Before The Hon’ble J & K State Electricity Regulatory Commission Tariff Revision Proposal for FY 2013-14 [February, 2013] Submitted by: Jammu & Kashmir Power Development Department Distribution

Transcript of Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the...

Page 1: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

Before The Hon’ble J & K State Electricity Regulatory Commission

Tariff Revision Proposal for FY 2013-14

[February, 2013]

Submitted by:

Jammu & Kashmir Power Development Department – Distribution

Page 2: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 2

BEFORE THE J&K STATE ELECTRICITY REGULATORY COMMISSION SRINAGAR/JAMMU

Filing No _______________ Case No ________________

IN THE MATTER OF: Filing of Annual Revenue Requirement (ARR) and tariff

petition for the FY 2013-14.

AND

IN THE MATTER OF Power Development Department – Distribution Wing,

Srinagar/Jammu through its Chief Engineer

(Commercial & Survey) - Applicant

The Applicant respectfully submits as under: -

1. Power Development Department-Distribution, Government of J&K

(hereinafter referred to as “JKPDD-D”) is a deemed licensee under section 14

of the Jammu and Kashmir Electricity Act, 2010 for supplying electrical energy

in the State of Jammu and Kashmir.

2. The Jammu & Kashmir State Electricity Regulatory Commission (JKSERC) has

been empowered to determine the electricity tariffs under Section 71 of Jammu

and Kashmir Electricity Act 2010. The JKSERC has issued Multi Year

Distribution Tariff Regulations, 2012, which defines the procedure to be

followed for determining the electricity tariffs. These Regulations requires the

licensee to submit the Annual Revenue Requirement (ARR) for control period

and get it approved from the Commission.

3. The JKPDD-D (as a deemed licensee) has already filed the petition before the

Hon’ble Commission for approval of ARR (Annual Revenue Requirement) for

the Financial Year 2013-14, FY 2014-15 & FY 2015-16 (hereinafter referred to as

FY 14, FY 15 & FY 16) under the regulations notified by the Commission.

4. The JKPDD-D now requests the Hon’ble Commission to approve the

proposed Tariff Revision Proposal for the FY 2013-14.

Sd/

16/02/2013 Chief Engineer (Commercial & Survey)

Jammu Power Development Department

Page 3: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 3

TABLE OF CONTENTS

1 CONTENTS OF THIS PETITION ................................................................................. 7

2 ANNUAL REVENUE REQUIREMENT ....................................................................... 8

3 REVENUE AT EXISTING TARIFF ............................................................................... 9

4 COVERAGE OF REVENUE GAP ................................................................................ 10

5 TARIFF REVISION PROPOSAL ................................................................................. 11

6 PROPOSED TARIFF SCHEDULES FOR FY 2013-14 ............................................... 14

7 PRAYER ............................................................................................................................ 28

Page 4: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 4

LIST OF TABLES

TABLE 1: ANNUAL REVENUE REQUIREMENT ............................................................................ 8 TABLE 2: REVENUE FROM SALE OF POWER AT EXISTING TARIFF.............................................. 9 TABLE 3: REVENUE GAP ............................................................................................................ 10 TABLE 4: REVENUE AT PROPOSED TARIFF ................................................................................ 11

Page 5: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 5

Notes:

In this Petition:

All currency figures used in this Petition, unless specifically stated

otherwise, are in Rs Crores and energy figures are in Million Units.

This petition contains the Main Text of the Petition.

All figures are actuals for FY 2011-12, unless otherwise stated.

Page 6: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 6

Tariff Revision Proposal for FY 2013-14

Page 7: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 7

1 Contents of this Petition

1. This Petition covers the summary of proposed ARR for FY 2013-14.

2. This petition also covers the proposed Retail Supply Tariffs for FY 2013-14 for

various categories of consumers.

Page 8: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 8

2 Annual Revenue Requirement

1. Table 1 summarizes JKPDD’s Annual Revenue Requirement for FY 2012-13

and MYT Control Period from FY 2013-14 to FY 2015-16.

2. Annual Revenue Requirement for FY 2012-13 is estimated to be Rs 5000.43

Crores.

3. Annual Revenue Requirement for FY 2013-14 is estimated to be Rs 5179.63

Crores.

Table 1: Annual Revenue Requirement

Annual Revenue Requirement 2011-12 (Actual)

2012-13 (Estd.)

2013-14 (Proj.)

2014-15 (Proj.)

2015-16 (Proj.)

