The 11th International Symposium on Water Supply ...

55
1 The 11 th International Symposium on Water Supply Technology SFPUC Water System Improvements to meet Levels of Service July 10, 2019 San Francisco Public Utilities Commission (SFPUC) Sam Young, P.E.

Transcript of The 11th International Symposium on Water Supply ...

Page 1: The 11th International Symposium on Water Supply ...

1

The 11th International Symposium on Water Supply Technology

SFPUC Water System Improvementsto meet Levels of Service

July 10, 2019

San Francisco Public Utilities Commission (SFPUC)Sam Young, P.E.

Page 2: The 11th International Symposium on Water Supply ...

Outline

• SFPUC Water System Overview

• Water System Improvement Program (WSIP)

o Level of Service Goals

o Key Projects

• SF Water System Overview

o Level of Service Goals

o Pipeline Replacement Program

2

Page 3: The 11th International Symposium on Water Supply ...

3

SFPUC Water System Overview

Page 4: The 11th International Symposium on Water Supply ...
Page 5: The 11th International Symposium on Water Supply ...
Page 6: The 11th International Symposium on Water Supply ...

End of Useful Life

LACK OF REDUNDANCY

Page 7: The 11th International Symposium on Water Supply ...

3 MAJOR EARTHQUAKE FAULTS

Page 8: The 11th International Symposium on Water Supply ...

It’s Not “IF” But “WHEN”

San Francisco 1906

7.9 M

Hayward 1868

6.8M

Loma Prieta 1989

6.9M

Page 9: The 11th International Symposium on Water Supply ...

Water System Improvement Program (WSIP)

• Initiated in 2002• 87 Projects

• 2 dams• 3 tunnels• 3 treatment facilities• Pipelines, pump stations,

reservoirs, tanks, etc.

• 7 Counties

• $4.8 Billion, Bond-Funded

• 2021 Completion

9

Page 10: The 11th International Symposium on Water Supply ...

• Establish performance standard

• Ensure / improve reliability of the system

• Develop capital improvement program that is tied to performance levels

• Identify deficiencies and cost-effective solutions

• Provide quantifiable basis for capital improvement projects

• Support stakeholder decision-making process

Why Set Level of Service Goals?

Page 11: The 11th International Symposium on Water Supply ...

Levels of Service Development

11

• Reliability Study Phase I – Defined system & identified hazards (1995)

• Reliability Study Phase II – Quantified hazards and evaluated system response (2000)

• Reliability Study Phase III – Reliability and risk analysis (2003)

• Performance Standards I & II – Developed alternative performance levels and improvement needs (2004)

• Water System Improvement Program – Levels of Service and Program Adoption (2005)

Page 12: The 11th International Symposium on Water Supply ...

Seismic Reliability

Delivery Reliability

Water Quality

Water Supply

Level of Service Goals

Page 13: The 11th International Symposium on Water Supply ...

Seismic Reliability LOS

Reduce vulnerability to earthquakes

• Design improvements to meet current seismic standards.

• After a major San Andreas, Hayward, or Calaveras earthquake:

• Deliver “basic service” to 3 region service area (SF, East/South Bay, and Peninsula);

• Basic service is Average Winter Month Usage (229 mgd);

• Delivery to at least 70 percent of the customer turnouts in each region

13

Page 14: The 11th International Symposium on Water Supply ...

Seismic Reliability LOS

• Restore facilities to meet average-day demand (up to 300 mgd) within 30 days after a major earthquake.

14

Page 15: The 11th International Symposium on Water Supply ...

15

Before WSIP: San Andreas 7.9M Event

Reliability Study Phase III, November 2004

Page 16: The 11th International Symposium on Water Supply ...

16

After WSIP: San Andreas EventProbabilities of Failure

Reliability Study Phase III, November 2004

Page 17: The 11th International Symposium on Water Supply ...

Key Projects

Page 18: The 11th International Symposium on Water Supply ...

Tesla Treatment Facility

• $114 Million

• 315 mgd capacity

• UV disinfection

• Compliance with latest EPA guidelines

• Design-Build contract

Page 19: The 11th International Symposium on Water Supply ...

19

Tesla UV Treatment Facility

Page 20: The 11th International Symposium on Water Supply ...

Tesla UV Treatment Facility

Page 21: The 11th International Symposium on Water Supply ...

New Irvington Tunnel

• $340 Million Water Transmission Tunnel

• 3.5-mile long, 13.5-ft dia.

• Convention mining

with roadheaders and

controlled detonation

• Redundancy

• Challenging ground conditions

• Gassy tunnel

Page 22: The 11th International Symposium on Water Supply ...

Drill and Blast Excavation

Page 23: The 11th International Symposium on Water Supply ...

CONVENTIONAL MINING METHOD

Page 24: The 11th International Symposium on Water Supply ...

BDPL Reliability Upgrade

• $347 Million (tunnel)

• $251 Million (pipeline)

• 5 mile tunnel under SF Bay

• 19 mile pipeline in East Bay & Peninsula

• Hayward Fault crossing

Page 25: The 11th International Symposium on Water Supply ...

Bay Bay Tunnel

Page 26: The 11th International Symposium on Water Supply ...

TBM at Launch Shaft

26

Page 27: The 11th International Symposium on Water Supply ...

