.00 0.00 333,668.00
2.4.10 Changes to SCART (Statutory Compliance and Risk Tool)
The SCART system has changed this year from a 99 item question set to 570 items, exploring
issues in considerably more detail. With the introduction of the additional question sets, it is
anticipated that our SCART score will drop initially, until systems and procedures can be put in
place to inform the updated tool. We are in the process of populating the system, so at this time
cannot predict how much our overall score will be affected.
Prior to introduction of the new question set the Board’s current average SCART score was
95.2% with no high risks identified; a screenshot of the SCART scoring system is at fig 6:
Page 23
Fig 6: SCART Screenshot Compliance Scores at April 2015
2.4.11 Planned Preventative Maintenance (PPM) and Reactive Maintenance As part of the hospital re-development, the Estates Team redesigned their PPM programme to suit the new buildings and systems. This was carried out during construction, allowing the new PPM programme to go live immediately following handover of the new buildings. Initially all the required PPM's (both statutory and non-statutory) aimed for a typical NHS model of 70% planned, 30% reactive work. This target was challenging, as the nature of the hospital means reactive maintenance has historically been higher than 30%. A further review followed after greater understanding of the buildings and systems was
achieved. This allowed a move towards implementing a Condition Based PPM programme for
non-statutory PPM’s. This was achieved by analysing completed PPM's on a quarterly basis and
adjusting frequencies where appropriate. Technology such as the Building Management System
(BMS) also contributed to more intelligent monitoring and analysis of systems. In addition,
technical staff were consulted regarding their view of the impact of any planned change. Any
PPM's that were adjusted were regularly monitored for an increase in reactive tasks and
breakdowns to ensure there was no detrimental effect.
Page 24
Condition Based Monitoring Case Study: Air Handling Units
Air handling units exist throughout the hospital and require maintenance to maintain efficiency
and ensure safety. Frequencies were revised from 3 monthly to 6 monthly intervals. The filters
are now changed in response to alerts from the BMS system which informs when there is a
significant change in that particular system or plant, or if it is performing outwith pre-
programmed parameters.
Condition Based Monitoring Case study: Biomass Boiler Maintenance
Biomass boiler maintenance is undertaken by an external contractor while performance and
service requirement is managed through our PPM system.
The maintenance contractor specification suggested service intervals of 800 hours. Through
monitoring the condition of the boiler internally via our PPM system and discussing the system
with technical staff, the service interval has been extended to 1,000 hours. During this time there
has been no detrimental effect on the boilers condition or operation. Plans are being developed
to extend the servicing intervals to 1,200 hours.
Page 25
A quarterly PPM audit ensures that all statutory PPM’s are being carried out in compliance with
the relevant guidance. A further monitoring audit is carried out by NHS National Services
Scotland, Health Facilities Scotland – Facilities Monitoring System (FMS) quarterly KPI returns.
The FMS KPI system is a useful indicator of how we as a Board are performing against other
Boards, and includes costing information per m2. A screen shot of some of the national
benchmarking data produced from the FMS KPI system is below at figure 7:
Fig. 7: National Benchmarking data from FMS KPI system
2.4.12 Sustainability, Energy and the Environment
Sustainability
The hospitals Sustainable Development Group includes representation from all areas of the
hospital including patients and is chaired by the Finance and Performance Management
Director, who is the Board’s Sustainability lead.
The Group has produced a Sustainable Development Action Plan (SDAP) which addresses
sustainability issues across the organisation. Initial work by The State Hospital on a Carbon
Management Plan has been further informed and developed through the StEEP (Strategic
Approach to Energy Efficiency) programme and the plan now addresses energy and carbon
reduction targets including lighting, waste, energy control software and staff awareness.
A Sustainability Reporting Tool is currently being produced by Scottish Government which will
require an annual report from Boards, beginning in October 2015.
To ensure that the Boards knowledge and thinking on issues remains current there is regular
interaction with Health Facilities Scotland (HFS) with attendance at the HFS Sustainability
Steering Group and sub groups. HFS Sustainability staff recently attended the State Hospital
Page 26
Sustainable Development Group to give an update to the group on the forthcoming mandatory
sustainability reporting requirements.
Environmental and Energy Management
The State Hospital Environmental Management System (Corporate Greencode) ensures
identification of all environmental aspects through an Aspects Register which links to a Legal
Register highlighting relevant legislative risks. These have been individually risk assessed and
the Board have no Red Risks for action.
Corporate Greencode is primarily managed by the Estates Team with input from the hospitals
Sustainable Development Group.
Energy and Greenhouse Gas targets
As reported in the 2014 – 2015 PAMS, since 2012 energy performance has been measured
year on year against a 2009 baseline. This baseline preceded the full commissioning of the new
hospital and resulted in performance significantly above targets.
Rather than the previous year-on year target model, targets are now percentage reduction
targets from a baseline year through to financial year 2020. Targets will apply to absolute energy
consumption and to GHG emissions from energy use only. The baseline year will be an average
of the three years 2011 – 2014.
