TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid...

144
CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015 TABLE OF CONTENTS 00000 - 1 TABLE OF CONTENTS DIVISION 1 - GENERAL REQUIRMENTS 01000 GENERAL 01010 SUMMARY OF WORK 01020 ADMINISTRATION AND SUPERVISION 01021 ALLOWANCES 01026 UNIT PRICES 01030 ALTERNATES 01041 PROJECT COORDINATION 01042 MECHANICAL AND ELECTRICAL COORDINATION 01045 CUTTING AND PATCHING 01060 REGULATORY REQUIREMENTS 01075 SPECIFICATION SYSTEM 01100 SPECIAL PROJECT PROCEDURES 01121 HAZARDOUS MATERIALS PROCEDURES 01200 PROJECT MEETINGS 01300 SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 01400 QUALITY CONTROL 01500 TEMPORARY FACILITIES 01600 MATERIALS AND EQUIPMENT 01700 CONTRACT CLOSEOUT 01710 CLEANING 01720 PROJECT RECORD DOCUMENTS 01730 OPERATING AND MAINTENANCE 01740 COMMISSIONING REQUIREMENTS DIVISION 2 – SITEWORK 02050 BASIC SITE MATERIALS & METHODS 02111 TREE AND PLANT PROTECTION DIVISION 31 – EARTHWORK 311000 SITE CLEARING 312323 TRENCHING AND BACKFILLING 312500 TEMPORARY EROSION AND SEDIMENTATION CONTROL DIVISION 32 – EXTERIOR IMPROVMENTS 321216 ASPHALT PAVING 321313 CONCRETE PAVEMENT 321373 CONCRETE PAVING JOINT SEALANTS DIVISION 33 – UTILITIES 331100 WATER UTILITY DISTRIBUTION PIPING

Transcript of TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid...

Page 1: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

TABLE OF CONTENTS

00000 - 1

TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIRMENTS

01000 GENERAL

01010 SUMMARY OF WORK

01020 ADMINISTRATION AND SUPERVISION

01021 ALLOWANCES

01026 UNIT PRICES

01030 ALTERNATES

01041 PROJECT COORDINATION

01042 MECHANICAL AND ELECTRICAL COORDINATION

01045 CUTTING AND PATCHING

01060 REGULATORY REQUIREMENTS

01075 SPECIFICATION SYSTEM

01100 SPECIAL PROJECT PROCEDURES

01121 HAZARDOUS MATERIALS PROCEDURES

01200 PROJECT MEETINGS

01300 SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01400 QUALITY CONTROL

01500 TEMPORARY FACILITIES

01600 MATERIALS AND EQUIPMENT

01700 CONTRACT CLOSEOUT

01710 CLEANING

01720 PROJECT RECORD DOCUMENTS

01730 OPERATING AND MAINTENANCE

01740 COMMISSIONING REQUIREMENTS

DIVISION 2 – SITEWORK

02050 BASIC SITE MATERIALS & METHODS

02111 TREE AND PLANT PROTECTION

DIVISION 31 – EARTHWORK

311000 SITE CLEARING

312323 TRENCHING AND BACKFILLING

312500 TEMPORARY EROSION AND SEDIMENTATION CONTROL

DIVISION 32 – EXTERIOR IMPROVMENTS

321216 ASPHALT PAVING

321313 CONCRETE PAVEMENT

321373 CONCRETE PAVING JOINT SEALANTS

DIVISION 33 – UTILITIES

331100 WATER UTILITY DISTRIBUTION PIPING

Page 2: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

GENERAL 01000 - 1

SECTION 01000

GENERAL 1.01 CONDITIONS AND REQUIREMENTS Division 1 - General Requirements shall govern work under all Divisions of the Specifications. 1.02 SPECIFICATION LANGUAGE EXPLANATION

Specifications are of abbreviated, simplified or streamlined type and include incomplete sentences. Omissions of words or phrases such as "the Contractor shall," "in conformity therewith," "shall be," "as noted on the Drawings," "a," "the" are intentional. Supply omitted words or phrases by inference in same manner as they are when "NOTE" occurs on Drawings. Supply words "shall be" or "shall" by inference when colon is used within sentences or phrases. Supply words "on the Drawings" by inference when "as indicated" is used with sentences or phrases. Where reference is made to specifications, societies, institutes, or associations or manufacturer's directions, they are, except as may be inconsistent herewith, made part of specifications, to same extent as if written out in full herein. Use latest edition, at time of bidding, if a date is not given.

1.03 SUBMITTALS A. Prepare data for use by the University of Colorado, Facilities Management personnel. B. Format: 1. Submit electronically in Portable Document Format (PDF) format as one

document, OCR (Optical Character Recognition) searchable, bookmarked according to the Construction Specifications Institute (CSI) standards.

2. Title shall be "SPECIFICATIONS", and shall include: a. Name of project and submittal stage and date of submittal (month, day,

and year). b. University of Colorado Project number (Include on cover and in header or

footer of each page)

1.04 CONTENT OF MANUAL A. An electronically-written table of contents shall be provided for each volume, arranged

according to CSI standards. Include the following:

1. Name of responsible installing principal contractor, address, and telephone number.

1.05 ABBREVIATIONS

References in Contract Documents to trade associations, technical societies, recognized authorities and other institutions include following organizations, which are sometimes referred to only by corresponding abbreviations: AA Aluminum Association AAMA Architectural Aluminum Manufacturer's Association ACI American Concrete Institute

Page 3: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

GENERAL 01000 - 2

AIMA Acoustical and Insulating Materials Association (successor to AMA and IBI)

AISC American Institute of Steel Construction AISI American Iron and Steel Institute AITC American Institute of Timber Construction AMA Acoustical Materials Association ANSI American National Standards Institute (successor to USASI and ASA) APA American Plywood Association ASHRAE American Society of Heating, Refrigerating and Air Conditioning

Engineers ASTM American Society for Testing Materials AWI Architectural Woodwork Institute AWPA American Wood Preservers Association AWS American Welding Society CDA Copper Development Associations, Inc. CM/GC Construction Manager/General Contractor CRA California Redwood Association CRSI Concrete Reinforcing Steel Institute CS Commercial Standard (U.S. Department of Commerce) DFPA Douglas Fir Plywood Association EPA Environmental Protection Agency FGMA Flat Glass Marketing Association FIA Factory Insurance Association FM Factory Mutual Engineering Division FS Federal Specification MIA Marble Institute of America MIL Military Specification MILMA Metal Lath Manufacturer's Association NAAMM The National Association of Architectural Metal Manufacturers NBFU National Board of Fire Underwriters NBS National Bureau of Standards NCMA National Concrete Masonry Association NEC National Electric Code (of NBFU) NEMA National Electrical Manufacturers' Association NFPA National Fire Protection Association NIOSH National Institute of Occupational Safety and Health NMWIA National Mineral Wool Insulation Association NPVLMA National Paint, Varnish and Lacquer Manufacturers' Association NTMA The National Terrazzo and Mosaic Association OSHA Occupational Safety and Health Administration PCA Portland Cement Association PCI Prestressed Concrete Institute PEI Porcelain Enamel Institute PS Product Standard (U.S. Department of Commerce) SCPI Structural Clay Products Institute SDI Steel Deck Institute SJI Steel Joist Institute SMACNA Sheet Metal and Air Conditioning Contractor's National Association SPA Southern Pine Association SPI The Society of Plastic Industry, Inc. SPR Simplified Practice Recommendation (U.S. Department of Commerce) SSPC Steel Structures Painting Council SWI Steel Window Institute

Page 4: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

GENERAL 01000 - 3

TCA Tile Council of America UL Underwriters' Laboratories, Inc.

WCLA West Coat Lumbermen's Association WRI Wire Reinforcement Institute WWPA Western Wood Products Association

1.04 LAYING OUT WORK

The Contractor will furnish reference bench mark and maintain bench mark and all other grades, lines, and levels and dimensions as indicated in the Contract Documents. Report any errors or inconsistencies in above to Owner before commencing work.

Except as delegated by subcontract or normal trade practice, the Contractor will be responsible for all lines, elevations, and measurements of work indicated.

1.05 EXAMINATION OF SITE

Failure to visit the site will in no way relieve any Contractor from the necessity of furnishing materials or performing work that may be required to complete work in accordance with the Contract Documents without additional cost to Owner.

END OF SECTION

Page 5: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUMMARY OF WORK 01020 - 1

SECTION 01010

SUMMARY OF WORK PART 1 - GENERAL 1.01 SCHEDULE OF DRAWINGS, SPECIFICATIONS AND ADDENDA The following Drawings, Project Manual, and Addenda from the Contract Documents.

