Tellmore Masocha (B .S c (Hons) Civil Eng)gcs-sa.biz › wp-content › uploads › 2015 › 07 ›...

25
Report Number: AISP/FBC/P12/10/02 19 June 2012 DRAFT DESIGN REPORT FORBES COAL NEW DISCARD DUMP Tellmore Masocha (B.Sc (Hons) Civil Eng)

Transcript of Tellmore Masocha (B .S c (Hons) Civil Eng)gcs-sa.biz › wp-content › uploads › 2015 › 07 ›...

  • Report Number: AISP/FBC/P12/10/02

    19 June 2012

    DRAFT DESIGN REPORT

    FORBES COAL NEW DISCARD DUMP

    Tellmore Masocha (B.Sc (Hons) Civil Eng)

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report ii June 2012

    Table of Contents

    TABLE OF CONTENTS ........................................................................................................................................................................... II

    1 INTRODUCTION ...................................................................................................................................... 1

    1.1 AIM OF THIS REPORT .............................................................................................................................................................. 1

    2 EXECUTIVE SUMMARY........................................................................................................................... 1

    2.1 TAILINGS STORAGE FACILITY DESIGN CRITERIA ....................................................................................................... 1

    2.2 RETURN WATER DAM CRITERIA ....................................................................................................................................... 2

    2.3 CLIMATIC DATA ........................................................................................................................................................................ 2

    2.4 DECANT SYSTEM....................................................................................................................................................................... 2

    2.5 UNDER DRAINAGE .................................................................................................................................................................. 2

    2.6 CLEAN AND DIRTY WATER SEPARATION CANALS ................................................................................................. 3

    2.7 SOLUTION TRENCH ................................................................................................................................................................ 3

    2.8 ACCESS ROAD ........................................................................................................................................................................... 3

    3 BATTERY LIMITS AND CONSTRAINTS .............................................................................................. 3

    3.1 SITE DESCRIPTION .................................................................................................................................................................... 3

    3.2 CONSTRAINTS ........................................................................................................................................................................... 4

    3.3 LEGISLATURE .............................................................................................................................................................................. 4

    4 HYDROLOGICAL ASSESSMENT ........................................................................................................... 4

    4.1 RAINFALL ...................................................................................................................................................................................... 4

    5 GEOTECHNICAL INVESTIGATIONS .................................................................................................... 6

    5.1 GROUND WATER ..................................................................................................................................................................... 6

    5.2 CONSTRUCTION MATERIAL ............................................................................................................................................... 7

    6 DISCARD DUMP DESIGN ........................................................................................................................ 7

    6.1 COAL TAILINGS CHARACTERISTICS ................................................................................................................................ 7

    6.2 DISCARD DUMP CAPACITY ANALYSIS ............................................................................................................................ 8

    6.3 PUSH-UP STARTER WALLS ................................................................................................................................................. 10

    6.4 UNDER DRAINAGE ............................................................................................................................................................... 11

    6.5 SOLUTION TRENCH ............................................................................................................................................................. 11

    6.6 ACCESS ROAD ........................................................................................................................................................................ 11

    6.7 CLEAN AND DIRTY WATER SEPARATION CANALS .............................................................................................. 11

    6.8 FENCING .................................................................................................................................................................................... 12

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report iii June 2012

    7 RETURN WATER DAM DESIGN .......................................................................................................... 12

    8 POLLUTION CONTROL MEASURES .................................................................................................. 15

    9 STABILITY ANALYSIS ........................................................................................................................... 15

    10 OPERATION ........................................................................................................................................ 16

    10.1 SUPERVISION AND MONITORING ................................................................................................................................. 16

    10.1.1 By the mine ............................................................................................................................................... 16

    10.1.2 By the Operating Contractor .................................................................................................................... 16

    10.1.3 Legal Appointments .................................................................................................................................. 16

    10.1.4 The Professional Engineer ....................................................................................................................... 16

    10.2 OPERATION PROCEDURES ................................................................................................................................................ 16

    10.2.1 Slurry Ponds ............................................................................................................................................. 16

    10.2.2 Return water dam ..................................................................................................................................... 16

    10.2.3 Maintenance ............................................................................................................................................. 17

