Technical Aspects of Interconnection
of the Power System of Ukraine
28th of February, 2006 Brussels
Electricity Sector of Ukraine:
Status and Plans Ahead
Ukraine Briefly
Total area is 603,700 sq. km
Total length of the borders is 7,590 km
Population is about 48,5 mln.
The capital is Kyiv
Border countries are:Belarus, Hungary, Moldova, Poland, Romania, Russia Slovakia,
Number of step-up substations 35-750 kV – 5 360 Total installed capacity of transformers – 157 600 MVATotal number of circuit breakers – above 113 000
Total length of electrical lines – above 1 000 000 kmTotal number of transformer substations – above 200 000
Installed Capacity of Generation Equipment
HPP 4784.7 MW9%
NPP 13835 MW27%
TPP 27150 MW52%
Industrial & CC TPP 6374.4 MW
12%
WMPP 59 MW0,11%
Energy Production for 2005
NPP 88756 mln.kW*h
48%
Industrial & CC TPP 22578 mln.kW*h
12%
TPP 61544 mln.kW*h
33%
HPP 12320 mln.kW*h
7%
WMPP 38 mln.kW*h
0,02%
Installed capacity of power plants is above 52 mln. kW
Total annual production is above 185 mln. MW*h
Generation Capacity of Ukraine
5 TPP Generation Companies- 14 TPPs, 97 units (800-150 MW) 1 NPP Generation Company - 4 NPPs, 15 units (1000- 440 MW)1 HPP Generation Company - 8 HPPs, 90 units (117 - 19 MW) 3 big CHP - 9 units (250 – 100 MW)
SE NPC “UKRENERGO”. Main Tasks
- provision of integrity of Ukrainian IPS;
- provision of operative-technological control of Ukrainian IPS with a provision of optimal modes for operation within Wholesale Electricity Market;
- provision of synchronous operation of the IPS of Ukraine with power systems of neighboring countries as well as implementation of special schemes for power transmission to these countries;
- prevention and liquidation of network disturbances and system accidents;
- provision of operation and maintenance of the backbone network and means for IPS of Ukraine control.
220 kV19%
500 kV2%
750 kV19%
800 kV0,4%
400 kV2%
330 kV58%
SE NPC “UKRENERGO”. Transmission Network
-132 substations with voltage level 750-220 kV-total capacity of transformer substations – 75.000 MVA-total length of transmission lines more than 22.000 km
-750 kV lines – 4115 km-500 kV lines – 375 km-400 kV lines – 340 km-330 kV lines – 13000 km-220 kV lines – 4170 km
SE NPC “UKRENERGO”. Dispatch Control
NPC “Ukrenergo”
Distributioncompanies(networks 150 kV and less)
DonbassPS
________
transmission
network
NorthPS
________
transmission
network
CrimeaPS
________
transmission
network
SouthPS
________
transmission
network
CenterPS
________
transmission
network
South-WestPS
________
transmission
network
WestPS
________
transmission
network
Hydro company“Ukrgidroenergo”
Generationcompanies
(TPP, NPP, CoTPP)
HPP
DneprPS
________
transmission
network
CountriesInterconnectin
g Lines 220-750kV
Russia 14
Moldova 7
Belarus 2
Poland 2
Slovakia 2
Hungary 4
Romania 2
Total 33
CountriesIntercon. lines 220-750kV
Russia 14
Moldova 7
Belarus 2
Poland 2
Slovakia 2
Hungary 4
Romania 2
Total 33
“Burshtyn TPP Island”
• Territory – 27 000 km 2
• Population – 3 millions• Export potential – up to 550 MW• Internal consumption – 1000-1050 MW• Power plants – Burshtyn TPP (2300
MW), Kalush TPP (200 MW) and Tereblia-Rikskaya HPP (27 MW)
Establishment of the «Burshtyn TPP Island»
Chronology of Events
• November 1-3, 1995 – initial meeting of UCTE experts with Ukrainian specialists in Lviv.
• January 1996 – first meeting of the Technical Committee UCTE/CENTREL/Ukraine.
