The EPC Contractors business

25
BUSINESS RELATIONS BETWEEN THE OPERATORS AND THE SERVICE INDUSTRY: WHO ASSUMES THE FINANCIAL RISK OF A PROJECT? OTC 2004 Daniel Valot Chairman and CEO

Transcript of The EPC Contractors business

Page 1: The EPC Contractors business

BUSINESS RELATIONS BETWEEN THE OPERATORS AND THE SERVICE INDUSTRY:

WHO ASSUMES THE FINANCIAL RISK OF A PROJECT?

OTC 2004

Daniel ValotChairman and CEO

Page 2: The EPC Contractors business

2

WHO ASSUMES THE FINANCIAL RISK OF A PROJECT?

Short Answer: The owner assumes the financial risk of its project

The Reality: While most oil companies are enjoying record profits, many oil service companies are incurring heavy losses on projects

An unhappy and unhealthy situation for everybodyThe E&C industry is in turmoilNevertheless, finding and development costs are rising

Page 3: The EPC Contractors business

3

I. THE E&C INDUSTRY IS IN TURMOIL

II. THE OIL COMPANIES ARE UNHAPPY TOO

III. THE WAY FORWARD

Page 4: The EPC Contractors business

I. THE E&C INDUSTRY IS IN TURMOIL

Page 5: The EPC Contractors business

5

GROWING IMBALANCE BETWEEN OIL AND E&C COMPANIES (1)

NET EARNINGS

A) 10 largest oil companies 23.223.2 75.775.7

1994 2003USD in Billions

0.8 - 0.3B) 10 largest E&C companies

Source: Bloomberg

Page 6: The EPC Contractors business

6

GROWING IMBALANCE BETWEEN OIL AND E&C COMPANIES (2)

SHAREHOLDERS’ EQUITY

A) 10 largest oil companies 235235 423423

1994 2003USD in Billions

8 9B) 10 largest E&C companies

Source: Bloomberg

Page 7: The EPC Contractors business

7

SHAREHOLDERS’ EQUITY: MAIN OIL COMPANIES

0

10 000

20 000

30 000

40 000

50 000

60 000

70 000

80 000

90 000

100 000

Exxon M

obil BP

Royal

Dutch / S

hell

TotalChe

vronTex

aco

Conoco

Phillips ENI

Repso

l

Statoil

Occide

ntalYE 1994 YE 2003USD in Millions

Page 8: The EPC Contractors business

8

SHAREHOLDERS’ EQUITY: MAIN E&C COMPANIES

-2 000

-1 000

0

1 000

2 000

3 000

4 000

5 000

Halli

burto

n

Tech

nip

Saip

em

JGCFluo

r

IHC

Cala

nd

Jaco

bs

Stol

t Offs

hore

McD

erm

ott

Fost

er W

heel

er

YE 1998 YE 2003

USD in Millions

Technip 1998 includes CoflexipSaipem 1998 includes Bouygues OS

Source: Bloomberg

Page 9: The EPC Contractors business

9

SIZE OF PROJECTS:GROWING FASTER THAN E&C COMPANIES’ SIZE

At Technip, the 5 largest contracts in backlog (Group share) amounted to:

10 years ago : € 1.6 Billion

5 years ago : € 2.1 Billion

Today : € 2.9 Billion

Average size of the 5 largest contracts is now close to €600m (~$700m) per contract: equivalent

to about 1/3 of the Group’s equity

Page 10: The EPC Contractors business

10

MEGA PROJECTS = HIGHER RISKS

In the SURF (Subsea Umbilicals Risers and Flowlines) business, as an example:

In the nineties, a typical project(North Sea tie-back) would be:

30 to 50 M€

Today, a typical SURF project(deepwater West Africa) is:

500 to 800 M€

Liability exposure equal to 15% of contract value was acceptable on small projectsThe same 15% exposure on a mega-project can kill an E&C co.

Page 11: The EPC Contractors business

II. THE OIL COMPANIES ARE UNHAPPY TOO

Page 12: The EPC Contractors business

12

TRENDS IN FINDING & DEVELOPMENT COST PER BARREL

$ / Boe

Oops!Oops!Oops!

Doing OKDoing OKDoing OK

7.12

6.48

4.60

4.594.945.04

4.19

4.204.58

5.065.07

1990 1992 1994 1996 1998 2000 2002 2004

Source: ABN Amro

Page 13: The EPC Contractors business

13

WHY ARE F&D COSTS RISING?

