The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office...
Transcript of The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office...
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
1/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
THE APPLICATION OF ZERO ENERGY
BUILDING CONCEPT IN THE MALAYSIAGREEN TECHNOLOGY CORPORATION
OFFICE BUILDING
Ng Ban Huat1, Zainal Abidin bin Akasah
2
Faculty of Civil and Environmental Engineering, UTHM
Abstract
Zero Energy Building (ZEB) which possess high energy efficient design and utilizes renewable energytechnology in order to fulfill its energy needs. Malaysia Green Technology Corporation office building is a
building designed base on ZEB concept; however Building Energy Index (BEI) for Malaysia Green Technology
office building has yet to achieve zero. This research focuses on the application of ZEB concept in Malaysia
Green Technology Corporation office building; secondly to identify the problems causing BEI of the studied
office building which did not achieve zero BEI; and lastly to propose approaches that can improve energy
efficiency for the office building. Interviews session with the office building management team, architect and
energy consultant have been carried out in order to achieve research objectives. Outcome of the research shows
that energy efficient design and renewable energy technology applied in the office building are passive design,active system, and Building Integrated Photovoltaic system (BIPV). The inefficiency at the cool part of the
cooling system, air movement, and chillers are the problems that have been identified. Recommendations such as
improving the efficiency of the cooling system, enhancing the air movement in the building, reduce the chillers
mailto:[email protected]:[email protected]:[email protected] -
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
2/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
1.1 INTRODUCTION
The over usage of fossil energy is the main contributor
towards global climate change [1]. This is due to the
excessive consumption of fossil energy will end up
releasing large amount of greenhouse gases. The
worlds fossil energy consumption rate has reached 82
percents [2].
Hence, the improvement of energy efficiency,
increasing the usage of renewable energy; preservationof a healthy building indoor environment; and
increasing the sustainability of natural resources are
among the approaches catching the worlds attention
[3].
Zero Energy Building (ZEB) is the building that
fulfills the needs stated above and capable in reducing
the dependence of fossil energy usage. This is because;ZEB manage to produce the amount of energy needs
by the buildings through environmentally friendly
manner.
1.2 PROBLEM STATEMENT
The development of energy efficient building or ZEB
is important, because the increase of buildingselectricity consumption contribute to the higher release
of greenhouse gasses compared to other sectors. This
is because; most of the electricity consumed by
1.3 RESEARCH QUESTION
(i) What are the ZEB components applied in the
office building?
(ii) What are the problems causing the Building
Energy Index (BEI) of the office building yet
to achieve zero?
(iii) What are the approaches that capable to
increase the energy efficiency of the office
building?
1.4 RESEARCH OBJECTIVE
The research objectives of this study are:
(i) To identify the application of ZEB concept in
the office building.
(ii) To identify the problems causing the Building
Energy Index (BEI) of the office building yet
to achieve zero.
(iii) To propose the approaches capable to increase
the energy efficiency of the building.
1.5 SIGNIFICANCE OF STUDY
This research is in aim to contribute to the following
parties:
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
3/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
(vi) Ministry of Energy, Green Technology, and
Water (KeTTHA), as the ministry responsible
in commercialize the activities related to green
technology as stipulated in Tenth Malaysia
Plan.
1.6 RESEARCH SCOPE
(i) This research was carried out in Malaysia
Green Technology Corporations office
building, Bandar Baru Bangi;
(ii) This research is focused on the ZEB
components applied in the office building. The
information is retrieved through the interview
with the buildings management team and the
architect involved during the design process.
(iii) This research is focus on the problems causing
the office buildings BEI did not achieve zero.The term energy used in this research is
referring to the energy used during the
operation of the building. The data were
retrieved through interview with the buildings
management team, and;
(iv) To acquire views from the office buildings
management team, architect, and energyconsultants involved during the design
process.
(iii) Building: Building is a structure such as a
house, church, or factory that has a roof and
walls [10].
ZEB concept emphasizes on the application of
commercial or residential building.