A. Set(s) of Drawings & project manuals dated July 2015 Drawing list is as follows: Titled CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4)

DRAWING INDEX

F0.00 – COVER SHEET

CIVIL

C0.10 – NOTES AND LEGEND

C0.20 – NOTES

C0.30 – EXISTING CONDITIONS AND DEMOLITION PLAN

C1.00 – WATER MAIN PLAN AND PROFILE

C2.00 – EROSION CONTROL PLAN

C3.00 – SITE RESTORATION PLAN

C7.00 – DETAILS

C7.10 – DETAILS

FIRE PROTECTION

FP0.10 – GENERAL NOTES

FP1.01 – DENISON ARTS AND SCIENCES PIPE TRENCH LEVEL

FP1.02 – DENISON ARTS AND SCIENCES 1ST LEVEL

FP1.03 – DENISON ARTS AND SCIENCES 2ND LEVEL

FP1.04 – DENISON ARTS AND SCIENCES 3RD LEVEL

FP2.00 – CLARE SMALL STANDPIPE DIAGRAM

FP2.01 – CLARE SMALL 3RD BASEMENT LEVEL

FP2.02 – CLARE SMALL 2ND BASEMENT LEVEL

FP2.03 – CLARE SMALL 1ST BASEMENT LEVEL

FP2.04 – CLARE SMALL 1ST LEVEL

FP2.05 – CLARE SMALL 2ND LEVEL

FP2.06 – CLARE SMALL 3RD LEVEL

FP2.07 – CLARE SMALL 4TH LEVEL

FIRE ALARM

FA0.10 – GENERAL NOTES

FA0.20 – SEQUENCE OF OPERATIONS AND RISER DIAGRAM

FA1.01 – DENISON ARTS AND SCIENCES 1ST LEVEL

FA1.02 – DENISON ARTS AND SCIENCES 2ND LEVEL

Page 6: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUMMARY OF WORK 01020 - 2

FA1.03 – DENISON ARTS AND SCIENCES 3RD LEVEL

B. Project Manual titled: CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-

M081M4) dated July 2015.

C. Addenda: All Addenda issued prior to bidding. 1.02 WORK COVERED BY CONTRACT DOCUMENTS A. Work covered: Work under this contract includes all materials, equipment and labor

necessary to complete the work indicated on the drawings, described in specifications, addenda or reasonably inferred.

1.03 CONTRACTORS

All work will be executed under one prime construction contract between the Owner and the Contractor. Except as indicated otherwise, all work under this contract will be under the direction of the prime contractor. The only exception shall be the Asbestos or lead abatement which will be contracted separately by Owner

1.04 JOB CONDITIONS A. Areas of the building immediately adjacent to areas under construction will be occupied by

the public during the work of this project. Limit construction operations to those methods and procedures which will not adversely and unduly affect the Owner's occupied spaces inclusive of parking facilities.

B. Do not interrupt building access and use, except as permitted by the Owner.

Provide eight (8) work days notice to the Owner of construction activities which will severely impact the occupancy and use of adjacent areas.

C. Provide temporary barriers and/or partitions as required to protect the occupants of the

building and the general public from injury due to the work of this project; and/or to protect adjacent areas of the building from the spread of dust and dirt caused by the work or this project.

Remove temporary barriers and partitions upon completion of the Project. 1. Temporary partitions shall be constructed of 1/2" plywood on the construction

face nominal 2" X 4" wood studs and 1/2" gypsum wallboard on the public occupied face.

D. Do not interrupt power, lighting, plumbing, telephone and HVAC services to occupied

areas without Owner's approval. Such interruptions must be scheduled at least eight (8) work days in advance and have Owner's approval.

Page 7: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUMMARY OF WORK 01020 - 3

1.05 PROTECTION OF WORK AND ADJACENT PROPERTY A. Buildings and property adjacent to work included in this project may be subject to damage

due to construction operations.

Prior to the start of the work included in this Contract engage the services of a photographer to record the existing condition of adjacent structures and property. Contractor shall provide one set set on disk to the Owner and retain one set for their records. Sufficient photos with adequate detail to thoroughly document the conditions surrounding the work shall be provided.

B. At the completion of the project, Contractor shall restore existing buildings, landscaping,

parking facilities and property to same condition as prior to the start of the work. C. In addition to the requirements of the General Conditions of the Contract for Construction,

the Contractor shall: 1. Notify, in writing, the Owner of University or private property which interferes with

the work and arrange with them for disposition of such property. 2. Provide and maintain proper shoring and bracing to prevent earth from caving or

washing into excavation. Provide temporary protection around openings through and at floors, roofs, and other openings.

3. Provide and maintain proper shoring and bracing for existing underground utilities, sewers, etc., encountered during excavation work, to protect them from collapse or other type of damage until such time as they are to be removed, incorporated into the work of this project, or can be properly back-filled upon completion of new work.

4. Weather Protection: Provide protection against rain, snow, wind, ice, storms, or heat so as to maintain work, materials, apparatus, and fixtures free from injury or damage. At the end of each day's work, cover new work likely to be damaged.

5. Provide and maintain adequate protection of the work from damage due to freezing, especially freezing earth and soils. Risk of proceeding with the work on or with freezing or frozen materials will be the sole responsibility of the Contractor.

6. Water Protection: Provide protection from damage at all times from rain water, ground water, backing up of drains or sewers, and other water. Provide pumps and equipment enclosures to provide this protection.

7. The Contractor will maintain free of obstructions and debris, all designated corridors and emergency exits, handicap access ramps and sidewalks to building. Provide temporary directional handicapped signage for routing to the nearest accessible facilities.

1.06 EXISTING FURNITURE AND EQUIPMENT

The Owner will remove or relocate existing movable furniture and equipment from the areas in which the Contractor is working. Notify the Owner not less than three days prior to starting work in areas where furniture and equipment require moving.

1.07 CONTRACTOR'S ACCESS PARKING AND STAGING AREAS A. Work included in this project will need to be performed within the limitations of available

access at the site. The University shall limit the area available for staging and parking due to the additional number of construction projects planned during the execution of this contract. Contractor shall adjust the means and methods of construction to allow for the restrictions surrounding the site.

Page 8: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUMMARY OF WORK 01020 - 4

B. All parking on campus except for some one-hour zones on city streets and a few metered spaces is under control and authority of the Parking and Transportation Services (PTS) of the University. All University parking is by permit only.

C. Types of parking and staging are defined as follows:

General Staging Areas are approved areas adjacent to the site when available or in University designated group staging yards. General Staging Areas may be used for any purpose, including employee parking, on a space available basis, but must be coordinated through the UCB Project Manager and PTS. Vehicles may not park outside of general staging areas except in areas coordinated and approved by PTS. Restricted Staging Areas are approved areas near the site for the construction dumpster, off-loading of equipment, contractor’s work trailer, and materials that are soon to be incorporated into the work. No vehicles shall park in a restricted staging area for more than 20 minutes between the hours of 8:00 a.m. and 5:00 p.m. weekdays. Contractor Employee Parking are areas for workers needing parking on campus. Coordinate through UCB Project Manager and PTS.

Prohibited Parking are areas designated in the Contract Documents as No Parking areas. The contractor shall not allow any parking in areas so designated under any circumstance.

D. The restrictions in this Section are in addition to any other restrictions or rules provided by

PTS. Fees shall be assessed for the use of any PTS facility for staging and construction activities.

1.08 OCCUPANCY REQUIREMENTS A. Owner may occupy designated areas for the purpose of storage of furnishings and

equipment and installation of equipment. B. Execute Certificate of Substantial Completion for each designated portion of work prior to

Owner occupancy. Contractor shall allow: 1. Access for Owner personnel. 2. Use of parking facilities. 3. Operation of HVAC and electrical systems. C. On occupancy, Owner will provide, for occupied areas: 1. Operation of HVAC and electrical systems. 2. Maintenance. 3. Security. 1.09 CONSTRUCTION AND SEQUENCE SCHEDULE:

A. In order to accommodate the uninterrupted operation of the existing building during the various phases of construction, the sequence of construction operations shall be as follows:

1. The sequence concept is to: (1) prepare the existing facility to function during Renovation hrough completion; (2) thence occupy the newly remodeled portion; and (3) upon completion, finally reoccupy the remodeled portions.

Page 9: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUMMARY OF WORK 01020 - 5

2. Utilizing this concept break down the Schedule into broad scope categories augmented by “Owner Action” and “Contractor action” columns that indicate coordination tasks which define the various phases of the work.

3. The intent of the categorization is to generally summarize the nature and extent of work to be performed without in any way limiting specific requirements of the Contract Documents.

4. Some overlapping between the several construction operations will occur, and where possible, permission may be granted to start certain portions of the work before the previous operations were completed in their entirety. Such detail scheduling shall be done as the work progresses, provided that the Owner’s operations remains uninterrupted, but in all cases must receive Owner approval.

5. Where it may not be possible to complete certain mechanical and electrical services in connection with making the work complete and ready for occupancy, temporary services as directed and as approved shall be installed to permit occupancy by the Owner at the earliest possible date.