• 1995–1997 - elaboration and approval of the Catalogue of Measures on integration of the «Burshtyn TPP Island» to UCTE/CENTREL.
• 1999 – Agreement on long-term physical delimitation of Burshtyn TPP Island from IPS of Ukraine was signed.
• April 6-20, 2002 – tests and 2 weeks trial operation of the «Burshtyn TPP Island» before connection to UCTE power system.
• July 1, 2002 – «Burshtyn TPP Island» was switched on one year trial parallel operation with UCTE.
• July 1, 2003 – Constant operation of «Burshtyn TPP Island» with UCTE.• October10, 2004 – Resynchronization of II synchronous zone of UCTE.
Switching on OHL 400 kV Mukachevo-Roshior (Romania)
1. Increasing of capacity of existing units of Burshtyn TPP
2. Modernization of switching equipment and relay systems
3. Increasing of power export up to 600 – 650 MW
4. Development of fiber-optical communication lines
“Burshtyn TPP Island”. Plans for Development
On the Way to Meet UCTE Requirements. Studies
-Studies of the adequacy of Ukrainian normative documentation to the OH standards;
-Studies of the adequacy of the Ukrainian IPS for synchronous operation with European Power System (N-1, stability, voltage regulation, power reserve control, emergency procedures, information exchange, etc.);
-Studies of generation units to participate in primary and secondary regulation;
-Studies of the electrical substations;
-Development of the Ukrainian Grid Code.
On the Way to Meet UCTE Requirements. Studies to Be Finished 2006
- Development of plan-schedule for II stage of HPP rehabilitation;
- Harmonization of Ukrainian energy industry legislation in accordance with European requirements;
- Development of project documentation for modernization of electrical substations;
- Development of plan-schedule for modernization of TPP units to participate in primary and secondary regulation;
- Development of plan-schedule for voltage control modernization.
Hydro Power Plant Exist / Reconstructed
Units
Units under AGC
Installed capacity
under AGC, MW
Regulation Zones
Kievskaya 20 / 8 1 22,4 Emergency only
Kremenchyckaya 12 / 6 1 57 All zones
Dneprodzerginskaya 8 / 6 1 48 All zones
Dneprovskaya 18 / 9 6 6*72=432 All zones
Kahovskaya 6 / 4 1 52 All zones
Dnestrovskaya 6 / 6 1 117 Emergency only
Total 70 / 39 12 728,4
On the Way to Meet UCTE Requirements. Secondary Control
- Installation of SCADA\EMS\AGC system - 400 MW of HPP is permanently under AGC control
On the Way to Meet UCTE Requirements. Network Construction
-Construction of OHL 330 kV HAES-Hmelnitska-Construction of OHL 330 kV RAES-Lutsk Pivnichna-Construction of N.Donbaska 500 kV substation-Construction of OHL 500 kV Donbaska-N.Donbaska-Increasing of voltage level of OHL RAES-Zahidnoukrainska to 750 kV- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -Modernization of relay protection-Installation of SCADA\EMS\AGC system -Construction of 1160 km of fiber cable communication link-Installation of WAMS system
750 kV Lines:
•Rivnenska NPP - Kyivska 750
330 kV Lines:
•N.Odeska – Artsyz
•Adgalyk – Usatovo
•Zahidnoukrainska – Bogorodchani
•Construction of connections of Dnestr PSPP to OHL Dnestr HPP-Ladygyn TPP
•Dnestr PSPP – Bar
Network modernization:
•Increasing of voltage level of line 220 kV Sevastopol – Simferopol up to 330 kV
•Construction of connections to line 330 kV Melitopol - Simferopol from Dgankoj substation
•Installation of series capacitor on Dgankoj substation
Generation
•Construction of Dnestr Pumped – Storage Power Plant
•Construction of Tashlyk Pumped – Storage Power Plant
On the Way to Meet UCTE Requirements. Network Construction till 2008
Technical Aspects of Interconnection
of the Power System of Ukraine
Volodymyr Luchnikov
Electricity Sector of Ukraine:
Status and Plans Ahead
Thank you for attention !