NHS Boards should have ‘basic’ and ‘stretch’ targets. The State Hospital targets are shown at
table 10 below. The basic target should be based on what the Board thinks could be achieved if
the investment for energy efficiency projects remains at current levels; although the changes
made in the new hospital leave us with less scope for improvement, we have been able to make
changes that allow us to set a “basic” target of 10% The stretch target should be based on what
the Board thinks could be achieved if all identified projects receive 100% funding. The State
Hospital projects, identified jointly with HFS through the Strategic Approach to Energy Efficiency
(StEEP) programme, are the introduction of intelligent lighting controls and the erection of a
wind turbine. The programme identified annual savings, both in terms of £’s and tCO2, other
potential income such as Feed in Tariff (FiT) and Renewable Heat Incentive (RHI), lifetime
savings, payback periods and a risk assessment for each project. Both projects are on an HFS
potential funding list, should central funding become available.
In addition, to energy consumption targets, Boards should specify the percentage of energy
consumption in 2020/21 to be delivered from renewable energy sources. A significant proportion
of State Hospital energy use is from renewable resources due to the use of biomass as our
heating fuel. This has also enabled us to be awarded the Renewable Heat Incentive, resulting in
an income in the region of £115k pa.
Page 27
Table 10: Energy targets
Criteria The State Hospitals Board for Scotland : Energy & GHG Reduction Targets for 2020/21 (against 3-year average baseline 2011/12, 2012/13 and 2013/14)
Basic Stretch
Energy Consumption (kWh/m2)
Electricity
-6%
Fossil Fuel
-2.8%
Biomass
-2%
Electricity
-30%
Fossil Fuel -9%
Biomass
-4.2%
Combined -3.4%
Combined -13.3%
Greenhouse Gas Emissions (kgCO2e/m2)
133 92.6
Criteria The State Hospitals Board for Scotland : Percentage of Total Energy Consumption from Renewable Energy Sources
Basic Stretch
Percentage of heat consumption from renewable energy
sources
55.6% 56.7%
Percentage of electricity consumption from renewable energy
sources
0% 30%
Percentage of total consumption from renewable energy
sources
39.6% 53.4%
Greenspace During the redevelopment of the hospital a landscape architect was employed as part of the
project team and greenspace was created across the site:
External art was commissioned and situated as a feature in the grounds in the form of
wooden benches sculpted to replicate the 360 degree visible horizon
Other benches are placed around the grounds to encourage exercise and maximise
opportunities to enjoy fresh air and the expansive views
Mosaic walls were installed at each of the entrances to the patient accommodation
buildings, made unique by incorporating the name of each of the buildings
Further greenspace work has been carried out by hospital staff; an internal greenspace
has been created with a botanic garden including a pond. This is actively used for staff,
patients and visitors
To fully utilise the wander paths which were incorporated as part of the redevelopment,
hospital staff and patients undertook a project to identify walking routes of varying length
and physical exertion which were then mapped and identified by colour coded bollards
throughout the site
Outdoor gymnasiums have been installed in various places around the grounds
The animal assisted therapy department encourages skills development and therapeutic interaction with a variety of animals
Page 28
“External art was commissioned and situated as a feature in the grounds in the form of wooden benches sculpted to replicate the 360 degree visible horizon”
“Other benches are placed around the grounds to
encourage exercise and maximise opportunities to
enjoy fresh air and expansive views”
“Mosaic walls were installed at each of the
entrances to the patient accommodation buildings,
made unique by incorporating the name of each of
the buildings”
Page 29
“Further greenspace work has been carried out by
hospital staff; an internal greenspace has been
created with a botanic garden including a pond.
This is actively used for staff, patients and visitors”
“To fully utilise the wander paths which were
incorporated as part of the redevelopment, hospital
staff and patients undertook a project to identify
walking routes of varying length and physical
exertion which were then mapped and identified by
colour coded bollards throughout the site”
“Outdoor gymnasiums have been installed in various places around the grounds”
Page 30
“The animal assisted therapy department encourages skills development and therapeutic interaction with a variety of animals”
The secure nature of the hospital means that it would not be appropriate to engage with Scottish
Natural Heritage or Forestry Commission Scotland to develop and promote our greenspace.
2.4.13 Fire Risk Assessments and Emergency Preparedness
Fire Risk Assessments
The EAMS fire and risk module, made mandatory for all Boards this year, is fully utilised at The
State Hospital; fire risk assessments have been undertaken for all buildings and entered onto
the system. Scottish Fire and Rescue have audited the majority of these risk assessments. The
system is also being used to record any fire calls or false alarms.
Exercises
A live exercise was held in June 2014 which had 4 fire appliances and an ambulance in
attendance. A vacant ward was filled with smoke and the exercise included the reporting of 4
people missing in the building. The exercise was successful, with some minor learning points
noted. Most of the issues have been addressed and a plan is in place to address those
remaining.
Page 31
2.4.14 Workforce plan
A workforce review is planned across The State Hospital during 2015 – 2016. Issues that
require further exploration across the Facilities and Estates areas of the hospital include:
Monitoring and performance information
The increase in demands from information systems has dramatically increased the demand on
estates staff. The size of The State Hospital and its Estates Department means this increased
workload falls on a smaller pool than in other Boards. This needs to be further assessed. A
review of the management arrangements within the Facilities Department was undertaken in
2013 with assistance from HFS, so the report from that exercise will provide a useful
benchmark.
