The General Architecture of a European Bridge Management

download The General Architecture of a European Bridge Management

of 23

Transcript of The General Architecture of a European Bridge Management

  • 7/29/2019 The General Architecture of a European Bridge Management

    1/23

    The General Architecture of a

    European BridgeManagement System

    PhD. Student, MSc, Dipl. Eng. Laurentiu Pavelescu

    Technical University of Civil Engineering Bucharest

    Faculty of Railways, Roads and Bridges

    Bucharest, Romania

    [email protected]

    INCER 2012Bucharest, Romania

    July 2012 INCER BUCHAREST CONFERENCE 1

  • 7/29/2019 The General Architecture of a European Bridge Management

    2/23

    I. INTRODUCTION

    A so-called Bridge Management System (often

    abbreviated as BMS) addresses all activitiesthroughout the life of a bridge from conception

    through design and construction, and finally to

    replacement or demolition and is aimed at

    ensuring their safety and functionality.

    This requires techniques and procedures that

    ensure that bridges are regularly inspected and

    assessed, and that appropriate maintenance is

    carried out to achieve a required standard of

    condition throughout their service life.

    July 2012 INCER BUCHAREST CONFERENCE 2

  • 7/29/2019 The General Architecture of a European Bridge Management

    3/23

    BMS - principal modules:1. Inventory of the stock;2. Knowledge of bridge and element condition

    and its variation with age;

    3. Evaluation of the risks incurred by users (including

    assessment of load carrying capacity);

    4. Management of operational restrictions and of

    the routing of exceptional convoys;5. Evaluation of the costs of the variousmaintenance strategies;

    6. Forecast the deterioration of condition and the

    costs of various maintenance strategies;

    7. Socio-economic importance of the bridge

    (evaluation of the indirect costs);8. Optimization under budgetary constraints;

    9. Establishment of maintenance priorities;

    10. Budgetary monitoring on a short and long-term

    basis.

    July 2012 INCER BUCHAREST CONFERENCE 3

  • 7/29/2019 The General Architecture of a European Bridge Management

    4/23

    Fig. 1: Interconnections between inputs,models and outputs for BMS (according to

    BRIME)

    July 2012 INCER BUCHAREST CONFERENCE 4

  • 7/29/2019 The General Architecture of a European Bridge Management

    5/23

    II. FRAMEWORK

    There is no easy way to define the inter-

    relationships between the BMS inputs, models

    and outputsthere are many variables that amanager should take into account and this

    yields very complicated flow charts for the

    entire BMS, if one wants to use full names for

    inputs, outputs and models.

    The models inter-connections are explained

    through the outputs of some models that can

    stand as derived inputs for other models (see

    Table 1).

    The models are analyzed in accordance withthe two levels of management: the project and

    network level.

    July 2012 INCER BUCHAREST CONFERENCE 5

  • 7/29/2019 The General Architecture of a European Bridge Management

    6/23

    III. MODELS

    The models range from a to j and they are the

    essential key of deriving an output from an initial

    input (keeping in mind that an output can play therole of a derived input for another model).

    a. This model is used to derive a measure for the

    condition of each structural element and

    component of the bridge inspection byobservations, material testing and information in

    the inventory.

    b. The model b provides a measure for the

    overall condition state of a bridge through thecombination of the condition state values for allelements and components.

    July 2012 INCER BUCHAREST CONFERENCE 6

  • 7/29/2019 The General Architecture of a European Bridge Management

    7/23

    c. The model c is supposed to use

    information in the inventory such as the

    engineering calculations and the final

    drawings to derive the initial loadcarrying capacity measured in terms of

    load, reduction factor or reliability index.

    At this stage, should be identified the

    most structurally vulnerable parts of the

    bridge as well.

    d. The key point for this model is to predict

    the variation of the condition of the

    bridge, in its entirety, or of some

    elements of the bridge. This prediction is

    made with the aid of the test histories

    and inspections conducted for the

    bridges in the managers stock. Theresults can be presented in a discrete

    fashion, i.e. for every n years we can

    derive the so-called condition state-

    time trajectory.

    July 2012 INCER BUCHAREST CONFERENCE 7

  • 7/29/2019 The General Architecture of a European Bridge Management

    8/23

    d. The model e is the one that predicts

    the imperative of maintenance works,

    whenever the poor condition of a

    specific bridge makes it unsafe /

    inadequate for the general use. This is a

    challenging matter for engineers andmanagers.

    The following inputs are to betaken into account:

    the latest load carrying capacity;the structurally vulnerable parts of the

    bridge;

    the condition state-time trajectory for the

    vulnerable parts;information from the assessment history

    of the bridge.