6. The construction sequence schedule and related drawings are intended to aid the Contractor in bidding and in the preparation of a specific construction schedule. Deviations of sequence may be made upon approval of the Owner and the Architect. The preparation of a specific construction schedule remains the responsibility of the Contractor

1.10 TEMPORARY ELECTRIC SERVICE A. Connect to existing power service. Power consumption shall not disrupt owners need for

continuous service. Owner to pay for power consumed. Provide power outlets for construction operations, branch wiring, distribution boxes, and flexible power cords as required.

END OF SECTION

Page 10: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

ADMINISTRATION AND SUPERVISION 01020 - 1

SECTION 01020

ADMINISTRATION AND SUPERVISION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the contract, including General and Supplementary

Conditions and other Division 1 Specification sections, apply to work of this section. 1.02 SURVEYS, LAYOUTS, AND LEVELS A. General: Working from lines and levels established by the existing building, and as

shown in relation to the work, establish and maintain bench marks and other dependable markers to set the lines and levels for the work of construction as needed to properly locate every element of the work of the entire project. Calculate and measure required dimensions as shown (within recognized tolerances if not otherwise indicated); do not scale the drawings to determine dimensions. Continuously advise tradesmen performing the work of the marked lines and levels provided for use in the layout of work.

1.03 PROJECT RECORD DOCUMENTS A. Maintain at job site, one copy of: 1. Contract Drawings 2. Specifications 3. Addenda 4. Reviewed Shop Drawings 5. Change Orders 6. Other Modifications to Contract 7. Field Test Records 8. As-Built Drawings B. Maintain documents in clean, dry, legible condition and do not use record documents for

construction purposes. Make documents available at all times for inspection by the Consultant and Owner.

C. Label each document "Project Record" in 1" or larger printed letters. D. Record drawing information in colored pencil with different colors for the various systems

and defined by color legend. E. Record drawings and specifications shall include the following: 1. Location of internal utilities and appurtenances concealed in construction

referenced to visible and accessible features of structure. Location of concealed valves, dampers, controls, balancing devices, junction boxes, clean-outs, and other items requiring access or maintenance.

2. Field changes of dimension and detail, changes made by Change Order or Field Order and details not on original contract drawings.

3. Fire protection and alarm systems shop drawings.

Page 11: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

ADMINISTRATION AND SUPERVISION 01020 - 2

F. Submit all record drawings to the Consultant at the completion of the project. 1.04 CLEANING A. Cleaning and Protection Work: At the time each unit of work or element of the

construction is completed (substantially) in each area of the Project, clean the unit or element to a condition suitable for occupancy and use (as intended), and restore minor or superficial damage. Replace units and elements which are damaged beyond successful restoration. Clean and restore adjoining surfaces and other work which was soiled or damaged (superficially) during the installation; replace other work damaged beyond successful restoration. Where the performance of subsequent work could possibly result in damage to the complete unit or element, provide protective covering or other provisions to minimize possible damage. Repeat cleaning and protection operations during remainder of construction period, wherever work might otherwise be damaged by sustained soiling or exposure.

B. During Construction: Oversee cleaning and ensure that building, grounds, and public

properties are maintained free from accumulation of waste materials and rubbish. At reasonable intervals during daily progress of work, clean up site and access and dispose of waste materials, rubbish, and debris. Vacuum clean interior building areas when ready and continue vacuum cleaning on an as-needed basis until building is ready for acceptance or occupancy.

1.05 PROJECT SIGN

Erect no project sign or job-site sign of any kind, except warning signs as specified in Section 01500, without written authorization of the Owner.

1.06 COORDINATION A. The Contractor shall coordinate the work so as not to interfere with the building

custodian's normal cleanup activities. B. The Contractor shall be responsible for coordinating all the work of the project. The

Contractor shall coordinate the efforts of all subcontractor(s) and the deliveries of suppliers so that the work progresses in an orderly fashion without delay towards timely completion of a complete project in accordance with the drawings and specifications.

C. The Contractor shall note that concurrent with his work, other contractors, suppliers, and

the Owner's facilities and maintenance personnel may be working in relatively close proximity. The Contractor will be solely responsible for coordinating his work with that of other contractors and will make no claims for failure to do so.

1.08 METHODS OF CONSTRUCTION A. The procedure and method of construction is the prerogative and the responsibility of the

Contractor. If professional assistance is required to safely implement method of construction, the Contractor shall, on his own, employ professional help.

END OF SECTION

Page 12: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

ALLOWANCES 01021 - 1

SECTION 01021

ALLOWANCES PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Schedule of allowances. 2. Selection of products. 3. Adjustment of costs. 1.02 ALLOWANCES FOR PRODUCTS A. The amount of each allowance shall include: 1. The cost of the Product to the Contractor. 2. Delivery to the site. 3. Applicable taxes. 4. Handling at the site. 5. Protection. 6. Labor. 7. Contractor's and Subcontractor's overhead and profit. 8. Other expenses required to complete the installation. 1.03 SELECTION OF PRODUCTS UNDER ALLOWANCES A. Contractor's Duties: 1. Assist Owner in determining qualified suppliers or installers. 2. Obtain proposals from suppliers and installers. 3. Make appropriate recommendations. 1.04 ADJUSTMENT OF COSTS A. Should the net cost be more or less than the specified amount of the allowance, the

Contract Sum will be adjusted accordingly by Change Order. 1. The amount of the Change Order will recognize: a. Any changes in handling costs at the site. b. Labor. c. Installation costs. d. Overhead and profit. e. Other expenses caused by the selection under the allowance. B. Submit any claims for anticipated additional costs at the site. C. At contract close-out, reflect all approved changes in contract amounts in the final

statement of accounting. PART 2 - PRODUCTS Not Used

Page 13: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

ALLOWANCES 01021 - 2

PART 3 - EXECUTION 3.01 SCHEDULE OF ALLOWANCES

END OF SECTION

Page 14: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

UNIT PRICES 01026 - 1

SECTION 01026

UNIT PRICES PART 1 - GENERAL 1.01 GENERAL

Quantities indicated on the drawing or extra quantities specified shall be included in the Contractor's Base Bid. For Adding or Deducting from Base Bid quantities, the unit prices described in this section will be applied. The Contractor will be notified, in writing, of the quantities applicable for each unit price, and the Contract Price will be adjusted accordingly by Change Order. All unit prices shall include all labor, materials, equipment, services, delivery to the project, overhead, profit, insurance, and all other incidental expenses to complete the work specified unless indicated otherwise. All work covered by unit prices shall be performed in accordance with requirements of the applicable sections of the Specifications.

1.02 UNIT PRICES ITEM UNIT PRICE a. $ each b. $ each c. $ each d. $ each e. $ each f. $ each g. $ each h. $ each

END OF SECTION

Page 15: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

ALTERNATES 01030 - 1

SECTION 01030

ALTERNATES

PART 1 - GENERAL 1.01 GENERAL ALTERNATE REQUIREMENTS A. General: The description for each alternate is recognized to be incomplete and

abbreviated but implies that each change must be complete for the scope of work affected. Refer to applicable sections and to applicable drawings for the specific requirements of the owner, whether or not references are so noted in the description of each alternate. Modify surrounding work as required to integrate with the work of each alternate.

1.02 SPECIFIC ALTERNATES A. Add Alternates:

1. 2. 3. .

END OF SECTION

Page 16: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

PROJECT COORDINATION 01041 - 1

SECTION 01041

PROJECT COORDINATION

PART 1 - GENERAL 1.01 SUMMARY A. General Contractor is responsible for all of the work of this contract. 1. Assign and subcontract portions of the work as required to assure that all work is

constructed in compliance with these documents. 2. Coordinate the work of the several subcontractors for the project. 3. Coordinate work of this contract with work by separate contractors. B. Each subcontractor shall: 1. Coordinate work of his own employees and subcontractors. 2. Expedite his work to assure compliance with schedules. 3. Coordinate his work with that of other subcontractors and work by separate

contractor. 4. Comply with orders and instructions of owner. C. Related Requirements 1. All Division 1 Sections. 1.02 CONSTRUCTION ORGANIZATION AND START-UP A. Establish on-site lines of authority and communications. 1. Attend pre-construction meeting with subcontractors upon commencement of the

project. 2. Establish procedures for intra-project communications. a. Submittals. b. Reports and records. c. Recommendations. d. Coordination Drawings. e. Schedules. f. Resolution of conflicts. 3. Interpret Contract Documents. a. Consult with Architect to obtain interpretation. b. Assist in resolution of questions or conflicts which may arise. c. Transmit written interpretations to subcontractors, and to other concerned

parties. 4. Assist in obtaining permits and approvals. a. Obtain building permits and special permits required for work or for

temporary facilities. b. Verify that subcontractors have obtained inspections for work and for

temporary facilities. 5. Control the use of site. a. Supervise field engineering and site layout. b. Allocate space for each subcontractor's use for field offices, sheds, work

and storage areas. c. Establish access, traffic and parking allocations and regulations. d. Monitor use of site during construction.

