The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office...

download The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

of 19

Transcript of The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office...

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    1/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    THE APPLICATION OF ZERO ENERGY

    BUILDING CONCEPT IN THE MALAYSIAGREEN TECHNOLOGY CORPORATION

    OFFICE BUILDING

    Ng Ban Huat1, Zainal Abidin bin Akasah

    2

    Faculty of Civil and Environmental Engineering, UTHM

    [email protected],

    [email protected]

    Abstract

    Zero Energy Building (ZEB) which possess high energy efficient design and utilizes renewable energytechnology in order to fulfill its energy needs. Malaysia Green Technology Corporation office building is a

    building designed base on ZEB concept; however Building Energy Index (BEI) for Malaysia Green Technology

    office building has yet to achieve zero. This research focuses on the application of ZEB concept in Malaysia

    Green Technology Corporation office building; secondly to identify the problems causing BEI of the studied

    office building which did not achieve zero BEI; and lastly to propose approaches that can improve energy

    efficiency for the office building. Interviews session with the office building management team, architect and

    energy consultant have been carried out in order to achieve research objectives. Outcome of the research shows

    that energy efficient design and renewable energy technology applied in the office building are passive design,active system, and Building Integrated Photovoltaic system (BIPV). The inefficiency at the cool part of the

    cooling system, air movement, and chillers are the problems that have been identified. Recommendations such as

    improving the efficiency of the cooling system, enhancing the air movement in the building, reduce the chillers

    mailto:[email protected]:[email protected]:[email protected]
  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    2/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    1.1 INTRODUCTION

    The over usage of fossil energy is the main contributor

    towards global climate change [1]. This is due to the

    excessive consumption of fossil energy will end up

    releasing large amount of greenhouse gases. The

    worlds fossil energy consumption rate has reached 82

    percents [2].

    Hence, the improvement of energy efficiency,

    increasing the usage of renewable energy; preservationof a healthy building indoor environment; and

    increasing the sustainability of natural resources are

    among the approaches catching the worlds attention

    [3].

    Zero Energy Building (ZEB) is the building that

    fulfills the needs stated above and capable in reducing

    the dependence of fossil energy usage. This is because;ZEB manage to produce the amount of energy needs

    by the buildings through environmentally friendly

    manner.

    1.2 PROBLEM STATEMENT

    The development of energy efficient building or ZEB

    is important, because the increase of buildingselectricity consumption contribute to the higher release

    of greenhouse gasses compared to other sectors. This

    is because; most of the electricity consumed by

    1.3 RESEARCH QUESTION

    (i) What are the ZEB components applied in the

    office building?

    (ii) What are the problems causing the Building

    Energy Index (BEI) of the office building yet

    to achieve zero?

    (iii) What are the approaches that capable to

    increase the energy efficiency of the office

    building?

    1.4 RESEARCH OBJECTIVE

    The research objectives of this study are:

    (i) To identify the application of ZEB concept in

    the office building.

    (ii) To identify the problems causing the Building

    Energy Index (BEI) of the office building yet

    to achieve zero.

    (iii) To propose the approaches capable to increase

    the energy efficiency of the building.

    1.5 SIGNIFICANCE OF STUDY

    This research is in aim to contribute to the following

    parties:

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    3/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    (vi) Ministry of Energy, Green Technology, and

    Water (KeTTHA), as the ministry responsible

    in commercialize the activities related to green

    technology as stipulated in Tenth Malaysia

    Plan.

    1.6 RESEARCH SCOPE

    (i) This research was carried out in Malaysia

    Green Technology Corporations office

    building, Bandar Baru Bangi;

    (ii) This research is focused on the ZEB

    components applied in the office building. The

    information is retrieved through the interview

    with the buildings management team and the

    architect involved during the design process.

    (iii) This research is focus on the problems causing

    the office buildings BEI did not achieve zero.The term energy used in this research is

    referring to the energy used during the

    operation of the building. The data were

    retrieved through interview with the buildings

    management team, and;

    (iv) To acquire views from the office buildings

    management team, architect, and energyconsultants involved during the design

    process.

    (iii) Building: Building is a structure such as a

    house, church, or factory that has a roof and

    walls [10].

