Tall Building Presentation
-
Upload
muhammad-azuan-tukiar -
Category
Documents
-
view
225 -
download
1
Transcript of Tall Building Presentation
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 1/44
TALL BUILDING ENGINEERING
ECS712
TWO INTERNATIONAL FINANCIAL CENTREHONG KONG
Prepared by:
Mohd Azuan Tukiar 2010300175Mohd Firdaus Barjumin 2009954675
Prepared for:
Prof. Ir. Dr. Hjh Siti Hawa Hamzah
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 2/44
Content of Presentation
Introduction to Two IFC
Architecture Design
Structural System
Geology and Foundation System
Studies Undertaken to Assess the Structural Implication
Remarks
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 3/44
Introduction to Two IFC1. The 88 storey of building was completed in 2003 with
height of 412m
2. Currently was at 12th places of tallest building in the worldaccording to the CTBUH Tall Building Database
3. The International Finance Center forms part of HongKong station Development on the central reclamationHong Kong
4. The development comprises of 47 million sq ft of primereal estate comprises of: 2.8 million sq ft office
0.8 million of retail and 2 hotels that totally over 1,00 rooms altogether
140,000 sq ft of designed public opened space and amenities
1,800 car parking space
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 4/44
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 5/44
Developers
Central Waterfront Properties1. Sun Hung Kai Properties Ltd2. Henderson Land Development Co Ltd3. Bank of China Group Investment Ltd4. Hong Kong & China Gas Co Ltd
Architect1. Cesar Pelli & Assc.2. Rocco Design Limited
Structural & GeotechniqueConsultant
Ove Arup & Partners
M&E Consultant J. Roger Preston Ltd
Main Contractor 1. E. Man2. Sanfield Contractors
Structural Steelwork Contractor1. NKK Corporation2. Sumimoto Corporation.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 6/44
Architecture Design of Two IFC
To achieve a mix of high quality office, hotel andretail expansion of Central Business Districtfunction as envisaged under Metropolitanframework.
To provide focal buildings which will compatiblewith the other nearby planned development inthe new reclamation area, and
To maintain high degree of inter visibility betweenVictoria Harbor and the Central Business District’s
landmark building in vicinity
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 7/44
Architecture Design of Two IFC
Master Layout Plan has planned to have 5 towers.However, due to commercial and environmentalaspect, it was decide to combine 2 office tower andTwo International Finance Center conceived
Height further highlight with vertical fins on the externalfaçade which is gradually lightened in color as itmounts to its top. The simple fin gave an extra value inaesthetic.
The color of building will appear to have varyingshades when looking at it at an oblique manner.
Towards to the top, a series of staggered step back reduce the plan dimension to 39mx39m at roof level.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 8/44
Structural System of Two IFC Tall building must have stability against
overturning, uplift and/or sliding of the structureas a whole.
Strength of the structural components of thebuilding also required to be sufficient towithstand imposed loading without failure duringthe life of the structure.
Tall building also need to satisfied serviceabilitycriteria, where inter storey and overall deflectionsare expected within acceptable limits.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 9/44
Structural System of Two IFC
The necessities of Two IFC design was to maximizethe views from the tower and to have flexibilityoffice layout
Outrigger system was adopted in preferences toother common tall building system.
This system contains three main elements which
are the
1. outrigger beam,
2. the core wall and
3. the exterior (external) columns.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 10/44
Structural System of Two IFC
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 11/44
Structural System of Two IFC
Typical Floor Framing
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 12/44
Structural System of Two IFC
RC Core Wall
1. Dimension of 27mx29m at the base with perimeter wall 1.5m and 1.25m thick
2. The core is constructing using conventionalreinforced concrete of grade 60 concrete
3. The use of core-wall system can be very effectiveand efficient structural system used in reducingresponses due to lateral load
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 13/44
Structural System of Two IFC
Maximum Wind Drift for Central Core with &without Outriggers
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 14/44
Structural System of Two IFC
Outriggers System
1. Core is stabilized by three outriggers each threestorey high
2. Located at the mechanical and refuge floor zonewhich is at R2/F to 33/F, R3/F to 55/F and to R4/F to67/F
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 15/44
Structural System of Two IFC
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 16/44
Structural System of Two IFC
Punched concrete core wall type outriggersprovide insufficient stiffness for providing anopening of significant M&E access.