    10.2.4 Inspection ................................................................................................................................................. 17

    11 CONCLUSIONS AND RECOMMENDATIONS ............................................................................... 17

    12 REFERENCES ....................................................................................................................................... 18

    LIST OF ANNEXURES ................................................................................................................................... 19

    ANNEXURE A: DRAWINGS ......................................................................................................................... 19

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report iv June 2012

    LIST OF FIGURES

    Figure 1: Magdalena Colliery average monthly rainfall ............................................................................................................................ 5

    Figure 2: Magdalena Colliery monthly average maximum and minimum temperatures ................................................................ 6

    Figure 3: Discard Dump design input .......................................................................................................................................................... 8

    Figure 4: Discard Dump capacity assessment ........................................................................................................................................... 9

    Figure 5: Discard Dump stage capacity graphs ...................................................................................................................................... 10

    Figure 6: Return Water Dam 1 capacity analysis .................................................................................................................................. 13

    Figure 7: Return Water Dam 2 capacity analysis .................................................................................................................................. 14

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report v June 2012

    LIST OF TABLES

    Table 1: Discard dump footprint centre coordinates ............................................................................................................................. 1

    Table 2: Trapezoidal solution trench section ......................................................................................................................................... 11

    Table 3: Pollution Controll Measures ...................................................................................................................................................... 15

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 1 June 2012

    1 INTRODUCTION

    Forbes Coal (formerly Slater Coal) embarked on an expansion program of its operations on Mooidoorn Hoek Farm

    No. 3722 near Dundee in KwaZulu Natal resulting in need for additional storage space to complement the existing coal

    discard which is almost at the end of its life. African Innovative Solutions and Projects (AISP) CC was appointed by

    Forbes Coal (Pty) Ltd to design the coal discard dump in April 2012.

    1.1 Aim of this report

    The purpose of this report is to provide an overview of the design criteria, design parameters used and the resulting

    design process output that will affect the successful operation and subsequent closure of the facility in an

    environmentally acceptable manner.

    2 EXECUTIVE SUMMARY

    This section summarises the design criteria of the coal slurry ponds and its associated storm water infrastructure.

    The proposed footprint area is located on the following geographical centre coordinates:

    Table 1: Discard dump footprint centre coordinates

    Description Latitude (o ‘ “) Longitude (o ‘ “)

    Centre of TSF 27o58’52.43” 30o11’45.29”

    2.1 Tailings Storage Facility design criteria

    The proposed discard dump foot print area is located within the mine’s property boundary. The proposed geometry

    was influenced by the existence of underground mine workings to the east of the new discard dump stretching from

    the north to the south. The design criteria are as follows:

    � Type of facility: coal discard dump.

    � Design life of mine estimated at: 22years.

    � Tonnage production per year: 640 000t

    � Assumed in-situ density: 1.469tm-3.

    � Total tonnage in life of mine: 14 080 000t

    � Total volume of residue: 9 584 751.5m3.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 2 June 2012

    2.2 Return Water Dam criteria

    The return water dam design was designed to adhere to the National Water Act and SANS 10286: 1998 regulations,

    and therefore the criteria for the design of the same are as follows:

    � Design return period: I:100year

    � Design flood: 146.2mm

    � Required volume: 14 500m3

    � Freeboard: 0.8m

    � Depth including freeboard: 4m

    The return water dam is designed with a clay / HDPE composite liner in line with statutory requirements for surface

    and ground water pollution control.

    2.3 Climatic Data

    Dundee receives an average of about 791.5mm of rain per year, with most rainfall occurring mainly during midsummer.

    Monthly distribution of average daily maximum and minimum temperatures range from about 8°C in mid winter to

    28°C in summer. Details of the rainfall and temperature variations of the area are dealt with in Section 0.

    2.4 Decant System

    It was envisaged that coal will be deposited in “dry” state and as such, no conventional decant system will be designed

    for this project. However, momentary rising of the phreatic surface can be expected from seepage especially after a

    prolonged low frequence storm. Supernatant water must then be drained off the top of the dump as soon as possible,

    and to achieve this purpose, an “emergency type” pump budge will be utilised. The system must be sized to decant a 24

    hour 1:100 year storm in not more than 72 hours (three days).