    ZEB concept emphasizes on the application of

    commercial or residential building.

    Hence, ZEB concept can be simplified as

    follows: A Zero Energy Building (ZEB) is a

    residential or commercial building with

    greatly reduced energy needs through

    efficiency gains such that the balance of

    energy needs can be supplied with renewable

    technologies [11].

    2.3 FACTORS AFFECTING THE

    BUILDINGS ENERGY CONSUMPTION

    Factors affecting the buildings energy consumption

    can be divided into two category, they are, non designfactors and passive design factors [12].

    2.3.1 NON DESIGN FACTORS

    Non design factors are the factors affected by:

    (i) Occupancy and management;

    (ii) Environmental standards; and(iii) Climate.

    2.3.2 PASSIVE DESIGN FACTORS

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    4/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    (i) Building orientation and shape

    (ii) Thermal mass

    (iii) Day lighting

    (iv) Passive ventilation

    (v) Solar thermal collector

    (vi) Plug load reduction

    2.4.2 ACTIVE SYSTEM

    Active system involves the mechanical and electrical

    approaches in order to improve energy efficiency of

    the building. Heat, Ventilation, and Air Conditioning

    (HVAC) are the mechanical system, light and

    electrical motor are the electrical system:

    (i) Active mechanical system

    (ii) Electrical power system

    2.5 RENEWABLE ENERGY TECHNOLOGY

    Renewable energy can be generated on-site by three

    different techniques, photovoltaic, wind energy, and

    biomass [14].

    2.5.1 PHOTOVOLTAIC PANEL (PV)

    Photovoltaic system is a system capable to convertlight energy into electrical energy [15].

    2.5.1.1 TYPES OF PV

    Guidelines for Energy Efficiency in Buildings, four

    typical buildings are defined to represent different

    expected levels of energy use in Malaysia. These four

    levels are: worst case, base case, proposed standard

    case and good practice case.

    (i) The worst case represents buildings that are

    among the most energy intensive buildings

    that might be encountered in Malaysia today.

    BEI = 240 kWh/m/yr.

    (ii) The base case building reflect a typical range

    of construction and energy use features now

    prevalent in Malaysian new commercial

    building construction. BEI = 166 kWh/m/yr.

    (iii) The proposed standard case reflects the level

    of energy efficiency expected to be achieved

    by the proposed Guidelines. BEI = 136

    kWh/m/yr.

    (iv) The good practice case represents a

    combination of energy efficient practice

    (including daylighting) that surpasses the

    requirements of the Guidelines proposed. BEI

    = 98 kWh/m/yr.

    3.1 RESEARCH METHODOLOGY

    Research Methodology is an important part in

    executing an academic research. The purpose of the

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    5/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    3.4 DATA COLLECTION

    In the research methodology, the obtained data can be

    categorized into two categories; they are primary data

    and secondary data.

    3.4.1 INTERVIEW

    Interview is a method to obtain the information or data

    from respondent through verbal communication, the

    responses from the interviewed respondent can be

    either opinions or advises. The information is very

    important because the interviewed respondent can

    explain the answer thoroughly. Interview will allow

    two ways communication between the interviewed

    respondent and researcher, this situation can contribute

    the additional opinions and different perspectives:

    (i) Malaysia Green Technology Corporations

    management team.

    (ii) Ruslan Khalid Associates Sdn. Bhd. is the

    architect firm which involved during the

    design of Malaysia Green Technology

    Corporation office building.

    (iii) IEN Consultants Sdn. Bhd. is the energy

    consultant of Malaysia Green TechnologyCorporation office building.

    3.4.2 OBSERVATION/FIELD OF STUDY

    4.0 DATA ANALYSIS AND RESEARCH

    OUTCOMES

    There are two types of method that had been being

    used throughout the research in order to achieve the

    research objectives; they are interview and

    observation/field of study.

