The Johns Hopkins UniversitySchool of Medicine
Office of Research Administration
Subgrants & Subcontracts Training
1
Nov 2014
Our Work is Divided into Two Categories…
Drafting, execution, and termination of outgoing subgrants and subcontracts
Purchase order creation, management, and termination
2
A subgrant or subcontract is necessary when:◦ The site will perform work which satisfies a direct
objective or deliverable of the Prime Award◦ The site will be responsible for programmatic decisions
or design related to the project/study under the Prime Award
◦ The site will be held accountable to the compliance regulations of the Prime Award (COI, IP, etc) or may seek to publish/co author the study results
◦ The site will use the Prime Award funds to carry out its own programmatic work
◦ The site provides cost sharing or has key personnel mentioned in the NGA
When is an Outgoing Subaward Necessary?
3
4
Service/Vendor Agreement (drafted by Purchasing, PO set up by dept):◦ If the site is providing standard services (those in the normal
operations and markets to a variety of customers)◦ If the site has not/will not provide significant contributions to the
design/conduct of the project◦ If the site is not responsible for the project results◦ If the site performs work that involves routine or repeated activities◦ If the site will not seek to publish or co-author based on the
academic standards such as the ICJME standards Storage (drug, supplies, etc.) Website design & management for a clinical trial. KKI Kirby Center Agreements Draft Examples: http://ssc.jhmi.edu/supplychain/forms/index.html
Data Use Agreement Complex Material Transfer Agreement Collaboration Agreement
Other Types of Agreements… (Not Drafted by Subawards Team)
Subgrants under Federal grants Subcontracts under Federal and state
contracts Subgrants under awards from foundations Subcontracts under commercial contracts Funding from multiple sources
◦ Please try to make us aware of all the sources of funding (commercial and non-commercial) for the subaward
Internal JHU awards
Types of Prime Sponsor Funding…
5
NTAP – Neurofibromatosis Therapeutic Acceleration Program
ABTC – Adult Brain Tumor Consortium TBCRC – Translational Breast Cancer
Consortium PACKARD – The Robert Packard Center for
ALS Research CRN – Clinical Research Network (AAHSRI,
GBMC, INOVA, PRMC, RHMC)
Internal JHU Funding/Other…
6
ORA Operations Analyst
sends NGA to
ORASUBCONTRACTS contacts departme
ntal contact for docs
Departmental
contact sends
information to
ORASUBCONTRACTS
ORASUBCONTRACTS assigns file to Subs Team
MemberSubs Team
Member evaluat
es information and drafts the
subcontract and submits
it for supervi
sory review
Subs Team memb
er sends contra
ct draft
to subsit
e.
Subs Team
member
requests sub-
IO, also known as the
“96 number
”. (Origina
l Agt)
Subs Team
member
creates shopping cart in
SAP. (It must
be approve
d). (Original Agt)
Subsite
sends back sub.
Potentially,
negotiations follow.
Subsite signs
sub and sends
back to Subs Team
member, with other
required docs.
Subs Team
member enters purchase order number on orig sub or
updates PO
(mod)
Subs team sends
PE contract, email
from site, to Subs
Manager for
signature
ORASUBS
sends FE sub to the subsit
e, dept.
contacts and JHU PI
ORASUBS
closes file and
database
7
For an original sub: A Subaward Determination Form
This is completed and signed by the JHU PI, and uploaded into COEUS during the proposal phase. The outgoing subs team will sign for ORA and keep the form in the Subaward file
A Subaward Information Sheet A budget for the subsite A statement of work for the subsite IRB/IACUC approval for the subsite Wire transfer agreements for subsites in foreign countries Conflict of Interest Documentation (Federal Prime) if site is not in the
FDP Clearinghouse http://sites.nationalacademies.org/PGA/fdp/PGA_070596
And for new sites … Questionnaire, DUNS #, SAM registration For modifications:
A Subaward Information Sheet A budget A statement of work (but only if it has changed) Updated IRB/IACUC approval Conflict of Interest Documentation (Federal Prime) if site is not in the FDP Clearinghouse
What Information is Necessary?