Therefore, it is necessary for steel truss to increasethe strength and stiffeners of perforated core.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 17/44
Structural System of Two IFC
Steel truss with shear stud before embedded intoreinforced concrete core wall
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 18/44
Structural System of Two IFC
Belt Truss
1. Belt truss are used to tie the peripheral columnbuilding while the outrigger engaged them with
reinforced concrete core wall
2. Study showed that the use of outrigger and thebelt truss has improved the serviceability of thestructure
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 19/44
Structural System of Two IFC
Four options are compared which1. model without belt truss and outriggers (MT0),
2. model with one belt truss and outriggers (MT1),
3. model with double belt truss and outrigger (MT2)
4. model with triple belt truss with outriggers (MT3)
There is 34% reduction in deflection by the useof one outrigger at the effective level
41% and 51% drop is achieved by the use oftwo and three outrigger levels with respect tomodel without belt truss and outriggers
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 20/44
Structural System of Two IFC
Comparisons of various outrigger options
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 21/44
Structural System of Two IFC
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 22/44
Structural System of Two IFC
Secondary Column
300x300mm dimension of column
Support gravity load only
There are three zone of such column each
extending a maximum of 20 storey which
are supported of transfer (belt) trusses at
each of the outrigger level
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 23/44
Structural System of Two IFC
The loads from the secondary column are effectivelycollected by these trusses and transferred to themega column
At the higher level where the corners of the floor plate are stepped back, these columns are removedthen the floor plates are cantilevered from the megacolumn
Considered for not having these columns throughoutthe building, however it will cause a significant costimpact due to additional weight of floor steel andexpected the large cantilevered floor system
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 24/44
Structural System of Two IFC
Mega Column
8 mega-columns rising from the raft at the base ofthe cofferdam up to the roof, supporting theexternal frame of the entire building at 24 meters
center to center
The mega column comprises of compositesteel/concrete in which the steel elements areencased with reinforced concrete
The structural steel component was split into anumber of sub sections that could be lifted andconnected with ease.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 25/44
Structural System of Two IFC Column Schedule
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 26/44
Structural System of Two IFC
Plinth for mega column
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 27/44
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 28/44
Fixing steel bars (50 mm diameter bars at the basesection) around the stanchions of a mega-columnbefore encasing it in concrete
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 29/44
Structural System of Two IFC Floor System
1. Composite steel/concrete floor with125mm thick slab acting compositely with the permanentdecking supported at up to 3m intervals of varietysteel beam size
2. The typical floor to floor height was 4.17m
3. The floor component is comprises of 460mm deepsteel secondary beam spanning 11.4m to 13.5mfrom the core to 900mm deep
4. Primary girders spanning 24m between the megacolumn, The beam sections were graduallyreduced in size for higher levels
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 30/44
Structural System of Two IFC
1. The inclusion of diagonal beam which conjunction withthe primary girder on the main faces provided continuous
tension ring around the floor plate thus enhanced
robustness and provide direct buckling restraint to the
column
2. The 24m primary girder comprised of asymmetric
fabricated section was structurally continuous with the
mega column
3. The weight of floor beam steel is 36kg/m2 based on the
gross constructed floor area
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 31/44
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 32/44
24 m edge beam spanning between the mega-columns at the lower section of the tower
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 33/44
Geology and Foundation System
The foundation of the high rise development inHong Kong has traditionally been piles or caissonbearing on the un-weathered rock normally at
depth of up to 40m or 50m
With the extension of land reclamation into theharbor the depth to rock has generally increased
up to 70 to 80m
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 34/44
Geology and Foundation System
Grade 3 granite with permissible bearing capacity of5Mpa was found approximately 35meters belowground level.
Above of this are layers of decomposed granite andalluvium and over the top 20 meters were layers of fillthat have been reclaimed for three years earlier.
Initially, the foundation was decided to have 72nosof end bearing bored piled with 3meter in diameter and cofferdam was also required to enable pilecape constructed at 30m below ground level.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 35/44
Geology and Foundation System
With reasonably constant rock head level asdetermined in site investigation, it was proposedraft foundation to be cast bearing directly onrock, thus omitting the need for bored piled
Rock level to the south west of the tower baseappeared with a maximum depth of rock up to-50 mPD, which was too deep for normal openexcavation
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 36/44
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 37/44
Geology and Foundation System
To overcome the problem, mixed foundationsolution was adopted
In location where to have maximum depth up to -50PD, barrettes (rectangular-section piles) wereinstalled to provide support to the building raft.
The whole excavation process was carried outdown to the formation level at -32 mPD. Includingthe treatment to the localized bedrock, the work took about 16 months to complete.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 38/44
Studies Undertaken to Assess theStructural Implication
Lateral Response of Building
Impact of Aircraft component on the keyelement of Structure
Vaporization of key element of the Structure
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 39/44
Lateral Response of Building
Wind tunnel performed by Roman William Davies & Irwin
Inc (RWDI) and Cermak Pterka Peterson (CPP)
Resulting from the study showed global characteristicbase bending moment and base shear were19,000MNm & 128MN respectively
Lateral acceleration were predict & compared againstNBCC, ISO and Davenport Criteria for occupancycomfort and it found that acceleration deemedacceptable w/o need any supplementary damping.
Lateral deflection under wind loading were H/450 inorthogonal direction & H/380 in the diagonal where H isheight of the building above pile cap
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 40/44
Impact of Aircraft component on the key element ofStructure
Analytical study undertaken by Arp Extreme EventMitigation Task Force
Investigated the performance of range of typicalcolumn in high rise structure when subject to the impactfrom an aircraft engine travelling at speed
Engine speed of 200mph(89.4m/s) and using columndimension of 3m x 1.8m RC encased composite columnhousing 604kg/m steel section
Finding- the composite mega column of Two IFCperformed well by exhibiting only limited concretecrushing and plastic straining of steel section
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 41/44
Vaporization of key element of the Structure
Study in the event where that such element areremoved
Finding:
Tower remain stable despite the column beingremoved
Tower experienced a gravity load path re-distribution
Increase gravity load in the outrigger is resistedby RC core which has demonstrate adequatelyredistribute these gravity load
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 42/44
Remarks Two IFC used of outriggers system as their
structural form
3 main elements of outriggers system which iscore wall, outrigger beam, mega column
Core wall dimension of 27mx29m at the base withperimeter wall 1.5m and 1.25m thick construct usingRC Grade 60.
Outrigger beam each three storey high located atthe mechanical and refuge floor zone which is atR2/F to 33/F, R3/F to 55/F and to R4/F to 67/F
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 43/44
Remarks
8 mega-columns supporting the external frame of theentire building at 24 meters center to center comprises of composite steel/concrete in which thesteel elements are encased with reinforced concrete
with varies grade concrete
For foundation system, mixed foundation solutionwas adopted. In location where to have
maximum depth up to -50PD, barrettes(rectangular-section piles) were installed toprovide support to the building raft.
7/27/2019 Tall Building Presentation
http://slidepdf.com/reader/full/tall-building-presentation 44/44
Q & A