Hence, ZEB concept can be simplified as
follows: A Zero Energy Building (ZEB) is a
residential or commercial building with
greatly reduced energy needs through
efficiency gains such that the balance of
energy needs can be supplied with renewable
technologies [11].
2.3 FACTORS AFFECTING THE
BUILDINGS ENERGY CONSUMPTION
Factors affecting the buildings energy consumption
can be divided into two category, they are, non designfactors and passive design factors [12].
2.3.1 NON DESIGN FACTORS
Non design factors are the factors affected by:
(i) Occupancy and management;
(ii) Environmental standards; and(iii) Climate.
2.3.2 PASSIVE DESIGN FACTORS
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
4/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
(i) Building orientation and shape
(ii) Thermal mass
(iii) Day lighting
(iv) Passive ventilation
(v) Solar thermal collector
(vi) Plug load reduction
2.4.2 ACTIVE SYSTEM
Active system involves the mechanical and electrical
approaches in order to improve energy efficiency of
the building. Heat, Ventilation, and Air Conditioning
(HVAC) are the mechanical system, light and
electrical motor are the electrical system:
(i) Active mechanical system
(ii) Electrical power system
2.5 RENEWABLE ENERGY TECHNOLOGY
Renewable energy can be generated on-site by three
different techniques, photovoltaic, wind energy, and
biomass [14].
2.5.1 PHOTOVOLTAIC PANEL (PV)
Photovoltaic system is a system capable to convertlight energy into electrical energy [15].
2.5.1.1 TYPES OF PV
Guidelines for Energy Efficiency in Buildings, four
typical buildings are defined to represent different
expected levels of energy use in Malaysia. These four
levels are: worst case, base case, proposed standard
case and good practice case.
(i) The worst case represents buildings that are
among the most energy intensive buildings
that might be encountered in Malaysia today.
BEI = 240 kWh/m/yr.
(ii) The base case building reflect a typical range
of construction and energy use features now
prevalent in Malaysian new commercial
building construction. BEI = 166 kWh/m/yr.
(iii) The proposed standard case reflects the level
of energy efficiency expected to be achieved
by the proposed Guidelines. BEI = 136
kWh/m/yr.
(iv) The good practice case represents a
combination of energy efficient practice
(including daylighting) that surpasses the
requirements of the Guidelines proposed. BEI
= 98 kWh/m/yr.
3.1 RESEARCH METHODOLOGY
Research Methodology is an important part in
executing an academic research. The purpose of the
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
5/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
3.4 DATA COLLECTION
In the research methodology, the obtained data can be
categorized into two categories; they are primary data
and secondary data.
3.4.1 INTERVIEW
Interview is a method to obtain the information or data
from respondent through verbal communication, the
responses from the interviewed respondent can be
either opinions or advises. The information is very
important because the interviewed respondent can
explain the answer thoroughly. Interview will allow
two ways communication between the interviewed
respondent and researcher, this situation can contribute
the additional opinions and different perspectives:
(i) Malaysia Green Technology Corporations
management team.
(ii) Ruslan Khalid Associates Sdn. Bhd. is the
architect firm which involved during the
design of Malaysia Green Technology
Corporation office building.
(iii) IEN Consultants Sdn. Bhd. is the energy
consultant of Malaysia Green TechnologyCorporation office building.
3.4.2 OBSERVATION/FIELD OF STUDY
4.0 DATA ANALYSIS AND RESEARCH
OUTCOMES
There are two types of method that had been being
used throughout the research in order to achieve the
research objectives; they are interview and
observation/field of study.
4.1 THE APPLICATION OF ZEB CONCEPT
IN THE OFFICE BUILDING
The application of ZEB concept in Malaysia Green
Technology office building can be classified in to two
categories, they are:
(i) Energy efficient design
(ii) Renewable energy technology
4.1.1 ENERGY EFFICIENT DESIGN
(i) Passive design
(ii) Active system
4.1.1.1 PASSIVE DESIGN
(i) Building orientation
The orientation of the office building is north-southaxis orientation, where, the building walls that has
large surface area is being designed to locate
perpendicular to the north-south axis, while the
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
6/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
Figure 4.1: Malaysia Green Technology Corporation
office buildings orientation
(ii) Insulation system
(a) Internal wall
The internal walls are installed with a layer of rockwool insulation in order to reduce thermal effects in
the office building.