Shift in workload
Increased monitoring and maintenance of systems to meet legislation may provide opportunities
to look at the skill sets in the department. As the department becomes more familiar with the
new requirements through the year we will be able to further assess the implications of the
change and how to address it.
Succession planning and resilience
We need to ensure that we are maximising the opportunities to develop our staff to enable them
to look to career progression in the future whilst also ensuring that the organisation is also
planning for the future. We also need to ensure that the department has resilience; it is a small
department with some areas of expertise held by a small pool of people.
Page 32
1 Where do we want to be?
The State Hospital is in the fortunate position of having all assets on a relatively small single site
with new or recently refurbished buildings that are all at or above condition “B” and a low
backlog maintenance requirement. The State Hospitals Board plans to continue to ensure the
assets continue to support the achievement of the strategic aims it is therefore critically
important that we do not become complacent and must continue to effectively monitor suitability,
quality, performance and condition. Regular consideration needs to take place of:
Significant national or local plans, Key targets and deliverables
Possible changes to need or linked services provided by others
Risks and challenges
3.1 Significant National or Local plans, Key targets and Deliverables
The Scottish Government has developed a Route Map to the 2020 Vision for Health and Social
Care, providing 12 priority areas for improvement and 25 key deliverables. The specialist nature
of The State Hospital means that some of the priority areas and deliverables are not applicable;
The Route Map as it applies to the hospital is shown below at table 11.
Page 33
Table 11: State Hospital Route Map to 2020 Vision
ROUTE MAP TO THE 2020 VISION FOR HEALTH AND SOCIAL CARE
Triple Aim Quality
Ambitions
12 Priority Areas
for Improvement 25 Key Deliverables
Quality of Care
Person-
centred
Person-centred
care
1 Person Centred Health & Care
Collaborative Implemented
2
Information and support to enable
people at home and during times of
transition
Safe Safe Care
3 Further increase in safety in Scottish
hospitals
4 New broader measure of safety
developed (SPSI)
5
Maternity, mental health and primary
care components of the Scottish
Patient Safety Programme
implemented with measurable
improvements
Health of the
Population
Effective
Prevention
19 Early detection of cancer
20 New restrictions on tobacco
advertising
Value &
Sustainability
Workforce
21 2020 Vision for NHSScotland
workforce
22 Detailed action plan agreed to deliver
2020 Workforce Vision
Innovation
23
A new fund to provide pump-priming
for innovative approaches to
healthcare
24
A new procurement portal will be
established to encourage working
with SMEs and third sector
Efficiency &
Productivity 25
Recommendations to increase
shared services
Page 34
The key deliverables for the organisation based on the 2020 Route Map are below at table 12.
Table 12: State Hospital Key Deliverables
25 Key Deliverables TSH Executive
Lead Contact LDP mapping
1 Person Centred Health & Care Collaborative
Implemented Nursing Director Section 8
2 Information and support to enable people at
home and during times of transition Nursing Director Section 8
3 Further increase in safety in Scottish hospitals Nursing Director Section 9
4 New broader measure of safety developed
(SPSI) Nursing Director Section 9
5
Maternity, mental health and primary care
components of the Scottish Patient Safety
Programme implemented with measurable
improvements
Nursing Director Section 9
19 Early detection of cancer Medical Director Section 10
20 New restrictions on tobacco advertising Medical Director Section 10
21 2020 Vision for NHSScotland workforce HR Director Section 11
22 Detailed action plan agreed to deliver 2020
Workforce Vision HR Director Section 11
23 A new fund to provide pump-priming for
innovative approaches to healthcare General Manager Section 11
24
A new procurement portal will be established
to encourage working with SMEs and third
sector
Finance and
Performance
Management
Director
Section 11
25 Recommendations to increase shared services
Finance and
Performance
Management
Director
Section 11
Page 35
Health and social care integration with the associated focus on care at home is likely to have a
major impact on much of the service delivered by territorial Health Boards; in addition, the
Shared Services Review may have some impact on some of the support services based at
hospital sites. These national streams of work will be closely monitored for impact. At present it
seems that national work streams and our key deliverables and their implementation are unlikely
to have a significant effect on our assets, which will continue to be based around delivery and
support of delivery of high secure mental health care at the current site. As actions against these
deliverables are reported and discussed at the SMT and Board, any implications for assets will
be identified at an early stage. A review of the Clinical Model is being considered, which will
further consider how our services are configured to meet need; it is not thought that this will
have any significant affect on assets.
The Scottish Futures Trust (SFT) “Smarter ways of working” programme has identified that The
State Hospital has office space that is significantly in excess of the national average; although
many of the opportunities for improvement available to other Boards are not available to us, we
will take opportunities to look for improvements when available. Reviews of the future of the
Occupational Health building and the Management Centre will take place in due course, and
occupancy trends may also lead to opportunities.
3.2 Possible changes to need or to associated services
The State Hospital is part of the Managed Care Network for Forensic Services (The Network).