    4.1 THE APPLICATION OF ZEB CONCEPT

    IN THE OFFICE BUILDING

    The application of ZEB concept in Malaysia Green

    Technology office building can be classified in to two

    categories, they are:

    (i) Energy efficient design

    (ii) Renewable energy technology

    4.1.1 ENERGY EFFICIENT DESIGN

    (i) Passive design

    (ii) Active system

    4.1.1.1 PASSIVE DESIGN

    (i) Building orientation

    The orientation of the office building is north-southaxis orientation, where, the building walls that has

    large surface area is being designed to locate

    perpendicular to the north-south axis, while the

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    6/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    Figure 4.1: Malaysia Green Technology Corporation

    office buildings orientation

    (ii) Insulation system

    (a) Internal wall

    The internal walls are installed with a layer of rockwool insulation in order to reduce thermal effects in

    the office building.

    Slanting roof

    Mineral wool is installed on the slanting roof as shown

    in Figure 4.3.

    Figure 4.3: Mineral wool layer is installed on theslanting roof [18].

    Uppermost floor

    Polystyrene layer is installed on the uppermost floor of

    the office building as shown in Figure 4.4, wherein the

    roof of the uppermost floor housed the Building

    Integrated Photovoltaic System (BIPV).

    Figure 4.4: Polystyrene layer is installed on theuppermost floor of the office building [18].

    (iii) Daylighting

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    7/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    Figure 4.5:(a) Diffuse daylight admitted through

    skylight [18].

    (b) Spectrally selective glazing.

    (c) Daylight source from sky light

    Daylight source from atrium roof

    Light source from PV panel acts as atrium roofallowing daylight enter the building through PV panel

    as shown in Figure 4.6.

    Figure 4.7: (a) Diffuse daylight entered into building

    [18]

    (b) Mirror light shelf

    (c) High reflective surface on the ceiling

    surface

    Internal layout

    Workplace is placed near to the window so that

    daylights are permitted to enter into the workplace

    area thoroughly while storage room is placed in the

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    8/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    Shading

    Shading plate, fixed ram unit, and step-in design are

    the types of shading applied in the office building as

    shown in Table 4.2 (Please refer to Appendix II).

    Reduced internal load

    Reducing plug load is the approach taken by Malaysia

    Green Technology Corporation in order to reduce the

    internal load. PC with CRT monitor are replaced by

    laptop or PC with LCD monitor as shown in Figure 4.9(Please refer to Appendix III).

    4.1.1.2 ACTIVE SYSTEM

    (i) Cooling system

    Cooling system of the building encompasses rainwater

    collection, trickling cool roof, cooling tower, chiller,Air Handling Unit (AHU), Phase Change Material

    (PCM), and radiant cooling system.

    (a) Trickling cool roof

    Trickling roof is an alternative approach to replace

    cooling tower. At the night time or during the low

    operation period, temperature of the water fromrainwater collection tank is reduced by draining

    through trickling cool roof, the process is assist by

    radiation convection evaporation and also the low

    (b) Cooling tower

    Cooling tower used in the Malaysia Green Technology

    Building has high energy efficient characteristic. The

    usage of cooling tower is complement to trickling cool

    roof. Cooling tower will function when trickling cool

    roof is not function.

    (c) Rainwater collection

    The filtered rainwater will be used for cooling

    purposes, and also for the irrigation system of the

    building. Rainwater collection tank has normal

    capacity which is 5280 gallon of water and its efficient

    capacity is 3700 gallon of water.

    (d) Phase Change Material (PCM)

    Phase Change Material (PCM) tank used in the

    building has dimension 3m x 3m x 2.5m as shown inFigure 4.12.

    Figure 4.12: Phase Change Material (PCM) [18]

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    9/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    Figure 4.14: VAV and VSD system installed in

    Malaysia Green Technology Corporation office

    building [18].

    (g) Radiant cooling system

    Chilled slab

    Chilled slab is the slab installed with PEX pipe which

    function to flow coolant under the floor so that the

    temperature in the room can be reduced through

    reduction of floor. Figure 4.15 shows PEX pipe

    installed on the slab during the construction.

    Fi 4 15 PEX i i ll d h l b d i h

    (ii) Energy efficient lighting system

    (a) Energy efficient electrical lighting system

    Energy efficient light, for example T5 and CFL are

    installed with proper circuit system, the goal is to

    reduce energy consumption. LED task light used in the

    building has 6.2 watt energy consumption rate. The

    energy efficient lights of the building have 300-400

    lux. as shown in Figure 4.17.

