Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning...

20
Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission Assessment 2010 Workshop 1 Phoenix, Arizona June 3-4, 2010 Robert Kondziolka, P.E. Salt River Project

Transcript of Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning...

Page 1: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

Regional Transmission PlanningUpdate on WECC TEPPC Efforts on Western

Interconnection Wide Planning

Arizona Corporation Commission

6th Biennial Transmission Assessment

2010 Workshop 1Phoenix, ArizonaJune 3-4, 2010

Robert Kondziolka, P.E.Salt River Project

Page 2: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

2

What is Planning?

Identification of future infrastructure needs: 1. Serve the expected load reliably2. Meet public policy directives3. Minimize cost and environmental impact

Transmission planning – identify future transmission capacity needs given a future set of loads and resources

Page 3: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

3

Reliability and Economic Planning

System Reliability can be characterized as maintaining energy supply to load while responding in a predictable fashion to both planned and unplanned outages in generation and transmission.

System Congestion is a measure of the economic performance which answers the question “while operating within the bounds of reliable operation, how well does the transmission system perform to deliver the lowest cost energy (or energy source of choice) to consumers?”

Page 4: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

4

●TEPPC’s analyses and studies focus on studies with Interconnection-wide implications

Reliability, Cost, Emissions

●TEPPC’s role does not include Detailed project-specific studiesAdvocating projectsIdentifying potential “winners” and “losers” Siting and cost allocation

●Provides governance over the RTEP (Regional Transmission Expansion Project) process

TEPPCTransmission Expansion Planning Policy Committee

Page 5: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

5

ARRA-funded via a $14.5M DOE Grant to WECC

Corresponding $12.0M Grant to WGAActivities managed by TEPPCWECC’s proposal available at the RTEP website – www.wecc.biz

RTEP Regional Transmission Expansion Planning

Page 6: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

6

Funding Opportunity AnnouncementRegional Transmission Planning

● Up to $60 million in DOE funding for: (A) Interconnection-level analysis and

planning (Topic A) (B) State cooperation on electric resource

planning and priorities (Topic B)

● Responses were due September 14, 2009 WECC submission - August 13, 2009

● Funds available under DE-FOA0000068 www.doe.gov/recovery

Page 7: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

7

Funding Opportunity AnnouncementKey Provisions

● Create interconnection-wide, long-term, scenario-based transmission plans Identify alternative transmission system configurations Quantify reliability and cost implications Address technology and policy uncertainties

● Deliverables due in June 2011 and June 2013● Establish a multi-constituency steering group to

guide scenario development 1/3 State representatives Non-traditional stakeholders

● Fund non-profit and non-governmental organization (NGO) participation in planning processes

Page 8: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

8

Overview of WECC responseWhat the proposal is

● Extraordinary opportunity to expand the capability of planning processes in the West

● An extension of existing TEPPC planning process Ability for broader input from other

stakeholders into planning processes Ability to study a broader range of scenarios

Determine impact of policy and technology drivers

Page 9: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

9

Overview of WECC responseWhat the proposal is NOT

● Radical shift in WECC processes

● Change in planning governance

● Significant long-term funding commitment by WECC and membership

● WECC involvement in siting or cost allocation processes

● No commitment to fund non-WECC activities beyond the DOE funding period

Page 10: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

10

Overview of WECC ResponseFunding Diagram

VGSIntegration

Topic B ProposalWGA WIRAB/CREPC

Public Policy

WREZPhases 3 & 4

NationalLabs

NREL

LBL

PNNL

SNL

Request for Technical Assistance/CoordinationTopic A Proposal

WECC/TEPPCInterconnection-wide Planning

ColumbiaGrid

CA/MXCAISOWest

Connect

SWAT

Other SPG

NTTG

CCPG Sierra

SPGTransmission Planning

NGO Participation

Energy Offices

Regulators

State/ProvincialPolicy/Participation

LRS/LSEResource/Load Planning

Legislators

Coordination

PCCReliability

UniversitiesTraining/Analysis

Page 11: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

11

Topic A$16.3 million

Topic B$14.0 million

Funding of Tasks Under Topics A and B4 Year funding period

Actual $14.5M

Actual $12.0M

Page 12: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

12

Item 2010 2011 2012 2013 Total

WECC Activities $1,787,298 $1,411,718 $1,207,018 $1,169,580 $5,575,614

SCG Activities $476,150 $476,150 $476,150 $476,150 $1,904,600

SPSG Activities $630,476 $630,476 $630,476 $630,476 $2,521,904

NGO Participation $546,200 $546,200 $546,200 $544,282 $2,182,882

University Activities $637,013 $758,846 $919,141 $0 $2,315,000

Total, RTEP Project $4,077,137 $3,823,390 $3,778,985 $2,820,488 $14,500,000

Summary of changes from original proposal

1. Removed National Lab funding

2. Reduced all other budgets by 11%

RTEP Budget

Page 13: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

13

Total Number

SPSG members on TEPPC

Representing

5 0 Technology Advocates (wind/solar/geothermal/nuclear/coal/EE/DSM)

