![Page 1: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/1.jpg)
![Page 2: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/2.jpg)
“Lean Construction”
Luai M. El‐Sabek, Ph.D., PE, PEng, PMP September 24, 2018
![Page 3: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/3.jpg)
Objectives
• Status of construction industry – identify the gap• Overcome stereotypes: “manufacturing”
“this is what we do” • Establish general awareness of Lean Construction: What? Why? How?
• Create an incentive to initiate / continue a Lean journey in your project(s) or organization
• Establish a demand for Lean education• Status of Lean Construction implementation in Qatar
![Page 4: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/4.jpg)
The Problem – 1) Poor Productivity
Productivity by industry in the US ( indexed; 1.0 = 1950)
![Page 5: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/5.jpg)
The Problem – 2) Waste
Manufacturing Construction
Construction Industry Institute, 2004
12%
57%
![Page 6: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/6.jpg)
The Problem – 3) Inefficiency
McGraw Hill 2013
![Page 7: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/7.jpg)
The Solution – Different Thinking
Observer Action Outcomes
Different Outcome =>Change Action(Incremental Learning)
(Breakthrough Learning)
![Page 8: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/8.jpg)
The Solution – Production Theory
(Koskela 1992)
![Page 9: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/9.jpg)
Does it Work?
• Toyota Production System (TPS) 1950s (Taiichi Ohno)• Construction Vs. Manufacturing • Project Vs. Production • Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary (Koskela, 2000).
• IGLC: construction is fundamentally different from manufacturing. Therefore, reinterpretation of the theory of is needed to develop a theory‐based methodology for construction.
• Lean + Construction = creativity
![Page 10: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/10.jpg)
What is Lean Construction?
• Creating ideal state of designing and constructing a facility using standard processes to:
• Provide / generate value• Eliminate waste• Continuously improve
• Business Philosophy ‐ Operation Strategy
![Page 11: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/11.jpg)
Lean Construction
• Lean Construction Institute (LCI)“Lean Construction is a production management‐based approach to project delivery – a new way to design and build capital facilities to maximize value
and minimize waste….”
• AGC OF America “Lean Construction is a set of ideas, practiced by individuals in the construction industry, based in the holistic pursuit of continuous
improvements aimed at minimizing costs and maximizing value to clients in all dimensions of the built and natural environment: planning, design,
construction, activation, operations, maintenance, salvaging, and recycling.”
![Page 12: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/12.jpg)
What is NOT Lean Construction?
• Lean Production grafted onto construction• Limited to Quality Management• Cost Cutting• Eliminating Jobs• Beating up suppliers and subcontractors• Doing Value Engineering During Construction• Being Stingy
![Page 13: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/13.jpg)
Value
• Value is generated when:
• Customer capabilities are expanded, covering new needs and purposes.
• The facility better fulfills the purposes and demands of customers, operators, and other stakeholders
• However, value is not just fitness for use or performance relative to cost
(LCI 2002)
![Page 14: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/14.jpg)
Waste
Wastes
Ohno (1988)
Examples of Wastes in Construction
ElSabek and McCabe 2018)
1) Overproduction Excess Materials of concrete or asphalt Over excavation
2) Inventories Raw materials on site work in progress
3) Over‐processing Scope elegance
4) Defects Non‐conformance to quality
5) Unnecessary motion Movement at site
6) Unnecessary transport Transportation of workers to/from labour camp to field and to/from break area
Mob / demob of materials
7) Waiting Worker waiting for work or work waiting for workers Idle equipment
![Page 15: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/15.jpg)
Traditional Construction Management
(Howell 2010)
![Page 16: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/16.jpg)
Integrated Project Delivery
(Howell 2010)
![Page 17: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/17.jpg)
Examples of Enabling Tools
• Integrated Project Delivery (IPD) • Last Planner ® System (LPS®)• IMPact Framework• Lean Design (Target Value Design, Process Design, BIM, and VDC) • Root cause analysis (5 Why and fishbone)• Problem Solving Techniques (A3s)• Decision Making System (Choosing By Advantages)• Continuous improvement (PDCA, Kaizen, Plus/Delta)• Error Proofing• 5S Plus Safety ‐ Lean Assembly (Sort, Set, Shine, Standardize, &
Sustain)
![Page 18: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/18.jpg)
Examples of Enabling Tools (con’t)
• Offsite fabrication• Just in Time (JIT) • Value Stream Mapping• Supply Chain Management• Daily crew huddles
![Page 19: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/19.jpg)
IMPact Framework
(ElSabek 2017)
![Page 20: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/20.jpg)
Lean Assembly – 5S + Safety
• Sort…Set…Shine…Standardize…Sustain + Safety• Cleaner site is safer and more productive
BEFORE AFTER
© Walbridge (images)
![Page 21: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/21.jpg)
Lean Assembly – 5S + Safety
• Everything in its place and a place for everything!
(Abdelhamid 2014)
![Page 22: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/22.jpg)
The Problem - Reasons for Unmet Weekly Commitments
![Page 23: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/23.jpg)
Golden Mine
We have to change what we do to get different results
“Breakthrough Learning”
![Page 24: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/24.jpg)
The Problem - Production Variation
Execution Failures
WorkloadVariation
Overburden
Waste
Capability
PlanningFailures
![Page 25: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/25.jpg)
the Solution - LPS®
• Developed by Glenn Ballard & Gregory Howell in 2002• Process design and not only product design• LAST PLANNER® SYSTEM (LPS®) ensures:
• Reliable commitment• Predictable workflows• Rapid learning
(Ballard et al. 2002)
![Page 26: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/26.jpg)
1) Master Scheduling2) Phase Scheduling
Project Zeneca Ag Products - Building 196 Run Date: 2/21/00 12:57
Other CommentsContract Design Submittals RFI's Material Prereq Equipment Labor Weather
Demo CMU wall 28-Oct Cal-Wrecking X X X X X Concrete at E-10 must be up to strength.