    Figure 4.17: (a) Compact Fluorescent Light (CFL)

    (b) Fluorescent Light

    (c) LED Light

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    10/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    4.1.2 THE PROBLEMS CAUSING BUILDING

    ENERGY INDEX (BEI) OF THE OFFICE

    BUILDING DID NOT ACHIEVE ZERO

    4.1.2.1 BUILDING ENERGY INDEX (BEI)

    Figure 4.18 (Please refer to V) shown that Building

    Energy Index (BEI) of the Malaysia Green

    Technology office building is 67-75 kWh/m2/year.

    The index shows that, energy produced by PV panels

    is still unable to fulfill the buildings energy needs.

    4.1.2.1 PROBLEMS CAUSING BUILDING

    ENERGY INDEX (BEI) DID NOT

    ACHIEVE ZERO

    Problems causing Building Energy Index (BEI) did not

    achieve zero is attributed to the cooling system design

    of the building.

    (i) Cold side of cooling system

    The problem is due to the cold side of the cooling

    system where the Phase Change Material (PCM) or Ice

    Storage did not turn into ice during the operation. This

    is due to supply water of the Chiller did not reach 7

    degree Celsius continuously for at least 8 hours when

    it reach the Phase Change Material (PCM) tank.Currently, the temperature of the supply water reached

    11 degree Celsius and above. Due to that reasons

    chiller has to operate longer hour during the day in

    (iii) The oversized Chiller

    The size of the current Chiller is 85 rth, it is too big

    and tends to consume more energy during its

    operation.

    4.1.3 THE APPROACHES THAT CAN

    IMPROVE ENERGY EFFICIENCY OF

    THE OFFICE BUILDING

    4.1.3.1 DISTRIBUTION OF ENERGY

    CONSUMPTION FOR MALAYSIA

    GREEN TECHNOLOGY

    CORPORATION OFFICE BUILDING

    Figure 4.20: Distribution of energy consumption for

    Malaysia Green Technology Corporation office

    building [18].

    Based on Figure 4.20, the highest energy consumption

    rate is cooling system, 72 percents, followed by others

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    11/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    (ii) Increase the air flow in the building

    Air flow in building can be improved through the

    installation of fan coil unit (FCU) in every level of the

    building. The installation of FCU as shown in Figure

    4.22 manages to improve the buildings air flow. This

    is because more chilled air can be channeled to the

    room in shorter time and its operation of the chiller

    can be reduced.

    Figure 4.22: Fan coil unit

    (iii) Reduce the chiller size

    The current chiller size has to be reduced to 45 rth. A

    smaller chiller will consume less energy compared to

    large chiller.

    (iv) Increase the temperature of slab radiantcooling system

    The original temperature of the slab radiant cooling

    (vi) Solar cooling system

    Solar thermal cooling is one of the types of solar

    cooling system. Solar thermal cooling uses solar

    thermal collector to ignite the absorption type of

    cooling system. Absorption cooling system can

    function well by only using thermal energy; hence,

    energy consumption can be reduced.

    (vii) Use desiccant in solar cooling system

    Desiccant like silica gel has ability to eliminate air

    moisture and its function is important to make sure

    cooling system can operate effectively. The desiccant

    can be regenerated by using solar thermal energy and

    not electricity.

    5.1 CONCLUSION AND

    RECOMMENDATION FOR FUTURE

    RESEARCH

    The summary of the research is the discussion of the

    objectives outcomes determined during the

    preliminary research. Besides that, recommendation

    for future research is given for a thorough research in

    the coming study

    5.2 FIRST OBJECTIVE OUTCOME

    The ZEB concept applied in the office building are

    passive design, active system, and renewable energy

    technologies. These systems have features that

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    12/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    5.5 RECOMMENDATION FOR FUTURE

    RESEARCH

    The results obtained from this study have led to a

    number of aspects to be considered in the future study.

    The recommendations are as follows:

    (i) Study on Energy Management System (EMS)

    of Malaysia Green Technology Corporation

    office building.

    (ii) Study on maintenance system of energy

    efficient buildings.

    (iii) Study on application of PV panel in residential

    building (etc.: energy efficient house in

    Malacca).