Costs

Power Purchase Cost 3,673.41 3,822.40 3,764.13 3,927.88 4,096.59

Water Usage Charges Payable - 305.65 305.65 305.65 305.65

Transmission Charges 119.49 171.77 203.14 243.88 295.03

Operation and Maintainence Cost 472.15 518.07 553.21 590.77 630.89

Interest Cost 13.99 16.36 19.15 23.10 28.17

Depreciation 80.83 179.60 204.19 238.30 276.05

Interest on Working Capital 0.00 0.00 144.26 153.25 163.08

Total Costs 4,359.87 5,013.85 5,193.72 5,482.83 5,795.46

Add: Return on Equity 0.00 0.00 0.00 0.00 0.00

Less: Non-Tariff Income 13.22 13.42 14.09 14.80 15.54

Annual Revenue Requirement 4,346.65 5,000.43 5,179.63 5,468.03 5,779.92

Page 9: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 9

3 Revenue at Existing Tariff

1. Revenue from sale of power for FY 2012-13 & FY 2013-14 is determined based

on the estimated/projected energy sales and category wise tariff prevalent in

the Jammu & Kashmir as per the Tariff Order for FY 2012-13.

2. Revenue billed from sale of power at existing tariff is expected to be Rs. 1601.51

Crores in FY 2012-13 and projected to be Rs. 1,743.28 Crores in FY 2013-14, as

shown in Table 2.

3. The table below summarizes the revenue from sale of power at existing tariff

for FY 2012-13 and FY 2013-14:

Table 2: Revenue from Sale of Power at Existing Tariff

Annual Revenue Requirement 2011-12

(Actual) 2012-13 (Estd.)

2013-14 (Proj.)

2014-15 (Proj.)

2015-16 (Proj.)

Annual Revenue Requirement 4,346.65 5,000.43 5,179.63 5,468.03 5,779.92

Covered by

Revenue Billed @ Existing Tariff 1354.21 1601.51 1743.28 1943.62 2084.95

Collection Efficiency 90% 95% 96% 97% 98%

Revenue Collected 1218.79 1,521.43 1,673.55 1,885.31 2,043.25

Revenue @ Existing Tariff 1,218.79 1,521.43 1,673.55 1,885.31 2,043.25

Page 10: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 10

4 Coverage of Revenue Gap

1. Table 3 summarizes the revenue gap at existing tariff at Rs. 3,479.00

Crores for FY 2012-13. Further, the revenue gap for FY 2013-14 is Rs. 3,526.88

Crores.

2. JKPDD would like to submit that the revenue gap takes into consideration the

collection efficiency levels also. The collection efficiency is expected to improve

from 95% in FY 2012-13 to 96% in FY 2013-14.

Table 3: Revenue Gap

Annual Revenue Requirement 2011-12

(Actual) 2012-13 (Estd.)

2013-14 (Proj.)

2014-15 (Proj.)

2015-16 (Proj.)

Annual Revenue Requirement 4,346.65 5,000.43 5,179.63 5,468.03 5,779.92

Covered by

Revenue Billed @ Existing Tariff 1354.21 1601.51 1743.28 1943.62 2084.95

Collection Efficiency 90% 95% 96% 97% 98%

Revenue Collected 1218.79 1,521.43 1,673.55 1,885.31 2,043.25

Revenue @ Existing Tariff 1,218.79 1,521.43 1,673.55 1,885.31 2,043.25

Revenue from power sold to outside state

Revenue Gap/(Surplus) 3,127.86 3,479.00 3,506.08 3,582.72 3,736.67

Page 11: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 11

5 Tariff Revision Proposal

1. Table 4 summarizes the revenue at proposed tariffs for FY 2013-14.

2. As depicted in Table 3, total Revenue Gap of Rs. 3,506.08 Crores for the FY

2013-14 is proposed to be covered through additional revenue from proposed tariff

revision as well as through financial support from Government of J&K

3. In addition, there is estimated Revenue Gap of Rs. 3,479.00 Crores in FY 2012-13,

for which suitable recovery mechanism need to be evolved.

4. The increase in tariff will reduce the revenue gap by Rs 253.94 Crores in FY 2013-

14.

5. However, even after the proposed tariff hike, gap of Rs 3,270.13 Crores is still

remains. This unmet gap can be met through financial support from Government

of J&K.

