The Primavera Suite: How the tools work togetherSession ID#: 15466
Prepared by:Alexander VosDirector of SchedulingPeter Kiewit Sons
![Page 2: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/2.jpg)
IntroductionAlexander VosDirector of Scheduling■ Peter Kiewit Sons for 6 years■ From: Oak Ridge, NC■ Live in Omaha, NE■ Experience in both construction field and IT
![Page 3: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/3.jpg)
■ Engineering and Construction■ North America and Australia■ Multiple Markets and Industries
![Page 4: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/4.jpg)
![Page 5: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/5.jpg)
Objectives
■ Explain how data is transferred between the applications▪ Publishing▪ ETL
■ Explain the architecture of the overall system
■ How administration of this new system has changed
![Page 6: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/6.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
ETLETL
Analytics
Dashboards
BI Publisher REPORTS ETLETL
Primavera
Member
Primavera Team
Member
iOS
HTTP
Context Sensitive Help
Overall Environment
![Page 7: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/7.jpg)
Oracle Database - Production
Energy
Infrs
Tech/IM
X01
X02
![Page 8: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/8.jpg)
Primavera Production Database
■ Oracle Database R11■ Where All Data Resides
▪ 5 Databases— Energy
— Infrastructure
— Estimating
— KCI
— X01 - Exception
![Page 9: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/9.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
ETLETL
Analytics
Dashboards
BI Publisher REPORTS ETLETL
Primavera
Member
Primavera Team
Member
iOS
HTTP
Context Sensitive Help
Primavera Professional (Client)
![Page 10: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/10.jpg)
P6 Windows (Desktop) Client
• ‘Heavy lifting’• TIAs (Time Impact
Analysis)• VDI (Virtual Desktop
Infrastructure)
Roles• Schedulers• Schedule Managers
Primavera P6 Release 8 “R8.2 Client”
![Page 11: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/11.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
ETLETL
Analytics
Dashboards
BI Publisher REPORTS ETLETL
Primavera
Member
Primavera Team
Member
iOS
HTTP
Context Sensitive Help
Primavera EPPM (Web Based)
![Page 12: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/12.jpg)
■ Oracle 11.2.0.2+ Enterprise■ Oracle Linux 64 Bit■ 3TB Storage
Primavera EPPM (Web Based)
![Page 13: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/13.jpg)
EPPM PortfoliosProject Codes help organize the projects in the EPS (Enterprise Project Structure) in groups according to specific categories, such as district, Type of Schedule, and Contract Type. By assigning project Codes P6 can filter, sort and provide reporting information for Kiewit Projects.
By entering in Project Codes using “Kiewit Standard Project Code
Assignment” Layout custom EPPM dashboards are populated.
Portfolio DrivesPortfolio Drives
Project Codes define portfolio criteria
Project Codes define criteria for the Dashboard
![Page 14: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/14.jpg)
Primavera Release 8.2 EPPM■ Web based access to Database
![Page 15: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/15.jpg)
Primavera Release 8 “R8.2 Web”• Role-based Views• Portfolio focused
Dashboards• Project-based
Collaboration Workspace• Risk Register• Project Documents• Issues• Team Communication
• Geospatial
![Page 16: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/16.jpg)
EPPM Dashboards
![Page 17: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/17.jpg)
![Page 18: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/18.jpg)
EPPM Enhancements
■ “Link selected” in order of clicks■ Control arrows for hierarchy■ Right click collapse all
![Page 19: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/19.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
ETLETL
Analytics
Dashboards
BI Publisher REPORTS ETLETL
Primavera
Member
Primavera Team
Member
iOS
HTTP
Context Sensitive Help
Primavera Analytics
![Page 20: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/20.jpg)
Proprietary and Confidential
• Advanced ‘Drill Down’ / Analytical Dashboards & Reports
• Trends• Robust Ad-hoc reporting• Geospatial reports• Combine third party data for joint
analysis
• Roles• Schedulers• Schedule Managers• District Management• Corp Management
Primavera Analytics
![Page 21: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/21.jpg)
Primavera Analytics - Dashboards
![Page 22: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/22.jpg)
Primavera Analytics
![Page 23: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/23.jpg)
■ P6 Analytics R3.1■ Oracle Linux 64 Bit■ 4 Core – 16 GB Ram■ 100GB Storage
Primavera Analytics
![Page 24: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/24.jpg)
Earlier Versions