Page 17: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

PROJECT COORDINATION 01041 - 2

1.03 CONTRACTOR DUTIES A. Construction Schedules. 1. Coordinate schedules with several subcontractors. 2. Monitor schedules as work progresses. a. Identify potential variances between schedules and probable completion

dates for each phase. b. Recommend adjustments in schedule to meet required completion dates. c. Adjust schedules of subcontractors as required. d. Document changes in schedule. 3. Observe work of each subcontractor to monitor compliance with schedule. a. Verify that labor and equipment are adequate for the work and the

schedule. b. Verify that product procurement schedules are adequate. c. Verify that product deliveries are adequate to maintain schedule. B. Process Shop Drawings, Product Data and Samples. 1. Review for compliance with Contract Documents. a. Field dimensions and clearance dimensions. b. Relation to available space. c. Relation to other trades, equipment and systems. d. Submit to Architect. C. Monitor the use of temporary utilities. 1. Verify that adequate services are provided and maintained. D. Inspection and Testing. 1. Inspection work to assure performance in accord with requirements of Contract

Documents. 2. Administer special testing and inspections of suspected work. 3. Reject work which does not comply with requirements of Contract Documents. 4. Coordinate testing laboratory services. a. Verify that required laboratory personnel are present. b. Verify that tests are made in accordance with specified standards. c. Review test reports for compliance with specified criteria. d. Recommend and administer required retesting. E. Monitor contractor's periodic cleaning. 1. Enforce compliance with specifications. 2. Resolve any conflicts. F. Coordinate changes. 1. Recommend necessary or desirable changes. 2. Assist owner in negotiating change orders. 3. Promptly notify all subcontractors of pending changes. G. Maintain Reports and Records at Job Site available to Architect and Subcontractors. 1. Log progress of work of each subcontractor. 2. Records a. Contracts. b. Purchase orders.

Page 18: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

PROJECT COORDINATION 01041 - 3

c. Materials and equipment records. d. Applicable handbooks, codes and standards. 3. Obtain information from subcontractors and maintain file of Project Record

Documents. 4. Assemble documentation for handling of claims and disputes. H. Coordinate work of this Contract and requirements of this section with work by Separate

Contract including but not limited to: 1. Removal of asbestos containing materials by separate contract. 1.04 CONTRACT CLOSEOUT A. Coordinate equipment start-up. 1. Provide seven days notification prior to start-up of each item. 2. Ensure that each piece of equipment or system is ready for operation. 3. Execute start-up under supervision of responsible persons in accordance with

manufacturer's instructions. 4. Perform required testing and balancing. 5. Record dates of start of operation of systems and equipment. Submit written

report that equipment or system has been properly installed and is functioning correctly.

6. Provide written notice of beginning of warranty period for equipment put into service. B. Demonstration and Instructions 1. Demonstrate operation and maintenance of products to Owner's personnel two

weeks prior to Substantial Completion. 2. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing,

maintenance, seasonal operation, and shutdown of each item of equipment. C. At completion of work of each Section, conduct an inspection to assure that 1. Specified cleaning has been accomplished. 2. Temporary facilities have been removed from site. D. At completion 1. Conduct an inspection to list work to be completed or corrected. 2. Supervise correction and completion of work as established in Certificate of

Completion. E. When a portion of the Project is occupied prior to final completion, coordinate established

responsibilities of each subcontractor. F. Final completion. 1. When each Subcontractor determines that work is finally complete, conduct an

inspection to verify completion of work. 2. Assist owner and architect in inspection. G. Administer contract closeout. 1. Receive and review Subcontractor's final submittals. 2. Transmit to architect with recommendation for action.

END OF SECTION

Page 19: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

MECHANICAL AND ELECTRICAL COORDINATION 01042 - 1

SECTION 01042

MECHANICAL AND ELECTRICAL COORDINATION

PART 1 - GENERAL 1.01 SUMMARY A. Carefully coordinate the interface between Division 15 (Mechanical) and Division 16

(Electrical) before submitting any equipment for review or commencing installation. B. Responsibility: Unless otherwise indicated, all motor and controls for Division 15

equipment shall be furnished, set in place and wired in accordance with the following schedule:

ITEM

FURNISHED

UNDER

SET IN

PLACE

UNDER

POWER

WIRING

UNDER

CONTROL

WIRING

UNDER

Equipment Motor

15

15

16

-

Automatically Controlled

Starter/contractors:

Separate

Factory Mounted &

Wired

In Motor Control Centers

15

15

16

16

15

16

16

16

16

15

15

16

Manually Controlled

Starter/Contractors:

Separate

Factory Mounted &

Wired

15

15

16

15

16

16

15

15

Motor Speed Controllers

15

16

16

16

Disconnect (Note 1) Switches

16

16

16

-

Contactors

16

16

16

-

Thermal Overload (Note 1)

Switches

16

16

16

-

Manual Operation (Note 2)

16

16

16

-

Switches

16

16

16

-

Page 20: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

MECHANICAL AND ELECTRICAL COORDINATION 01042 - 2

Control Relays (Note 2)

15

15

-

15

Control Transformers

15

15

16

15

Control Circuit Outlets

16

16

16

-

Thermostats (Note 2)

15

15

-

15

Page 21: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

MECHANICAL AND ELECTRICAL COORDINATION 01042 - 3

ITEM

FURNISHED

UNDER

SET IN

PLACE

UNDER

POWER

WIRING

UNDER

CONTROL

WIRING

UNDER

Time Switches (Note 2) Not in

Control Panel

15

15

16

15

Push Button Stations, Pilot

Lights

16

16

16

16

Thermostats (Note 2)

Controls: Integral with

Equipment or Directly

Applied to Ducts, Pipes, etc.

15

15

16

15

Valve Motors, Damper Motors,

Solenoid

Valves, etc.

15

15

-

15

EP Valves or Switches, P.E.

Switches, etc.

15

15

-

15

Control Circuit Outlets

16

16

16

-

Fire Alarm Systems

16

16

16

16

Fire Sprinkler Alarm

16

16

-

16

Firestats

16

16

- 16

Smoke Detectors Including

Relays for

Fan Control

16

16

-

16

Control Air Compressor

15

15

16

15

Refrigerated Air Dryer

15

15

16

15

Equipment Interlocks

15

15

-

15

Boiler and Water Heaters

15

15

16

15

NOTES: 1. If furnished as part of factory wired equipment furnished and set in place under

Division 15, wiring and connections under Division 16. 2. If float switches, line thermostats, P.E. switches, time switches, or other controls

carry the FULL LOAD CURRENT to any motor, they shall be furnished under Division 15, but they shall be set in place and connected under Division 16 except that where such items are an integral part of the mechanical equipment, or directly attached to ducts, piping, or other mechanical equipment, they shall be set in place under Division 15 and connected under Division 16. If they do not

Page 22: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

MECHANICAL AND ELECTRICAL COORDINATION 01042 - 4

carry the FULL LOAD CURRENT to any motor, they shall be furnished, set in place and wired under Division 15.

C. Control Wiring: Consists of wiring in pilot circuits of contact or starters, sensors,

controllers, and relays, and wiring for valve and damper operators. 1. Connections: Connections to all controls directly attached to ducts, piping and

mechanical equipment shall be made with flexible connections. D. Starters: Provide magnetic starters for all three phase motors and equipment complete

with: 1. Control transformers. 2. 120V holding coils. 3. Integral hand-off-auto switch. 4. Auxiliary contacts required for system operation plus one (1) spare. E. Remote Switches and Push Button Stations: Provide all remote switches and/or push

button stations required for manually operated equipment (if no automatic controls have been provided) complete with pilot lights of an approved type lighted by current from load side of starter.

F. Special Requirements: Motors, starters and other electrical equipment installed in moist

areas or areas of special conditions, such as explosion proof, shall be designed and approved for installation in such areas with appropriate enclosure.

G. Identification: Provide identification of purpose for each switch and/or push button station

furnished. Identification may be either engraved plastic sign or permanent mounting to wall below switch, or stamping on switch cover proper. All such identification signs and/or switch covers in finished areas shall match other hardware in the immediate areas.

H. Control Voltage: 1. Maximum allowable control voltage 120V. Fully protect control circuit conductors

in accordance with National Electrical Code. 2. Provide 20A breakers in emergency panels under Division 16 as required for

Building Management System Air Temperature Controls (BMS/ATC). Provide all control transformers, control wiring and connections to circuits under Section 15950 of Division 15.

I. Related Requirements 1. Section 16480: Electric Motors a. Coordinate with efficiency requirements. J. Contractor must review all concrete embedded items (including conduit) with owner prior

to placement.

Page 23: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

MECHANICAL AND ELECTRICAL COORDINATION 01042 - 5

PART 2 - PRODUCTS 2.01 MOTOR HORSEPOWER A. In general, all motors 1/2 HP and above shall be three phase, all motors less than 1/2 HP

shall be single phase. B. Voltage and phase of motors as scheduled on the electrical drawings shall take

precedence in the case of a conflict between the mechanical and electrical drawings or General Condition 2.01 A., above.