8
[email protected] for processing and assignment to a Subawards Team Member
Subawards Specialists draft subs under Federal Grants When the prime award is a federal contract, a commercial
contract, or an award from a foundation, it will be handled by:◦ Melody:
Original subcontracts under federal and all commercial contracts
CRN SSA’s, NTAP, TBCRC, internal accounts◦ Michelle:
Subs under foundation awards Modifications of subcontracts under federal contracts ABTC
Who Does the Department Submit Outgoing Subaward Paperwork to?
9
JHU contact information The “Financial Contact” is the person who processes invoices and
goods receipts The “Study Contact” is the person who can answer scientific
questions about the protocol. Most recent subsite contact information
In most cases, the contact should be in the Research Administration office at the subsite.
Verify that it is current each year an Information Sheet is submitted. SAP grant #, COEUS IPN #, Prime award/contract IO #, PI’s cost center
# Sponsor grant/contract # (JHU is only the “sponsor” under 800 act's) Deliverables and due dates/time-lines for new/revised SOW’s Whether animal and/or human subjects research is going to be
conducted at the subsite. Budget Period for the sub & amount to pay the subsite (PO amount) Information related to the Study for Clinical Trials Information related to Transfer of drug, equipment or materials.
Subcontract Information Sheet…
10
Budgets for subs under Federal grants should include: Names of personnel Breakdown of costs for equipment, supplies, and “other
expenses” Explanation of travel costs
In all budgets, if the site is going to be paid for each patient it accrues, or for each sample it obtains, etc., the budget must indicate the number of patients/samples and the amount that will be paid for each one.
Consider whether the costs are allowed under the terms of the award/contract.
Budgets…
11
Alternately known as a “work scope”, the SOW is a short paragraph describing what the Subsite is doing. The SOW should NOT be a summary of the whole grant.
The SOW should also state what the subsite is going to provide to JHU in exchange for being paid (“deliverables”). Examples include patient data from clinical trials, blood samples, tissue samples, assays, scans, and analysis of samples, or even reports/publications and conference calls to discuss results. Deliverables can be tied to payment. ◦ For example, the site will be paid $10,000 for every five patients it enrolls in a clinical
trial.
SOW should be understandable to non-scientists. The SOW is used in a dispute to determine whether the site is
performing in accordance with the agreement, so be clear and specific.
The Deliverables table will be part of the SOW and subaward and should include concrete due dates/time lines
Statement of Work…
12
It is up to the Subsite’s IRB/IACUC to determine whether human subjects and/or vertebrate animals research is being conducted.
ORA does NOT need the Subsite IRB approval to send the Agreement, but we must have it to fully-execute the Agreement.
KKI and the CRN site Study Team Members should be included as part of the JHU IRB approval prior to submission of paperwork to ORASUBS
13
IRB and IACUC approvals
Contains bank account and payment information for the Subsite.
Is attached to the Subaward as an exhibit
Must be copied onto Subsite letterhead New foreign vendors also require a W8 if the site is using a domestic bank
NOTE: new domestic vendors may also require a W9 so that a vendor number can be requested for the PO
14
Wire transfer agreements
Under Federal grants and contracts, all Subrecipients should be registered in the System for Award Management (“SAM”), and must have a DUNS number◦ SAM website: https://sam.gov◦ DUNS number requests: http://fedgov/dnd.com/webform
High Risk Subrecipient Monitoring:◦ ORASUBS will identify sites that need to complete a Subrecipient
Questionnaire ◦ The Dept will send the Welcome Packet and Questionnaire to the
identified sites and return it to ORASUBS◦ ORA rates the sites and notifies the dept and Internal Audits who
confirms the rating and performs subsite audits◦ High Risk Subrecipients must submit invoices on template included as
exhibit to the cost reimbursement Sub Agreement.◦ The JHU dept must complete additional invoice audits per the new risk
management regulations which took effect on 7/1/14.
Special Considerations for High Risk Subsites Under
Federal Funds…
15
As of 8/24/12: Subsites are required to submit COI information at the time of JHU application to the JHU Grants Associates if they are not registered in the FDP Clearinghouse.
2 Options: ◦ Complete, and certify best ability at time of JHU application◦ Opt to complete certification at time of Subagreement award
Subs team will choose appropriate COI language for the Agreement
If SCF was not completed at time of JHU application and the site is not registered in the FDP Clearinghouse, Subs team will request that the dept get an SFI from the Subsite prior to submission of Subaward documents to ORASUBCONTRACTS.