Table 4: Revenue at Proposed Tariff

S# Tariff Category

Average Tariff (FY 2013-14) Average Cost of Supply (Actual) Average Cost of Supply (Prudent)

Average existing billing

rate

%hike

Average proposed

billing rate

Actual Cost of Supply

Proposed realization

as a %age of COS

GAP +/-

Prudent Cost of Supply

Proposed realization as

a %age of PCOS

GAP +/-

Total Revenue

at Proposed

Tariff

1 Domestic 2.13 10% 2.33 9.45 25% 7.12 6.36 37% 4.03

Metered 2.11 7% 2.25 9.45 24% 7.20 6.36 35% 4.11

up to 30 units per month 1.29 0% 1.29 9.45 14% 8.16 6.36 20% 5.07 13.06

31-100 units per minth 1.72 7% 1.84 9.45 19% 7.62 6.36 29% 4.53 70.45

101-200 units per month 2.18 7% 2.33 9.45 25% 7.12 6.36 37% 4.03 109.11

>200 units per month 3.22 7% 3.44 9.45 36% 6.01 6.36 54% 2.92 63.68

-

Un Metered 2.14 13% 2.42 9.45 26% 7.04 6.36 38% 3.95

up to 1/4 KW 1.07 0% 1.07 9.45 11% 8.38 6.36 17% 5.29 31.75

1/4-1/2 KW 2.36 15% 2.72 9.45 29% 6.74 6.36 43% 3.64 98.51

1/2-3/4 KW 2.35 15% 2.71 9.45 29% 6.75 6.36 43% 3.66 64.77

3/4-1 KW -

1-2 KW 3.86 15% 4.44 9.45 47% 5.01 6.36 70% 1.92 24.79

Above 2 KW (avg. 3.5 KW) 3.95 15% 4.55 9.45 48% 4.91 6.36 71% 1.82 22.70

-

2 Non Domestic/Commercial 3.37 9% 3.67 9.45 39% 5.79 6.36 58% 2.70

Metered Connection 3.71 9% 4.03 9.45 43% 5.43 6.36 63% 2.34

Single Phase -

up to 100 units/month 2.49 0% 2.49 9.45 26% 6.96 6.36 39% 3.87 24.97

101-200 units/month 2.62 10% 2.88 9.45 30% 6.57 6.36 45% 3.48 26.23

>200 units per month 3.73 10% 4.10 9.45 43% 5.36 6.36 64% 2.26 28.01

Three phase -

For all units 4.85 10% 5.33 9.45 56% 4.12 6.36 84% 1.03 103.18

-

Un Metered 2.17 11% 2.41 9.45 25% 7.05 6.36 38% 3.95

up to 1/4 KW 1.94 0% 1.94 9.45 20% 7.52 6.36 30% 4.42 7.28

1/4-1/2 KW 2.62 15% 3.01 9.45 32% 6.44 6.36 47% 3.35 12.87

1/2-1 KW 2.77 15% 3.19 9.45 34% 6.27 6.36 50% 3.17 7.14

1-5 KW 0.97 15% 1.11 9.45 12% 8.34 6.36 18% 5.25 2.60

Above 5 KW 3.17 15% 3.65 9.45 39% 5.81 6.36 57% 2.71 1.41

-

3 State/central Govt department

6.31 15% 7.26 9.45 77% 2.20 6.36 114% -0.89

11 kV supply 6.31 15% 7.26 9.45 77% 2.20 6.36 114% -0.90 377.40

Page 12: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 12

S# Tariff Category

Average Tariff (FY 2013-14) Average Cost of Supply (Actual) Average Cost of Supply (Prudent)