The Network is hosted at the hospital and the State Hospital’s Medical Director is also the
Medical Director of The Network. This position gives us a central and well informed place in the
planning and delivery of forensic services in Scotland. In addition, State Hospital staff attend
strategic and governance meetings of the English High Security Hospitals, allowing us to remain
well informed about service changes across the UK.
As described in 1. Where are we now?, the hospital is currently operating across 11 wards.
National demand for high secure services has dropped slightly, but not far enough or for long
enough that it can be regarded as sufficiently robust for long term planning.
Most of our patients who move on from the hospital are returned to prison or rehabilitated
through Medium Secure units, and the opening of beds at the Rohallion unit has added sufficient
capacity to the medium secure estate to ensure that patients are usually able to move within
appropriate timescales. The potential for geographically reconfiguring medium secure beds
exists, and should this occur the system is likely to become more efficient. The change to health
care delivery across the prison service, with the responsibility for health care now vested with
Health Boards, has improved communication and continuity, but has had no impact on the
requirement for high security beds.
Page 36
As regards legislation, demographics and the care and treatment delivered to those requiring
mental health care in conditions of security, there is unlikely to be any changes that would
significantly affect the assets required to support that care within the life of this (P)AMS.
3.3 Consultation and Engagement
The hospital endeavours to work in partnership with staff, patients, carers and other
stakeholders. Any significant change in the delivery of services will be fully consulted on with
those affected. This is particularly high on the agenda of the Board, as previous changes
affecting patients have resulted in legal challenge, particularly relating to consultation. A
previous example of effective stakeholder engagement is the development and delivery of the
new hospital, when consultation and engagement took place with staff, patients and carers, a
model that improved the process and outcome.
3.4 Risks and Challenges
The wider healthcare environment and The State Hospital face significant challenges in coming
years; in order to meet these challenges and continue to meet the needs of our patients it is
important that our assets remain effective in supporting our service. There are:
Risks that we need to address
Work streams nationally that we need to remain engaged with
Work streams within the organisation that we need to commission or conclude
Practices that we need to continue
Risks that we need to address
Potential service risks are explored above; it is unlikely that there will be any significant changes
to the service the State Hospital is required to provide within the life of this (P)AMS.
The organisation does face financial challenges, as absence and overtime remain high and
savings targets need to be met. Although financial balance was achieved in 2014 – 2015, the
balance of the savings delivered was non-recurring, and further work is required through this
year to deliver savings and to redress this balance. Significant savings were delivered in 2014 –
2015 through oil prices, which remain low, but have the potential to change quickly in response
to global events.
Any savings targets that have the potential to affect asset performance must be carefully risk
assessed.
At present there are no risks associated with the (P)AMS that are of sufficient significance to warrant inclusion on the corporate risk register. This will be reviewed as part of the annual (P)AMS review and regular risk review.
Page 37
National Work Streams
Health and Social Care integration and the Shared Service Review are both likely to have some
impact on the organisation, though current thinking suggests that it will not significantly impact
on assets. We will continue to engage with these work streams and monitor for any likely
impact.
Work streams within the organisation
We need to:
Continue the process of disposal of non operational land
Review the use of the Management Centre and OHS buildings within 2 years
Conclude the fleet review and identify actions whilst remaining engaged and informed
regarding the national review
Continue the investment in alarm and communication systems
Complete the review of the Security systems, identify requirements and plan to address
them
Complete the review of the IM&T network, identify requirements and plan to address
them
Procure and commission the telephone system
Identify any workforce issues through a review of the Facilities department with particular
reference to increased information system demands and increased monitoring
Engage with any internal reviews such as the potential review of the Clinical Model
Work we need to continue
We need to:
Monitor patterns of bed occupancy
Maintain the systems and processes that manage risk and identify issues, reporting as
necessary to the SMT and Board
Engage with Stakeholders in order to inform and consult
Explore, and implement as appropriate, Condition based monitoring to reduce non -
statutory PPM’s
Regularly review and continue to implement the SDAP and CMP
Take advantage of funding if available to introduce projects that meet “stretch” energy
targets
Page 38
4. How do we get there?
The State Hospital is unlikely to require any significant service change across the life of this
(P)AMS and beyond. The Board is informed on this position by close links with major national
work streams and its close connections with the Network. Our journey to “Where we want to be”
will be dependent on capital funding continuing at recent levels, additional funding being made
available for some major projects and revenue continuing to be available whilst savings targets
are met.
Structures are in place to:
Monitor and report on asset performance
Identify and plan for changes in need
Engage effectively with stakeholders
Prioritise any competing investment needs
Implement any investment plans
Investment project management arrangements are shown below at figure 8.
Figure 8: Investment Project Management Arrangements
Project
Project Managers:
Head of eHealth
Physical Security Manager
Head of Estates and Facilities
Security Director:
responsible for Capital
Planning
Senior Management
Team: representation
from all areas of the
hospital
The State Hospitals Board
Project Team:
Membership as appropriate
Page 39
4.1 Projects and plans; costs, procurement, benefits, project lead and risks.
4.1.1 Minor planned or possible investment (to be managed within normal capital /
revenue allocation):
Telephones
This project has a projected cost of under £100k, with a high level of certainty
The project is currently in the process of procurement via traditional tendering and capital
funding.