    July 2012 INCER BUCHAREST CONFERENCE 8

  • 7/29/2019 The General Architecture of a European Bridge Management

    9/23

    e. Evidently, the manager and the

    engineers will base their maintenance

    strategies on the cause of the

    deteriorations and they will implementthose strengthening / repairing /

    consolidating techniques that best fit the

    situation. It is a direct relationship

    between the maintenance method and

    the cost that is involved, so this model

    should as accurate as possible.

    f. One of the biggest challenges for a

    bridge manager is to generate

    economic viable solutions whenever the

    traffic restrictions are imposed due to

    maintenance work. There are means by

    which the engineers can predict thecosts involved by these traffic disruptions,

    using, for instance, traffic data, the

    duration of the predicted restriction and

    the type of vehicles that will be rerouted.

    July 2012 INCER BUCHAREST CONFERENCE 9

  • 7/29/2019 The General Architecture of a European Bridge Management

    10/23

    g. There are several ways that a manager of a

    pile of bridges can use in order to select the

    correct maintenance strategy, such as the

    analysis of the results generated byinventory, the cost of different interventions,

    the cause of the observed deteriorations,

    the costs generated by the traffic disruptions,

    the minimum required life after the

    consolidation / repair / strengthening of the

    bridge, etc.

    h. There are many intervention strategies that

    an administrator can choose, but some of

    them are imposed by the bridges condition.

    If a bridge has a poor condition but it meets

    the load carrying capacity demands, the

    most likely strategy of intervention is ageneral repair. A preventive approach is the

    right one whenever deterioration has not yet

    occurred to a great level but the choice for

    such an action will conduct to reducing the

    rate of deterioration and lifetime costs.

    July 2012 INCER BUCHAREST CONFERENCE 10

  • 7/29/2019 The General Architecture of a European Bridge Management

    11/23

    i. The final objective of a Bridge Management

    System is to generate a maintenance

    programme for every bridge in a specific pile

    (we refer to this as the project level). Thisintervention should take into account

    optimization methods for reducing the total

    life-time costs and improve the general

    condition based on factors such as:

    information in the inventory;

    the choice of optimal maintenance method;maintenance costs and lives;

    delay costs;

    the rate of deterioration (condition state-time

    trajectories);

    the life required of the bridge;

    the extent of deterioration;the date when essential maintenance

    becomes necessary;

    the discount rate used in lifetime costing.

    July 2012 INCER BUCHAREST CONFERENCE 11

  • 7/29/2019 The General Architecture of a European Bridge Management

    12/23

    The models from a to j are involved with

    analyzing data and deriving based on them the

    correct decisions about the intervention

    strategies of particular bridges, the project levelof a bridge management system. The next four

    models, model to model analyze and

    conduct a manager to take the right decisions

    for pile of bridges, the so-called network level of

    a bridge management system.

    The bridges chosen to be within the stock candepend on many factors such as:

    the region of the stock of bridges;

    type of road: European and national roads,

    county roads, rural / local roads;

    type of bridgehere we can imaginedifferent classification factors, such as

    material, the obstacle they cross, etc.

    July 2012 INCER BUCHAREST CONFERENCE 12

  • 7/29/2019 The General Architecture of a European Bridge Management

    13/23

    Sometimes, it is not feasible to undertake the

    intervention operations for each bridge due to

    the budgetary restrictions (the most pressingones) or due to different constraints that can

    occur. This status quo involves a differential

    approach for improving a whole network than

    the particular operations a bridge needs in

    order to be fully functional.

    These considerations imply restrictions /constraints that the optimization should imbed,

    such as:

    budgetary constraints;

    the efficiency of the whole network, ratherthan a particular bridge;

    the public policies.

    July 2012 INCER BUCHAREST CONFERENCE 13

  • 7/29/2019 The General Architecture of a European Bridge Management

    14/23

    The administrator is most likely to wish that his

    policy targets (yet another constraint) for the

    condition of the whole stock and individual

    bridges are being satisfied. According to BRIME,some policy target parameters may include the

    following:

    number of bridges with load restrictions of

    different degrees;

    number of bridges with other traffic restrictions

    number of substandard bridges;annual traffic delay costs due to restrictions

    and maintenance works;

    number of bridges overdue an inspection;

    number of replacements each year;

    average condition of the stock;

    number of bridges with condition state greaterthan X;

    number of bridges containing one or more

    elements with a condition state greater than Y.

    July 2012 INCER BUCHAREST CONFERENCE 14

  • 7/29/2019 The General Architecture of a European Bridge Management

    15/23

    IV. THE FRAMEWORK BASIC

    INPUTSAs can be seen in Figure 1, a letter is assigned for every input,

    varying from A, for Inventory up to O for the Policy

    Parameter Targets. A full list is given bellow:

    A - Inventory

    B - Inspection

    C - Test Data

    D - Inspection history

    E - Test history

    F - Assessment history

    G - Traffic data

    H - Duration of restriction

    I - Future maintenance free life

    (MFL) of repair

    J - Compendium of

    maintenance life/costs

    K - Future life required

    L - Maintenance history/policy

    M - Discount Rate

    N - Constraints

    O - Policy Parameter Targets

    July 2012 INCER BUCHAREST CONFERENCE 15

  • 7/29/2019 The General Architecture of a European Bridge Management

    16/23

    V. THE FRAMEWORK

    MODELLING

    A list of the calculations (or models)

    representing the actual means by which we

    can obtain an output starting from an initialinput is presented below.

