Technical Review Committee Meeting March 16, 2011 Bri-Mathias Hodge Gregory Brinkman Debra Lew
description
Transcript of Technical Review Committee Meeting March 16, 2011 Bri-Mathias Hodge Gregory Brinkman Debra Lew
NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy operated by the Alliance for Sustainable Energy, LLC
Technical Review Committee Meeting March 16, 2011
Bri-Mathias HodgeGregory Brinkman
Debra LewNational Renewable Energy Laboratory
Golden, Colorado USA
Western Wind and Solar Integration Study - Phase 2: Proposed Modeling Efforts
Background: WWSIS Phase 1 Modeling
• Production simulation was conducted with GE MAPS
• WECC represented as 14 transmission zones
• 5 balancing areas
• Hourly simulation over three years
• Used 2008 Ventyx database
• WECC database - with updates - used for transmission
National Renewable Energy Laboratory Innovation for Our Energy Future
PLEXOS Overview
• MIP formulation allows the addition of constraints on generator operating regions• Can then explicitly model times when cycling occurs
• Can easily incorporate cycling and ramping costs
• Can consider these costs when making unit commitment and dispatch decisions
• Easily switches between explicit transmission modeling and zonal modeling• Can focus on certain regions to examine interesting areas
more closely
• Allows dispatch at five minute time steps• Can easily examine interesting events in further detail
National Renewable Energy Laboratory Innovation for Our Energy Future
PLEXOS – Renewable Integration Studies
• CAISO 20% Study
• CAISO 33% Study
• MISO Wind Integration Study
National Renewable Energy Laboratory Innovation for Our Energy Future
Benchmarking
• No benchmarking with Phase 1 MAPS model runs• Plan on benchmarking with TEPPC 2019 ProMod
simulations• Intended to be qualitative, not quantitative• Only need to verify that high level information is within a
reasonable range• Percentage of capacity by generator type• Percentage of energy by generator type• Total costs• Inter-area flows are of the correct order• etc…
National Renewable Energy Laboratory Innovation for Our Energy Future
Model Configuration - Timescales
• Timescales• Day-ahead unit commitment • Hourly dispatch
• PLEXOS allows dispatch at the five minute level• Can use this capability to examine a limited number of
interesting events
• Can use PLEXOS medium term horizon (load duration curves) in order to optimize over longer time horizons
National Renewable Energy Laboratory Innovation for Our Energy Future
Model Configuration – Balancing Area CooperationPossible Ideas
• Balancing authorities• 5 region
• WestConnect, Columbia grid, NTTG, CAISO, Canada
• More regions (14?)
• Cooperation between BAs• High cooperation
• Zero hurdle rates (WWSIS 1)
• Medium cooperation• High hurdle rates between BAs
on commitment
• Low hurdle rates between BAs in hour-ahead and dispatch
National Renewable Energy Laboratory Innovation for Our Energy Future
Model Configuration - Transmission
• Nodal representation vs. Zonal representation• Plan to use Zonal representation, as
in Phase 1• Avoids the explicit planning of low
voltage transmission for new renewable sites
• New transmission between zones• Plan to use WECC 2019/20 targets
and revise/expand with TRC input
National Renewable Energy Laboratory Innovation for Our Energy Future
Model Configuration - Policy
• Production Tax Credit• None in phase 1
• Fixed Operating Reserve Levels• 3% of load spinning per BA in
phase 1• Will need to address if problems
occur (e.g., load shedding)
• Carbon Tax• $30/ton in phase 1
National Renewable Energy Laboratory Innovation for Our Energy Future
Model Configuration - Cycling Costs
• The case that includes cycling costs will include these costs in the unit commitment and dispatch optimization algorithms• Optimize around the cycling costs instead of just adding them to the
otherwise optimal schedule• GE will also add cycling costs to the results of phase 1 study in order to
get a ceiling on maximum costs
• Cycling costs considered:• Additional start-up costs
• Hot start
• Warm start
• Cold start
• Minimum generation level costs• Additional ramping costs for both normal and fast ramp rates
National Renewable Energy Laboratory Innovation for Our Energy Future
Proposed Scenarios
• Plan to examine the impacts of cycling costs through scenarios that both explicitly consider and neglect the costs of cycling
• Varying levels of renewable penetration• 10%• 20%• 30%
• Mitigation strategies to be included:
• Turning off coal generators in the spring• More flexible thermal generation• etc…
National Renewable Energy Laboratory Innovation for Our Energy Future
National Renewable Energy Laboratory Innovation for Our Energy Future
Emissions analysis
Part-load and full-load properties
Data from Continuous Emission Monitors
Run PLEXOS with unit-specific heat rate curves, emission cost sensitivities
50 100 150 200 250 300
6
8
10
12
14
16
18
Ave
rag
e h
ea
tra
te (
mm
btu
/MW
h)
Gen (MWh)
Coal (Martin Drake)
0 100 200 300
6
8
10
12
14
16
18
Ave
rag
e h
ea
tra
te (
mm
btu
/MW
h)
Gen (MWh)
Combined Cycle (Front Range)
12
0 10 20 30 40 50
6
8
10
12
14
16
18
Ave
rag
e h
ea
tra
te (
mm
btu
/MW
h)
Gen (MWh)
Combustion Turbine (Fountain Valley)
National Renewable Energy Laboratory Innovation for Our Energy Future
NOx emissions vs. heat input, ramp rate
13
0 1000 2000 3000 4000 50000
200
400
600
800
1000
NO
x (lb
s)
HtIn (mmbtu)
Comanche (470), unit 2 (Coal Dry bottom wall-fired boiler)
-200 -100 0 100 200-200
-100
0
100
200
300
NO
x re
sidu
al (
lbs)
RampRate (mw/hr)
Correlation coefficient is 0.00
0 500 1000 1500 20000
50
100
150
200
NO
x (lb
s)
HtIn (mmbtu)
Fort St. Vrain, unit 2 (Pipeline Natural Gas Combined cycle)
-150 -100 -50 0 50 100 150-40
-20
0
20
40
60
80
NO
x re
sidu
al (
lbs)
RampRate (mw/hr)
Correlation coefficient is -0.02
NOx curves vary widely between generators
Little evidence that dynamic ramping impacts emissions
Difficulties
National Renewable Energy Laboratory Innovation for Our Energy Future
1500 2000 2500 3000 3500 4000200
400
600
800
1000
1200
1400
1600
NO
x (lb
s)
HtIn (mmbtu)
Comanche (470), unit 1 (Coal Tangentially-fired)
-150 -100 -50 0 50 100 150-800
-600
-400
-200
0
200
400
600
NO
x re
sidu
al (
lbs)
RampRate (mw/hr)
Correlation coefficient is -0.03
Poor fits, unexplainable residuals
Possible time lags in the system