Consultation regarding the new telephone system indicates that users require a system
with similar functionality to that in place, with increased resilience. The project will
address the resilience risk posed by the current system and provide users with an
effective and robust system for coming years that is matched to the user’s requirements.
The project will be led by the Head of Estates and Facilities. A project plan will be
created that is tailored to the new system once identified, and the plan will be approved
and monitored by the SMT.
There are no significant risks to this project.
Staff Safety System
This project has a projected cost of up to £20k with a high level of certainty.
The Staff Safety System is a large and complex system comprises of a number of
overlapping systems that provide a resilient response to any need for assistance across
the site. Component systems include:
o Individually held personal alarms
o A public address system
o Response pagers
o Radio system
Regular investment will continue to take place; approximately £20k per annum has been
required to ensure all components remain effective and current. Procurement is usually
restricted to the system installer.
Investment will ensure that the system remains effective provides a safe system of
requesting assistance in emergency situations.
The project will be led by the Physical Security Manager.
There are no significant risks to this project
Page 40
Vehicles
This project has an estimated cost of under £100k; as the draft report is still under
consideration this estimate has a low level of certainty
Any potential procurement route will be established when the draft report has been fully
assessed.
The review will be submitted to the SMT with an associated action and investment plan
for approval.
Potential benefits of the project will be increased energy efficiency, reduced GHG
emissions, reduced capital cost due to a smaller fleet, and reduced revenue cost due to
reduced maintenance and fuel costs.
The lead for this project is the Head of Estates and Facilities.
There are no significant risks to this project
4.1.2 Significant planned or possible investment (requiring additional funding):
Secure Perimeter
The estimated cost of this project is £5m. The stage of the review of the perimeter
means that this estimate has a low level of certainty.
The perimeter comprises:
o A 5.2m security fence
o Detection systems
o Lighting system
o Thermal Image and Optical cameras
o A 24/7 Control Room with alarm and control systems
Work will continue through the coming year to fully identify future requirements,
potentially leading to a business case for investment in 2017 – 2018.
The procurement route for improvements to the perimeter will be established once the
size and scope of the project is identified
The Secure Perimeter is essential to ensure that public, staff and patient safety is
maintained. The provision of a secure perimeter also allows the effective implementation
of the clinical model.
This project be led by the Physical Security Manager, reported to the SMT and submitted
to the Board for approval.
This project is potentially complex. Project risks include:
o Failure to adequately assess need, resulting in a perimeter that is insufficiently
secure
o Failure to plan effective implementation of change, resulting in potential security
failings during implementation
Plans are in place to mitigate these risks; a specialist in physical security has been
commissioned to undertake the review of the perimeter; the nature of the equipment and
implementation will require specialist project management, and similar expertise will be
sought to project manage the implementation of any changes.
Page 41
IM&T Network
This project has an estimated cost of £0.5 - 1m. The stage of the network review means
that this estimate has a low level of certainty
Reliable and resilient IM&T system are essential to the effective working of the hospital.
Over recent years IT system developments have become central to the day to day
working of the organisation. Particular developments include the introduction of an
Electronic Patient Record and a Patient Movement and Tracking System that monitors
all patient movement within the hospital. Through the course of the coming year the
network audit will identify any investment requirements, including plans to replace the
data centres which have a projected future life of approximately 2 ½ years.
A procurement route will be established once plans are developed to an appropriate
stage
This work will be led by the Head of eHealth and reported to the SMT, with Board
approval sought for any associated business case.
This project is potentially complex. Project risks include:
o Failure to adequately assess need, resulting in a network that is not fit for
purpose
o Failure to plan effective implementation of change, resulting in potential failings
during implementation
Plans are in place to mitigate these risks. A specialist has been commissioned to undertake the
review of the infrastructure. The nature of the equipment and implementation will require
specialist project management, and similar expertise will be sought to project manage the
implementation of any changes
Turbine and Lighting controls
These projects have a projected cost of £1.3m and £37k. The well developed nature of
these plans means this projection has a high level of certainty
These projects are not currently affordable within State Hospital budgets and are on an
HFS potential funding list. Procurement will be led by HFS.
The benefit of these projects will be significant reductions in energy consumption and
GHG production coupled with potential income from the Feed In Tariff.
The lead for liaison with HFS, and for implementation should funding become available,
is the Head of Estates and Facilities in conjunction with HFS.
There are no significant risks related to these projects.
Page 42
4.1.3 Other Work Streams
Backlog Maintenance
Backlog maintenance has a projected annual cost of £60k. This can be predicted with a high
level of certainty. The low requirement for backlog maintenance means this should be
affordable within current budgets, though given the challenging savings targets for the coming
year this will require careful monitoring by the SMT and Board. A plan is in development for
approval by the SMT that will prioritise areas of risk and balance operational requirements with
the need to address the backlog maintenance requirement over the period of this (P)AMS.
There are no significant statutory compliance risks.