    2.5 Under Drainage

    Previous site studies have indicated that the water table is high and that there is need for pollution control measures to

    ensure seepage does not come into contact with ground water under the impoundment. The topography of the site is

    such that seepage flows downhill and an under-drainage system incorporated at the toe will capture all seepage; and

    also help with consolidation necessary for strength gain and stability of the discard dump. The system will consist of

    perforated or slotted geo-pipes just behind the starter push-up walls connected to out-falling solid pipes discharging

    into the solution trench and then to the return water dam.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 3 June 2012

    2.6 Clean and Dirty Water Separation Canals

    To prevent storm water pollution, cut off trenches will be excavated in phases on the upstream of the facility to divert

    “clean” storm water received on the upstream catchment to the stream without passing through the contaminated site.

    The positions of the storm diversion trenches will be clearly marked on the detailed layouts.

    2.7 Solution trench

    The solution trench will be designed to contain flows resulting from the cumulative effects of the following:

    (i) Seepage from under drains, plus

    (ii) discard dump supernatant water resulting from a 1:100 year 24hour storm, plus

    2.8 Access Road

    Gravel “dirty” roads sufficiently network the site under any weather conditions. Since the envisaged method of

    deposition is upstream mechanical tipping by truck, the impoundment has been designed with five mitre wide berms at

    every five mitre vertical lift to enable access by tipper trucks at any point around the dam. Maintenance shall follow

    procedures stipulated in the Operations Manual to ensure access under any weather conditions and at any time.

    3 BATTERY LIMITS AND CONSTRAINTS

    3.1 Site Description

    The terms of reference for the design of the coal residue deposit at Mooidoornhoek Hoek Farm No. 3722 are to

    design the discard dump within the existing statutory requirements promulgated under various South African Acts as

    outlined in section a) and to be capable of satisfying the design criteria stipulated in section 2.1.

    The proposed site for the discard dump was chosen by the client, however, best practice industry guidelines were

    applied to optimise the selected area. Two options were provided and are presented in the attached layouts giving due

    diligence to the following factors:

    (i) Environmental considerations: to ensure the chosen area causes the least land degradation and pollution,

    and that safety risks are minimised as far as is practical,

    (ii) Mine planning: consideration was given to ensure no ore sterilisation or any encroachment of the facility

    to future mining plans,

    (iii) Economic considerations: all the options considered will be rigorously investigated and the most cost

    effective choice recommended to the client.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 4 June 2012

    3.2 Constraints

    Constraints considered include the following:

    a) Property boundary: the facility is to be wholly located within the property boundary of the mine which is

    Mooidoorn Hoek Farm No. 3722,

    b) Underground mine workings: there exist underground workings traversing the proposed extension area

    ranging from as shallow as 25m below natural ground level to 50m. The Minerals Act and provisions of SANS

    10286:1998 prohibits erection of a structure within 100m of underground workings without written

    permission from the Minister;

    c) An open pit the mine is using as a return water facility is in the middle of the proposed extension area

    3.3 Legislature

    The detailed design presented in this report was completed in accordance with the requirements of the following

    legislation which pertains to the design, construction, operation and management of mine residue deposits:

    • The National Water Act (Act 36 of 1968).

    • The Minerals Act (Act 50 of 1991).

    • Mineral and Petroleum Resources Development Act (Act 28 of 2002)

    • The Mine Health and Safety Act (Act 29 of 1996).

    • The Mines and Works Act (Act 45 of 1965).

    • The Environmental Conservation Act (Act 100 of 1982).

    • The Soils Conservation Act (Act 76 of 1969).

    Additionally, the following documents were referenced;

    • Department of Mineral and Energy (DME) guideline for the compilation of a mandatory code of practice for

    mine residue (DME 16/3/2/5-A1)

    • South African National Standards (SANS) Code of Practice for Mine Residue (SANS 10286:1998)

    4 HYDROLOGICAL ASSESSMENT

    The mine lies in the Buffalo Catchment Management area and is drainage region V32.

    4.1 Rainfall

    Dundee receives an average of about 791.5mm of rain per year, with most rainfall occurring mainly during midsummer.