Slanting roof
Mineral wool is installed on the slanting roof as shown
in Figure 4.3.
Figure 4.3: Mineral wool layer is installed on theslanting roof [18].
Uppermost floor
Polystyrene layer is installed on the uppermost floor of
the office building as shown in Figure 4.4, wherein the
roof of the uppermost floor housed the Building
Integrated Photovoltaic System (BIPV).
Figure 4.4: Polystyrene layer is installed on theuppermost floor of the office building [18].
(iii) Daylighting
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
7/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
Figure 4.5:(a) Diffuse daylight admitted through
skylight [18].
(b) Spectrally selective glazing.
(c) Daylight source from sky light
Daylight source from atrium roof
Light source from PV panel acts as atrium roofallowing daylight enter the building through PV panel
as shown in Figure 4.6.
Figure 4.7: (a) Diffuse daylight entered into building
[18]
(b) Mirror light shelf
(c) High reflective surface on the ceiling
surface
Internal layout
Workplace is placed near to the window so that
daylights are permitted to enter into the workplace
area thoroughly while storage room is placed in the
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
8/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
Shading
Shading plate, fixed ram unit, and step-in design are
the types of shading applied in the office building as
shown in Table 4.2 (Please refer to Appendix II).
Reduced internal load
Reducing plug load is the approach taken by Malaysia
Green Technology Corporation in order to reduce the
internal load. PC with CRT monitor are replaced by
laptop or PC with LCD monitor as shown in Figure 4.9(Please refer to Appendix III).
4.1.1.2 ACTIVE SYSTEM
(i) Cooling system
Cooling system of the building encompasses rainwater
collection, trickling cool roof, cooling tower, chiller,Air Handling Unit (AHU), Phase Change Material
(PCM), and radiant cooling system.
(a) Trickling cool roof
Trickling roof is an alternative approach to replace
cooling tower. At the night time or during the low
operation period, temperature of the water fromrainwater collection tank is reduced by draining
through trickling cool roof, the process is assist by
radiation convection evaporation and also the low
(b) Cooling tower
Cooling tower used in the Malaysia Green Technology
Building has high energy efficient characteristic. The
usage of cooling tower is complement to trickling cool
roof. Cooling tower will function when trickling cool
roof is not function.
(c) Rainwater collection
The filtered rainwater will be used for cooling
purposes, and also for the irrigation system of the
building. Rainwater collection tank has normal
capacity which is 5280 gallon of water and its efficient
capacity is 3700 gallon of water.
(d) Phase Change Material (PCM)
Phase Change Material (PCM) tank used in the
building has dimension 3m x 3m x 2.5m as shown inFigure 4.12.
Figure 4.12: Phase Change Material (PCM) [18]
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
9/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
Figure 4.14: VAV and VSD system installed in
Malaysia Green Technology Corporation office
building [18].
(g) Radiant cooling system
Chilled slab
Chilled slab is the slab installed with PEX pipe which
function to flow coolant under the floor so that the
temperature in the room can be reduced through
reduction of floor. Figure 4.15 shows PEX pipe
installed on the slab during the construction.
Fi 4 15 PEX i i ll d h l b d i h
(ii) Energy efficient lighting system
(a) Energy efficient electrical lighting system
Energy efficient light, for example T5 and CFL are
installed with proper circuit system, the goal is to
reduce energy consumption. LED task light used in the
building has 6.2 watt energy consumption rate. The
energy efficient lights of the building have 300-400
lux. as shown in Figure 4.17.
