The General Architecture of a European Bridge Management
-
Upload
laurentiu-pavelescu -
Category
Documents
-
view
218 -
download
0
Transcript of The General Architecture of a European Bridge Management
-
7/29/2019 The General Architecture of a European Bridge Management
1/23
The General Architecture of a
European BridgeManagement System
PhD. Student, MSc, Dipl. Eng. Laurentiu Pavelescu
Technical University of Civil Engineering Bucharest
Faculty of Railways, Roads and Bridges
Bucharest, Romania
INCER 2012Bucharest, Romania
July 2012 INCER BUCHAREST CONFERENCE 1
-
7/29/2019 The General Architecture of a European Bridge Management
2/23
I. INTRODUCTION
A so-called Bridge Management System (often
abbreviated as BMS) addresses all activitiesthroughout the life of a bridge from conception
through design and construction, and finally to
replacement or demolition and is aimed at
ensuring their safety and functionality.
This requires techniques and procedures that
ensure that bridges are regularly inspected and
assessed, and that appropriate maintenance is
carried out to achieve a required standard of
condition throughout their service life.
July 2012 INCER BUCHAREST CONFERENCE 2
-
7/29/2019 The General Architecture of a European Bridge Management
3/23
BMS - principal modules:1. Inventory of the stock;2. Knowledge of bridge and element condition
and its variation with age;
3. Evaluation of the risks incurred by users (including
assessment of load carrying capacity);
4. Management of operational restrictions and of
the routing of exceptional convoys;5. Evaluation of the costs of the variousmaintenance strategies;
6. Forecast the deterioration of condition and the
costs of various maintenance strategies;
7. Socio-economic importance of the bridge
(evaluation of the indirect costs);8. Optimization under budgetary constraints;
9. Establishment of maintenance priorities;
10. Budgetary monitoring on a short and long-term
basis.
July 2012 INCER BUCHAREST CONFERENCE 3
-
7/29/2019 The General Architecture of a European Bridge Management
4/23
Fig. 1: Interconnections between inputs,models and outputs for BMS (according to
BRIME)
July 2012 INCER BUCHAREST CONFERENCE 4
-
7/29/2019 The General Architecture of a European Bridge Management
5/23
II. FRAMEWORK
There is no easy way to define the inter-
relationships between the BMS inputs, models
and outputsthere are many variables that amanager should take into account and this
yields very complicated flow charts for the
entire BMS, if one wants to use full names for
inputs, outputs and models.
The models inter-connections are explained
through the outputs of some models that can
stand as derived inputs for other models (see
Table 1).
The models are analyzed in accordance withthe two levels of management: the project and
network level.
July 2012 INCER BUCHAREST CONFERENCE 5
-
7/29/2019 The General Architecture of a European Bridge Management
6/23
III. MODELS
The models range from a to j and they are the
essential key of deriving an output from an initial
input (keeping in mind that an output can play therole of a derived input for another model).
a. This model is used to derive a measure for the
condition of each structural element and
component of the bridge inspection byobservations, material testing and information in
the inventory.
b. The model b provides a measure for the
overall condition state of a bridge through thecombination of the condition state values for allelements and components.
July 2012 INCER BUCHAREST CONFERENCE 6
-
7/29/2019 The General Architecture of a European Bridge Management
7/23
c. The model c is supposed to use
information in the inventory such as the
engineering calculations and the final
drawings to derive the initial loadcarrying capacity measured in terms of
load, reduction factor or reliability index.
At this stage, should be identified the
most structurally vulnerable parts of the
bridge as well.
d. The key point for this model is to predict
the variation of the condition of the
bridge, in its entirety, or of some
elements of the bridge. This prediction is
made with the aid of the test histories
and inspections conducted for the
bridges in the managers stock. Theresults can be presented in a discrete
fashion, i.e. for every n years we can
derive the so-called condition state-
time trajectory.
July 2012 INCER BUCHAREST CONFERENCE 7
-
7/29/2019 The General Architecture of a European Bridge Management
8/23
d. The model e is the one that predicts
the imperative of maintenance works,
whenever the poor condition of a
specific bridge makes it unsafe /
inadequate for the general use. This is a
challenging matter for engineers andmanagers.
The following inputs are to betaken into account:
the latest load carrying capacity;the structurally vulnerable parts of the
bridge;
the condition state-time trajectory for the
vulnerable parts;information from the assessment history
of the bridge.