    Figure 1 shows the average rainfall values for the project site.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 5 June 2012

    Figure 1: Magdalena Colliery average monthly rainfall

    The monthly distribution of average daily maximum temperatures (Figure 2) shows that the average midday

    temperatures for the project area range from 23°C in mid winter (which occurs in June or July) to 28°C in summer.

    The region is the coldest during June and July when the mercury drops to 8°C on average during the night. Consult

    Figure 2 for an indication of the monthly variation of average minimum daily temperatures.

    145.60

    112.10

    76.00

    44.10

    14.80 12.80

    5.60

    18.60

    36.60

    86.10

    108.80

    130.40

    -

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    140.00

    160.00

    January February March April May June July August September October November December

    Average Rainfall (mm)

    AVERAGE RAINFALL [mm]

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 6 June 2012

    Figure 2: Magdalena Colliery monthly average maximum and minimum temperatures

    5 GEOTECHNICAL INVESTIGATIONS

    Geotechnical data as used for this project was adopted from previous reports as contained in the following available

    data:

    � Technical Design Report - November 2008

    � Code of practice – prepared 2008

    � Annual Report 2010,

    � Annual Report 2012,

    � Survey in CSV format.

    As an ongoing design and monitoring process, more samples will need to be taken for analysis now, to enable results

    comparison and to allow adjustments in both the design and operation accordingly.

    5.1 Ground water

    Ground water is reported to have been encountered at depths below 6m, and is envisaged not to affect construction

    or operation of both the storage and return water systems as both these are designed at a depth not exceeding 5m

    below ground level.

    28 28 28

    26

    25

    23 23

    24

    26

    27 27 27

    17 17 17

    14

    10

    9

    8

    10

    12

    14

    16

    17

    0

    5

    10

    15

    20

    25

    30

    January February March April May June July August September October November December

    AVERAGE HIGH TEMPERATURE [oC]

    AVERAGE LOW TEMPERATURE [oC]

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 7 June 2012

    5.2 Construction material

    The ferricrete specified for the construction of both the slurry ponds’ and return water dam embankments was

    reported to have been found in the western portion of the site. There is a reported transition from sandy hill-wash

    soils at the top to silty-sand through clayey sand to firm/stiff silts and clays at depth around the site. From the

    laboratory results, the clay has low to medium activity.

    The suitability of the clay to use as a liner will need to be investigated further. Samples of both the clay and slurry from

    the plant will be taken for determination of these geotechnical design parameters.

    6 DISCARD DUMP DESIGN

    6.1 Coal tailings characteristics

    The following design input was used as researched and also as supplied by the client in some instances.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 8 June 2012

    Figure 3: Discard Dump design input

    6.2 Discard Dump capacity analysis

    The survey data supplied by the client was modelled in the computer package AutoCAD Civil 3D. The stage capacity

    graphs are included in Figure 4 and Error! Reference source not found. below for visual identification purposes.

    It can be seen from the capacity analysis that the discard dump as modelled cannot sustain the full 22year life span but

    just 63% (14years). However, area immediately east of the underground workings can be incorporated to balance the

    shortfall of 8years.