Average existing billing

rate

%hike

Average proposed

billing rate

Actual Cost of Supply

Proposed realization

as a %age of COS

GAP +/-

Prudent Cost of Supply

Proposed realization as

a %age of PCOS

GAP +/-

Total Revenue

at Proposed

Tariff

33 kv supply and above 6.24 15% 7.17 9.45 76% 2.28 6.36 113% -0.81 10.22

LT supply -

-

4 Agriculture 3.08 11% 3.43 9.45 36% 6.03 6.36 54% 2.94

Metered 1.57 6% 1.66 9.45 18% 7.79 6.36 26% 4.70

0-20 HP 0.78 0% 0.78 9.45 8% 8.67 6.36 12% 5.58 13.48

Above 20 HP 4.56 10% 5.01 9.45 53% 4.44 6.36 79% 1.35 22.78

-

Un Metered 6.75 14% 7.69 9.45 81% 1.76 6.36 121% -1.33

0-20 HP 2.46 0% 2.46 9.45 26% 6.99 6.36 39% 3.90 4.16

Above20 HP 7.74 15% 8.90 9.45 94% 0.56 6.36 140% -2.54 65.15

-

5 Public Street Lighting 4.68 13% 5.27 9.45 56% 4.18 6.36 83% 1.09

Metered connection 5.08 10% 5.59 9.45 59% 3.86 6.36 88% 0.77 9.62

Unmetered connection 4.35 15% 5.01 9.45 53% 4.45 6.36 79% 1.35 10.44

-

6 Public water works 3.91 15% 4.50 9.45 48% 4.96 6.36 71% 1.86

LT Connection -

Metered 5.45 15% 6.26 9.45 66% 3.19 6.36 98% 0.10 138.56

Un-Metered 2.22 15% 2.55 9.45 27% 6.90 6.36 40% 3.81 57.73

HT Connection -

Metered Connection -

11 KV supply 4.34 15% 4.99 9.45 53% 4.46 6.36 78% 1.37 51.07

33 KV supply and Above -

Un-Metered connection -

-

7 LT Industrial supply 2.97 15% 3.42 9.45 36% 6.03 6.36 54% 2.94

Metered connection 2.97 15% 3.42 9.45 36% 6.03 6.36 54% 2.94 134.75

Un-Metered connection -

up to 8 hrs shift -

8-12 hrs shift -

above 12 hrs shift -

-

8 HT Industrial supply 3.11 20% 3.73 9.45 39% 5.72 6.36 59% 2.63

11 KV supply 3.11 20% 3.73 9.45 39% 5.72 6.36 59% 2.63 242.93

33 KV supply and above -

-

9 HT PIU 3.52 20% 4.22 9.45 45% 5.23 6.36 66% 2.14

11 KV supply 3.52 20% 4.22 9.45 45% 5.23 6.36 66% 2.14 53.36

33 KV supply and above -

-

10 Bulk supply 4.07 20% 4.88 9.45 52% 4.57 6.36 77% 1.48

11 KV supply 4.12 20% 4.94 9.45 52% 4.52 6.36 78% 1.42 71.56

33 KV supply and above 3.31 20% 3.97 9.45 42% 5.48 6.36 62% 2.39 3.48

Total 3.18 13.53% 3.61 9.45 38% 5.84 6.36 57% 2.75 1979.23

6. It may be seen that there is a large gap between the average cost of supply and

category-wise average tariff, part of which is attributed to the fact that after the

tariff revision in the year 1999, the next tariff revision was done by Hon’ble

Commission for FY 2007-08 and thereafter in 2010-11, 2011-12 & 2012-13

respectively. However, average tariff still adequate enough to cover only 38% of

average cost of supply. Further besides agriculture and domestic consumers, non-

domestic and industrial consumers are also heavily subsidized. Hence following

proposal is made to increase average tariff to reduce this gap gradually.

Page 13: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 13

7. Further, Tariff Hike currently proposed is based on the consideration of Prudent

Average Cost of Supply i.e. Rs 6.36 p.u. Prudent Average Cost of Supply has been

computed using national average loss level of 25.27% as mentioned in the annual

report for FY 2011-12 on the Working of State Power Utilities and Electricity

Departments, Planning Commission, Government of India, October 2011.

8. It is evident that even after proposed hike, except State Central Government

categor, all categories like Domestic, NDNC, Agriculture, Public Street Lighting,

LT industrial Supply, HT Industrial Supply, HT-PIU Industrial Supply, HT Public

Water Works & General Purpose / Bulk Supply are still below Average Cost of

Supply at Prudent Loss Level.

9. Also in this proposal, the average hike proposed for unmetered consumers is more

as compared to average hike proposed for metered consumers in same category.

10. No Hike has been proposed in the Miscellaneous Charges.

11. KVAh tariff (in Energy Charges only) is proposed to be introduced in following

categories for connected load > 20 kW (metered connections only):

a. Non Domestic / Commercial

b. State / Central Government Departments

c. LT Industrial Power Supply

d. LT Water Works

The rationale behind introduction of kVAh tariff is to encourage consumers to

initiate on their own, the steps to improve their power factor. The kWh and kVAh

tariffs are currently proposed to be introduced in energy charges only and are

proposed to be kept at par with each other so that at unity power factor there is no

disparity in the charges paid by the consumers in the same category for same

consumption.

12. In line with Commission’s Observation in last Tariff Order (clause 10.7) it is

proposed that the Minimum Charges are proposed to be discontinued from next

Financial Year and instead same Fixed Charges are proposed to be introduced in

these categories.

Page 14: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 14

6 Proposed Tariff Schedules for FY 2013-14

Schedule 1: Domestic Supply

Applicability

This tariff category shall be applicable to supplies pertaining to domestic premises,

religious institutions, group housing societies, orphanages, old-age and infirm homes, charitable institutions providing services free of cost or on nominal charges, post

offices at residences of villagers and residential premises of architects, engineers,

advocates, doctors, teachers, artists, weavers, stitching and embroidery workers

occupying not more than 20% of built up area for respective professional purposes.