1 0 Transmission Owner/Operator/Developer1 0 Lands protection advocate1 0 Wildlife advocate8 2 State Officials (PUC, Energy Office)1 0 Provincial Official1 0 Canadian Utility Representative2 1 Consumer Advocates – One from TEPPC1 1 Environmental Representative from TEPPC1 1 WECC Board member from TEPPC1 1 SPG representative from TEPPC1 1 LSE representative from TEPPC1 0 Tribal Representative25 7 TOTAL

SPSGScenario Planning Steering Group Representation

Page 14: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

14

Stakeholder Requests

(Open Season)

Study ProgramDevelopment(Study Plan)

Scenario Development

(SPSG)

Create Study Cases

Analysis

Reporting & Creation of

Plan(s)

Review andPublic Comment

Process

Recommend Approval

ScenarioAnalysis Meets

StrategicGuidance

YES

Decision BodyScenario Planning Steering Group

TEPPC

WECC Board

TEPPC Workgroup Concensus

Public

NO

Approval ofPlan(s)

PublishReport and

Plan(s) YES

NO

Note – The small boxes represent opportunities for stakeholders to be directly involved in planning processes.

TEPPC Workgroup activities are open to all and decisions are made by consensus. It is at these meetings where many of the details of the planning process are decided.

SPG plan

ConsensusTEPPC has final decisionSection 4.1.4

Overview of WECC Response Expanded TEPPC Regional Planning Process

Page 15: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

15

WECC ProposalPlanning Activities (new activities in Red)

Long Term20 Years

Reg

iona

l(W

EC

C)

Medium Term5-10 Years

· OTC, TTC· Rating Process· TEPPC (5yr)

Short Term0-5 Years

Sub

regi

onal

(SP

G)

Loca

l(U

tiliti

es)

· TEPPC Congestion Analysis

· 10yr Regional Plan· Project Planning &

Rating Process· Reliability Assessment

· 20yr Regional Trans Target Plan

· LSE Planning Coordination (WIRPF)

· OTC, ATC· Short-term

Assessment· Short-term Design

Planning

· Sub-Reg Trans Biennial Cap

· Annual Econ Study· SPG 10yr Att K Plan · 10yr SPG Coordinated

Reliability Plan

· Attachment K or equivalent

· Compliance Studies

· OATT studies· Operating Studies· Compliance

Studies

· Long-range studies

Page 16: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

16

September 201110-Year Regional Transmission PlanSPG Foundational Project ListPlanning Engineer Education ProgramTechnology Reliability Assessment

September 2013Updates to the June 2011 deliverables20-Year Regional Transmission Target Plan

Deliverables to DOE

Page 17: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

17

Congress FERC DOE

WECC-TEPPC•Manage the Regional Transmission Planning Process•Create Annual Study Program•Complete expanded transmission studies•Create 10- and 20-Year Plans

SPSG•Guide RTEP Project•Ensure stakeholder involvement

Energy Agencies PUCs

Energy Providers

SPG’s•Coordinate local processes

Transmission Providers

Electricity Planning

Page 18: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

18

Increased coordination among entities in the Western Interconnection Increased awareness of how energy policy decisions impact reliability and cost Ability to answer key policy questions at State, Provincial and Federal levels Additional information for use by decision makers in siting and cost allocation proceedings

RTEP Desired OutcomesValue Propositions

Page 19: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

19

Board approved the RTEP project Scenario Planning Steering Group (SPSG)

Seated through Board consent on MarchRequest for a Tribal representative sent

Contract with DOEFinal Contract nearly ready

TEPPC document changes complete Close coordination of activities with the State and Provincial-led activities

RTEP Update

Page 20: Regional Transmission Planning Update on WECC TEPPC Efforts on Western Interconnection Wide Planning Arizona Corporation Commission 6 th Biennial Transmission.

20

Questions?

Robert Kondziolka, P.E.Salt River Project

[email protected]

Regional Transmission PlanningUpdate on WECC TEPPC Efforts on Western Interconnection

Wide Planning

Sources of Information – Previous presentations by:Brad Nickell, WECC DirectorScott Cauchois, TEPPC ChairRobert Kondziolka, TEPPC Member