16
Conflict of Interest Under Federal Funds…
Under Federal subs…(MTDC) For subs under federal grants and contracts, JHU takes additional IDC on the
first $25K of the subcontract budget. For every subaward agreement drafted JHU IDC is requested
Ex: Proj A, Core, Proj B under P50 – all to UMB, different PI’s = multiple 96s and POs and agreements = JHU additional IDC one time.
Under non-Federal agreements…(TDC) Generally, under foundation awards and commercial contracts, the same IDC
rate is applied to both the JHU and the subsite budget. For foundation awards, it must be determined if the awarded IDC is shared with
the subsite or if the subsite TC is part of the JHU TDC. If the IDC is shared JHU does not take additional IDC against the 96. If the
subsite total costs are part of the JHU TDC, JHU takes the additional IDC % allowed by the Sponsor against the entire Subsite amount, not just the first 25K.
When setting up 96 numbers for subs under commercial agreements with fixed fee budgets, JHU does NOT charge any additional IDC against the 96#; o For commercial clinical trials a “receipt tax” is charged at the time the money
is paid to JHU. When setting up 96 numbers for subs under commercial agreements with cost
reimbursement budgets, JHU does charge additional IDC against the 96# per the prime award budget/terms;
Subcontracts and Indirect Costs…
17
The 96 number simply refers to the SAP account number for the sub.
A 96 number is a “child” of a “parent” Internal Order number (IO), which will always start with “900”.
The 96 # will be set up with the sub amount, plus whatever IDC JHU is entitled to take. o Except in the case of commercial clinical trials and most
foundation awards. Generally speaking, the IDC rate for the 96 # must
match the IDC rate for the IO # it is based upon, although there may be some (limited) exceptions.
After the first year of the Subaward, the departments are responsible for distributing money to the 96 #.
The 96 Number…
18
JHU has negotiated a number of IDC rates with the NIH. Determining which rate applies to the 96 number depends in part upon whether the work for the Prime Award (at JHU) is conducted “on- campus” or “off-campus.”
“On-campus”- means that the University is paying for the space where the work is conducted.
“Off-campus”- means that the University is NOT paying for the space where the work is conducted.
Note that the decision about which rate to use for the 96 number is made based on the work being performed at JHU. It has nothing to do with the location of the subsite.
19
The 96# and JHU IDC
ORA’s default position on carry over: subs follow the terms of the prime grant or contract
However, even in cases where the prime grant/contract allows for automatic carryover, the department and PI may request ORA to set up subs so that the subsite must obtain authorization to carry over any funding.
In order for funding to be carried over under Federal funding, the balance should be reported on the Financial Status Report as an “unliquidated obligation.”
If the prime award is from a foundation, the carryover process should comply with award guidelines about how much money can be carried over, etc.
Carry Over of Funding…
20
Carryover modifications are always necessary when the prime grant or contract requires JHU to obtain authorization for carrying over prime grant/contract funding. ◦ Almost always necessary for P and U awards
A carryover modification authorizes the subsite to carryover funding from one subgrant/contract budget period to another.
Carryover modifications must specify the amount of funding being carried over, but do not need to include a whole new budget.
Carryover Modifications…
21
The Federal Funding Accountability and Transparency Act (“FFATA”) was a 2006 federal law intended to hold the government accountable for its spending by allowing individuals to track information on federal grants and contracts on a searchable website (www.USASpending.gov)
Under FFATA, recipients of federal grants and contracts must report Subaward and Subcontract spending.
The SOM Subawards Coordinator will handle the reporting Subsites will be asked to provide certain information to
facilitate the reporting process.
The Federal Funding Accountability and
Transparency Act (FFATA)…
22
What’s in a Sub Agreement??
Payment Information
Technical and
Financial Reporting
Indemnifica-tion
Adverse Event
Reporting
Contact Information
Confid-entiality
Intellectual Property
Period of Perform-
ance
Termination
Certifica-tions to the Grantor or Sponsor
23
Managing Purchase Orders
What the Subs group does in relation to purchase orders:
Creation: P.O. is created when the contract is created.