    It should be underlined that the Roman lettersstand for the project level of a Bridge

    Management System, whereas the Greek

    letters represent the network level of a BMS.

    July 2012 INCER BUCHAREST CONFERENCE 16

  • 7/29/2019 The General Architecture of a European Bridge Management

    17/23

    July 2012 INCER BUCHAREST CONFERENCE 17

    a Condition state of element

    b Condition state for bridgec Assessment of LCC assuming no deterioration

    d Rate of deterioration/prediction future condition

    e Predict future LCC

    f Cause/extent of deterioration

    g Traffic delays

    hOptimal maintenance methodi Decide maintenance strategy

    jOptimal maintenance programme

    Prioritization model

    Implication model

    Comparison model Budget variation model

  • 7/29/2019 The General Architecture of a European Bridge Management

    18/23

    VI. THE FRAMEWORK OUTPUTS

    In direct correspondence with the previous

    chapter, here-bellow is presented the

    frameworks outputs, with the mention that the

    values in parenthesis represent the outputs for

    the network level BMS, the first (from 1 to 11)

    being the outputs for the project level of a BMS.

    1 Current condition state (elements)

    2 Current condition state (bridge)

    3 Original LCC and Critical areas

    4

    Condition state/time trajectory for eachelement

    5 Condition state/time trajectory for bridge

    6 Date for essential maintenance

    7 Cause/extent of deterioration

    July 2012 INCER BUCHAREST CONFERENCE 18

  • 7/29/2019 The General Architecture of a European Bridge Management

    19/23

    July 2012 INCER BUCHAREST CONFERENCE 19

    8 Delay costs due to maintenance or restrictions9 Optimum maintenance method

    10 Best maintenance strategy

    11 Optimal maintenance programme(12) Prioritized maintenance programme

    (13) Values of policy parameters

    (14) Degree of compliance with policyparameter targets

    (15) Budget needed to obtain say 90%

    compliance

    From Table 1 one can easily read any inputs that

    are associated with a specific output.

    Remembering the fact that some of the outputs

    can play the role of derived inputs, i.e. some of theoutputs are inputs themselves for different models

    (or calculations) and generate other outputs, theFigure 1 can be rearranged in a more synthetic

    fashion as in Table 1.

  • 7/29/2019 The General Architecture of a European Bridge Management

    20/23

    July 2012 INCER BUCHAREST CONFERENCE 20

    OUTPUT DERIVED INPUTS BASIC INPUTS

    1 A,B,C

    2 1

    3 A

    4 D

    5 E

    6 3,4 F

    7 B,C

    8 6 G,H

    9 7,8,10 A,I,J

    10 1,3,4,6,8 A,K,L

    11 4,3,8,9,7,6 A,J,K,M

    (12) 11 N

    (13) (12)

    (14) (13) O

    (15) (14)

    TABLE I. INPUTS

    ASSOCIATED WITH OUTPUTS(SEE FIGURE 1)

  • 7/29/2019 The General Architecture of a European Bridge Management

    21/23

    CONCLUSIONSThe key point of this paper is that a computerised

    Bridge Management System can be createdstarting from the main activities of management

    such as, maintenance, inspections, technical

    expertise, testing, etc.

    The analyses was conducted respecting the two

    levels of management, i.e. the project level

    (dealing with specific, particular bridges) and the

    network level (dealing with a whole pile of bridges).

    This framework was developed as a result of acomparative analysis of the European BridgeManagement Systems that are in force nowadays

    and is the proposal of the BRIME committee for a

    unified management system.

    July 2012 INCER BUCHAREST CONFERENCE 21

  • 7/29/2019 The General Architecture of a European Bridge Management

    22/23

    CONCLUSIONSRomania has to implement a Bridge Management

    System of this kind that must comply, notnecessarily in its entirety, with the general

    architecture of this European BMS and also

    incorporate the supplementary constraints of our

    technical norms in force.

    The advantages of having o fully operational BMS is

    that the managers are aided in their decisions by a

    systemized and computerised tool that can help

    them find answers to a variety of questions, one of

    the most important one being the prediction

    question what if... ?.

    This kind of management system can be further on

    developed to be intergrated into a more complex

    one: a inter-connected Pavement Management

    System with a Bridge Management System.

    July 2012 INCER BUCHAREST CONFERENCE 22

  • 7/29/2019 The General Architecture of a European Bridge Management

    23/23

    July 2012 INCER BUCHAREST CONFERENCE 23