Excavate footing 4-Nov Cal-Wrecking Possible delay caused by oversized footing.
Install bottom rebar mat 9-Nov McGrath X X X X X X X X X X
Install footing dowels 9-Nov NLB X X X X X X X X X X
Plumbing rough-in 10-Nov Perryman X X X X X X X X X X
Install top rebar mat and stirrups 11-Nov McGrath X X X X X X X X X X
Rebar inspection 12-Nov ICI, C of R X X X X X X X X X X
Place footing 16-Nov NLB X X X X X X X X X X
Install 1st floor wall rebar 19-Nov McGrath X X X X X X X X X X
Above sequence 2-Dec X X X X X X X X X X
Total Activities 27
Activities Ready 25
AMR Week - 1 Ratio 92.59%
InputsCriteria ResourcesID Activity Description Start Responsible
Make‐ready Plan With Constraint Analysis
1 WEEK PLANPROJECT: Pilot FOREMAN: PHILLIPACTIVITY DATE: 9/20/96
Est Act Mon Tu Wed Thurs Fri Sat Sun PPC REASON FOR VARIANCESGas/F.O. hangers O/H "K" xxxx xxxx No Owner stopped work (48 hangers) Sylvano, Modesto, Terry (changing elevations)Gas/F.O. risers to O/H "K" xxxx xxxx xxxx xxxx No Same as above-worked on (3 risers) Sylvano, Mdesto, Terry backlog & boiler blowdown36" cond water "K" 42' xxxx xxxx xxxx Yes 2-45 deg 1-90 deg Charlie, Rick, Ben
Chiller risers (2 chillers wk.) xxxx xxxx xxxx No Matl from shop rcvd late Thurs.Charlie, Rick, Ben Grooved couplings shipped late.
Hang H/W O/H "J" (240'-14") xxxx xxxx xxxx xxxx xxxx xxxx YesMark M., Mike
Cooling Tower 10" tie-ins (steel) xxxx xxxx xxxx xxxx xxxx xxxx Yes (2 towers per day) Steve, Chris, Mark W.
Weld out CHW pump headers xxxx xxxx xxxx xxxx xxxx xxxx Yes "J" mezz. (18) Luke
Weld out cooling towers (12 towers) xxxx xxxx xxxx xxxx xxxx xxxx No Eye injury. Lost 2 daysJeff welding time
F.R.P. tie-in to E.T. (9 towers) 50% xxxx xxxx xxxx xxxx xxxx xxxx YesFirt, Packy, Tom
WORKABLE BACKLOGBoiler blowdown-gas vents -rupture disks
Weekly Work Planning
Planning System Measurement
0%10%20%30%40%50%60%70%80%90%
100%
0%10%20%30%40%50%60%70%80%90%100%
PPC4 Week Moving Average
(LCI 2002)
the Solution - LPS®
![Page 27: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/27.jpg)
Domains of Project Delivery
Command & ControlDirectives‐Driven
2D/3D
CPM‐based; Activity‐Centered; Management by Exception
Individualcraft‐contracts
(Abdelhamid 2014)
![Page 28: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/28.jpg)
Domains of Project Delivery
2D/3D
CPM‐based; Activity‐Centered; Management by Exception
Individualcraft‐contracts
(Abdelhamid 2014)
IPD/IFOARelational
Dialogue & Collaboration
Lean‐based; Management by Means
BIM/VDC
(systemoptimization)
(planning inclusive of execution party; fire prevention)
(planning is an ongoing conversations)
Command & ControlDirectives‐Driven
![Page 29: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/29.jpg)
LEAN PROJECT DELIVERY SYSTEM (LPDS)
(Ballard 2006)
![Page 30: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/30.jpg)
Culture of Lean Construction
• Problems are recognized as opportunities
• It’s okay to make legitimate mistakes
• Problems are exposed because of increased trust
• People are not problems – they are problem solvers
• Emphasis is placed on finding solutions instead of “who did it”
![Page 31: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/31.jpg)
The Radical Shift
Non-Lean LeanPlanning Knowledge Learning
Scheduling“Start Early”
Activities are performed as soon as possible
“Finish Early”Activities are performed at the last
responsible moment
Control Tracking & Reacting Peering, Clearing, Steering
Focus Acceleration Reliability
Organizational Behavior Managers are empowered Executers are the planners
Collaboration, Respect, and Trust
Coordination Follow Orders Making & Keeping Promises
Site Management Point Speed &100% Utilization Manage workflow
Management Trades Cost for Speed Reduce Cost and Increase Speed
Design Project Design Process Design
![Page 32: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/32.jpg)
Lean Construction in Qatar
• Implemented in 3 pilot projects at Lusail City
• Adapted by PWA in March 2018
![Page 33: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/33.jpg)
How to Start?
• Be patient
• Be determined
• Look for change‐agents
• Conversation
• Leading by examples
• Judging by results
![Page 35: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/35.jpg)
Benefits of Lean Construction
McGraw Hill 2013
![Page 36: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/36.jpg)
Success Stories
• Temecula Valley Hospital 2013• $700 million project• 40% below market cost• Realized 200% increasein labor productivity through the 7 partners
• 30% operational cost improvement in the facility
• Sutter Health ( $5 billion program)
![Page 37: The Big5 Qatar - Lean Construction · •Construction projects are unique and have distinctive peculiarities i.e. on site production, one‐of‐a‐kind production, and temporary](https://reader034.fdocuments.in/reader034/viewer/2022042106/5e85873411a63b78a671cc1e/html5/thumbnails/37.jpg)
Thank you for attending!See you next year