Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe...

24
Technical Challenges on the Colongra Lateral Pipeline Project Mar 2009 Tony Mills Andrew O’Neill

Transcript of Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe...

Page 1: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

Technical Challenges on the Colongra Lateral Pipeline Project

Mar 2009 Tony Mills Andrew O’Neill

Page 2: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

2

Project Context

• Delta Colongra Power Station- 667MWe peaker• Gas via Sydney Newcastle Pipeline- lacks capacity for

continuous supply.• Lateral required to perform as storage vessel.

Page 3: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

3

Project Overview

This presentation will focus on pipelines, especially 42 inch.

MCS

MDS GTPS

MDP 300m DN400 Cl 300

MGP Feeder 4.0km DN250

SNPL Tie In 70m DN250SNPL

MOMS

MGP 5.4km DN1050

MGP Interconnect

MGP Looping 3.6km DN1050

Red denotes fatigue service pipeline

Page 4: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

4

Project Participants

•Jemena: Design, construction and operation of gas facilities•GHD: Concept, FEED, then detailed design of pipelines•Diona / Codmah: Pipeline Construction•EFXP: EPCM Contractor for the facilities (stations)•Supporting Roles: - EPCM – Project management support to Jemena - Brian Martin & Associates – CP & earthing - Welding Technology Institute of Australia - ANSTO – Fatigue analysis - Phil Venton & Assoc and Leigh Fletcher Consulting – Early concept work - Advantica, BMT Rail (Bob Andrews) – Fatigue and fracture control verification - Many others!

Page 5: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

5

Project Timing

• Detailed Design: 4Q2007 – 3Q2008• Construction Apr 2008 - Feb 2009• Commisioning Mar 2009• Commercial Operation Apr 2009

Page 6: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

6

Pipeline Specifics – 42 inch section

Material UOE X70 24mm & 30mm wt

Pressure Cycle Range

3.4 to 13 MPag

Required Pressure Cycles

4,000

Gas-In (via compressors) 1.7TJ/hr (recharge ~24hrs)

Gas-Out (To Power Station) 8.2 TJ/hr (approx 5hr run time)

Usable Gas Storage 36 TJ (at 15 deg)

Operating Temps very close to design temps for this pipeline

-10 to 55 deg C

Toughness 121 Joules (body)

Coating 2FBE with liquid epoxy joints

Design Standard AS 2885-2007 – One of the first……

Page 7: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

7

Challenges- The 9km route with everything

• Fatigue !• T1 Residential Location Class• Need for serpentine storage loop• Need for an underground interconnect station• AC Interference from numerous HV power lines• Mine subsidence• Inundation / swamp zones• Major bored crossings (Pacific Hwy microdrill & 5m deep

railway thrust bore)• Orchids• Bends and bend control• Everything is big!

Page 8: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

8

Fatigue- The Issue

Factory Seam Weld Production Girth Weld

Cyclic Pressure

Cyclic Hoop Stress

Propagation of SMALL flaws

Cyclic Pressure

Cyclic Temperature

Seasonal effects

Cyclic Axial Stress

Bend & Soil Effects

Real world joint tolerances

Real world welding defects

Pipe ordered: -before stresses known- with varying IDs

Significant engineering challenge!

Non-governing case

Page 9: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

9

Methods for Fatigue Design

• AS 2885 Appendix N (IGE / TD1 Method 5)

Impractically thick wall Does not address girth welds well

• Other S-N Curve Methods, eg Maddox TWI Encouraging results (8,000 to 11,000 cycles predicted) Not comfortable to rely on this.

• Fracture Mechanics Models BS 7910, API 579, or DNV RP-C203 Software: R6, Crackwise, FlawCheck, GHD Spreadsheet

• Augment with FEA

Page 10: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

10

Fatigue Drives Construction Methods 1 of 2

Selected value for this Project

Typical Value

Angular Misalignment(End Squareness + Root Gap Variation)

0.26 deg API 5L limits end squareness to 1.6mm/diaAS 2885.2 limits gap variation to ±0.6Result 0.25 °However, permits weld angles up to 3 °

Axial Misalignment (Hi-Lo)(Ovality+Seam Peaking+Centreline Mismatch)

Despite API tolerances, this size UOE pipe can have 6-7mm Hi-Lo (worst case).Pipes rotated / selected as necessary to achieve 4mm.

-For thinner pipe, clamps help to re- round ovality.-For ERW pipe, minimal peaking.