    (iv) Study on implication of energy efficient

    building from the aspects of (economy, indooror outdoor environment, and occupants

    wellbeing).

    (v) Study on energy efficiency of UTHM

    buildings (etc.: UTHM library).

    5.6 CONCLUSION

    Overall, a continuous study is needed in order to

    improve energy efficiency of buildings. Particularly

    for the country like Malaysia have advantages in using

    Zero Energy, High-Performance Green Buildings.

    Dicapai pada Mac 17, 2010, dari ms. 13 di

    http://www.bfrl.nist.gov/buildingtechnology/documents

    /FederalRDAgendaforNetZeroEnergyHighPerformance

    GreenBuildings.pdf[4] Raman, M. (2009). Mitigating Climate Change:

    What Americas Building Industry Must Do.Dicapai pada Mac 31, 2010, di

    http://www.di.net/articles/archive/3097/

    [5] Kok, C. (2009, Oktober 31). Malaysias GreenEnergy Gap. The Star. Dicapai pada Julai 1, 2010,

    darihttp://thestar.com.my/

    [6] Choong, M. Y. (2009, Disember 15). Major

    breakthrough. The Star. Dicapai pada Julai 2,

    2010, darihttp://thestar.com.my/

    [7] Butti, K. & Perlin, J. (1980). A Golden Thread,

    2500 Years of Solar Architecture and Technology.

    dlm. Hernandez, P. & Kenny, P. (2009). From Net

    Energy to Zero Energy Building: Defining Life

    Cycle Zero Energy Buildings (LC-ZEB) [versi

    elektronik]. Energy and Buildings, 42(6), 815-821.

    Dicapai pada Mac 17, 2010, darihttp://www.sciencedirect.com/

    [8] Soanes, C. & Stevenson, A. (2006). The Oxford

    Dictionary of English. 2nd ed. Oxford: Oxford

    University Press.

    [9] Walter, E. (Ed.) (2005). Cambridge Advanced

    Learner's Dictionary. 2nd ed. New York:

    Cambridge University Press.

    [10]

    Summers, D. (Ed.) (2003). LongmanDictionary of Contemporary English. 4th ed. New

    York: Longman.

    [11] Torcellini, P., Pless, S., & Deru, M. (2006).

    http://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.di.net/articles/archive/3097/http://www.di.net/articles/archive/3097/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://thestar.com.my/http://thestar.com.my/http://www.di.net/articles/archive/3097/http://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdf
  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    13/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    [17] Kannan, K. S. (2007). Development of an

    rating system for office building. Dicapai pada

    Mac 24, 2010, dari ms. 3 di

    http://www.irbnet.de/daten/iconda/CIB11464.pdf

    [18]

    Lojuntin, S. A. (2010, Mei). Green EnergyOffice BuildingA Low Carbon FootprintBuilding. [handout]. Malaysia Green Technology

    Corporation.

    http://www.irbnet.de/daten/iconda/CIB11464.pdfhttp://www.irbnet.de/daten/iconda/CIB11464.pdfhttp://www.irbnet.de/daten/iconda/CIB11464.pdf
  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    14/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    APPENDIX I

    Level Layout plan

    Level One

    Level Two

    Ground Level

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    15/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    APPENDIX II

    Types of shading Photo

    Plate shading:

    Fixed ram unit

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    16/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    APPENDIX III

    Figure 4.9: Energy consumption rate based on types of computer used (Malaysia GreenTechnology Corporation, 2010).

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    17/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    APPENDIX IV

    Types of PVpanel

    PV Panel Information

    Package A

    Poly-crytalline

    Panel 394 nos

    Produce 47 kWp

    356 meter square

    Package B

    Amorphous

    silicon

    Panel 95 nos

    Produce 6kWp

    100 meter square

    Package C

    Mono-

    crystalline, see

    through

    Panel 64 nos

    Produce 12kWp

    110 meter square

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    18/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    18

    APPENDIX V

    Figure 4.18: Building Energy Index (BEI) of Malaysia Green Technology Corporation Office Building (Malaysia Green Technology

    Corporation, 2010)

  • 8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre

    19/19

    Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

    19

    APPENDIX VI

    Figure 4.21: Schematic diagram of cooling system (Malaysia Green Technology Corporation, 2010)