More complex projects (deepwater, frontier areas)

No new wave of major technological innovations (such as 3D seismic and horizontal drilling during the 90’s)

Ever-increasing local content requirements by host countries

Higher euro impacting contractors’ euro-based costs

More recently, rising steel prices and freight costs

Page 14: The EPC Contractors business

14

THE PARADOX

In order to cut finding & development costs, oil companies are inclined to tighten terms and conditions on projects:

- Lower margins for higher risks- Heavier liabilities (up to 100% of revenues !!)- Negative cash flows- Lower insurance coverage

Paradoxically, such an approach is more likely to lead to higher costs on projects (+ a few casualties among the E&C companies)

The current relationship between the oil companies and their contractors is flawed by a few conceptual mistakes

Page 15: The EPC Contractors business

15

A FEW CONCEPTUAL MISTAKES

MISTAKE #1: “ALWAYS LOW PRICES. ALWAYS.”

Trend of awarding contracts based on lowest offered price (even if it is obviously a dumping offer) and irrespective of:

Track recordTechnological expertiseProject management capabilities

In such cases, project execution is often very poor, with delays, cost overruns, claims and counterclaims.

Most of the time, at the end of the day, the ‘lowest price’ is not delivered

Page 16: The EPC Contractors business

16

A FEW CONCEPTUAL MISTAKES

MISTAKE #2: LUMP-SUM CONTRACTING IN UNCHARTERED TERRITORIES

Can only lead to higher costs:

When risks are difficult or impossible to evaluate:E&C companies will raise contingencies - as much as competition will allow to cover these risks

When the competition does not allow increased contingencies:experience has shown time and again that the “winning” contractor suffers a flow of red inktriggering additional costs and delays for the client

Page 17: The EPC Contractors business

17

A FEW CONCEPTUAL MISTAKES

MISTAKE #3: FAST TRACK PROJECTS FOR NEW TECHNOLOGIES

A sure recipe for disaster

the necessary engineering and testing cannot be performed before the start-up of the project

Fast-track should be limited

to projects for which scope of work and technologies are clearly defined and proven

Page 18: The EPC Contractors business

18

A FEW CONCEPTUAL MISTAKES

MISTAKE #4: CHANGING THE RULES OF THE GAME DURING THE GAME

Examples:

Organize bidding, then rebidding and even re-rebidding (as if the cost of bidding were not material for E&C companies)

Utilize mysterious criteria to weight the offers from competitors during the bidding process

During contract execution, change the scope of work first and negotiate variation orders second

E&C companies need the rules of the game that areclear, stable and fair

Page 19: The EPC Contractors business

19

A FEW CONCEPTUAL MISTAKES

MISTAKE #5: ALLOCATE RISKS AND COSTS TO THE WRONG PARTY

In addition to their job (contractor), E&C companies are often requested to act as:

A commercial bank (negative cash-flows on projects)

An insurance company (providing insurance coverage for clients’ risks)

A Forex gambler (contract in $, costs in various currencies)

Given their size and financial strength, oil companies have cheaper access than E&C companies to funding, insurance and forex hedging

Transferring these risks / costs to the E&C companies does not make economic sense:

IT CAN ONLY LEAD TO MORE EXPENSIVE PROJECTS

Page 20: The EPC Contractors business

III. THE WAY FORWARD: WHAT IS NEEDED TO RESTORE A MORE BALANCED RELATIONSHIP

Page 21: The EPC Contractors business

21

THE WAY FORWARD: CONTRACTUAL TERMS (1)

Payment in multi-currencies in line with contractor’s cost structure

Provide to contractor a neutral, if not positive, cash flow

Late payments should incur financial costs

Right of suspension / termination in case of non-payment

Page 22: The EPC Contractors business

22

THE WAY FORWARD: CONTRACTUAL TERMS (2)

Provide to contractor insurance coverage for major risks

Compensate cost increases linked to major economic disruptions (steel prices…)

Stop the extravaganza on liabilities: cap on liabilities per project should not exceed 1% of a world-class contractor equity

Page 23: The EPC Contractors business

23

THE WAY FORWARD: A NEW BEHAVIOR?

Contracting strategy:

Clarify and stabilize the rulesLimit EPIC contracts to well-defined scope and technologiesAllocate risks/costs to the right party

Relationship:

Let business people run the show (rather than lawyers)… and provide them some give-and-take authorityForget short-termism and focus on long-term partnerships

In their best interest, oil companies should try to re-establishan appropriate risk-reward balance for their contractors

Page 24: The EPC Contractors business

OTC 2004

Page 25: The EPC Contractors business

25

THE OVERALL FINANCIAL PERFORMANCE OF E&C COMPANIES

NET INCOME (US GAAP) / REVENUES IN 2003

STOLT OFFS

GLOBAL INDU

HALLIBURTO

FOSTER WH

MCDERMOTT

TECIPR

CHIYODAIH

C CALAND

JABS

SAM

STRIES

HORE

EELER

N

4.6%2.8%2.5%2.1%

ABB 1.8%1.6% 1.8%

JGC

FLUO

IPEHN

CO

-4.1%-4.2% -4.1%-5.0%

-14.0%

-28.3%

Source: Bloomberg