Disposals
The planned disposal of non-operational land will continue, with the intent to conclude this by
the end of this calendar year. Receipts from the disposal are likely to be in the region of £200k.
This figure has a high level of certainty. The lead for this project is the Head of Estates and
Facilities. Progress with this work will be reported to the SMT and Board as appropriate. On the
conclusion of the disposal of this land it is not anticipated that any other disposals will take place
for the foreseeable future.
Review of use of Management Centre and OHS Building
During the next 2 years a review of the use and future of these buildings will be concluded. The
Management Centre review will take regard of the future IM&T plans for changes to Data Centre
location and associated network changes; the OHS Building review will consider the review and
tendering of the OHS service. Both reviews will consult with all involved, identify potential
savings and service implications and look for best value. The lead for the review of the
Management Centre will be the Security Director, working closely with the Head of eHealth; the
lead for the review of the OHS Building will be the Security Director working closely with the HR
Director. The result and recommendations of these reviews will be presented to the SMT and
Board for approval.
Workforce Review
A review of The State Hospital workforce will be undertaken within this calendar year, led by the
HR Director. Within this overarching piece of work, the Estates and Facilities department will
consider our resilience needs and the demands of changing information systems, monitoring
routines and consider succession planning. The lead within Estates and Facilities will be the
Head of Estates and Facilities.
Page 43
Service Changes
Changes to the need for High Secure or other forensic services will be identified through the
regular needs assessment undertaken by the Network. The pattern of need has remained
relatively stable for over 20 years, and there is no indication that this will change in any
significant way over in the short to medium term.
The review of the Clinical Model at The State Hospital may result in minor change to the asset
requirement, and this will be monitored as the work progresses.
Sustainability and Energy
Performance against the Sustainability Action Plan will continue to be reported to the SMT and
the Board.
The HFS KPI dashboard will be reported regularly to the SMT and performance monitored.
4.2 Affordability
As described above, the PAMS has significant future challenges relating to ensuring funds are available. The 2015 – 2020 Capital Plan is shown below at table 12. The plan may require some revision to ensure alignment with future (P)AMS and any emerging issues, which should be affordable within the overall envelope of available capital. The plan covering years 2015 - 2018 has been approved by The State Hospitals Board and in principle by SGHD. The years 2018 – 2020 are assumptions based on known allocations and information and have not yet received State Hospital or SGHD approval.
Table 12: Capital Expenditure 2015– 2020
Capital Expenditure 2015- 2020 2015 - 2016 £000s
2016 - 2017 £000s
2017 - 2018 £000s
2018 - 2019 £000s
2019 - 2020 £000s
Statutory Compliance and Backlog Maintenance
50 50 50 50 50
Other (Perimeter Security) 5000
Total Property Expenditure 50 50 5050 50 50
Medical Equipment 25 25 25 25 25
Vehicles 25 25 25 25 25
Plant and Machinery 100 100 100 100 100
Total Equipment Expenditure 150 150 150 150 150
E-Health projects 100 1100 100 100 100
Total IM&T Expenditure 100 1100 100 100 100
Other Capital Expenditure 0 0 0 0 0
Total Gross Direct Capital Expenditure 300 1300 5300 300 300
Page 44
Appendix 1 National Asset and Facilities Performance Framework
Quality
Ambition
Performance
Measure
KPI
Number
Key Performance
Indicator
Indicative 10
year
performance
benchmark
Current
Performance
Performance
Score (For
SGHD / HFS
use)
Patient
Centred
Quality of Physical
Environment
1 % of properties in “A”
or “B” Physical
Condition
90% 100%
2 % of properties “A” or
“B” Quality
90% 100%
Patient opinion of
healthcare
environment
3 +ve response to
patient questionnaire
hospital environment
rating
95% N/A: TSH
patients not
included in
survey
Patient needs are
accommodated in
modern, well
designed facilities
4 % of properties below
50 Yrs old
70% 98%
PAMS reflective of
service need and
patient preferences
5 PAMS Quality
Checklist Overall
Score (X/100)
95
Safe Statutory
Compliance status of
property asset base
6 Overall SCART
compliance %
95% 95.2%
Backlog
Maintenance
expenditure
requirement
7 Backlog Maintenance
£ / M2
£100 £14.13
Level of risk
associated with
outstanding backlog
maintenance
requirement
8 Significant & High
Risk Backlog
Maintenance % of
total
10% 37%
Effective
and
Efficient
Functional Suitability 9 % of properties “A” &
“B” Functional
Suitability
90% 100%
10 % of property “Fully
Utilised”
90% 88.17%
11 Building Volume (m3)
per 1000 population
2240 N/A: Building
Volume
64055m3
National
service,
population
approx 6m
N/A
Property
Maintenance Costs
12 Property Maintenance
£ / m2
£958 £35 £35
Rent and Rate Costs 13 Rent & Rates £ per
m2
£411 £921 £552
Energy Costs 14 Energy
£ per m2
£617 £1,193 £1,393
Energy Consumption 15 Gigajoules per m2 per
year
44 55.53
Total Overall Performance Score
Page 45
Appendix 2 - Scottish Health Board Report - The State Hospitals Board for Scotland
Table 1: An analysis of the existing estate by area
Area (Sq.m) % of Total Area Value 05 Mental Health Hospital 18,691.33 79.19 £48,661,908.00
23 Offices 1,899.45 8.05 £0.00
24 Support Facilities 3,011.64 12.76 £0.00
TOTALS 23,602.42 100.00 £48,661,908.00
NB: Value is Net Book Value using only Block '00'. Blocks with Code No '00' have been excluded from the Area calculation. 3rd Party Tenure has been excluded from this table.