July 2012 INCER BUCHAREST CONFERENCE 8
-
7/29/2019 The General Architecture of a European Bridge Management
9/23
e. Evidently, the manager and the
engineers will base their maintenance
strategies on the cause of the
deteriorations and they will implementthose strengthening / repairing /
consolidating techniques that best fit the
situation. It is a direct relationship
between the maintenance method and
the cost that is involved, so this model
should as accurate as possible.
f. One of the biggest challenges for a
bridge manager is to generate
economic viable solutions whenever the
traffic restrictions are imposed due to
maintenance work. There are means by
which the engineers can predict thecosts involved by these traffic disruptions,
using, for instance, traffic data, the
duration of the predicted restriction and
the type of vehicles that will be rerouted.
July 2012 INCER BUCHAREST CONFERENCE 9
-
7/29/2019 The General Architecture of a European Bridge Management
10/23
g. There are several ways that a manager of a
pile of bridges can use in order to select the
correct maintenance strategy, such as the
analysis of the results generated byinventory, the cost of different interventions,
the cause of the observed deteriorations,
the costs generated by the traffic disruptions,
the minimum required life after the
consolidation / repair / strengthening of the
bridge, etc.
h. There are many intervention strategies that
an administrator can choose, but some of
them are imposed by the bridges condition.
If a bridge has a poor condition but it meets
the load carrying capacity demands, the
most likely strategy of intervention is ageneral repair. A preventive approach is the
right one whenever deterioration has not yet
occurred to a great level but the choice for
such an action will conduct to reducing the
rate of deterioration and lifetime costs.
July 2012 INCER BUCHAREST CONFERENCE 10
-
7/29/2019 The General Architecture of a European Bridge Management
11/23
i. The final objective of a Bridge Management
System is to generate a maintenance
programme for every bridge in a specific pile
(we refer to this as the project level). Thisintervention should take into account
optimization methods for reducing the total
life-time costs and improve the general
condition based on factors such as:
information in the inventory;
the choice of optimal maintenance method;maintenance costs and lives;
delay costs;
the rate of deterioration (condition state-time
trajectories);
the life required of the bridge;
the extent of deterioration;the date when essential maintenance
becomes necessary;
the discount rate used in lifetime costing.
July 2012 INCER BUCHAREST CONFERENCE 11
-
7/29/2019 The General Architecture of a European Bridge Management
12/23
The models from a to j are involved with
analyzing data and deriving based on them the
correct decisions about the intervention
strategies of particular bridges, the project levelof a bridge management system. The next four
models, model to model analyze and
conduct a manager to take the right decisions
for pile of bridges, the so-called network level of
a bridge management system.
The bridges chosen to be within the stock candepend on many factors such as:
the region of the stock of bridges;
type of road: European and national roads,
county roads, rural / local roads;
type of bridgehere we can imaginedifferent classification factors, such as
material, the obstacle they cross, etc.
July 2012 INCER BUCHAREST CONFERENCE 12
-
7/29/2019 The General Architecture of a European Bridge Management
13/23
Sometimes, it is not feasible to undertake the
intervention operations for each bridge due to
the budgetary restrictions (the most pressingones) or due to different constraints that can
occur. This status quo involves a differential
approach for improving a whole network than
the particular operations a bridge needs in
order to be fully functional.
These considerations imply restrictions /constraints that the optimization should imbed,
such as:
budgetary constraints;
the efficiency of the whole network, ratherthan a particular bridge;
the public policies.
July 2012 INCER BUCHAREST CONFERENCE 13
-
7/29/2019 The General Architecture of a European Bridge Management
14/23
The administrator is most likely to wish that his
policy targets (yet another constraint) for the
condition of the whole stock and individual
bridges are being satisfied. According to BRIME,some policy target parameters may include the
following:
number of bridges with load restrictions of
different degrees;
number of bridges with other traffic restrictions
number of substandard bridges;annual traffic delay costs due to restrictions
and maintenance works;
number of bridges overdue an inspection;
number of replacements each year;
average condition of the stock;
number of bridges with condition state greaterthan X;
number of bridges containing one or more
elements with a condition state greater than Y.
July 2012 INCER BUCHAREST CONFERENCE 14
-
7/29/2019 The General Architecture of a European Bridge Management
15/23
IV. THE FRAMEWORK BASIC
INPUTSAs can be seen in Figure 1, a letter is assigned for every input,
varying from A, for Inventory up to O for the Policy
Parameter Targets. A full list is given bellow:
A - Inventory
B - Inspection
C - Test Data
D - Inspection history
E - Test history
F - Assessment history
G - Traffic data
H - Duration of restriction
I - Future maintenance free life
(MFL) of repair
J - Compendium of
maintenance life/costs
K - Future life required
L - Maintenance history/policy
M - Discount Rate
N - Constraints
O - Policy Parameter Targets
July 2012 INCER BUCHAREST CONFERENCE 15
-
7/29/2019 The General Architecture of a European Bridge Management
16/23
V. THE FRAMEWORK
MODELLING
A list of the calculations (or models)
representing the actual means by which we
can obtain an output starting from an initialinput is presented below.