C. Work under Division 15 includes coordinating the electrical requirements of all

mechanical equipment with the requirements of the work under Division 16, before ordering the equipment.

1. If motor horsepower is changed under the work of Division 15, without a change in duty of the motor's driven device, coordination of additional electrical work (if any) and additional payment for the work (if any) shall be provided under the section of Division 15 initiating the change. Increases or decreases in motor horsepower from that specified shall not be made without written approval from the Engineer.

PART 3 - EXECUTION NOT USED.

END OF SECTION

Page 24: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CUTTING AND PATCHING 01045 - 1

SECTION 01045

CUTTING AND PATCHING

PART 1 - GENERAL 1.01 DESCRIPTION A. Work Included: This section establishes general requirements in addition to those

indicated in the General Conditions of the Contract for Construction pertaining to cutting, fitting, and patching of the work required to:

1. Make the several parts fit properly. 2. Uncover work to provide for installation, inspection, or both, of ill-timed work. 3. Remove and replace work not conforming to requirements of Contract

Documents. 4. Patch new construction into existing construction. B. Related Work: 1. In addition to requirements specified, upon the Consultant's request, uncover

work to provide for inspection of covered work, and remove samples of installed materials for testing.

2. Do not cut or alter work performed under separate contract without the Consultant's written permission.

1.02 QUALITY ASSURANCE A. Perform all cutting and patching in strict accordance with pertinent requirements of the

Specifications and, in the event no such requirements are determined, in conformance with the Consultant's written direction.

1. Use skilled workmen to perform all cutting and patching work. 2. Use methods least likely to damage existing surfaces and materials to remain,

while providing proper surfaces to receive installation of repair, patching, and/or new work.

B. Visual Quality: 1. Do not cut and patch work exposed to public view, and the exterior and/or interior

of the building in a manner that will result in an unacceptable appearance as determined by the Consultant.

2. Do not cut and patch work in a manner that will result in obvious appearance that cutting and patching work was done.

3. When cutting existing structural concrete, do not extend saw cuts beyond the corners of the required opening on either side of the opening.

1.03 EXISTING CONSTRUCTION A. Where cutting and patching of existing construction is required; prior to start of work,

inform Owner of existing construction to be disturbed. Owner will determine if elements of existing construction contain asbestos. Do not proceed with work until after Owner has examined areas to be disturbed. Refer to Exhibit A, Project Pre-Inspection for Possible Presence of Asbestos for additional information concerning the possible presence of materials containing asbestos.

Page 25: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CUTTING AND PATCHING 01045 - 2

1.04 SUBMITTALS A. Submit proposed cutting and patching procedures in writing for the following categories of

work prior to proceeding with this work: 1. Cutting new openings in existing structural concrete walls, parapets, and

suspended slabs. 2. Cutting new openings in existing roofs and roofing materials. B. Submittals shall comply with Section 01300. PART 2 - PRODUCTS 2.01 MATERIALS A. Except as otherwise indicated in pertinent sections of these specifications, or as directed

by the Consultant, use materials which are identical to existing materials in workmanship, appearance, and performance.

B. If identical materials are not available, match existing as closely as possible, especially

existing visual characteristics. PART 3 - EXECUTION 3.01 INSPECTION A. Before proceeding, inspect existing conditions, including elements subject to movement

or damage during cutting, excavating, backfilling, and patching. B. After uncovering the work, inspect conditions affecting installation of new work. C. If uncovered conditions are not as anticipated or if existing construction is not as indicated

on the Drawings, immediately notify the Consultant for further instructions. 3.02 PREPARATION A. Provide shoring, bracing, and support as required to maintain structured integrity of the

project. B. Take all necessary action required to protect adjacent existing surfaces from damage due

to the work of this section. C. Take all precautions necessary to protect existing surfaces and materials, new work, and

the work of this section from damage due to adverse weather conditions. D. Provide temporary support of work to cut and adjacent work to prevent failure or damage

due to the work of this section. E. Properly prepare substrate surfaces exposed during cutting as required to receive the

work of this or other sections of these specifications in strict compliance with manufacturer's recommendations and these specifications.

Page 26: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CUTTING AND PATCHING 01045 - 3

3.03 EXECUTION A. Perform all required cutting and patching as required or reasonably implied under

pertinent sections of these specifications.

B. Perform cutting and demolition by methods which will prevent damage to other portions of the work and will provide proper finished installation complying with the specified tolerances and finishes.

3.04 PERFORMANCE A. Execute cutting and demolition by methods which will prevent damage to other work, and

will provide proper surfaces to receive installation of repairs and new work. Saw-cut and otherwise isolate areas to be demolished.

B. Repair or otherwise rebuild and/or construct all surfaces affected by cutting and

demolition. Execute fitting and adjustment of products to provide totally finished installation to comply with tolerances, finishes, and profiles of adjacent surfaces, whether new or existing.

C. Restore work which has been cut or exposed by demolition; install new construction in

compliance with specifications for type of new work to be done or as required to match existing adjacent surfaces. In no case shall any exposed existing surface be left in a raw, marred, or unfinished surface.

D. Refinish entire surfaces as necessary to provide an even finish. 1. Continuous Surfaces: To nearest intersections. 2. Assembly: Entire refinishing.

END OF SECTION

Page 27: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

REGULATORY REQUIREMENTS 01060 - 2

SECTION 01060

REGULATORY REQUIREMENTS

PART 1 - GENERAL 1.01 RELATED DOCUMENTS: A. Drawings and general provisions of the Contract, including General Conditions and other

Division 1 - Specification sections, apply to work of this section. 1.02 SUMMARY: A. Section Includes: 1. General administrative requirements and procedures and related applicable codes. 1.03 APPROVAL AND RECOMMENDATION AGENCIES: A. The University of Colorado at Boulder has jurisdiction for the interpretation and

enforcement of code requirements for construction of projects. 1.04 CODES: A. All Contractors shall comply with all applicable codes, ordinances and regulations in effect

at the time of bid openings.

APPROVED STATE BUILDING CODES The following approved building codes and standards have been adopted by State Buildings Programs (SBP) as the minimum requirements to be applied to all state-owned buildings and physical facilities including capital construction and controlled maintenance construction projects.

https://www.colorado.gov/pacific/sites/default/files/approvedstatebldgcode.pdf https://www.colorado.edu/fm/planning-design-construction/design-construction/building-construction-standards

• Adopted Codes & Standards • Code Review System/Format for UCB Projects • City of Boulder Amendments to the IFC

1.05 OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA): A. The Contractor shall have sole responsibility for compliance on the job site to all

applicable portions of the Occupational Safety and Health Act. The Contractor is responsible for other regulatory requirements as they relate to occupational Health and Safety requirements. For example, NIOSH, ANSI, and MSA.

B. Protection of life, health and public welfare as it relates to the execution of the

construction contract is the responsibility of the Contractor. The Owner’s Representative may, at their discretion, observe, inspect, or comment on plans, procedures, or actions employed at the project as they relate to safety of life, health or public welfare. If conditions are imposed by the Owner which interfere with, or imply actions detrimental to

Page 28: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

REGULATORY REQUIREMENTS 01060 - 3

safety, written notice shall be returned to the Owner for action prior to affecting any unsafe conditions.

C. Contractors shall use OSHA Lock Out / Tag Out procedures when working with energized

equipment.

D. All contractors entering confined spaces owned by CU or while conducting work under contract with CU shall develop a written program and utilize procedures that, at a minimum, comply with all federal, state and local confined space standards and all applicable regulatory requirements. Contractors shall, independent of the University, monitor the space to obtain their own data to ensure a safe entry and exit. Any data generated by a contractor’s confined space entry, should be provided to the Facilities Management confined Space Program Manager.

E. When contractors perform work that may involve Facilities Management controlled permit

required confined spaces, Facilities Management will: 1. Inform contractors of permit required confined spaces and that entry is allowed

only after compliance with the confined space entry standard; 2. Require contractors planning to enter a confined space to provide the Facilities

Management Confined Space Program Manager in charge of that space, 48-hour advance notice of such planned entry. The contractors entry will be in accordance with the current Occupational Safety and Health Administration confined space entry standard and a signed document stating such, shall be provided to the FM Confined Space Program Manager prior to entry.