![Page 25: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/25.jpg)
Primavera Analytics
PxSchema
![Page 26: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/26.jpg)
Primavera Analytics - Publishing
Energy
Infrs
Tech/IM
X01
X02
![Page 27: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/27.jpg)
■ Px Schema▪ Life line of Analytics▪ Only fields in Px Schema are available in Analytics
Primavera Analytics - Publishing
![Page 28: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/28.jpg)
Primavera Analytics – ETL(Extract Transform Load)
Energy
Infrs
Tech/IM
X01
X02
![Page 29: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/29.jpg)
■ Extracting data from PMDB
■ Transforming it into format acceptable to Star Schema
■ Loading into Star Schema
Primavera Analytics – ETL(Extract Transform Load)
![Page 30: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/30.jpg)
Primavera AnalyticsEnhancements
■ Add Successor and Predecessor fields to Analytics■ More training available■ Analytics UPK packages
![Page 31: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/31.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
ETLETL
Analytics
Dashboards
BI Publisher REPORTS ETLETL
Primavera
Member
Primavera Team
Member
Publish
Hourly
Hourly
iOS
HTTP
Context Sensitive Help
Business Intelligence Publisher
![Page 32: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/32.jpg)
■ Java JDK 1.6.0_27■ WebLogic 11gR1 (10.3.5)■ Oracle Linux (64 Bit)■ 8 Core - 16GB Ram■ 250 GB Storage
Business Intelligence Publisher
![Page 33: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/33.jpg)
■ Star Database – Analytics▪ Extended Schema▪ Hierarchical Relationships▪ Efficient & Flexible Analysis
■ ODS (Operational Data Store) – BI Publisher▪ Simplified & Easy to Understand for Reporting▪ Views Similar to P6 EPPM
— OBS, project, cost, and resource data
Star Database vs. ODS
![Page 34: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/34.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
ETLETL
Analytics
Dashboards
BI Publisher REPORTS ETLETL
Primavera
Member
Primavera Team
Member
iOS
HTTP
Context Sensitive Help
Primavera Team Member
![Page 35: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/35.jpg)
Proprietary and Confidential
Team Member Updates
• Simplified ‘no training’ Project Statusing
• Web Application• iPhone Application• E-mail Statusing
• Roles• Schedulers• Superintendents• Subcontractors• Superintendents
![Page 36: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/36.jpg)
Team Member App Updates – iOS App
![Page 37: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/37.jpg)
• Quickly update tasks via Web• Requires little to no training• Predecessor and successor
P6 Team Member - Web App
![Page 38: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/38.jpg)
P6 Team MemberEnhancements
■ Edit Resource Assignment UDFs in Team Member
![Page 39: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/39.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
ETLETL
Analytics
Dashboards
BI Publisher REPORTS ETLETL
Primavera
Member
Primavera Team
Member
Publish
Hourly
Hourly
iOS
HTTP
Context Sensitive Help
Primavera User Productivity Kits (UPK)
![Page 40: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/40.jpg)
■ Technical Info▪ IIS Server▪ SQL Database
Primavera User Productivity Kits (UPK)
![Page 41: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/41.jpg)
• Animated Demonstrations• See it! Try it! Do it! Print it!• Primavera Library• Develop Kiewit specific• Processes / Other
Applications• Minimize training / retraining• Reduce Support calls
• Roles• Schedulers• Super Users• Schedule Managers• Off Site Users
Primavera User Productivity Kits (UPK)
![Page 42: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/42.jpg)
UPK Creation – Record It
■ Adds “team member” functionality for UPK
■ Scheduler can create training video and allow admin to approve and publish to web
![Page 43: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/43.jpg)
Proprietary and Confidential
UPK Record It Licenses
• Rules of Engagement• Script is available via KCI
• Wizard Based• End Users Ability to Create Videos
![Page 44: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/44.jpg)
Overall Administration
■ All admin features are in EPPM■ “Loading” master data now requires coding instead of SDK
![Page 45: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/45.jpg)
Conclusion
■ The overall Primavera Suite is now much more than a database and a “thick client”
■ Multiple moving parts which DBA’s, SA’s, need to work hand in hand with “functional” people
■ Administration of Primavera requires more knowledge of coding (SDK vs API)
![Page 46: The Primavera suite how the tools work together - Oracle Primavera Collaborate 14](https://reader033.fdocuments.in/reader033/viewer/2022051315/55cee468bb61ebab108b4578/html5/thumbnails/46.jpg)