Modification:Time and/or money added (or removed) when sub is modified.
Close-out:P.O. is closed when project period of grant/contract ends, or
sub is terminated early. If money is left on 96#, the close out process will unencumber it.
**Do NOT have Purchasing or SAP help do these things!**
24
ORA closes the Purchase Order once the final invoice is approved, submitted to AP, confirmed and paid. If the period of performance for the subaward has expired, the department sends the ORA Subawards Team ([email protected]) and email with the PO number indicating to close it. PLEASE DO NOT EMAIL PURCHASING/AP/SPSS/SAP/PO MAINTENANCE FIRST!
The Subawards Team does not move money off of or unencumber money from the 96. If this does not automatically happen when the PO closes, please reach out to [email protected] or [email protected] for more help.
If there were expenses on a P.O. before the January 2007 conversion to SAP, they will show up on the 642400 general ledger number, which links to the IO number, NOT to the 96 number. Thus, if we are closing a P.O., and there is money on 642400, the Real Time Grant Report will still show that there is an encumbrance on the IO number. ORA cannot fix this problem. For help, contact the SAP help line and/or Purchasing.
25
Closing out PO’s
There are several situations where a Subaward might need to be closed out before the period of performance expires.
If the period of performance has not expired AND a final invoice has been paid: ◦ The department should send an infosheet to ORASUBCONTRACTS◦ On the infosheet the period of performance should start on the date of their last
agreement and end on the final invoiceable date◦ On the infosheet the amount should be the total amount paid for that period of
performance◦ ORA will send the site a termination modification AND close out the PO/SC once
the mod is fully executed The period of performance has expired AND a final invoice has not been sent:
◦ The department should send an infosheet to ORASUBCONTRACTS◦ On the infosheet the period of performance should start on the date of their last
agreement and end on the last date the sub PI completed work for JHU◦ ORA will send the site a termination modification◦ The department should email ORASUBCONTRACTS when the final invoice is paid◦ ORA will close out the PO/SC at that time
26
Closing out PO’s/Subawards
If the subsite PI is moving to another subsite and will still conduct work for JHU under the project◦ The department should request paperwork from
ORASUBCONTRACTS for a new subsite◦ The department should complete and return the paperwork to
ORASUBCONTRACTS◦ ORA will draft and submit the new sub AND create new 96/PO
If the subsite is appointing another sub-PI to do the work at their Institution◦ The department should send an infosheet to ORASUBCONTRACTS
with the new PI’s information on it and a new budget for that PI for the remaining portion of the current grant year
◦ ORA will modify the current agreement with the subsite◦ The existing 96/PO will continue to be used
27
Closing out PO’s/Subawards
• Process and pay invoices
• Complete goods receipts
• Ensure consistency with Real Time Grant Report and BW reports
What the Departments do in relation to purchase
orders:
28
Per the terms of our contracts, subsites should send invoices to the department financial contact on the sub information sheet.
If ORA receives an invoice erroneously, it will be forwarded to the Financial Contact for the sub.
Confirm with the PI that the work has been performed and that any necessary reports have been submitted. PI should be aware of payments.
Certification for Payment should be completed and signed by PI
Departmental contact sends invoice and Certification to Accounts Payable via e-mail. Make sure to keep a copy. The e-mail should indicate if the invoice should be split between lines on the purchase order and how much to put on each line.
For Fixed Fee/Per Patient budgets, dept should send an email to ORASUBS asking for money to be added to the PO BEFORE submission of the invoice to AP.
Invoice Process
29
Invoice Process: Enhanced Invoice Review Guidance
Review for Standard Invoice Elements
1. Name of the subrecipient2. JHU purchase order number3. Date of the invoice4. Invoice number and project title5. Period of performance covered by the
invoice6. Breakdown of costs in accordance
with expenditure categories7. Current period costs and cumulative
project costs8. Cost sharing (if applicable)9. Program income (if generated)10. Contact person for invoice questions11. Shouldn’t overlap with previous
invoice and should NEVER exceed the termination date.
12. Certification as to the truth and accuracy of the invoice
30
1
2
3
4
4 5
6
7
10
11
Review for standard invoice elements as required by current policy (e.g., cumulative costs, certification etc.)
