The Plan and Plan Review

37
1 The Plan and Plan Review Issued May 2009 Level IB: Advanced Fundamentals Seminar Education and Training Certification Requirements for Persons Involved with Land Disturbing Activities

description

The Plan and Plan Review. Level IB: Advanced Fundamentals Seminar Education and Training Certification Requirements for Persons Involved with Land Disturbing Activities. Issued May 2009. Introduction. The Erosion, Sedimentation and Pollution Control Plan (ES&PC Plan) - PowerPoint PPT Presentation

Transcript of The Plan and Plan Review

Page 1: The Plan and Plan Review

1

The Plan and Plan Review

Issued May 2009

Level IB: Advanced Fundamentals Seminar

Education and Training Certification Requirements for Persons Involved with Land

Disturbing Activities

Page 2: The Plan and Plan Review

2

Introduction

The Erosion, Sedimentation and Pollution Control Plan

(ES&PC Plan)• Plan development process• Plan review process• Plan review checklist • Reading the plan

Page 3: The Plan and Plan Review

3

ES&PC Plan

An ES&PC plan shows:• a series of structural and vegetative best

management practices (BMPs) to control erosion and prevent sedimentation within a disturbed area.

• Detailed requirements for monitoring, inspections, reporting and record keeping.

Page 4: The Plan and Plan Review

4

The Plan Development Process

Page 5: The Plan and Plan Review

5

Steps to an Effective ES&PC Plan1. Project requirements2. Project/resources description3. Data collection (site visit)4. Data interpretation5. Plan preparation6. Plan Review/Approval7. Implementation8. Operations, maintenance and inspections9. Final stabilization

Page 6: The Plan and Plan Review

6

Project Construction Issues

• Project location

• Required pre-design site visit

• Project size

• Project type

• Project phasing

• Project schedule

Page 7: The Plan and Plan Review

7

Required Site Visit• What a designer looks for:

– Existing vegetation– Potential U.S./State Waters– Flood plain– Springs– Soils– Drainage basins (both onsite and offsite)– Wetlands– Other possible critical areas

Page 8: The Plan and Plan Review

8

Planning

• Stripping of vegetation, regrading and other development activities shall be conducted in such a manner so as to minimize erosion

• Cut and fill operations must be kept to a minimum

• Development plans must conform to topography and soil type, so as to create the lowest practicable erosion potential

• Whenever feasible, natural vegetation shall be retained, protected and supplemented

Page 9: The Plan and Plan Review

9

Planning

• Disturbed soil shall be stabilized as quickly as possible

• Temporary vegetation or mulching shall be employed to protect exposed critical areas during development

• A series of well designed, installed, and maintained best management practices (BMPs) shall be implemented to control erosion at the source and prevent suspended sediments from leaving the site

Page 10: The Plan and Plan Review

10

Planning• Adequate provisions must be provided to minimize damage from

surface water to the cut face of excavations or the sloping surface of fills

• Cut and fills may not endanger adjoining property

• Fills may not encroach upon natural watercourses or constructed channels in a manner so as to adversely affect other property owners

• Any proposed disturbance within a stream buffer must complete all necessary applications and receive all necessary approvals before beginning disturbance

Page 11: The Plan and Plan Review

11

Plan Concepts

• Adapt the plan to resources available• When possible, fit the project into the

existing terrain• Recommendations must be cost effective• The plan must be flexible• Maintain open communication with

developer, contractors and local issuing authority

Page 12: The Plan and Plan Review

12

Plan Concepts

• Notes and instructions must be clear and simple

• Timing and scheduling are very important

• Establish an effective maintenance program

• Identify critical areas offsite

Page 13: The Plan and Plan Review

13

Construction Sequencing• Plan sequence with contractor

• Advise inspector/LIA of sequence at pre-construction meeting

• Evaluate sequence during implementation

• Make sequence revisions if necessary

• Resubmit revised plans for approval to LIA or local SWCD

• Final stabilization plan

Page 14: The Plan and Plan Review

14

What types of plan revisions require additional design and review?

• The onsite addition of silt fence, check dams, and other generic BMPs DO NOT require design and review (BMPs must still conform with minimum standards set forth in the Manual)

• Modifications and addition/removal of designed structural BMPs such as sediment basins require professional design and review and approval!

Page 15: The Plan and Plan Review

15

The Erosion, Sedimentation and Pollution Control Plan

ChecklistsThree checklists:

• Stand Alone Projects• Infrastructure Projects• Common Developments

Appendix 1

Available atwww.gaswcc.georgia.gov

Page 16: The Plan and Plan Review

16

Updates

• The new checklists include all previous requirements of the June 2007 version

• Updated to include provisions of the new NPDES General Permits

Page 17: The Plan and Plan Review

17

Elements of the Checklist

• Site Plan– Site Location

Information– Surveys, Maps,

Soils, Hydrology Study

– Delineation of State Waters and Buffers

– Phasing of ES&PC Plan

• Narrative Notes and Other Information– Maintenance Notes– Contact Info– Signature and Seal– BMP Details – Storage Calculations– Vegetative Plan– Compliance with

NPDES Permits

Page 18: The Plan and Plan Review

18

Importance of Using Checklist

• The designer refers to checklist before, during and after design. Obtain all necessary information and visit the site BEFORE beginning the design!!!