Character of Services

(a) Alternating current (A.C.) 50 Hz, 230 Volts, for Single-phase upto a load of 5 kW

(b) A.C, 50 Hz, three phase, 400 volts for load above 5 kW upto 100 kW (115 kVA)

Rate of Charge

Proposed tariffs for Domestic Consumers

Particulars Existing Tariff Proposed Tariff

Energy Charges for Metered Connection (Rs. / kWh)

0- 30 units/month 1.19 1.19

30 -100 units/month 1.54 1.65

101-200 units/month 1.90 2.03

> 200 units/month 2.91 3.11

Minimum Charges for connected load (Rs. / month) Fixed Charges (Rs. / month)

Upto ¼ kW 15 15

above 1/4 kW upto 1/2 kW 25 27

above 1/2 kW upto 1 kW 40 43

above 1 kW for every 250 W, or part thereof

10 11

Flat Rate for Unmetered Connection (Rs. / month)

upto ¼ kW 89 89

above 1/4 kW upto 1/2 kW 260 299

above 1/2 kW upto 3/4 kW 397 457

above 3/4 kW upto 1 kW 534 614

above 1 kW upto 2 kW 1,041 1,197

above 2 kW (for every additional ½ kW)

Rs. 1,041 + Rs. 451 for every additional 1/2 kW or part thereof

Rs. 1,197 + Rs. 483 for every additional 1/2 kW or part thereof

Page 15: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 15

Schedule 2: Non-Domestic/ Commercial Supply

Applicability

This tariff category shall be applicable to the followings: shops, showrooms, business

houses, offices, educational/ technical institutions, clubs, meeting halls, places of public entertainment, hotels, cinemas, hospitals, dispensaries, clinics, nursing homes,

X-ray units, diagnostic centers, pathological labs, fisheries, aqua-culture, sericulture,

dairy, hatcheries, printing presses, milk chilling centers, poultry farms, cattle breeding farms, nurseries, plantations, mushroom growing, carpenters and furniture makers,

juice centers, hoardings and advertisement services, typing institutes, internet cafes,

STD/ISD PCO’s, FAX/ photocopy shops, tailoring shops, photo studios and colour

labs, laundries, cycle shops, compressors for filling air, restaurants, eating

establishments, guest houses, marriage gardens, welding transformer and lathe

machines for repair works and services, book binders, petrol pumps and service stations, lifts and other appliances in shopping centres and offices, tourist house boats,

and similar other establishments.

In addition, any connection not covered under the other categories shall be billed under this category. However, this would exclude connections pertaining to State/

Central Government or Defence services, which have been included in a separate

category.

Character of Services

(a) AC, 50 Hz, 230 Volts, Single-phase upto a load of 5 kW.

(b) AC, 50 Hz, three phase, 400 volts supply for load above 5 kW upto 100 kW (115

kVA).

Rate of Charge

Proposed Tariff for Non-Domestic/ Commercial Category

Particulars Existing Tariff Proposed Tariff

Energy Charges for Metered Connection

Single Phase

Upto 100 units/month (Rs./kWh) 2.31 2.31

101 to 200 units/month (Rs./kWh) 2.44 2.68

above 200 units/month (Rs./kWh) 3.53 3.88

Three Phase -

For all units with Connected load <= 20 kW (in Rs / kWh)

4.11 4.52

For all units with Connected load > 20 kW (in Rs / kVAh)

4.11 4.52

Fixed Charges (Rs. / kW / month)

Single Phase 39 43

Three Phase 90 99

Page 16: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 16

Particulars Existing Tariff Proposed Tariff

Fixed Charges (Rs. /kW/ month) Load (in kW) to be rounded off to the next 1/2 kW for the purpose of application of Fixed Charges. For connections with sanctioned load below 100kW (115 kVA) supplied and metered on HT, 5% rebate on energy charges of Non-Domestic/Commercial Tariff shall be allowed.

Flat Rate for Unmetered Connection (Rs. / month)

Upto 1/4 kW 251 251

above 1/4 kW up to 1/2 kW 620 713

above 1/2 kW up to 1 kW 1,239 1,425

Above 1 kW (and part thereof for every kW above 1 kW)

1,593 1,832

Page 17: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 17

Schedule 3: State/ Central Government Departments

Applicability

This tariff category shall be applicable to the State/ Central Government department

category to connections taken by Departments of the State and the Central Governments, defense and Para-military forces, excluding public sector enterprises/

undertakings. This shall not include connections taken for agricultural purposes,

water pumping and street lighting by the State Government Departments for which tariffs provided in the appropriate tariff schedules shall apply.