    Client: FORBES COAL

    Project: NEW COAL DISCARD DUMP DESIGN

    Description: CAPACITY DETERMINATION

    Project No.: P12 - 10

    Date: 23-Apr-12

    Author: AiSP - TM

    1.00 GENERAL INFORMATION

    1.01 Name of Mine FORBES COAL

    1.02 Postal Address of Mine

    1.03 Telephone Number (Area code in Brackets)

    1.04 Magisterial District

    1.05 Dept of Mineral and Energy Affairs Region

    1.06 Nearest Town Dundee

    1.07 Distance to Town 22 km

    1.08 Direction from Town North North-West

    1.09 Name of person responsible for residue deposit to Minerals Act Regulations

    1.10 Number of deposit

    1.11 Common name of deposit Coal Discard

    1.12 Name of closest river/stream to the deposit

    2.00 DESIGN PARAMETERS

    2.01 Reserves 14 080 000 t

    2.02 Specific Gravity 2.65

    2.03 Production Rate 53 333 tpm

    2.04 % to tailings dam: 100%

    2.05 Supply 640 000 t/year

    2.06 Insitu Density 1.47 t/m3 - (average)

    2.07 Lifetime 22.00 years

    2.08 Side Slope (Overall) 1.00 vertical to

    3.00 horizontal

    2.09 Max Rate of Rise 4.50 m/year

    2.10 Solids Concentration by Mass Cw 100.00 %

    2.11 Mass flow rate Ms 73.06 t/h

    2.12 Start of deposition 2012 year

    2.13 Mean annual precipitation 791.5 mm/y

    2.14 Mean annual evaporation 1670.5 mm/y

    2.15 Evaporation correction factor 84% %

    2.16 1 in 100 year 24 hr rainfall 146.2 mm

    DISCARD DUMP DESIGN - INPUT

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 9 June 2012

    Figure 4: Discard Dump capacity assessment

    Elevation

    (masl)

    Cumulative

    Volume

    (m3)

    Incremental

    Volume

    (m3)

    Surface

    Area

    (m2)

    Surface

    Area

    (ha)

    1255 - 0.00 - 0.00

    1260 8 788.41 8788.4135 3 515.37 0.35

    1265 74 860.76 66072.3435 22 913.57 2.29

    1270 221 058.68 146197.9228 35 565.60 3.56

    1275 415 584.88 194526.196 42 244.88 4.22

    1280 632 370.11 216785.239 44 469.21 4.45

    1285 901 955.59 269585.4793 63 364.98 6.34

    1290 1 257 518.30 355562.708 78 860.11 7.89

    1295 1 682 927.22 425408.9148 91 303.46 9.13

    1300 2 198 219.04 515291.819 114 813.27 11.48

    1305 2 788 204.77 589985.739 121 181.03 12.12

    1310 3 392 739.11 604534.3363 120 632.71 12.06

    1315 3 991 033.11 598294.001 118 684.89 11.87

    1320 4 570 507.02 579473.9083 113 104.67 11.31

    1325 5 120 537.19 550030.1715 106 907.40 10.69

    1330 5 636 823.56 516286.3658 99 607.15 9.96

    1335 5 986 090.29 349266.7288 40 099.54 4.01

    Project No.: P12 - 10

    Date: 23-Apr-12

    Author: AiSP - TM

    DAM CAPACITY

    Client: FORBES COAL

    Project: NEW COAL DISCARD DUMP DESIGN

    Description: CAPACITY DETERMINATION

    1250

    1260

    1270

    1280

    1290

    1300

    1310

    1320

    1330

    1340

    - 1 000 000 2 000 000 3 000 000 4 000 000 5 000 000 6 000 000 7 000 000

    Ele

    vati

    on

    (mas

    l)

    Volume (m3)

    Dam Capacity

    1250

    1260

    1270

    1280

    1290

    1300

    1310

    1320

    1330

    1340

    - 20 000 40 000 60 000 80 000 100 000 120 000 140 000

    Ele

    vati

    on

    (m

    asl)

    Surface Area (m2)

    Dam Surface Area

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 10 June 2012

    Figure 5: Discard Dump stage capacity graphs

    6.3 Push-up starter walls

    An initial box-cut of 750mm deep must be cut into the in-situ material over twice the width of the embankment crest

    for anchorage. The clay material on the walls will be compacted to 98% Proctor Density within 2% of the optimum

    moisture content. Care must be taken during compaction that the clay is compacted in layers not exceeding 200mm,

    Under all circumstances, the optimum moisture content must be maintained as per specifications.

    tons From To

    years 2012 2026

    t/m3

    Description: CAPACITY DETERMINATION

    640 000

    Deposition Rate

    (tons/year)

    Date

    8 960 000

    Tonnage Stored (106 tons)

    Tim

    e (years

    )

    STAGE / CAPACITY CURVES

    1.469Assumed in-situ dry density:

    Client:

    Project:

    FORBES COAL

    Cre

    st E

    levation (m

    asl)

    NEW COAL DISCARD DUMP DESIGN

    Tonnage Delivered (106 tons)

    23-Apr-12

    Rate of Rise (metres/year)

    Project No.: P12 - 10

    Tim

    e (years

    )

    Rate of Rise (metres/year)

    Cre

    st E

    levation (m

    asl)

    14Delivery period:

    Outer wall side slopes: 1V:3H

    Total tonnage delivered:

    Date:

    Author: AiSP - TM

    1 260

    1 270

    1 280

    1 290

    1 300

    1 310

    1 320

    1 330

    1 340010203040

    1 260

    1 270

    1 280

    1 290

    1 300

    1 310

    1 320

    1 330

    1 3400 2 4 6 8 10

    0

    2

    4

    6

    8

    10

    12

    14010203040 0

    2

    4

    6

    8

    10

    12

    140 2 4 6 8 10

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 11 June 2012

    6.4 Under drainage

    Internal under drainage is of vital importance to minimising of ground water pollution hence the environmental safety.