Hayward Fault Crossing

Page 28: The 11th International Symposium on Water Supply ...

DESIGN CONCEPT AT TRACE B

Page 29: The 11th International Symposium on Water Supply ...

DESIGN CONCEPT ANIMATION

Page 30: The 11th International Symposium on Water Supply ...

Typical Section At Fault Zone

Page 31: The 11th International Symposium on Water Supply ...

North box pulled by 4 actuators to create strike-slip offset of 198 mm (Design offset = 6.5 ft)

South box fixed to lab structure and modular reaction wall

Secant pile wall

Precast U Shaped

45 degrees

Test Bed at Cornell University

Page 32: The 11th International Symposium on Water Supply ...

32

Ball JointBall Joint and Slip Joint Construction

Page 33: The 11th International Symposium on Water Supply ...

Calaveras Dam Replacement

• $823 Million

• New seismically safe dam

• Restore original storage level (31 Billion gallon)

• Difficult geological conditions

• Environmental challenges

Page 34: The 11th International Symposium on Water Supply ...

8/25 aerial

New Dam

Old Dam

Spillway

Left Abutment

Right Abutment

Stilling Basin

Water

Treatment

System

Intake Tower

Disposal Sites

Borrow

Area

Page 35: The 11th International Symposium on Water Supply ...

Dam and Spillway Excavation

Right abutment

Left abutment

Stilling basin

Spillway

Outlet pipe bench

Axis of new dam

Page 36: The 11th International Symposium on Water Supply ...

Cross Section of Replacement Dam

• Zoned Earth and Rock-Filled Dam

• 220 feet high & 1200 feet in length

• 80’ Crest and 1,180’ Base

S - Upstream N - Downstream

Page 37: The 11th International Symposium on Water Supply ...

Construction Time Lapse Video

Page 38: The 11th International Symposium on Water Supply ...

Calaveras Dam 2019

38

Page 39: The 11th International Symposium on Water Supply ...

HTWTP Long-Term Improvements

• $359 Million

• 140 mgd capacity

• Seismic retrofit

• Process improvements

• New seismic risks

• Plant challenges

San Andreas Fault

Raw water quality

Site limitations

Maintain Operations

Page 40: The 11th International Symposium on Water Supply ...

Project Components

Eastern Fault

Western Fault

Page 41: The 11th International Symposium on Water Supply ...

41

New Filters

Page 42: The 11th International Symposium on Water Supply ...

11 MG Treated Water Reservoir

Page 43: The 11th International Symposium on Water Supply ...

43

TWR Contactor and Storage Cell

Page 44: The 11th International Symposium on Water Supply ...

44

TWR Roof Construction

Page 45: The 11th International Symposium on Water Supply ...

45

Completed Site

Page 46: The 11th International Symposium on Water Supply ...

46

SF Water System Overview

• 5 regional transmission mains

• 1,240 miles of distribution pipeline

• 17 storage tanks and reservoirs

• 10 pump stations

• 24 pressure zones

Page 47: The 11th International Symposium on Water Supply ...

47

SF Water Distribution System

• 1,240 miles of pipeline

o Cast iron

o Ductile iron

o Steel

• 220 miles over 100 yrs

• Average age of pipes: 57yrs

Page 48: The 11th International Symposium on Water Supply ...

WSIP Local Projects

48

• 27 Seismic Upgrade Projects

• Reservoirs, Pump Stations and Tanks

• Large transmission pipelines and valves

Page 49: The 11th International Symposium on Water Supply ...

SF Potable Water Seismic LOS

• WSIP LOS provides post-earthquake water to 4 out of 5 locations in San Francisco

• Expand LOS for SF post-earthquake reliability

• SF Seismic Reliability LOS being developed

• “Critical Network” to be determined

• Earthquake Resistant Ductile Iron Pipe (ERDIP)

49

Page 50: The 11th International Symposium on Water Supply ...

SF Potable Water Seismic LOS

• Storage: 2 days average day demand + 2 hours of fire suppression each pressure zone

• Water Supply Restoration

• 24 hours - limited services to Critical Care Facilities

• 72 hours - limited secondary distribution system pressurized

• 7 days - limited transmission and distribution mains restored to potable service.

• 90 days - secondary distribution system restored to potable service.

50

Page 51: The 11th International Symposium on Water Supply ...

• Reliability Analysis (2011)

• Total Risk Scores for all pipes

• 320 miles identified for priority replacement

• Replacement goal: 15 miles/year

• $55M Annual Budget

51

Pipeline Replacement Program

Page 52: The 11th International Symposium on Water Supply ...

52

320 Miles of Priority Pipeline

Page 53: The 11th International Symposium on Water Supply ...

Seismic Backbone System

Page 54: The 11th International Symposium on Water Supply ...

Summary

• LOS need to be matched to customer/stakeholder expectations, funding/resources, & delivery schedules.

• Consistent LOS help control project scopes and budgets, and assist in recovery planning.

• Resources/facilities needed to achieve and maintain LOS should be carefully predicted through iterative planning and modeling, and extensive stakeholder involvement.

54

Page 55: The 11th International Symposium on Water Supply ...

Questions?

Contact Information:Sam Young, P.E.

[email protected]

55