Character of Services

(a) AC, 50 Hz, 230 Volts; Single-phase upto a load of 5 kW

(b) AC, 50 Hz, three phase; 400 volts supply for sanctioned load above 5 kW upto 100

kW (115 kVA)

(c) AC, 50 Hz, three phase; 11 kV supply for sanctioned load upto 1 MVA

(d) AC, 50 Hz, three phase; 33 kV and above supply for sanctioned load above 1 MVA

Rate of Charge

Proposed Tariff for State/ Central Government Departments

Particulars Existing Tariff Proposed Tariff

Energy Charges (Rs./ kWh)

LT Supply – Connected load <= 20kW (in Rs / kWh)

6.20 7.13

LT Supply – Connected load > 20kW (in Rs / kVAh)

6.20 7.13

For Connections at higher voltages of 11 kV and 33 kV, 2.5% and 5% rebate on Energy Charges shall be applicable.

Fixed Charges Rs./ kW Load (in KW) to be rounded off to the next whole number for the purpose of application of Fixed Charges

For metered consumers 25 29

Minimum Charges for connected load (Rs./ month)

Upto 1/4 kW Nil Nil

Above 1/4 kW (for every additional ½ kW)

Nil Nil

Page 18: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 18

Schedule 4: Agricultural Supply

Applicability

This tariff category shall be applicable to the agricultural loads and lift irrigation

connections including threshers and de-watering pumps used for bona-fide agricultural purposes.

Character of Services

(a) AC, 50 Hz, 230 Volts, Single-phase upto a load of 5 kW (6 kVA)

(b) AC, 50 Hz, three phase, 400 volts supply for sanctioned load upto 100 kW (115

kVA)

Rate of Charge

Proposed Tariff for Agriculture Category

Particulars Existing Tariff Proposed Tariff

Energy Charges for Metered Connections (Rs. / kWh)

0 to 20 HP 0.64 0.64

Above 20 HP 4.22 4.64

Minimum Charge for connected load (Rs./ HP/ Annum) Fixed Charges (Rs/HP/month)

0 - 20 HP 250 21

Above 20 HP 900 83

Provisional monthly billing will be done subject to annual adjustment

Flat Rate for Unmetered Connection (Rs./ HP/ month)

0 to 20 HP 168 168

Above 20 HP 1,168 1,343

Page 19: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 19

Schedule 5: Public Street Lighting

Applicability

The tariffs for this category will be applicable to public street lighting established

and maintained by Corporations, Municipalities, Town Area/ Notified Area Committees, other local bodies and agencies authorized by the State Government

to establish and maintain public street lighting.

Character of Services

(a) AC, 50 Hz, 230 Volts, Single-phase up to a load of 5 kW;

(b) AC, 50 Hz, three-phase, 400 volts supply for load above 5 kW.

Rate of Charge

Proposed Tariffs for Public Street Lighting

Particulars Existing Tariff Proposed Tariff

Energy Charge for Metered Connections in Rs / kWh

For all units 4.96 5.46

Fixed Charges Rs./ kW Load (in KW) to be rounded off to the next whole number for the purpose of application of Fixed Charges

Rs./ kWh (for metered consumers)

37 41

Minimum Charges

Rs./ kW or any part thereof / month

Nil Nil

Flat Rate Charges for Unmetered Connections

Rs./ kW or any part thereof / month

1,180 1,357

Page 20: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 20

Schedule 6: LT Public Water Works

Applicability

The tariffs for this consumer category shall apply to water works and sewerages/ drainage installations established and maintained by Corporations,

Municipalities, Town Area/ Notified Area Committees, other local bodies and

Government agencies authorized by the State Government to establish and maintain public water works/ sewerage installations.

Character of Services

(a) AC, 50 Hz, 230 Volts, Single-phase upto a load of 5 kW (6kVA)

(b) AC, 50 Hz, three phase, 400 volts supply for sanctioned load upto 100 kW

Rate of Charge

Proposed Tariff for LT Public Water Works

Particulars Existing Tariff Proposed Tariff

Energy Charge for Metered Connections For all units with connected load <= 20 kW (in Rs / kWh)

5.35 6.15

For all units with connected load > 20 kW (in Rs / kVAh)

5.35 6.15

Fixed Charges Rs./ kW Load (in KW) to be rounded off to the next whole number for the purpose of application of Fixed Charges

Rs./ kWh (for metered consumers)

41 47

Minimum Charges

Rs. / kW, or part thereof/month

Nil Nil

Flat Rate Charges for Unmetered Connection

Rs. / kW, or part thereof/month

1250 1438

Page 21: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 21

Schedule 7: HT Public Water Works

Applicability

The tariffs for this consumer category shall apply to water works and sewerages/

drainage installations established and maintained by Corporations, Municipalities, Town Area/ Notified Area Committees, other local bodies and

Government agencies authorized by the State Government to establish and

maintain public water works/ sewerage installations.