    As such a reticulation of drains was provided on the inside toe of the push up starter wall right through the dam

    perimeter. The under-drainage will facilitate the following:

    • Collect leachate to the solution trench and then onto the return water dam,

    • Minimise ground water pollution,

    • Maintaining a low phreatic surface hence reduce pore pressure on the pond embankment walls especially the

    downstream ones,

    The drainage system comprises 110mm diameter perforated geo-pipes (Drainex) within the drainage catchment of each

    basin connected to 110mm diameter solid imperforated pipes (Kabelflex). Leachate collected in these is discharged into

    the solution trench which in turn discharges into the return water dam through a silt trap.

    6.5 Solution trench

    The solution trench was sized to carry the following:

    (i) Drain flows, and

    (ii) Supernatant water drainage.

    Table 2: Trapezoidal solution trench section

    Item Description Quantity

    1 Side slope: 1v:?h 1.5

    2 Bottom width 1000mm

    3 Depth 1000mm

    6.6 Access road

    Access to the entire coal discard storage facility will be provided by means of a 4m wide gravel crest access roads at

    each 10m vertical lift of the dump. The crest access was designed of gravel (G4 –G6) material readily available on site

    and suitable for use as pavement material, and can with stand loads by any mine vehicular plant under any weather

    conditions. Maintenance will follow specifications stipulated in the Operations Manual.

    6.7 Clean and Dirty water separation canals

    Storm water diversion canals will be constructed in phases so as to reduce the volume of storm water being handled at

    any particular point in time. The clean and dirty water separation canals will be clearly marked on the detailed layouts.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 12 June 2012

    6.8 Fencing

    Allowance was made in the bills of approximate quantities to cater for fencing around the storage facility to prohibit

    access by unauthorised people.

    7 RETURN WATER DAM DESIGN

    The return water dam was sized to contain flows as follows:

    (i) A 24hour 1:100 year storm event onto the discard dump, and

    (ii) Storm water caught within the return water dam.

    Spillage will be permitted not more than once in 100years.

    Due to the topography of the site, two return water dams were designed: one for a capacity of 8 000m3 and the other

    for a capacity of 7 500m3. These volumes were modelled from the supplied survey data onto the available space using

    AutoCAD Civil 3D to produce a layout as shown on the drawings. Capacity analysis was then conducted to establish if

    the design requirements were fulfilled and the results are shown in Figure 6 and Figure 7.

    Under normal operations, the volume of water in the return water dam will be kept not more than 4 000m3.

    As discussed in 6.1, clay liner will be compacted to 98% Proctor Density at +/- 2% of the optimum moisture content,

    and G4-G6 embankment at 98% MoD AASHTO at +/-2% of the optimum moisture content.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 13 June 2012

    Figure 6: Return Water Dam 1 capacity analysis

    RETURN WATER DAM 1 CAPACITY

    Client: FORBES COAL

    Project: NEW COAL DISCARD DUMP DESIGN

    Description: CAPACITY DETERMINATION

    Project No.: P12 - 10

    Date: 23-Apr-12

    Author: AiSP - TM

    Elevation

    (masl)

    Cumulative

    Volume

    (m3)

    Incremental

    Volume

    (m3)

    Surface

    Area

    (m2)

    Surface Area

    (ha)