Figure 4.17: (a) Compact Fluorescent Light (CFL)
(b) Fluorescent Light
(c) LED Light
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
10/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
4.1.2 THE PROBLEMS CAUSING BUILDING
ENERGY INDEX (BEI) OF THE OFFICE
BUILDING DID NOT ACHIEVE ZERO
4.1.2.1 BUILDING ENERGY INDEX (BEI)
Figure 4.18 (Please refer to V) shown that Building
Energy Index (BEI) of the Malaysia Green
Technology office building is 67-75 kWh/m2/year.
The index shows that, energy produced by PV panels
is still unable to fulfill the buildings energy needs.
4.1.2.1 PROBLEMS CAUSING BUILDING
ENERGY INDEX (BEI) DID NOT
ACHIEVE ZERO
Problems causing Building Energy Index (BEI) did not
achieve zero is attributed to the cooling system design
of the building.
(i) Cold side of cooling system
The problem is due to the cold side of the cooling
system where the Phase Change Material (PCM) or Ice
Storage did not turn into ice during the operation. This
is due to supply water of the Chiller did not reach 7
degree Celsius continuously for at least 8 hours when
it reach the Phase Change Material (PCM) tank.Currently, the temperature of the supply water reached
11 degree Celsius and above. Due to that reasons
chiller has to operate longer hour during the day in
(iii) The oversized Chiller
The size of the current Chiller is 85 rth, it is too big
and tends to consume more energy during its
operation.
4.1.3 THE APPROACHES THAT CAN
IMPROVE ENERGY EFFICIENCY OF
THE OFFICE BUILDING
4.1.3.1 DISTRIBUTION OF ENERGY
CONSUMPTION FOR MALAYSIA
GREEN TECHNOLOGY
CORPORATION OFFICE BUILDING
Figure 4.20: Distribution of energy consumption for
Malaysia Green Technology Corporation office
building [18].
Based on Figure 4.20, the highest energy consumption
rate is cooling system, 72 percents, followed by others
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
11/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
(ii) Increase the air flow in the building
Air flow in building can be improved through the
installation of fan coil unit (FCU) in every level of the
building. The installation of FCU as shown in Figure
4.22 manages to improve the buildings air flow. This
is because more chilled air can be channeled to the
room in shorter time and its operation of the chiller
can be reduced.
Figure 4.22: Fan coil unit
(iii) Reduce the chiller size
The current chiller size has to be reduced to 45 rth. A
smaller chiller will consume less energy compared to
large chiller.
(iv) Increase the temperature of slab radiantcooling system
The original temperature of the slab radiant cooling
(vi) Solar cooling system
Solar thermal cooling is one of the types of solar
cooling system. Solar thermal cooling uses solar
thermal collector to ignite the absorption type of
cooling system. Absorption cooling system can
function well by only using thermal energy; hence,
energy consumption can be reduced.
(vii) Use desiccant in solar cooling system
Desiccant like silica gel has ability to eliminate air
moisture and its function is important to make sure
cooling system can operate effectively. The desiccant
can be regenerated by using solar thermal energy and
not electricity.
5.1 CONCLUSION AND
RECOMMENDATION FOR FUTURE
RESEARCH
The summary of the research is the discussion of the
objectives outcomes determined during the
preliminary research. Besides that, recommendation
for future research is given for a thorough research in
the coming study
5.2 FIRST OBJECTIVE OUTCOME
The ZEB concept applied in the office building are
passive design, active system, and renewable energy
technologies. These systems have features that
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
12/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
5.5 RECOMMENDATION FOR FUTURE
RESEARCH
The results obtained from this study have led to a
number of aspects to be considered in the future study.
The recommendations are as follows:
(i) Study on Energy Management System (EMS)
of Malaysia Green Technology Corporation
office building.
(ii) Study on maintenance system of energy
efficient buildings.
(iii) Study on application of PV panel in residential
building (etc.: energy efficient house in
Malacca).
(iv) Study on implication of energy efficient
building from the aspects of (economy, indooror outdoor environment, and occupants
wellbeing).
(v) Study on energy efficiency of UTHM
buildings (etc.: UTHM library).
5.6 CONCLUSION
Overall, a continuous study is needed in order to
improve energy efficiency of buildings. Particularly
for the country like Malaysia have advantages in using
Zero Energy, High-Performance Green Buildings.