Expense in line with budget category amounts Amounts aren’t round dollars solely based on a percentage of budget Previous expense + Current expense = Cumulative expense for each
budget category Column totals equal the amount of individual column amounts in total Fringe cost are in line with salary expense for the agreed upon fringe
rate Facilities and Administrative (F&A) costs are in line with applicable
costs for the agreed upon F&A rate Period of performance invoiced is not in advance of the current
calendar date unless immediate cash needs are being met. If so, cash balances and interest must be tracked and reconciled before additional payments can be made.
Be sure that cumulative amount invoiced is less than or equal to total amount of the subaward/subcontract.
31
Invoice Review: Financial Accuracy
Invoice Process: Enhanced Invoice Review Guidance
Review for Financial Accuracy
32
No round dollars
Recalculate totals
Recalculate fringe
Recalculate F&A
Review period of
performance
Previous + Current =
Cumulative
Matching expenditur
e categories
Certification for Payment and Performance must be completed for all invoices
Confirm with the PI that the work has been performed and that any necessary reports have been submitted. PI should be aware of payments.
Approval by both Financial Analyst and Principal Investigator is required
Form must be included with invoice in order to process payment in SAP
Form is emailed to JHU PI with every fully executed agreement and is located on JHU Finance website. https://apps.finance.jhu.edu/policy_procedures/policy/sub/cert_pymt_perf.docx
33
Invoice Process: Certification for Payment form
High-risk subrecipients will be required to submit general ledger summary and detailed financial reports along with all invoices
Departmental personnel will be responsible for completing a summary comparison of the invoice to the financial reports
Every six months, departmental personnel will complete a more detailed review of a subrecipient financial report supporting one invoice, including obtaining supporting documentation for a selection of charges
The Certification for Payment and Performance form has been revised to evidence these reviews◦ A summary review is required to be performed and must be
documented on the Certification for Payment and Performance◦ Date of last detailed review must also be documented
Problems identified with billings must be resolved and the resolution documented
35
Invoice Process: High Risk Monitoring
Invoice Process: Additional Monitoring for High-Risk
Subrecipients Invoice Summary Review
(every invoice)
36
eUM Financial SystemProject 10011338Start Date 11/1/2013End Date 12/31/2013
G/L Account Posting Date contractor Description PaymentSalary & Wages 11/15/2013 Jacque Ravel Pay Period 11/1 - 11/15 2775.37
11/30/2013 Jacque Ravel Pay Period 11/16 - 11/30 2775.3612/15/2013 Jacque Ravel Pay Period 12/1 - 12/15 2775.3712/31/2013 Jacque Ravel Pay Period 12/16 - 12/31 2775.36
Total Salary & Wages11101.4
6
Employee Benefits11/15/2013 NA Employee Benefits 933.8511/30/2013 NA Employee Benefits 933.8412/15/2013 NA Employee Benefits 933.8512/31/2013 NA Employee Benefits 933.84
Total Employee Benefits 3735.38
Professional Services 0Total Professional Servicies 0
Travel 0Total Travel 0
Equipment 0Total Equipment 0
Supplies11/13/2013Fedex Postage 43.711/21/2013Carolina Plastic Pippets 535
12/5/2013Carolina Glass Screw-Cap Vials 526.2512/7/2013Thermo Scientific Phusion RT PCR Kits 1545
12/13/2013GraingerChemical Buffer Solution 155.8
12/17/2013Airgas Oxygen 20 CU FT 1069.44Total Supplies 3875.19
Other Direct Cost
11/13/2013Fisher ScientificStandard Mini-Centrifuge 1445.15
Total Other Direct Cost 1445.15
Indirect Cost11/30/2013 Indirect Cost 4721.1712/31/2013 Indirect Cost 5357.48