F. The FM Confined Space Program Manager, following receipt of notice of contractor

planned entry, will: 1. Apprise contractor of the hazards identified in the confined space and of any prior

experience that is documented on the space; 2. Appraise the contractor of any precautions or procedures that CU has

implemented for the protection of workers in or near the confined space; 3. Coordinate entry operations with the contractor when both Facilities Management

and contractor personnel are working in or around the confined space; 4. Debrief the contractor at the end of the entry operations regarding hazards

confronted or created. 1.06 HOT WORK PERMITS A. All contractors shall be required to obtained a Hot Work Permit, three (3) working days in

advance, for work that involves welding, heat treating, grinding, thawing pipe, hot riveting, soldering and brazing, power driven fasteners and similar activities involving spark, flame or heat. Compliance with the requirements of the applicable fire code, the International Building Code, and NFPA Standard 51B are mandatory and all contractors performing hot work activities shall read and understand these code requirements. To obtain a current Hot Work Permit, go to website:

http://fm.colorado.edu/firesafety/hotwork.html B. Contractors shall read and comply with the procedures and requirements for Fire Watch,

Fire Alarm Interruption and Fire Suppression Interruption as found on the following websites:

Fire Watch Procedures: http://fm.colorado.edu/firesafety/firewatch.html Fire Alarm and Detection System Interruption/Outage: http://fm.colorado.edu/firesafety/firealarmdetectsys.html Fire Suppression System Interruption/Outage:

http://fm.colorado.edu/firesafety/firesupressionsystems.html

Page 29: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

REGULATORY REQUIREMENTS 01060 - 4

C. No hot work shall be conducted in any campus facility without a hot work permit. Any person or firm who conducts hot work without a permit shall be fined one thousand dollars ($1,000) for each occurrence and their non-permitted activities shall be stopped immediately until they obtain a hot work permit. Contractor shall be responsible for any damages caused as a result of improper hot work activities or the work stoppage.

D. Individuals or firms who obtain a permit shall fully read, understand and implement the

requirements of the permit. Any person or firm who conducts hot work without the full implementation of the permit requirements shall be fined five hundred dollars ($500) the first time and one thousand dollars ($1,000) for subsequent occurrences. When the requirements of the hot work permit are not being implemented, the improper activities shall be stopped immediately until a hot work permit is obtained. Contractor shall be responsible for any damages caused as a result of improper hot work activities or the work stoppage. Any contractor who is found to be in non-compliance a third time, will not be allowed to work on campus until further notice by Facilities Management.

E. The campus inspectors, project managers and fire marshal shall have the authority to

stop improper or non-permitted hot work activities. F. The Contractor shall notify the CU Fire Alarm Supervisor to deactivate all smoke alarms

in the vicinity of the work prior to any demolition and construction work activity. Failure of the Contractor to comply with the smoke alarm deactivation requirement and cause a false alarm and arrival of the Boulder Fire Department shall be a $400 fine per occurrence.

1.07 PERMITS A. The contractor must obtain a no fee building permit prior to starting work from Office

Manager, Facilities Management at (303) 492-2904 in the Planning, Design and Construction Office, Research Laboratory No. 2, 1540 30th Street, Boulder, Colorado. Building permits are required on all projects except those work items specifically exempted by Section 105 of IBC

B. The contractor must post the permit(s) in a prominent location at the jobsite including all

inspection reports. The contractor shall have an updated set of contract documents available at the jobsite for all inspections.

1.08 INSPECTIONS

A. The Contractor must schedule all required inspections 48 hours in advance by calling (303) 492-2922. CU or their designated inspectors will complete these inspections within 48 hours with the exception of weekends and state holidays.

B. The contractor is required to arrange for the following inspections:

1. Required inspections: General. Reinforcing steel or structural framework of any part of any building of structure shall not be covered or concealed without first obtaining the approval of the building official.

2. Lath or gypsum board inspection: To be made after lathing and gypsum board, interior and exterior, is in place, but before any plastering is applied or before gypsum board joints and fasteners are taped and finished.

3. Final inspection: To be made after finish grading and the building is completed and ready for occupancy.

4. Special inspection: Special inspection may be required on special projects and special types of construction.

5. Re-inspections: A re-inspection fee may be assessed for each inspection or reinspection when such portion of work for which inspection is called is not complete or when corrections called for are not made.

Page 30: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

REGULATORY REQUIREMENTS 01060 - 5

C. The Contractor will be responsible for all cost related to re-inspections and will be billed at a rate of $50.00 per hour for CU re-inspections and at the testing agency bill-out rate for other re-inspections.

1.09 UNIVERSITY OF COLORADO SEXUAL HARASSMENT POLICY

A. Contractors should be aware of and review the University of Colorado at Boulder’s policies that prohibit discrimination and harassment on the basis of race, color, national origin, sex, age, disability, creed, religion, sexual orientation or veteran status. These policies are located on the web at: http://www.colorado.edu/odh/ Contractor personnel must adhere to these policies and conduct themselves in a manner that does not discriminate or harass as a result of interacting with an around the University of Colorado faculty, staff and students and visitors.

1.10 FIRE ALARM INTERRUPTION A. Contractor shall contact CU Fire Alarm Systems Supervisor at 303-492-0633 prior to all

interruptions or shutdowns of fire alarm systems. Interruptions or shutdowns shall be scheduled three (3) working days in advance with CU Fire Alarm Systems Shop, CU Project Manager and building proctor. Contractor shall provide a fire watch as directed by CU Fire Alarm Systems Shop during interruption or shutdown.

B. The Contractor shall be responsible for preventing nuisance alarm due to activities at their

work site. Common sources of nuisance alarms are: 1. Smoke (soldering, welding, cooking, etc.) 2. Grinding 3. Dust (drilling, sweeping, canister vacuums, sand blasting, etc.) 4. Water leaking (plumbing leaks, overflows) 5. Water sprayed on or near detectors (pressure washing or cleaning with water) 6. Popcorn or other food burning in microwaves 7. Static electricity (covering or uncovering detectors) 8. Changing filters on air handling units (dust) 9. Steam (leaks, pressure pop-offs) 10. Broken or frozen sprinkler heads 11. Sprinkler drain valves turned by mistake 12. Vandalism

Precautions to prevent nuisance alarms are:

1. During construction projects, treat all buildings, except totally new construction, as though they were occupied buildings with live systems.

2. Do not assume that all detectors are in plain sight. Contact University personnel for verification.

3. Maintain dust control measures per UCB Standards: a. Maintaining barriers b. Covering air returns c. Asking CU personnel to cap or disable smoke detectors (Note any

capping or disabling of fire safety devices is to be done ONLY by CU personnel, not contractors.)

d. Avoiding recirculation of dust or smoke through the building air handling system.

4. Follow campus hot work procedures. Refer to specification Section 01060, paragraph 1.06.

3. Do not expose fire alarm devices to water or extreme temperatures. 4. Contact Fire Systems Group for any actions that affect fire detection, alarm, and

suppression systems.

Page 31: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

REGULATORY REQUIREMENTS 01060 - 6

1.11 STORMWATER MANAGEMENT PLAN (SWMP) A. Stormwater Management Plan (SWMP): Prior to any construction activity disturbing one

acre of land or more, an approved SWMP and a Stormwater Permit for Construction Activity application from the Colorado Department of Public Health and Environment (CDPHE) are required. The SWMP shall be prepared in accordance with the CDPHE requirements for “Contents of the Stormwater Management Plan” and the UDFCD’s Urban Storm Drainage Criteria Manual, Volume 3, “Best Management Practices” (UDFCD Drainage Criteria Manual). Stormwater quality management and erosion control measures are to be constructed and maintained in accordance with the SWMP and the UDFCD Drainage Criteria Manual.

1.12 ENVIRONMENTAL/STORMWATER POLLUTION PREVENTION

A. Contractors working on the UCB campus must comply with all applicable University, City,

State and Federal environmental regulations and standards. The contractor shall keep material such as saw-cut slurry, drywall mud, grout and mortar, paint, sediment, and all other wastes and process water out of gutters, streets, storm drains and parking lots. The contractor shall also be responsible for proper disposal of all waste materials. Immediately notify 911, EH&S 303-492-6025 and project manager of accidental hazardous materials releases.

B. Contractors are required to locate drains or other water discharge points in the area of the

project and provide measures to protect from illicit discharges, prior to construction activities. For assistance with determining where a drain leads to (storm vs. sanitary, especially floor drains), contact the Facilities Management service center at 303-492-5522.

C. The contractor shall be responsible for all costs associated with damages and clean-up

as a result of contractor caused illicit discharges of process water or other materials into the storm water system. Also, in addition to any penalties or fines imposed by the City, State or Federal agencies, the contactor shall be fined one thousand dollars ($1,000) by UCB for the first time an incident occurs and may be put on probation from working on campus. The contractor will be prohibited from working on campus, until further notice by UCB, if they are found to be responsible for an illicit discharge a second time.

D. For the purpose of eliminating storm water pollution, the contractor shall implement

effective Best Management Practices (BMPs). BMPs include general good housekeeping practices, appropriate scheduling of activities, operational practices, maintenance procedures and other measures to prevent the discharge of pollutants directly or indirectly to the storm water system. These BMPs shall be maintained for the duration of the contractor's work. Contractors are required to visit website: http://www.bouldercolorado.gov/www/pace/government/index.html for examples of BMP’s that are applicable to project activities. The Contractor shall ensure that all applicable employees and sub-contractors who work on site are trained and comply with storm water pollution prevention methods and proper BMP’s.

