2 Dr. Daniel Brickwell
Company Profile and Key Milestones
Since its foundation in 2003 by BARD has developed from a project developer to a manufacturer of
Offshore wind turbines and provider of Offshore Wind Parks (OWPP).
2
Formation Transformation Executing BARD Offshore I
Mar 2004
Application for building permission for BARD Offshore 1 wind farm
2006
Cuxhaven Steel Construction GmbH established
Apr 2007
BARD received approval for BO1
Oct 2008
Start of tripile production; prototype at Hooksiel installed
Apr 2010
Start of operation of Installation-vessel Wind Lift 1
Dec 2010
Shares of Bekker family transferred to trustee vehicle
Sep 2003
BARD Engineering GmbH founded by Dr. Bekker
2005
BARD Emden Energy GmbH & Co. KG founded
2006
Manufacturing of rotor blades and offshore wind energy converters started
Feb 2008
BARD Engineering signed EPC contract with Ocean Breeze
Aug/Dec 2009
Approval for wind farm Veja Mate and Dutch projects
Jun 2010
Installation of first nacelle BO1
Dec 2010
Energy from BO1 fed into the grid for the first time
Q1 2011
New management team installed, Mr. Ranneberg appointed as CEO, Mr. Althoff as CFO
Oct 2011
Realignment of management team completed, Mr. Struck appointed as COO
Dec 2007
First prototype up and running at Rysumer Nacken
Q1 2012
First BARD 6.5 WEC in operation onshore
Aug 2011
Sale of Dutch project rights (600MW) to Typhoon Offshore
3 Dr. Daniel Brickwell
The BARD - Group
1
4 Dr. Daniel Brickwell
BARD has a sustainable business
model
BARD has an attractive growth
perspective
2 approved projects:
BARD OFFSHORE 1: 80 x 5
MW
VEJA MATE: 80 x 5 MW
To be installed 2010 – 2015
5 BARD projects still in pipeline
About 4.000 Megawatt in total
BARD‘s project pipeline and facilities
3
5 Dr. Daniel Brickwell
BARD Emden Energy GmbH
Perfect Infrastructure
Serial production of rotor blades
Assembly of nacelles and e-units,
hubs
More than 400 Employees
Direct deep water access
Portal crane with 500 ton capacity
ISO 9001 certified
6 Dr. Daniel Brickwell
Cuxhaven Steel Construction
Logistics is everything
Production facility with an area of 17.000 m²
State of the art and weather independent
production
Perfect logistics for shipment of offshore
components
Direct access to waterfront
Portal crane with 600 tons lifting capacity
Quality is priority no. 1
(DIN EN ISO 9001:2008; DIN 18800 Part
7E; BS OSHAS 18001: 2007; DIN EN
ISO 38342)
Cuxhaven Steel Construction GmbH
7
7 Dr. Daniel Brickwell
Cuxhaven Steel Construction GmbH
495 tons in
transit
8 Dr. Daniel Brickwell
BARD is pioneer in deep water
installation of 5 MW+ WTG
9 Dr. Daniel Brickwell
Delay of own installation vessel
more than one year
Trouble during transport and the
installation of converter platform
Serious accident while installing
piles
Strong weather restrictions for
each step of the offshore
installation
Already installed cables showed
technical problems and had to
be recovered
Problems a pioneer in offshore wind
farm installation is facing
10 Dr. Daniel Brickwell
Project „BARD Offshore 1“
Logistical challenge
48 Tripile foundation systems
installed in the North Sea
31/19 offshore wind turbines
installed
First 3 wind clusters have begun to
feed-in
42 cable connections laid
Project is on track to be fully
installed by end of 2013
Valuable lessons were learned and
new concepts developed
Project BARD Offshore 1
13
11 Dr. Daniel Brickwell
Project BARD Offshore 1
Logistical Challenge:
Up to 320 Employees on site
„Windlift I“
„Thor“
„JB 115“
„Natalie“
„Natalia Bekker“
Cable laying ships, diving vessels,
marine safety vessels, etc.
12 Dr. Daniel Brickwell
Transformer plattform „BARD 1“
Construction and transport
13 Dr. Daniel Brickwell
Project „BARD Offshore 1“
Installation with Jack-up Vessels
14 Dr. Daniel Brickwell
Environmental Protection & Ramming Silencing
• Limit for
acoustic
emission 160
db
• Actual
numbers
measured in
peaks > 175
db
=> In search of
solutions
15 Dr. Daniel Brickwell
Collaborative research project
Smaller Bubble Curtain (SBC)
Results of first offshore
test OFT 1 (prototype):
• Small Bubble Curtain
can deliver up to 14 db
in sound reduction
• More compressors do
not necessarily reduce
more sound
• Permission limit not
quite reached 161,3
db as low
• OFT 2 in preparation