Bevels & Transitions

-1:4 commonly used-AS 2885 permits 1:1.17 taper

Steel Toughness

Driven by SMS / Fracture Control Plan

24mm WT body:121J 30mm WT body: 93J 24mm WT weld: 70J 30mm WT weld: 64J

Same

2L

d

2L2L

d

2L

Page 11: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

11

Modifying Pipe Bevels

Machine Required To:- Compound bevel- Cut internal tapers

back to counterbores

- Operate with tight tolerances so as to avoid worsening Hi-Lo

Page 12: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

12

Fatigue Drives Construction Methods 2 of 2

Selected value for this Project

Typical Value

Weld Toughness

Only available after trials commenced.

86J Not explicitly limited.

Weld Toe Angle

135 deg Not explicitly limited.

Weld Heat Input Fatigue calculations assumed 2.9kJ/mm limit. No PWHT. Further analysis sanctioned slightly higher values.

Would be similar. Would avoid low heats due to H2 cracking.

Load Cycle Profile

Considered summer and winter. Assumed full depth cycles

Not explicitly limited.

Stresses Caesar model outputs + roping allowance

-Both max stress and stress range are critical. -Roping 600D (0.1°/dia)(169MPa)

-Limits longitudinal stress-No limit on stress range-Strain limits

Size limit for defects

•Crack like•Extended undercut

Tier 1: 3 x 25mm surface breaking or within 5mm of surface (Need high confidence of detection)

Option of larger defects , eg Tier 2

Page 13: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

13

Challenge of Controlling Tolerances and Roping Stresses with a 30 Tonne Pipe String

Page 14: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

14

Fatigue Analysis Conclusions

• Can achieve 4,000 cycles.• Failure predicted by ductile

rather than brittle mode.• Many conservatisms,

especially not counting cycles to initiate cracks.

• Avoided “special construction”, however required increased NDT and no roping at some locations.

• BMT independent review and endorsement.

Page 15: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

15

Determining Special Requirements at High Stress Locations

DN1050 MGP Stresses

Interconnect2nd Highest Stress

Range:103904.2 kPa

Location: Station-end side of gradual bend on East Loop

Interconnect Max Stress Range:

139651.3 kPaLocation: Vertical S-Bend before

DN1050 Pig Reciever

Interconnect Max Tensile Stress:

164977.2 kPa(at same location as Max Stress Range)

-20000

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

0 211 537 587 664 788 1198 1216 1235 1268 1274 1790 1866 2209 2228 2248 2283 2569 2620 2752 3176 3217 3243 3266 3399

Chainage for MGPInterconnect Section (Approx)

Stre

ss (k

Pa)

Stress Range Max Tensile Stress

Max Stress Range at MDS Inlet:

128776.8 kPa

Tensile Stress at MDS Inlet:

149564.9 kPa

Worst Stress Locations

More Representative

Locations

Page 16: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

16

Fatigue- Recommendations

• Assess real temperatures and possibly strains during commissioning.

• Monitor real cycles so that a future Rainflow analysis can determine actual fatigue life.

• Intelligent pigging (cannot rely entirely on calculations)

0

2

4

6

8

10

12

14

0 5 10 15

Pressure(Mpa)

0

2

4

6

8

10

12

14

0 5 10 15

Pressure(Mpa)

Page 17: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

17

Serpentine Storage Loop 1 of 2

Page 18: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

18

Serpentine Storage Loop 2 of 2

Page 19: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

19

Underground Interconnect Station

Page 20: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

20

AC Interference

330kV

66kV

33kV

330kV

330kV

Page 21: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

21

Mine Subsidence

• MSB requires pipelines to be “designed for subsidence”• No mining plans yet exist to define subsidence parameters.

• SCFs at transitionsResults• Passes code• Assumes to upsidence

MSB Parameters

Subsidence

Strain (+/-)

Tilt

MSEC

Reverse engineer mining plans to produce these MSB parameters

0

30

45

60

90

Superimpose mining plans at various angles to pipeline

Axial & Trans Soil Displaceme nts to Apply to Pipe

CAESAR Model

Pass / Fail ?

Page 22: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

22

Inundation and Swamp Zones

Page 23: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

23

Everything is big!

6MW+ Water bath heater

42” Pipe arriving at Munmorah Delivery Station

Page 24: Technical Challenges on the Colongra Lateral Pipeline ProjectPipeline Construction ... Weld Toe Angle. 135 deg: Not explicitly limited. Weld Heat Input. Fatigue calculations assumed

24

Thankyou….

Tony Mills Andrew O’NeillGHD Pty Ltd Jemena Asset Management07 3316 3923 0418 957 898 02 9397 9263