• Designers and reviewers both work on many plans and using the checklist on every set of plans will help ensure important info is not forgotten.

Page 19: The Plan and Plan Review

19

Submitting an ES&PC Plan for Review

•Once ES&PC plan is complete (all checklist

items addressed), submit plans to local

issuing authority. If the local issuing

authority does not have an MOA, they

forward plans to the local SWCD.

•Must include copy of checklist with page

numbers indicating where information can be

found.

Page 20: The Plan and Plan Review

20

Original Submittal

• Typically, there will be some form of comments during the original submittal

• Plans received without the signature and seal of the Design Professional will not be reviewed.

Page 21: The Plan and Plan Review

21

Second and Third Submittals

• By submitting a complete ES&PC plan on first submittal, plans can usually be approved on first or second submittal.

• Plans that have extensive comments on original submittal, typically are not approved until at least the third submittal and this can dramatically delay the permitting process.

Page 22: The Plan and Plan Review

22

Submitting an ES&PC Plan for Review• In areas where there

is not a certified issuing authority, 1 copy of the plan is submitted to EPD’s Watershed Protection Branch and 1 copy to the appropriate EPD District office

Page 23: The Plan and Plan Review

23

Relationship between Designers and Reviewers

• The Design Professional designs plans and is ultimately responsible if plans fail

Adjacent property owner’s lake impacted due to poor planning and implementation

Page 24: The Plan and Plan Review

24

Reviewer’s Role

• Ensure all checklist items are addressed• Reviewers do more than check off checklist

– Make sure plans consist of three phases with a series of sound Best Management Practices

– Ensure BMPs are designed in accordance with specifications set forth in the “Green Book”

– Adequate sediment storage for each drainage basin onsite

– Look for stream buffer encroachments that are not going for EPD variance application

Page 25: The Plan and Plan Review

25

Relationship between Designers and Reviewers• Reviewer “double

checks” plan to ensure minimum requirements are met

• Designer should welcome reviewer’s comments and concerns

Page 26: The Plan and Plan Review

26

Reading the Plans

Page 27: The Plan and Plan Review

27

Reading the Plan

• A good ES&PC plan provides all the necessary information that will allow an individual to view the site plan and understand what is taking place at any given time.

Page 28: The Plan and Plan Review

28

Reading the Plan• Recognize existing and proposed grading

activities• Evaluate topography, slope steepness and

slope profiles, using given contours on plans

• Recognize drainage patterns and basins • Check the selection, location, and

effectiveness of approved BMPs as shown on plans

Page 29: The Plan and Plan Review

29

Topographic Mapping

Most grading plans are based on some type of topographic map. Topographic information allows a trained viewer to see the plan in three dimensions, thus enabling the viewer to see changes in grade within the site.

Page 30: The Plan and Plan Review

30

The flow of water is always perpendicular to the contour

“saddle”

summit

Page 31: The Plan and Plan Review

31

Reading the Plans

• Perhaps, the most important aspect of reading the plans is understanding the onsite and offsite drainage patterns for pre, during and post construction conditions.– Initial plan for perimeter control and initial

sediment storage– Intermediate plan for grading and drainage– Final ES&PC plan

Page 32: The Plan and Plan Review

32

The first step in identifying drainage basins within a site is to find the high and low points and determine the overall directions of flow. The ridges and valleys start to “appear”.

790800

810

820

820

820

830

840

850

860

850

840

830

820

810

790

800

810

857

864.41

Drainage Basin Delineation

Page 33: The Plan and Plan Review

33

790800

810

820

820

820

830

840

850

860

850

840

830

820

810

790

800

810

857

864.41

Study where the water

flows

Page 34: The Plan and Plan Review

34

Drainage boundaries can then be drawn along the ridges where the flow patterns break in opposite directions. Drainage basins, also called “watersheds”, are now defined. Each basin can now be treated as a separate site.

790800

810

820

820

820

830

840

850

860

850

840

830

820

810

790

800

810

857

864.41

Page 35: The Plan and Plan Review

35

Scale 1” = 40 feet

734

732

drainage boundary in graded area

Sd3

Cd

X

X

X

X

X

X

X

X

X

X

Page 36: The Plan and Plan Review

36

Plans on the Site

• An approved set of plans must be on site at all times.

• Use approved plans for each inspection.

Page 37: The Plan and Plan Review

37

Questions???