Character of Services

(a) AC, 50 Hz, three phase; 11 kV supply for load upto 1 MVA.

(b) AC, 50 Hz, three phase; 33 kV and above supply for sanctioned load above 1MVA

Rate of Charge

Proposed Tariff for HT Public Water Works

Particulars Existing Tariff Proposed Tariff

Energy Charges for Metered Connection (Rs./kVAh)

11 kV Supply 3.81 4.38

33 kV Supply and above 3.68 4.23

Demand Charges for Metered Connection(Rs./ kVA or part thereof / Month)

11 kV Supply 210 242

33 kV Supply and above 204 235

For Connections above 100 kW supplied on LT, Additional 5% Surcharge on Demand and Energy Charges at 11 KV tariff shall be chargeable.

Flat Rate Charges for Unmetered Connection

Rs./ kW, or part thereof / Month

Nil Nil

Note:

The billing demand for any month shall be taken to be the higher of the actual

maximum recorded demand or 75% of the Contract Demand.

Page 22: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 22

Schedule 8: LT Industrial Supply

Applicability

This tariff category shall be applicable to all units registered with the Industries &

Commerce Department, Government of J&K, and covered under the Factories Act. The list of entities covered shall include various industrial installations and

workshops with manufacturing facilities, where raw materials are converted to

finished goods. This shall mean and include all energy consumed in factory, offices, stores, canteen, compound lighting, etc. and the consumption for

residential use therein.

Character of Services

(a) AC, 50 Hz, 230 Volts, single-phase upto a load of 5 kW.

(b) AC, 50 Hz, three phase, 400 volts supply for sanctioned load upto 100 kW

Rate of Charge

Proposed tariffs for LT Industrial Supply

Particulars Existing Tariff Proposed Tariff

Energy Charges for Metered Connections

For all units connected load <= 20 kW (in Rs./kWh)

2.65 3.05

For all units connected load >20 kW (in Rs./kVAh)

2.65 3.05

Fixed Charges for Metered Connection

Rs./KW/month 43 49

Load (in KW) to be rounded off to the next ½ kW for the purpose of application of Fixed Charges

*For Connections with sanctioned load below 100 kW supplied and metered on HT, 5% rebate on Energy Charges of the LT Industrial Tariff shall be allowed.

Page 23: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 23

Schedule 9: HT Industrial Supply

Applicability

This tariff category shall be applicable to all units registered with the Industries

department, Government of J&K, and covered under the Factories Act. This shall mean and include all energy consumed in factory, offices, stores, canteen, compound

lighting, etc. and residential use therein, excluding power intensive industries.

Character of Services

(a) AC, 3 phase; 50 Hz on 11 KV with sanctioned load above 100 kW upto 1 MVA

(b) AC, 3 phase; 50 Hz, 33 KV and above for sanctioned load of 1 MVA and above

Rate of Charge

Proposed Tariff for HT Industrial Supply

Particulars Existing Tariff Proposed Tariff

11 kV Supply

Energy Charge (Rs./ kVAh) 2.42 2.90

Demand Charge (Rs./ kVA/ month) 127 152

For Connections with sanctioned load above 100 kW up to 1 MVA metered on LT, additional 5% Surcharge on Demand & Energy Charges at 11 KV tariff shall be chargeable

33 kV Supply

Energy Charge (Rs./ kVAh) - Normal 2.35 2.82

Demand Charge (Rs./ kVA/ month) 127 152

For 66 kV – 1.5% Rebate on the Energy Charge for 33 kV Supply.

Note:

The billing demand for any month shall be taken to be the higher of the actual

maximum recorded demand or 75% of the Contract Demand.

Page 24: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 24

Schedule 10: HT Industrial Supply for Power Intensive Industries

Applicability

This tariff category shall be applicable to all units registered with the Industries &

Commerce Department, Government of J&K, and covered under the Factories Act.

This category shall apply to HT consumers manufacturing any one of the following

products and/ or industries engaged in any one or more of the processes listed below

and/ or using induction/ arc furnaces. This shall mean and include all energy

consumed in factory, offices, stores, canteen, compound lighting, etc. and the

consumption for residential use therein.