E. In addition to the BMP’s the contractor will be required to sign an Environmental Responsibilities form for all projects. The contractor shall post a copy of this form on site, throughout the duration of the project, in a visible area for all workers to see. Also, the contractor will be required to fill out a Pre-Construction Water Quality Certification form indicating any/all potential discharges of process water, chemicals, de-watering, or other materials to sewer systems or landscape areas that are expected to result from project activities.

1.13 UTILITY LOCATES

Contractor MUST CALL 811 (or 1-800-922-1987) for utility locates BEFORE DIGGING on any project at the University of Colorado at Boulder. This includes even small projects such as, but

Page 32: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

REGULATORY REQUIREMENTS 01060 - 7

not limited to, planting trees or shrubs, sidewalk removal/installation or fence post installation. Digging without calling can disrupt service to the campus or surrounding neighborhoods and potentially result in fines and repair costs.

END OF SECTION

Page 33: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SPECIFICATION SYSTEM 01075 - 1

SECTION 01075

SPECIFICATION SYSTEM

PART 1 - GENERAL 1.01 SUMMARY A. Work Included: 1. Specification system format. 2. Grammar (syntax) description. 1.02 DESCRIPTION A. These specifications have been derived from automated specification systems, and

include minor deviations from format and traditional writing forms. Such deviations must be recognized as a normal result of this production technique, and no other meaning will be implied or permitted.

B. Imperative language of the technical sections is directed to the Contractor. The term

"provide" used repeatedly in the text is defined to mean..."furnish and install, complete, in place and ready for operation and use unless specifically indicated otherwise."

C. Specifications are of abbreviated, simplified or streamlined type and include incomplete

sentences. Omissions of work or phrases such as "the Contractor shall”, "in conformity therewith," "shall be," "as noted on the Drawings", "A", "The", are intentional. Supply omitted words or phrases by inference in same manner as they are when "Note" occurs on Drawings. Supply words "on the Drawings" by inference when "as indicated" is used with sentences or phrases.

PART 2 - PRODUCTS Not used PART 3 - EXECUTION Not used

END OF SECTION

Page 34: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SPECIAL PROJECT PROCEDURES 01100 - 1

SECTION 01100

SPECIAL PROJECT PROCEDURES

PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Remodel Work scheduling. 2. Construction sequence scheduling. B. Related Sections: 1. Section 01500 - Temporary Facilities and Controls. 1.02 SYSTEM DESCRIPTION A. An essential condition of this Contract shall be the scheduling and conduct of all phases

of construction operations in such a manner that the Owner's operations and use of the existing buildings and campus shall be uninterrupted at all times, except for such limited interruption as is required and approved by the owner.

B. Contractor shall repair at his own expense all damage done to Owner's property,

unknown utilities and adjoining public property as a result of Contractor's construction activities.

1.03 PROJECT/SITE CONDITIONS A. Access and use of site: 1. Contractor shall use the designated site access for construction offices and

material storage in such a manner that access to existing buildings and campus remain accessible at all times for use.

2. Confine operations to as limited a use of the existing building and campus as possible. A route of access to and from the work for employees shall be agreed upon and it shall be the Contractor's responsibility to see that the agreed route is maintained in order to prevent unwarranted or unnecessary traffic through the existing buildings or site.

B. Owner notice and approval: 1. All arrangements and scheduling in connection with the work of this Contract shall

be made with and subject to the approval of the Consultant and the Owner. 2. All work under this Contract which will require interruption of service of the

existing building shall be scheduled to suit the need and convenience of the Owner's operation, and arrangements shall be made with the Owner and the Architect at least eight (8) working days in advance of the start of such work.

PART 2 - PRODUCTS Not Used

Page 35: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SPECIAL PROJECT PROCEDURES 01100 - 2

PART 3 - EXECUTION 3.01 REMODELING A. Construction activities of all areas to be constructed in existing facilities shall be

completely separated from the rest of the building by dust-proof enclosures erected by Contractor.

B. All surfaces in existing facilities not indicated to be remodeled, or removal of existing

items by any Contractor, shall be repaired by the responsible Contractor to match existing adjoining similar surfaces.

3.02 CLEAN-UP A. All areas within existing facilities, which are not within enclosed areas to be constructed

used for access to work areas shall be completely cleaned of all debris and made "broom-clean" at the end of each day's work.

B. Dust, which permeates areas of existing facilities because of improperly constructed dust-

proof barriers, shall be the responsibility of the Contractor. The Contractor shall employ the services of a professional cleaning company to clean any area outside of the designated construction dust barriers that are contaminated by Contractor’s operations. Completely clean all such areas to the satisfaction of the Owner at no additional cost.

END OF SECTION

Page 36: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

HAZARDOUS MATERIAL PROCEDURES 01121 - 1

SECTION 01121

HAZARDOUS MATERIAL PROCEDURES

PART 1 - GENERAL 1.01 RELATED DOCUMENTS: A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 1 - Specification sections, apply to work of this section. 1.02 SUMMARY: A. Section Includes: 1. General administrative requirements and procedures for Hazardous

Communication Program. B. Related Sections: 1. Summary of Work: Section 01010. 1.03 WORK BY OWNER:

A. Asbestos: 1. Pursuant to Colorado Department of Public Health and Environment, Air Quality

Control Commission Regulation No. 8 Part B – Asbestos, Section V.H.1.d, the undersigned Architect/Engineer and Contractor, as duly authorized representatives for their firms, hereby certify that to the best of his/her knowledge, information and belief, the materials incorporated into the project, and as used during the construction process, are free of any type of asbestos containing materials (ACM). The undersigned acknowledge that not all asbestos building materials have or were ever completely banned (EPA/TSCA-1999).

2. The Owner has completed an Environmental Site Assessment to identify

asbestos containing materials and other immediate Health and Safety items. Do not begin work until Form Exhibit A (copy following the Supplementary General Conditions) has been executed. Where asbestos materials or other hazardous conditions are known to exist in locations affected by this project, remediation measures will be taken by the Owner under separate contract. The Contractor shall coordinate his sequence and schedule with that of the environmental remediation work.

3. In the event that the Contractor encounters any material on the site which is

reasonably believed hazardous, which has not been rendered harmless, the Contractor shall:

a. Stop work immediately in affected areas. b. Report the condition in writing to the Department of Facilities

Management Project Administrator. c. Report the condition in writing to the Architect. d. Resume work only under the provisions of this section. 1.04 SUBMITTALS: A. Material Safety Data Sheets (MSDS): 1. Copies of all material safety data sheets for all applicable products, including but

not limited to; paint, adhesives, mastics, solvents, and finishes, etc., shall be retained on site by the Contractor for all applicable products used during the construction and/or remodeling work. Furnish copies of all MSDS’s to the Owner and Architect and include in the Project Record Document submittal.

Page 37: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

HAZARDOUS MATERIAL PROCEDURES 01121 - 2

1.05 QUALITY ASSURANCE: A. Asbestos containing materials may exist within the general project area where such

materials are not expected to be disturbed during the work. The Contractor shall review the Environmental Health and Safety Environmental Site Assessment Form at the project site and become familiar with known asbestos and hazardous containing materials in the work areas.

1.06 PROJECT/SITE CONDITIONS: A. Hazard Communication Requirements: 1. All Contractors are responsible for compliance with mandatory federal rules and

regulations concerning Hazard Communication, including, but not limited to those regulations contained in 29 CFR 1910.1200 Hazard Communication, 1910.146 Confined Space, 1910.147 Lock-out Tag-out, 1910.1101 Asbestos, and 1926.62 Lead. Contractor and all subcontractors working at sites under the control of the Owner shall make available to the Architect, upon request, copies of the Hazard Communication Program used by their firm. In addition to this requirement, all regulations related to Multi-employer workplaces shall be adhered to. These regulations are found in 29 CFR 1910.1200, (e) (2) (I) through (e) (4) specifically:

(e) (2) Multi-employer workplaces. Employers who produce, use, or store hazardous chemicals at workplace in such a way that employees of other employer(s) may be exposed (for example, employees of a construction contractor working on site) shall additionally ensure that the hazard communication programs developed and implemented under paragraph (e) include the following:

(e) (2) (i) The methods the employer will use to provide the other employer(s) with a copy of the material safety data sheet, or to make it available at a central location in the workplace, for each hazardous chemical the other employer(s)’ employees may be exposed to while working;

(e) (2) (ii) The methods the employer will use to inform the other employer(s) of any precautionary measures that need to be taken to protect employees during the workplace’s normal operating conditions and in foreseeable emergencies; and,

(e) (2) (iii) The methods the employer will use to inform the other employer(s) of the labeling system used in the workplace (e) (3) The employer may rely on an existing hazard communication program to comply with these requirements, provided that it meets the criteria established in this paragraph (e). (e) (4) The employer shall make the written hazard communication program available, upon request, to employees, their designated representatives, the Assistant Secretary and the Director, in accordance with requirements of 29 CFR 1910.20 (e).

2. The referenced regulations were excerpted from 29 CFR 1910.1200. This excerpt shall not be relied upon for compliance with mandatory federal, state and local regulations. The Contractor shall comply with all such regulations and shall be solely liable for insuring that all requirements under applicable regulations are met.