    1272.8 - 0.00 1 909.44 0.19

    1273 393.09 393.089 2 021.45 0.20

    1274 2 711.48 2318.39 2 615.33 0.26

    1275 5 651.96 2940.4795 3 265.63 0.33

    1276 9 270.94 3618.9795 3 972.33 0.40

    1276.6 11 789.67 2518.728 4 423.43 0.44

    1272.5

    1273

    1273.5

    1274

    1274.5

    1275

    1275.5

    1276

    1276.5

    1277

    - 1 000 2 000 3 000 4 000 5 000 6 000 7 000 8 000 9 000 10 000 11 000 12 000 13 000

    Ele

    vati

    on

    (mas

    l)

    Volume (m3)

    Dam Capacity

    1272.5

    1273

    1273.5

    1274

    1274.5

    1275

    1275.5

    1276

    1276.5

    1277

    1 500 2 000 2 500 3 000 3 500 4 000 4 500 5 000

    Ele

    vati

    on

    (m

    asl)

    Surface Area (m2)

    Dam Surface Area

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 14 June 2012

    Figure 7: Return Water Dam 2 capacity analysis

    RETURN WATER DAM 2 CAPACITY

    Client: FORBES COAL

    Project: NEW COAL DISCARD DUMP DESIGN

    Description: CAPACITY DETERMINATION

    Project No.: P12 - 10

    Date: 23-Apr-12

    Author: AiSP - TM

    Elevation

    (masl)

    Cumulative

    Volume

    (m3)

    Incremental

    Volume

    (m3)

    Surface

    Area

    (m2)

    Surface Area

    (ha)

    1247 - 0.00 - 0.00

    1248 250.27 250.2748 500.55 0.05

    1249 1 388.16 1137.88155 1 775.21 0.18

    1250 4 111.75 2723.58965 3 671.97 0.37

    1251 9 019.35 4907.60475 6 143.24 0.61

    1251.5 12 499.83 8388.088575 7 512.15 0.75

    1246.5

    1247

    1247.5

    1248

    1248.5

    1249

    1249.5

    1250

    1250.5

    1251

    1251.5

    1252

    - 1 000 2 000 3 000 4 000 5 000 6 000 7 000 8 000 9 000 10 000 11 000 12 000 13 000 14 000

    Ele

    vati

    on

    (mas

    l)

    Volume (m3)

    Dam Capacity

    1246.5

    1247

    1247.5

    1248

    1248.5

    1249

    1249.5

    1250

    1250.5

    1251

    1251.5

    1252

    - 1 000 2 000 3 000 4 000 5 000 6 000 7 000 8 000

    Ele

    vatio

    n (m

    asl)

    Surface Area (m2)

    Dam Surface Area

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 15 June 2012

    8 POLLUTION CONTROL MEASURES

    A synergistic effect can be achieved by combining different controls together. Inclusion of the features in the table

    below is likely to give rise to the lowest pollution potential for the slurry ponds, taking not only the capital and

    operating costs into account, but also the contingent liability associated with potential water contamination.

    Table 3: Pollution Controll Measures

    Control Type Description

    Clean water diversion � The design will include clean water diversion systems for surface water

    inflow from drainage systems within the natural catchment basins and

    precipitation runoff. The clean water systems were sized to ensure it is

    not likely to spill into any dirty water system more than once in 100 years

    (SANS 10286:1998).

    � Appropriate erosion protection and energy dissipation measures will be

    included in the design (if necessary) for long-term closure requirements

    Under-drainage and reuse of

    contaminated water

    � The design includes the implementation of an under drainage system to

    collect seepage for re-use as process water.

    � The return water dam was sized to contain seepage from the under

    drainage systems and not to spill into any clean water system more than

    once in 100 years (SANS 10286:1998).

    9 STABILITY ANALYSIS

    A conservative overall slope of 1v:3h (11.3o) known to produce factors of safety above 1.5 for similar slurry ponds

    projects was adopted. The South African statutory required factor of safety is 1.3 hence the dam slopes are expected

    to be stable.

    The free draining nature of tailings is expected to cause a positive effect on consolidation and the strength gain of the

    tailings hence enhanced stability. By induction, it is envisaged that the dam will be stable.

    The heights of the dam walls average 2.5 above the natural ground level, which reduces the potential for failure.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 16 June 2012

    10 OPERATION

    10.1 Supervision and Monitoring

    10.1.1 By the mine

    In terms of South African legislation, the General Manager is ultimately responsible for the correct and safe operation

    of the coal slurry dams. However, these responsibilities are delegated to competent persons within the Mine’s

    management structure. A senior manager must be tasked with the duty to oversee the operation of the coal slurry

    dams. He could be assisted by an experienced foreman who can monitor the operations on a daily basis.