Total Indirect Cost10078.6
5
Total Costs - 1001133830235.8
3
Ensure totals match
Invoice Process: Additional Monitoring for High-Risk Subrecipients
If high-risk subrecipient:
◦ A summary review is required to be performed and must be documented on the Subrecipient Payment and Performance Certification
◦ Date of last detailed review must also be documented
37
Invoice Process: Additional Monitoring for High-Risk
Subrecipients Step 1: Invoice Detailed
Review (every six months)
38
eUM Financial SystemProject 10011338Start Date 11/1/2013End Date 12/31/2013
G/L Account Posting Date contractor Description PaymentSalary & Wages 11/15/2013 Jacque Ravel Pay Period 11/1 - 11/15 2775.37
11/30/2013 Jacque Ravel Pay Period 11/16 - 11/30 2775.3612/15/2013 Jacque Ravel Pay Period 12/1 - 12/15 2775.3712/31/2013 Jacque Ravel Pay Period 12/16 - 12/31 2775.36
Total Salary & Wages11101.4
6
Employee Benefits11/15/2013 NA Employee Benefits 933.8511/30/2013 NA Employee Benefits 933.8412/15/2013 NA Employee Benefits 933.8512/31/2013 NA Employee Benefits 933.84
Total Employee Benefits 3735.38
Professional Services 0Total Professional Servicies 0
Travel 0Total Travel 0
Equipment 0Total Equipment 0
Supplies11/13/2013Fedex Postage 43.711/21/2013Carolina Plastic Pippets 535
12/5/2013Carolina Glass Screw-Cap Vials 526.2512/7/2013Thermo Scientific Phusion RT PCR Kits 1545
12/13/2013GraingerChemical Buffer Solution 155.8
12/17/2013Airgas Oxygen 20 CU FT 1069.44Total Supplies 3875.19
Other Direct Cost
11/13/2013Fisher ScientificStandard Mini-Centrifuge 1445.15
Total Other Direct Cost 1445.15
Indirect Cost11/30/2013 Indirect Cost 4721.1712/31/2013 Indirect Cost 5357.48
Total Indirect Cost10078.6
5
Total Costs - 1001133830235.8
3
Ensure totals match
Invoice Process: Additional Monitoring for High-Risk
Subrecipients Step 2: Invoice Detailed
Review (every six months)
39
eUM Financial SystemProject 10011338Start Date 11/1/2013End Date 12/31/2013
G/L Account Posting Date contractor Description PaymentSalary & Wages 11/15/2013 Jacque Ravel Pay Period 11/1 - 11/15 2775.37
11/30/2013 Jacque Ravel Pay Period 11/16 - 11/30 2775.3612/15/2013 Jacque Ravel Pay Period 12/1 - 12/15 2775.3712/31/2013 Jacque Ravel Pay Period 12/16 - 12/31 2775.36
Total Salary & Wages11101.4
6
Employee Benefits11/15/2013 NA Employee Benefits 933.8511/30/2013 NA Employee Benefits 933.8412/15/2013 NA Employee Benefits 933.8512/31/2013 NA Employee Benefits 933.84
Total Employee Benefits 3735.38
Professional Services 0Total Professional Servicies 0
Travel 0Total Travel 0
Equipment 0Total Equipment 0
Supplies11/13/2013Fedex Postage 43.711/21/2013Carolina Plastic Pippets 535
12/5/2013Carolina Glass Screw-Cap Vials 526.2512/7/2013Thermo Scientific Phusion RT PCR Kits 1545
12/13/2013GraingerChemical Buffer Solution 155.8
12/17/2013Airgas Oxygen 20 CU FT 1069.44Total Supplies 3875.19
Other Direct Cost
11/13/2013Fisher ScientificStandard Mini-Centrifuge 1445.15
Total Other Direct Cost 1445.15
Indirect Cost11/30/2013 Indirect Cost 4721.1712/31/2013 Indirect Cost 5357.48
Total Indirect Cost10078.6
5
Total Costs - 1001133830235.8
3
Review transactions for allowability against
subaward agreement and relevant OMB
Circular
Invoice Process: Additional Monitoring for High-Risk
Subrecipients Step 2: Invoice Detailed Review
(every six months)
Ensure all amounts agree between ledger and invoices
40
eUM Financial SystemProject 10011338Start Date 11/1/2013End Date 12/31/2013
G/L Account Posting Date contractor Description PaymentSalary & Wages 11/15/2013 Jacque Ravel Pay Period 11/1 - 11/15 2775.37
11/30/2013 Jacque Ravel Pay Period 11/16 - 11/30 2775.3612/15/2013 Jacque Ravel Pay Period 12/1 - 12/15 2775.3712/31/2013 Jacque Ravel Pay Period 12/16 - 12/31 2775.36
Total Salary & Wages11101.4
6