Land Values are included within the Net Book Values.
Chart 1A: Physical Condition – Percentage of Blocks with Overall Block Condition
NB: Third Party Ownership tenure has been excluded. Block No. 00 has been excluded.
Page 46
Chart 1B: Physical Condition – Percentage of Square Metres with Overall Block Condition
NB: Third Party Ownership tenure has been excluded. Block No 00 has been excluded.
Table 2: The physical condition of the estate
Physical Condition Backlog (and Impending Backlog) Cost/Percentage of Total A-New B-Acceptable Condition C-Requires Investment D-Unacceptable Condition Unreported
Type Cost % Cost % Cost % Cost % Cost % Total
05 Mental Health Hospital 3,955.00 0.07 5,306,230.00 94.45 286,229.00 5.09 21,449.00 0.38 0.00 0.00 5,617,863.00
23 Offices 0.00 0.00 11,300.00 33.33 18,080.00 53.33 4,520.00 13.33 0.00 0.00 33,900.00
24 Support Facilities 0.00 0.00 28,250.00 89.29 3,390.00 10.71 0.00 0.00 0.00 0.00 31,640.00
% of Overall Total 3,955.00 0.07 5,345,780.00 94.06 307,699.00 5.41 25,969.00 0.46 0.00 0.00 5,683,403.00
NB: 3rd Party Tenure and PFI Tenure have been excluded from this table. Blocks with Code No'00' have been included.
Page 47
Table 3: Physical Condition – Risk profiled backlog costs
Physical Condition Backlog Cost/Percentage of Total Type Low % Moderate % Significant % High % UnReported % Total
05 Mental Health Hospital 0.00 0.00 202,383.00 65.78 105,295.00 34.22 0.00 0.00 0.00 0.00 307,678.00
23 Offices 1,130.00 5.00 4,520.00 20.00 16,950.00 75.00 0.00 0.00 0.00 0.00 22,600.00
% of Overall Total 1,130.00 0.34 206,903.00 62.01 125,635.00 37.65 0.00 0.00 0.00 0.00 333,668.00
NB: This table includes only Costs where the Physical Condition grading is Not A or B. 3rd Party Ownership and PFI Tenures are excluded from this table. Blocks with Code '00' have been included.
Chart 4: Physical Condition – Risk profiled backlog costs
NB: This chart only includes costs where the Physical Condition grading is Not A or B. Third Party Ownership tenure and PFI tenure are excluded.Blocks with Block No '00' are included.
Page 48
Table 5: Statutory Compliance – Risk profiled backlog costs
Statutory Compliance Cost/Percentage of Total Type Low % Moderate % Significant % High % Unreported % Total
05 Mental Health Hospital 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
23 Offices 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
24 Support Facilities 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
% of Overall Total 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
NB: This table includes all Statutory Compliance (A,B,C,D) including unreported. Third Party Ownership and PFI tenure are excluded. Blocks with code '00' are included in this table.
Table 7: Energy Performance Certificate
EPC Ratings
C or Better D E F G Not Required Unreported
Type Area sq m No of
Bldgs. Area sq m No of
Bldgs. Area sq m No of
Bldgs. Area sq m No of
Bldgs. Area sq m No of
Bldgs. Area sq m No of
Bldgs. Area sq m No of
Bldgs.
05 Mental Health Hospital 17,185.64 6 1,304.77 1 200.92 1 0.00 0 0.00 0 0.00 0 0.00 0
23 Offices 0.00 0 1,899.45 2 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0
24 Support Facilities 2,935.65 4 0.00 0 0.00 0 0.00 0 0.00 0 75.99 1 0.00 0
TOTALS 20,121.29 10 3,204.22 3 200.92 1 0.00 0 0.00 0 75.99 3 0.00 0
This table shows the total GIA and the number of all blocks with a record in the Block Condition table with a facet of 9 - Environment. All condition ratings are included plus Unreported, but A, B and C
condition ratings are shown added together in one column. Blocks with Block No 00 are excluded.
Page 49
Table 8: Results from the appraisal of functional suitability
Functional Suitability
A –Very Satisfactory B - Satisfactory C – Not Satisfactory D - Unacceptable Unreported Type Area sq m % Area Sq m % Area sq m % Area sq m % Area sq m % Total
05 Mental Health
Hospital
17,839.09 98.98 183.93 1.02 0.00 0.00 0.00 0.00 0.00 0.00 18,023.02
23 Offices 1,369.25 75.50 444.31 24.50 0.00 0.00 0.00 0.00 0.00 0.00 1,813.56
24 Support
Facilities
2,460.23 83.93 470.95 16.07 0.00 0.00 0.00 0.00 0.00 0.00 2,931.18
% of Overall Total 21,668.57 95.17 1,099.20 4.83 0.00 0.00 0.00 0.00 0.00 0.00 22,767.77
NB: This table is based on ratings allocated against Rooms/Areas. Third Party Ownership Tenure has been excluded.