It should be underlined that the Roman lettersstand for the project level of a Bridge
Management System, whereas the Greek
letters represent the network level of a BMS.
July 2012 INCER BUCHAREST CONFERENCE 16
-
7/29/2019 The General Architecture of a European Bridge Management
17/23
July 2012 INCER BUCHAREST CONFERENCE 17
a Condition state of element
b Condition state for bridgec Assessment of LCC assuming no deterioration
d Rate of deterioration/prediction future condition
e Predict future LCC
f Cause/extent of deterioration
g Traffic delays
hOptimal maintenance methodi Decide maintenance strategy
jOptimal maintenance programme
Prioritization model
Implication model
Comparison model Budget variation model
-
7/29/2019 The General Architecture of a European Bridge Management
18/23
VI. THE FRAMEWORK OUTPUTS
In direct correspondence with the previous
chapter, here-bellow is presented the
frameworks outputs, with the mention that the
values in parenthesis represent the outputs for
the network level BMS, the first (from 1 to 11)
being the outputs for the project level of a BMS.
1 Current condition state (elements)
2 Current condition state (bridge)
3 Original LCC and Critical areas
4
Condition state/time trajectory for eachelement
5 Condition state/time trajectory for bridge
6 Date for essential maintenance
7 Cause/extent of deterioration
July 2012 INCER BUCHAREST CONFERENCE 18
-
7/29/2019 The General Architecture of a European Bridge Management
19/23
July 2012 INCER BUCHAREST CONFERENCE 19
8 Delay costs due to maintenance or restrictions9 Optimum maintenance method
10 Best maintenance strategy
11 Optimal maintenance programme(12) Prioritized maintenance programme
(13) Values of policy parameters
(14) Degree of compliance with policyparameter targets
(15) Budget needed to obtain say 90%
compliance
From Table 1 one can easily read any inputs that
are associated with a specific output.
Remembering the fact that some of the outputs
can play the role of derived inputs, i.e. some of theoutputs are inputs themselves for different models
(or calculations) and generate other outputs, theFigure 1 can be rearranged in a more synthetic
fashion as in Table 1.
-
7/29/2019 The General Architecture of a European Bridge Management
20/23
July 2012 INCER BUCHAREST CONFERENCE 20
OUTPUT DERIVED INPUTS BASIC INPUTS
1 A,B,C
2 1
3 A
4 D
5 E
6 3,4 F
7 B,C
8 6 G,H
9 7,8,10 A,I,J
10 1,3,4,6,8 A,K,L
11 4,3,8,9,7,6 A,J,K,M
(12) 11 N
(13) (12)
(14) (13) O
(15) (14)
TABLE I. INPUTS
ASSOCIATED WITH OUTPUTS(SEE FIGURE 1)
-
7/29/2019 The General Architecture of a European Bridge Management
21/23
CONCLUSIONSThe key point of this paper is that a computerised
Bridge Management System can be createdstarting from the main activities of management
such as, maintenance, inspections, technical
expertise, testing, etc.
The analyses was conducted respecting the two
levels of management, i.e. the project level
(dealing with specific, particular bridges) and the
network level (dealing with a whole pile of bridges).
This framework was developed as a result of acomparative analysis of the European BridgeManagement Systems that are in force nowadays
and is the proposal of the BRIME committee for a
unified management system.
July 2012 INCER BUCHAREST CONFERENCE 21
-
7/29/2019 The General Architecture of a European Bridge Management
22/23
CONCLUSIONSRomania has to implement a Bridge Management
System of this kind that must comply, notnecessarily in its entirety, with the general
architecture of this European BMS and also
incorporate the supplementary constraints of our
technical norms in force.
The advantages of having o fully operational BMS is
that the managers are aided in their decisions by a
systemized and computerised tool that can help
them find answers to a variety of questions, one of
the most important one being the prediction
question what if... ?.
This kind of management system can be further on
developed to be intergrated into a more complex
one: a inter-connected Pavement Management
System with a Bridge Management System.
July 2012 INCER BUCHAREST CONFERENCE 22
-
7/29/2019 The General Architecture of a European Bridge Management
23/23
July 2012 INCER BUCHAREST CONFERENCE 23