Employee Benefits11/15/2013 NA Employee Benefits 933.8511/30/2013 NA Employee Benefits 933.8412/15/2013 NA Employee Benefits 933.8512/31/2013 NA Employee Benefits 933.84
Total Employee Benefits 3735.38
Professional Services 0Total Professional Servicies 0
Travel 0Total Travel 0
Equipment 0Total Equipment 0
Supplies11/13/2013Fedex Postage 43.711/21/2013Carolina Plastic Pippets 535
12/5/2013Carolina Glass Screw-Cap Vials 526.2512/7/2013Thermo Scientific Phusion RT PCR Kits 1545
12/13/2013GraingerChemical Buffer Solution 155.8
12/17/2013Airgas Oxygen 20 CU FT 1069.44Total Supplies 3875.19
Other Direct Cost
11/13/2013Fisher ScientificStandard Mini-Centrifuge 1445.15
Total Other Direct Cost 1445.15
Indirect Cost11/30/2013 Indirect Cost 4721.1712/31/2013 Indirect Cost 5357.48
Total Indirect Cost10078.6
5
Total Costs - 1001133830235.8
3
Sample transactions from ledger and obtain supporting documentation from
subrecipient
Jacque RivalAppointment LetterLabor Distribution
Effort reporting (if available)Timesheets (if applicable)
Fedex Invoice
Airgas Invoice
How to handle discrepancies identified during invoice reviews:◦ Must be resolved prior to payment◦ Partial payments of invoices are allowable (e.g.,
withholding questioned costs)◦ Significant discrepancies may indicate the need for a
100% desk audit of the specific invoice or all invoices depending on the nature of the concern
◦ Resolutions must be formally documented on the invoice or payment certification form
◦ At discretion of departments, results may dictate future invoicing requirements (e.g., submission of timesheets with every invoice)
41
Invoice Process: High Risk Monitoring
Discrepancies
Goods Receipts (GR) are confirmations that goods or services have been received. A GR must be completed for each invoice that is submitted to AP for payment.
Goods Receipts facilitate the “Three Way Match”, which means that the P.O., the Goods Receipt, and the vendor invoice all show the same price and quantity. A GR request is sent to the ORA STM’s ECC inboxes, who
forwards it to the ECC inbox of the appropriate departmental contact.
The Subawards Manager is able to reverse GR’s that were done through the ECC inbox. The dept contact is able to reverse GR’s that were done through Central Receiving.
Two methods for completing goods receipts (see handout). (Central Receiving SAP Role: ZESC_SC_RCV_CNT_All)
SAP manuals available at: http://ssc.jhmi.edu/supplychain/training GRs can be reversed by the dept if it was completed via Central
Receiving or by the Subawards Manager if not
Goods Receipts
42
Complicating factors in completing a sub:◦ Subsite wants indemnification from sponsor◦ Subsite has not obtained IRB approval◦ Sponsor has to approve something- like the replacement of a
project director.◦ Payment/Purchase Order issues
Please do NOT:◦ Make payments to subsites via online check requests◦ Provide subsites with purchase order numbers before original
contracts are fully-executed.◦ Create goods receipts before the invoice has been posted in SAP.
43
Its taking too long! Can I pay the subsite without the fully executed Subaward?
Generally speaking, the Subs group cannot resolve BW and Real Time Grant Report issues (incorrect encumbrances, etc.).
We only close the PO/SC, and reverse GRs.
For encumbrance issues contact Purchasing, PO Maintenance, or SPSS accordingly.
44
Troubleshooting…
If you have questions about what you need to submit or something the subsite is asking for, please call or e-mail us.
In General…
Melody Snow, M.H.S. Subawards Manager443-287-0701
Michelle Sloan, M.H.A. Subawards Associate410-614-1716
Rhanota Edwards, M.S. Subawards Specialist410-502-7349
Jessica Spielman, B.S. Subawards Specialist [email protected]
Paul Stuart, B.S. Subawards Specialist410-502-0558
45