Table 10: Results from the appraisal of space utilisation
Space Utilisation
E – Empty Not Used U – Under Utilised F – Fully Utilised O - Overcrowded Unreported Type Area sq m % Area Sq m % Area sq m % Area sq m % Area sq m % Total
05 Mental Health Hospital 1,216.78 6.75 1,358.16 7.54 15,448.09 85.71 0.00 0.00 0.00 0.00 18,023.02
23 Offices 0.00 0.00 91.40 5.04 1,722.16 94.96 0.00 0.00 0.00 0.00 1,813.56
24 Support Facilities 14.00 0.48 0.00 0.00 2,905.08 99.11 12.10 0.41 0.00 0.00 2,931.18
% of Overall Total 1,230.78 5.41 1,449.56 6.37 20,075.33 88.17 12.10 0.05 0.00 0.00 22,767.77
NB: This table is based on the ratings allocated against Room Areas. Third Party Ownership is excluded.
Page 50
Table 11: Results from the appraisal of Quality
Quality
A –Very Satisfactory B - Satisfactory C – Not Satisfactory D - Unacceptable Unreported Type Area sq m % Area Sq m % Area sq m % Area sq m % Area sq m % Total
05 Mental Health Hospital 6,106.46 33.88 11,916.56 66.12 0.00 0.00 0.00 0.00 0.00 0.00 18,023.02
23 Offices 0.00 0.00 1,813.56 100.00 0.00 0.00 0.00 0.00 0.00 0.00 1,813.56
24 Support Facilities 0.00 0.00 2,931.18 100.00 0.00 0.00 0.00 0.00 0.00 0.00 2,931.18
% of Overall Total 6,106.46 26.82 16,661.31 73.18 0.00 0.00 0.00 0.00 0.00 0.00 22,767.77
NB: This table is based on ratings allocated against Rooms/Areas. Third Party Ownership Tenure has been excluded.
Table 12: Typical Analysis of Property Types
Functional Type Endowment
(GIA) sq m
Leased (GIA)
Sq m
Owned (GIA)
Sq m
PFI (GIA) Sq
m
Unreported
(GIA Sq m
Area (GIA) Sq
m
% of Total
Area
05 Mental Health Hospital 0.00 0.00 18,691.33 0.00 0.00 18,691.33 79.19
23 Offices 0.00 0.00 1,899.45 0.00 0.00 1,899.45 8.05
24 Support Facilities 0.00 0.00 3,011.64 0.00 0.00 3,011.64 12.76
TOTALS 0.00 0.00 23,602.42 0.00 0.00 23,602.42 100.00
NB Block Code 00 has been excluded from this table. Third Party Tenure has been excluded from this table.
Page 51
Table 13: Typical Analysis of Property Ownership
Area (GIA) sq m % of Total
Area
Count of
Blocks
Owned 23,602.42 100.00 17
TOTALS 23,602.42 100.00 17
NB: Block 00 has been excluded from this table
Chart 14: Analysis of Size Range of Properties
NB: Block 00 has been excluded from this table. Third Party Ownership has been excluded.
Page 52
Table 15: Age Profile of Properties
Count of Blocks Area (m2) Backlog Cost
Pre 1900 0 0.00 £0.00
1900 - 1960 3 429.79 £276,285.00
1961 - 1980 0 0.00 £0.00
1981 - 2000 1 1,433.73 £16,950.00
2001 or more recent 13 21,738.90 £40,433.00
UnReported 0 0.00 £0.00
TOTALS 17 23,602.42 £333,668.00
NB: Block 00 has been excluded from the Area Calculation but included in the Backlog Costs. Backlog Costs include Physical Condition C, D or Unreported and all Statutory Compliance conditions ratings. All
other costs have been excluded. Costs included only Owned, Leased or Endowment tenure. Count and Area Include all tenures except Third Party Ownership.
Table 16: Summary of Property Appraisal Results
Functional Type Gia Sq.m GIA as % of
Total Area
Backlog Expenditure Required
Low Risk Moderate Risk Significant Risk High Risk UnReported Total
05 Mental Health Hospital 18,691.33 79.19 - £202,383.00 £105,295.00 - - £307,678.00
23 Offices 1,899.45 8.05 £1,130.00 £4,520.00 £16,950.00 - - £22,600.00
24 Support Facilities 3,011.64 12.76 - - £3,390.00 - - £3,390.00
UnReported 0.00 0.00 - - - - - -
TOTALS 23,602.42 100.00 £1,130.00 £206,903.00 £125,635.00 - - £333,668.00
NB: Block 00 has been excluded from the area calculation but included in the backlog costs. Backlog Costs include Physical Condition C, D or Unreported and all Statutory Compliance conditions ratings. All
other costs have been excluded. Third Party Ownership has been excluded.