This presentation is dedicated to the memory of Merle Collins.
Thorough His determination and effort the long time dream of Virginia Ranch Dam was finally realized.
Browns Valley Irrigation District honored His name by officially naming the Lake
MERLE COLLINS RESERVOIR“To forever be known as Collins Lake”
March 2010, Thank You Merle. Bob Bordsen, BVID Director Div 1
![Page 2: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/2.jpg)
![Page 3: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/3.jpg)
THE BUILDING OF A DAM
Construction of
Virginia Ranch Dam by
Browns Valley Irrigation Districtforming
Merle Collins Reservoir
![Page 4: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/4.jpg)
![Page 5: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/5.jpg)
After 40 plus years of trying various methods of securing funding Browns Valley Irrigation District (BVID) was able to secure a commitment from
United States Bureau of Reclamation (USBR) for the necessary financing through a USBR loan to build the
Virginia Ranch Dam (VRD).
![Page 6: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/6.jpg)
VRD site as seen March 1958
![Page 7: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/7.jpg)
![Page 8: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/8.jpg)
Substantial design and planning was accomplished prior
to the vote to approve the contract for the USBR loan.
![Page 9: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/9.jpg)
![Page 10: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/10.jpg)
.
![Page 11: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/11.jpg)
SPRING 1958East end of future VRD location viewed from across Dry Creek
![Page 12: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/12.jpg)
![Page 13: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/13.jpg)
May 1958Design
exploration
![Page 14: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/14.jpg)
![Page 15: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/15.jpg)
Confidence Prevailed Within the BVID
Directors, as well as landowners, felt that after 40 plus years of attempts this time we were going to build a Dam.
So confident that In March of 1959, even before the election to approve the USBR loan, a Ground Breaking Ceremony was held.
![Page 16: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/16.jpg)
![Page 17: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/17.jpg)
![Page 18: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/18.jpg)
![Page 19: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/19.jpg)
![Page 20: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/20.jpg)
![Page 21: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/21.jpg)
![Page 22: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/22.jpg)
![Page 23: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/23.jpg)
On September 13, 1960, by a vote of 238 to 8, BVID voters approved the District to enter into a contract with the United States Department of Interior for a no interest, 50 year, $5,000,000, loan for the construction of the VRD as well as rebuilding and extending the distribution system.
![Page 24: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/24.jpg)
On Sept. 8, 1961 a contract was signed and in spring of 1962 work commenced toward a projected completion date of late Nov. 1962.
![Page 25: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/25.jpg)
![Page 26: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/26.jpg)
![Page 27: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/27.jpg)
Contractor Shop Under Construction
![Page 28: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/28.jpg)
![Page 29: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/29.jpg)
Clearing the VRD site
![Page 30: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/30.jpg)
East end embankment cleared
![Page 31: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/31.jpg)
![Page 32: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/32.jpg)
Excavating west end foundation keyway
![Page 33: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/33.jpg)
Dry Creek area of Dam Site
![Page 34: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/34.jpg)
Forming and rebar for outlet works
![Page 35: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/35.jpg)
Building the outlet works
![Page 36: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/36.jpg)
On May 3, 1962 there was a Northern California Laborers Union strike lasting to July 5, 1962. The 2 months delay prevented placing of the embankment prior to winter storms causing the projected completion date to be moved to Oct. 1, 1963.
![Page 37: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/37.jpg)
Fall 1962Overview of construction site
![Page 38: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/38.jpg)
A Columbus Day storm in October of 1962 brought record breaking rains to the area.
Gage stations at the VRD site recorded 11” of rain in one day.
The unexpected high water damaged completed work as well as loss of some of
the contractors equipment.
![Page 39: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/39.jpg)
Site overview
after high
water
![Page 40: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/40.jpg)
High water line can be seen here
![Page 41: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/41.jpg)
Outlet works shortly after flood damage
![Page 42: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/42.jpg)
Debris is from flood water being diverted uncontrolled through outlet works and into tunnel
![Page 43: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/43.jpg)
Completed outlet works
![Page 44: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/44.jpg)
Concrete flume from outlet works into tunnel
![Page 45: The Building of a Dam Slides Part 1](https://reader030.fdocuments.in/reader030/viewer/2022020301/586e25f41a28ab20708b9f4d/html5/thumbnails/45.jpg)
Outlet works valves