Dicapai pada Mac 17, 2010, dari ms. 13 di
http://www.bfrl.nist.gov/buildingtechnology/documents
/FederalRDAgendaforNetZeroEnergyHighPerformance
GreenBuildings.pdf[4] Raman, M. (2009). Mitigating Climate Change:
What Americas Building Industry Must Do.Dicapai pada Mac 31, 2010, di
http://www.di.net/articles/archive/3097/
[5] Kok, C. (2009, Oktober 31). Malaysias GreenEnergy Gap. The Star. Dicapai pada Julai 1, 2010,
darihttp://thestar.com.my/
[6] Choong, M. Y. (2009, Disember 15). Major
breakthrough. The Star. Dicapai pada Julai 2,
2010, darihttp://thestar.com.my/
[7] Butti, K. & Perlin, J. (1980). A Golden Thread,
2500 Years of Solar Architecture and Technology.
dlm. Hernandez, P. & Kenny, P. (2009). From Net
Energy to Zero Energy Building: Defining Life
Cycle Zero Energy Buildings (LC-ZEB) [versi
elektronik]. Energy and Buildings, 42(6), 815-821.
Dicapai pada Mac 17, 2010, darihttp://www.sciencedirect.com/
[8] Soanes, C. & Stevenson, A. (2006). The Oxford
Dictionary of English. 2nd ed. Oxford: Oxford
University Press.
[9] Walter, E. (Ed.) (2005). Cambridge Advanced
Learner's Dictionary. 2nd ed. New York:
Cambridge University Press.
[10]
Summers, D. (Ed.) (2003). LongmanDictionary of Contemporary English. 4th ed. New
York: Longman.
[11] Torcellini, P., Pless, S., & Deru, M. (2006).
http://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.di.net/articles/archive/3097/http://www.di.net/articles/archive/3097/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://thestar.com.my/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://thestar.com.my/http://thestar.com.my/http://www.di.net/articles/archive/3097/http://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdfhttp://www.bfrl.nist.gov/buildingtechnology/documents/FederalRDAgendaforNetZeroEnergyHighPerformanceGreenBuildings.pdf -
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
13/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
[17] Kannan, K. S. (2007). Development of an
rating system for office building. Dicapai pada
Mac 24, 2010, dari ms. 3 di
http://www.irbnet.de/daten/iconda/CIB11464.pdf
[18]
Lojuntin, S. A. (2010, Mei). Green EnergyOffice BuildingA Low Carbon FootprintBuilding. [handout]. Malaysia Green Technology
Corporation.
http://www.irbnet.de/daten/iconda/CIB11464.pdfhttp://www.irbnet.de/daten/iconda/CIB11464.pdfhttp://www.irbnet.de/daten/iconda/CIB11464.pdf -
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
14/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
APPENDIX I
Level Layout plan
Level One
Level Two
Ground Level
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
15/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
APPENDIX II
Types of shading Photo
Plate shading:
Fixed ram unit
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
16/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
APPENDIX III
Figure 4.9: Energy consumption rate based on types of computer used (Malaysia GreenTechnology Corporation, 2010).
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
17/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
APPENDIX IV
Types of PVpanel
PV Panel Information
Package A
Poly-crytalline
Panel 394 nos
Produce 47 kWp
356 meter square
Package B
Amorphous
silicon
Panel 95 nos
Produce 6kWp
100 meter square
Package C
Mono-
crystalline, see
through
Panel 64 nos
Produce 12kWp
110 meter square
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
18/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
18
APPENDIX V
Figure 4.18: Building Energy Index (BEI) of Malaysia Green Technology Corporation Office Building (Malaysia Green Technology
Corporation, 2010)
-
8/11/2019 The Application of Zero Energy Building Concept in the Malaysia Green Technology Corporation Office Building-libre
19/19
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)
19
APPENDIX VI
Figure 4.21: Schematic diagram of cooling system (Malaysia Green Technology Corporation, 2010)