Using Primavera Analytics across multiple remote site locations
Prepared by:Alexander VosDirector of SchedulingPeter Kiewit Sons
A pragmatic approach to remote site connections.
Session ID#: 15474
![Page 2: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/2.jpg)
IntroductionAlexander VosDirector of Scheduling■ Peter Kiewit Sons for 6 years■ From: Oak Ridge, NC■ Live in Omaha, NE■ Experience in both construction field and IT
![Page 3: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/3.jpg)
■ Engineering and Construction■ North America and Australia■ Multiple projects in remote locations
![Page 4: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/4.jpg)
![Page 5: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/5.jpg)
![Page 6: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/6.jpg)
![Page 7: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/7.jpg)
Objectives
■ Explain the tiered environment strategy developed for remote sites
■ How “check in/check out” can benefit this process■ Demonstrate the benefits and understanding of what
analytics is, use cases, and examples
![Page 8: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/8.jpg)
Tiered Environments I-V
Individual Laptop “Tier V”•EPS Tree Matching Corporate EPS
•“Administrator” Profile•Local Database and Client Install
•Limited options for IM maintenance
•No VDI, EPPM, TM, etc
JobSite Server “Tier IV”•Database on Jobsite server•Local client Install•Maintained by IM Dept•No VDI, EPPM, TM, etc•Preferred remote setup
District Office “Tier III”•Database on District Office Server
•Maintained by IM•No VDI, EPPM, TM, etc•Most uncommon setup
Exception “Tier II”•Same as above•Reserved for anomalies
Main Database “Tier I”•Database in Data Center•EPPM•Client available on Citrix (VDI)•Maintained Corporately•Standard Master Data
REPORTS TO P6 ANALYTICSCHECK IN/OUT FEATURE TO ALLOW ANALYTICS
![Page 9: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/9.jpg)
What does the Tier I environment look like?
This is a subtitle or bulleted list
![Page 10: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/10.jpg)
PrimaveraProfessional (VDI)
XENA
Primavera EPPM (Web
Based)
Import/ Export
Updates
KMC
EPPM Dashboards
Analytics
Dashboards
BI Publisher REPORTS
Primavera
Member
Primavera Team
Member
iOS
HTTP
Context Sensitive Help
Tier I and II Environment
ETL
ODSEnergy
Infrs
Tech/IM
X01
X02
![Page 11: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/11.jpg)
Tiered Environments
■ Tier 1 and Tier 2 – Are different but share the following attributes▪ “Hooked up” to Analytics▪ EPPM, Client on Citrix▪ Inside Corporate Data Center
■ Tier 3 / Tier 4 / Tier 5 – Used for remote sites or areas with remote connectivity and here are the shared attributes▪ Projects checked into Tier I minimum monthly for reporting▪ Kiewit Standardized EPS root possessing a placeholder in Tier 1
for the respective project
![Page 12: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/12.jpg)
Tier V Environment
■ Installed on end user machine referred to “stand alone”■ Individual projects will need to be checked in and checked out
into Tier I Environment▪ Minimum checked in Monthly▪ Allows for Analytics
■ Does not require internet access (except during Check In/Out)▪ Can be checked in while on “turnaround”▪ File can be sent to Corporate to check it in
![Page 13: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/13.jpg)
Tier V Environment Installation Preparation
■ Primavera V7.3 Oracle Stand Alone Data Base with Developer Kit (SDK) installed.
■ Oracle XE Database■ Use the SDK to populate standard master data■ Upgrade Data Base to Primavera Release 8.2.2.1■ Establish upgraded Data Base as “Gold Standard”■ Restore Primavera “Gold Standard” Data Base on end user
machine
![Page 14: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/14.jpg)
What determines if a Tier V environment is needed?■ Internet connection speed
▪ 1800 m/s■ Client requirements
![Page 15: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/15.jpg)
Tier V Environment Schedule Process
Individual Laptop “Tier V”4. Check the file into the database5. Develop schedule with project team6. Matching the update periods, check the schedule back into the Tier I environment
Main Database “Tier I”1. Create EPS node within Standard Structure2. Create Project File with associated master data3. Check the file out of the main database7. “ETL”s will the pick up updated information for analytics and reporting
![Page 16: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/16.jpg)
Has anyone ever used the Check in/out feature?
This is a subtitle or bulleted list
![Page 17: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/17.jpg)
Check ‘it’ Out… or In – What?
■ Schedules can be checked out (exported) so that they can be worked on remotely – a sort of ‘versioning’.
■ Difference between checked out and export – checked out schedules cannot be modified until they are checked back in – regardless of user access.
■ Multiple schedules can be checked out (as an export to an XER) to the same user.
■ Existing schedules can be replaced with the remote copy by using the Check In (import) wizard.
■ As with the export option, baselines are not included.■ A ‘reflection’ schedule cannot be merged into a source
schedule that is checked out.■ Past period actuals cannot be modified when the schedule is
checked out.
![Page 18: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/18.jpg)
Check ‘it’ Out… or In – Why?
■ The Kiewit enterprise structure (library of projects) is the standard for all databases (‘remote’ included)▪ All project schedules
(‘remote’ included) will have their place (EPS node) in the Enterprise Project Structure
▪ Consistency is key for analyses and reporting
![Page 19: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/19.jpg)
Check ‘it’ Out… or In – When?
■ There are two options when checking in (update project or replace project).
■ Update Project – does not delete baselines■ Replace Project – DOES DELETE baselines. However, the
user is warned that all project data will be deleted, including BASELINES.
■ Check Out▪ After ‘initial’ schedule is added, project team has been assigned
■ Check In▪ After schedule baseline is submitted▪ After schedule update has been submitted and approved
![Page 20: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/20.jpg)
Check ‘it’ Out…
■ Open the schedules to be checked out – rules of the XER will apply (i.e. can be multiple files).
■ File menu, Check Out
■ Select the schedule(s) from the Open Projects list. ▪ (Note: The schedule must be
open in order to check it out.)
■ Type the name of the file and the location to save the XER.
■ Click Finish
![Page 21: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/21.jpg)
Check ‘it’ Out… or In – How? (cont.)
■ Select the data to check in by modifying the layout configuration in the Update Project Options dialog box▪ Note: Global data is not
affected by the Delete option
![Page 22: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/22.jpg)
Check ‘it’ Out… or In – How? (cont.)
■ Open the schedules to be checked in
■ File menu, Check in■ Select the file to check in■ Double click the Import Action
field to select how the project data is checked in
■ Click Finish
![Page 23: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/23.jpg)
Check ‘it’ Out… or In – Who?
■ Check Out access▪ User must have Project
Security Profile option, “CheckIn / CheckOutProject”
■ Check In access▪ Users much have Project
Security Profile option, “CheckIn / CheckOutProject”
▪ User must have Global Security Profile option, “Import Global Information”
![Page 24: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/24.jpg)
Analytics
■ Dashboard to manage Tier III-V environments■ Project Code denotes the environment■ Other Project Codes show additional details■ Conditional Formatting shows if the data date is over 60 days
from Data Date
Tier V
![Page 25: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/25.jpg)
Analytics demonstration
Analytics Production Link
This is a subtitle or bulleted list
![Page 26: Using primavera analytics across multiple remote site locations - Oracle Primavera P6 Collaborate 14](https://reader034.fdocuments.in/reader034/viewer/2022051101/58f0af441a28ab767c8b45fd/html5/thumbnails/26.jpg)
Please complete the session evaluationWe appreciate your feedback and insight
You may complete the session evaluation either on paper or online via the mobile app