War Room Set-up Guide
War Room Set-Up
• Once a suitable location is secured. Start building your room using this basic format.
Assessment Summary Commitment Letter Action Plan Action Plan indicators Sustaining Indicators Project Status
Project #:
Supplier: Holset, Charleston, SC USA Dates of Assessment : 7/18-7/27
Critical Prism Focus Customer Problem: Turbo Noise – Cummins
Bent Blades – Holset.
Direct Root Cause: Bent Blade - Manual Process.
Detection Root Cause: Reliance on Variable Sorting Rig (VSR) tester.
Systemic Cause (5- Why Based):
New process did not consider bent blades at assembly station as a possible failure mode during introduction.
Process Control Focus FMEA Adequacy: FMEA is not a living document. No linkage to operation . FMEA did not match
Control Plan. Ranking system not appropriate or consistent. FMEA construction is incorrect.
Control Plan Adequacy:
Control Plan and PFMEA linkage is inconsistent.
Implementation Adequacy:
Some items on plan not evident on floor, particularly Receiving Inspection
Systemic Analysis – Weakness:
PFMEA not used as a tool, not up to date, Lessons Learned seldom incorporated in existing products. Items on FMEA not consistently carried through to Control Plan.
System Focus Systemic Analysis – Weakness: 1
Visual Management- Visual factory, 5-S, and scoreboards not used effectively on plant floor.
Weakness: 2 Material Flow Control- Control of Non-conforming material, Handling practices, part Identification, and Hidden Factories not effective. Note: Inconsistent with documented process flow. The following, are key weakness, noted during the assessment; hidden factories, improper usage and storage of racks, whip/supplied & finished product storage and identification/disposal of non-conforming material.
Weakness: 3 LPA- LPA system is not well defined. LPA is not used to drive improvements. Process is immature.
------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Dates: Start – Target Finish –
---------------------------------------------------------------------------------------------------------------------------------------
Concurrence:
Supplier Project Leader:
Name: Date: Signature:
Supplier Sr. Executive Sponsor:
Name: Date: Signature:
QAAT Director:
Name: Date: Signature:
Chrysler Group SQ Sr. Mgr:
Name: Date: Signature:
------------------------------------------------------------------------------------------------------------------------------------------------------------------
Supplier locations for read across:
1.
2. 3. 4.
------------------------------------------------------------------------------------------------------------------------------------------------------------------ Monthly Progress Review Meeting Schedule:
ID #
Metric (where applica
ble)
ChampionStart Date
End Date Status Comment
1
1a1aa1ab1ac
1b1ba1bb1bc
2
2a2aa2ab2ac
2b2ba2bb2bc
QAAT Action Plan
Supplier :
Action ItemID #
Metric (where applica
ble)
ChampionStart Date
End Date Status Comment
1
1a1aa1ab1ac
1b1ba1bb1bc
2
2a2aa2ab2ac
2b2ba2bb2bc
QAAT Action Plan
Supplier :
Action Item
0
50
100
Identify high risk suppliers for quality spills
Analyze PRISM’s and other indicators for selected high risk suppliers to determine deficient business processes
Establish “improvement need” with supplier at corporate level
Perform assessment of appropriate supplier processes using standard tools
Complete Assessment document and Identify Systemic Deficiencies
Form Project Team, including supplier, QAAT, Assembly SQ, subject experts as required (Supplier leads)
Analyze Assessment document, develop corrective action work plan, and determine project deliverables
Develop and sign statement of work with committed improvement, measures, and timing
Make focused training available to the Project Team
Execute the work plan
Measure project results, monitor work plan adherence, and provide weekly status reports
Confirm Agreement on Identified Systemic Deficiencies
QUALITY ASSURANCE AND AUDIT TEAM
Work Process
Assembly Supplier Quality
QAAT & Assembly SQ
Assembly SQ, Commercial Procurement, QAAT, Supplier Sr. Exec.
QAAT Lead Assessor, Supplier Leader, QAAT Leader
QAAT Lead Assessor, Supplier Leader, QAAT Leader
Supplier Leader, QAAT Leader
Project Team
Project Team & Supplier Sr. Executive
Project Team
Project Team
Project Team
Supplier Sr. Executive, QAAT Leader
Step 1
Step 2
Step 3
Step 5
Step 6
Step 8
Step 9
Step 10
Step 11
Step 12
Step 13
Step 7
Participants
Establish “improvement need” with supplier on-site at manufacturing location
Step 4Assembly SQ, QAAT, Supplier manufacturing location Exec. Mgt.
0
50
100
0
50
100
Cust. Prob: MF0Direct Root Cause: HF0Detection R/C: C0Sys. Cause (5 why based): CC0
Actual 5-Why
FMEA Adequacy: Weakness 1: LP0C/P Adequacy: Weakness 2: OC0Imp. Action Adequacy: Weakness 3: SS0Systemic Analysis Weakness:
OS0SV0M0
WAR BOARD
Issue Focus Detail (SLIDE)
ISSUE FOCUS System Weekness 1
MF0 Action Plan HF0 Action Plan
Supplier Lead Sheet
(Supplier Overview)
QAAT Assessment Phases Issue /
Control / System Focus
Control Focus Detail
(SLIDE)
CONTROL FOCUS SYSTEM FOCUS System Weekness 2
LP0 Action Plan OC0 Action Plan
SV0 Action PlanSystem
Focus Detail (SLIDE)
QAAT ASSESSME
NT TOOL (completed)
System Weekness 3
OS0 Action Plan
*Alternate Arrangement
* Also known as the Jeffcean War board
Print the following slides for your set-up.
Assessment Summary
Commitment Letter
Action Plan
Action Plan Indicators
Sustaining Indicators
Project Status
War Room Set-Up• As each Focus is completed add
Documentation.
Issue Focus Control Focus System Focus
ID #
Metric (where applica
ble)
ChampionStart Date
End Date Status Comment
1
1a1aa1ab1ac
1b1ba1bb1bc
2
2a2aa2ab2ac
2b2ba2bb2bc
QAAT Action Plan
Supplier :
Action Item
ISSUE FOCUSCONTROL FOCUS SYSTEM FOCUS
Systemic Weakness SummaryThe Critical Few
Project Commitment Letter
Improvement Plan
Read Across
System Assessment
QAAT Process Control Focus
FMEA & ControlPlan Effectiveness
FMEA Adequate?
Control PlanAdequate?
Effectively Implemented?
CONTROL FOCUS
System Assessment Analysis of General Process Control:
Purpose:FMEA & Control Plan AdequacyDegree of implementationMethods of Detecting Issues
Method:Review Selective Parts (over period of time)Document linkages (FMEA, Control Plan…)Implementation on the floorRelationship to Real Issues (Scrap, defects,…)Detection Audit
Detection Audit
Dedicated Detection
Audit
Detection Methods
Adequate?
Issue Focus
Control Focus
System Focus
Vijay Example