    10.1.2 By the Operating Contractor

    The contractor must have an experienced and competent supervisor to manage the teams doing the deposition. The

    distribution of the slurry must be uniformly maintained all round the dam.

    10.1.3 Legal Appointments

    All managerial and supervisory personnel are to be appointed in accordance with the provisions of the Minerals Act.

    The duties at each level are to be clearly set out in a letter of appointment.

    10.1.4 The Professional Engineer

    The Mine shall appoint a professional engineer who will be required to inspect the coal slurry dams from time to time.

    He shall satisfy himself that the facility is in a safe and stable condition. If not, he shall specify remedial action to be

    implemented by the Mine.

    10.2 Operation Procedures

    10.2.1 Slurry Ponds

    Once uniform deposition all around the coal slurry dam has been established, the following points are to be observed:

    � The beach zone must be managed so that the pool will lie at the penstock inlet.

    � No pools must be allowed to develop anywhere else in the basin.

    10.2.2 Return water dam

    This is to be operated such that it is kept virtually empty at all times thus maintaining sufficient capacity to store 1:100

    year design storm run-off from the slurry dams without spilling. The pumps and return water pipeline must have

    sufficient spare capacity to empty the dam within a reasonable period after a storm inflow.

  • AfriCan Innovative Solutions and Projects CC Draft Design Report

    Forbes Coal Draft Design Report 17 June 2012

    10.2.3 Maintenance

    The slurry dams, return water dam and the effluent trench must be inspected on a regular basis and deficiencies

    rectified immediately. Items to watch out for and to be repaired according to standard practice are inter alia:

    � Erosion gullies

    � Pipe burst

    � Rat holes

    Other deficiencies observed and which must be reported to the Professional Engineer without delay are:

    � Signs of seepage on the slopes

    � Sloughing

    � Movement or slips

    � Blocked drain outlets

    The Professional Engineer will determine the remedial measures to be implemented by the Mine to rectify the

    deficiencies and to prevent a recurrence.

    10.2.4 Inspection

    Regular inspections shall be undertaken by the Professional Engineer, Coal Discard Manager, Coal Discard Foreman and

    the Contractor in accordance with the Mine’s standard procedure.

    11 CONCLUSIONS AND RECOMMENDATIONS

    It is recommended that:

    � The overall factors of safety at all the analyzed sections are above 1.3 indicating satisfactory conditions.

    � Monthly monitoring of the technical data and hazard management system should be carried out.

    � Under drain from selected waste rock or filter stone must be constructed to collect and direct rainwater

    seepage that percolates through the discard facility, from the base areas to the solution trenches.

    � Tonnages transported to the slurry dams must be recorded on a daily basis.

    � Freeboard should be measured and evaluated against the statutory requirement and must be monitored.

    � A code of practice and operating manual should be prepared to ensure that the facility is designed, operated

    and rehabilitated in a responsible manner.

    � Daily rainfall and evaporation must be recorded at the coal slurry dam.

  • 18

    12 REFERENCES

    1) Design Report: 2008.

    2) A Guide to Tailings Dams and Impoundments, ICOLD, Bulletin 106, 1996.

    3) Tailings Dams Design of Drainage, ICOLD, Bulletin 97, 1994.

    4) Reference Number: DME 16/3/2/5_A1, Guideline for the compilation of a Mandatory Code of

    Practice ,3 May 2000

    5) SANS 0286: 1998, The South African Code of Practice – Mine Residue

    6) The following South African Acts:

    (i) The Minerals Act (Act 50 of 1991).

    (ii) The Environmental Conservation Act (Act 100 of 1982).

    (iii) The Mine Health and Safety Act (Act 29 of 1996).

    (iv) The Mines and Works Act (Act 45 of 1965).

    (v) The Soils Conservation Act (Act 76 of 1969).

    (vi) The National Water Act (Act 36 of 1968).

  • 19

    LIST OF ANNEXURES

  • 20

    ANNEXURE A: DRAWINGS