(a) Calcium carbide

(b) Caustic soda

(c) Charge chrome

(d) Ferro manganese

(e) Ferro silicon

(f) Ferro alloys

(g) Potassium chlorate

(h) Silicon carbide

(i) Sodium chlorate

(j) Sodium metal

(k) Chlorates/ per chlorates

(l) Melting of metals and alloys

(m) Industries engaged in electro-chemical/ electro-thermal processes

(n) Industries using induction/ arc furnace

Page 25: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 25

(o) Where the cost of power is more than 25% of the cost of the product manufactured.

Character of Services

(a) AC, 3 phase; 50 Hz, 11 KV upto 1 MVA

(b) AC, 3 phase; 50 Hz, 33 KV and above supply for sanctioned load of 1 MVA and

above

Rate of Charge

Proposed Tariff for HT Industrial Supply for Power Intensive Industries

Particulars Existing Tariff Proposed Tariff

11 kV Supply

Energy Charge (Rs./ kVAh) 2.83 3.40

Demand Charge (Rs./ kVA/ Month)* 180 216

33 kV Supply

Energy Charge (Rs./ kVAh) - Normal 2.77 3.32

Demand Charge (Rs./ kVA/ Month)* 174 209

*Or part thereof on billing demand For 66 kV – 1.5% rebate on the Energy Charge for 33 kV Supply

Note:

The billing demand for any month shall be taken to be the higher of the actual maximum recorded demand or 75% of the Contract Demand.

Page 26: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 26

Schedule 11: General Purpose Bulk Supply

Applicability

This category contains all non-industrial consumers having mixed type of load greater

than 100 kW (115 kVA) and those consumers having multiple connection with aggregate load more than 100kW in an Electric Circle. This includes domestic

consumers, offices, educational/ technical institutions, religious institutions,

residential colonies, commercial establishments and other similar loads.

All connections having load of 100 kW or above and not covered in any other

categories shall be billed under tariffs applicable to this category. However, any

such connections belonging to State/ Central Governments, Defense and Para-military forces shall not be considered in this category.

Character of Services

(a) AC, 3 phase; 50 Hz on 11 KV upto 1 MVA.

(b) AC, 3 phase; 50 Hz on 33 KV and above .for load of 1 MVA and above

Rate of Charge

Proposed Tariff for General Purpose Bulk Supply

Particulars Existing Tariff Proposed Tariff

11 kV Supply

Energy Charge (Rs./ kVAh) 3.50 4.20

Demand Charge (Rs./ kVA/ Month)* 184 221

For Connections above 100 kW supplied on LT, additional 5% Surcharge on Demand & Energy Charges at 11 kV tariff shall be chargeable

33 kV Supply

Energy Charge (Rs./ kVAh) - Normal 3.31 3.97

Demand Charge (Rs./ kVA/ Month) * 178 214

*Or part thereof on Billing Demand

For 66 kV – 1.5% Rebate on the Energy Charge for 33 kV Supply.

Note: The billing demand for any month shall be taken to be the higher of the

actual maximum recorded demand or 75% of the Contract Demand.

Page 27: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 27

Schedule 12: LT and HT Temporary Connections

Applicability

This tariff category shall be applicable to all loads of temporary nature, such as

exhibitions, touring talkies, circuses, fairs, marriages, temporary agricultural loads, temporary supply for construction including civil works by Government departments

and other similar purposes.

Rate of Charge

The proposed tariff for temporary connections at 1.5 times the applicable rates (on

fixed/ demand and energy charges).

SCHEDULE OF MISCELLANEOUS CHARGES

Schedule of Miscellaneous charges has been kept at same level as approved for

FY 2012-13.

Page 28: Tariff Revision Proposal for FY 2013-14 · 5 Tariff Revision Proposal 1. Table 4summarizes the revenue at proposed tariffs for FY 2013-1 . 2. As depicted in Table 3, total Revenue

J & K Power Development Department Tariff Revision Proposal for FY 13-14

Page 28

7 Prayer

1. JKPDD requests the Hon’ble Commission to:

a. Admit the Tariff Revision Proposal of FY 2013-14.

b. Approve the Tariff Revision Proposal of FY 2013-14.

c. Make the approved Retail Supply Tariffs applicable from April 1, 2013.

d. Condone any inadvertent omissions/ errors/ shortcomings and permit

the Petitioner to add/ change/ modify/ alter this filing and make

further submissions as may be required at a future date.

e. Allow further submissions, addition and alteration to this Petition as

may be necessitating from time to time.

f. And pass such other and further orders as are deemed fit and proper in

the facts and circumstances of the case.