PART 2 - PRODUCTS (Not applicable)

Page 38: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

HAZARDOUS MATERIAL PROCEDURES 01121 - 3

PART 3 - EXECUTION 3.01 EXAMINATION: A. Asbestos and Hazardous Materials Discovery: 1. The Contractor is cautioned to be alert to the possibility that his work may

uncover asbestos- containing or hazardous materials. If suspected materials are found, the Contractor shall notify the Owner and stop all work in the area immediately. If the suspected materials prove to contain asbestos or hazardous materials, the Owner will arrange to have the materials abated in a timely manner.

3.02 HAZARDOUS MATERIALS/EQUIPMENT REMOVAL: A. Definition: 1. Removal of hazardous materials/equipment is extremely dangerous. Hazardous

materials/equipment is defined to include, but not limited to the following: a. Fume hoods

b. Hood exhaust duct work c. Exhaust fans d. Laboratory casework and equipment e. PCB ballast’s f. Mercury and Sodium Vapor Lights g. Adjacent material that could come in contact with workers or public.

B. Protection:

1. Hazardous materials/equipment removal shall include the protection of personnel, material, environment and safe legal disposal of the equipment; and further includes the following: a. Notification of Project Administrator and appropriate Environmental

Health and Safety Unit b. Proper protective clothing for personnel involved in the removal. c. Appropriate emergency and first aid facilities. d. Removal procedures shall be accomplished during minimal occupancy of

the remainder of the building on the weekends or at night. C. Disposal:

1. All equipment related to the use, storage or processing of hazardous materials/equipment shall be removed and properly disposed of under the direct, full-time supervision of a qualified Laboratory Specialist fully conversant with the chemistry and properties of the material/equipment involved. Certification is required. Contractors are responsible for the removal of all hazardous materials/equipment and chemicals from the work site as well as proper disposal of all hazardous waste generated by their project.

2. Hazardous waste disposal must include prior notification to the Department of

Environmental Health and Safety in order to verify that the appropriate procedures and documentation are used. Copies of all paper work for shipping and disposing of these materials (hazardous waste manifests, land disposal restrictions, etc.) will be provided by the Contractor to the Department of Environmental Health & Safety (303) 492-6025. Where appropriate, the Main Campus EPF ID COD007431505 will be used for these shipments.

3. Hazardous chemicals, waste, and other pollutants may not be discharged to the

sanitary or storm sewer systems at anytime. Releases to the environment must be reported to CUPD/EH&S immediately.

END OF SECTION

Page 39: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

PROJECT MEETINGS 01200 - 1

SECTION 01200

PROJECT MEETINGS

PART 1 - GENERAL 1.01 REQUIREMENTS A. The types and minimum requirements for project meetings are included but are not

necessarily limited to the following categories: Pre-construction meeting Progress and Coordination meetings Specially called meetings B. The pre-construction meeting will be scheduled within fifteen days after date of Notice to

Proceed, at a central site location designated by the Owner and convenient for all parties. 1. Attendance: a. Owner's Representative b. Consultant and his sub-consultants, as applicable c. Contractor's Superintendent d. Major Subcontractor(s) e. Others as appropriate 2. Suggested Agenda: a. Distribution and discussion of: List of major subcontractors and suppliers Projected construction schedules Critical work sequencing Major equipment deliveries and priorities Project Coordination Designation of responsible personnel b. Procedures and processing of: Field decisions Proposal requests Submittals Change Orders Applications for Payment c. Adequacy of Distribution of Contract Documents d. Procedure for Maintaining Record Documents e. Inspections f. Stormwater Management Plan (SWMP) C. The Architect/Engineer will: Record the minutes; including significant proceedings and

decisions. D. The Contractor shall schedule and administer subcontractor and vendor pre-construction

meetings throughout progress of the work. He will: 1. Prepare agenda for meetings. 2. Distribute written notice of each meeting four days in advance of meeting date. 3. Make physical arrangements for meetings. 4. Preside at meeting. 5. Record the minutes; including significant proceedings and decisions. 6. Representatives of Contractors, Subcontractors, and Suppliers attending

meetings shall be qualified and authorized to act on behalf of the entity each represents.

Page 40: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

PROJECT MEETINGS 01200 - 2

7. Use of Premises: Office, work, staging and storage areas Owner's requirements 8. Temporary construction Facilities, Utilities, Controls and Construction Aids 9. Safety, First-aid, Security and Housekeeping Procedures 10. Administrative Procedures and Documents as Required by Owner 1.02 PROGRESS AND COORDINATION MEETING The Contractor will schedule and administer job progress and coordination meeting at the site. A. Attendance: 1. Owner as needed 2. Consultant and his sub-consultants as needed 3. Subcontractor as appropriate to the agenda 4. Suppliers as appropriate to the agenda 5. Others B. Suggested Agenda: 1. Review of work progress since previous meeting. 2. Field observations, problems and conflicts. 3. Problems which impede Construction Schedule. 4. Review of off-site fabrication and delivery schedules. 5. Corrective measures and procedures to regain projected schedule. 6. Revisions to Construction Schedule. 7. Coordination of schedules. 8. Progress and schedule during succeeding work period. 9. Review submittal schedules and expedite as required. 10. Maintenance of quality standards. 11. Pending changes and substitutions. 12. Review proposed changes for: a. Effect on Construction Schedule and on completion date. b. Effect on other contracts of the Project. C. The Architect/Engineer shall record and distribute the minutes of all progress meetings

throughout the construction period and shall visit the site a minimum of once every two weeks. The Architect/Engineer shall average one visit per week during construction.

The structural engineer shall visit the site immediately prior to every major structural concrete slab pour; every major foundation wall pour; at least twice for each major segment of work [i.e., caissons, columns, steel roof joists, etc].

END OF SECTION

Page 41: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 01300 - 1

SECTION 01300

SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. Submit shop drawings, product data and samples as required by various sections of the specifications. 1.02 QUALITY ASSURANCE A. Shop Drawings: 1. Drawings shall be presented in a clear and thorough manner. 2. Details shall be identified by reference to sheet, detail, schedule, or room

numbers shown on drawings. B. Product Data: 1. Preparation: a. Clearly mark each copy to identify pertinent products or models. b. Show performance characteristics and capabilities. c. Show dimensions and clearances required. d. Show wiring or piping diagrams and controls. 2. Manufacturer's standard schematic drawings and diagrams. a. Modify drawings and diagrams to delete information that is not applicable

to the work. b. Supplement Standard information to provide information specifically

applicable to the work. C. Samples: 1. Office samples shall be of sufficient size and quantity to clearly illustrate: a. Functional characteristics of the product with integrally related parts and

attachment devices. b. Full range of color, texture and pattern D. Mock-ups: 1. Provide complete mock-up of exterior materials to be incorporated into the work. a. Mock-up shall include a sample of all materials used in exterior

construction, whether specified elsewhere or not in these documents, including but not limited to, masonry, stone, window systems, precast concrete, roof systems, flashing, sealants, masonry paving, paint and other readily visible materials.

b. Secure Owner approval of mock-ups prior to ordering and placement of materials. Modify mock-ups as directed by the Architect or Owner until acceptable.

c. Confirm exact mock-up(s) required by Owner prior to fabrication of mock-up(s).

2. Remove mock-up at the conclusion of the project or when directed by the Architect.

a. Restore or finish site to finish condition indicated on the Drawings.

Page 42: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 01300 - 2

E. Responsibilities of the Contractor: 1. Review shop drawings, product data, samples and project record drawings for

specification performance prior to submission. 2. Determine and Verify: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with specifications 3. Coordinate each submittal with requirements of the work and of the Contract

Documents. 4. Notify the Consultant in writing, at the time of submission, of any deviations in the

submittals for requirements of the Contract Documents. 5. Begin no fabrication or work that requires submittals until return of submittals with

Consultant's acceptance. 6. Contractor’s responsibility for deviations in submittals from requirements of

Contract Documents is not relieved by Consultant’s review of submittals. 7. Contractor shall stamp, sign or initial, and date each submittal to show

compliance with the Contract Documents prior to submittal to the Consultant. 1.03 SUBMITTALS A. Make submittals promptly in accordance with approved schedule and in such sequence

as to cause no delay in the work. B. Number of Submittals Required: 1. Shop Drawings: PDF email submittals, cover page, submittal #; and division

section # - CSI format 2. Product Data: PDF email submittals, cover page, submittal #; and division

section # - CSI format 3. Samples: Submit the number stated in each specification section. C. Submittals shall contain: 1. Date of the submission and dates of any previous submissions. 2. Project title and number. 3. Contract identifications. 4. Names of: a. Contractor and Subcontractor(s), if applicable. b. Supplier c. Manufacturer 5. Identification of product with the specification section number. 6. Field dimensions, clearly identified as such. 7. Relation to adjacent or critical features of the work or materials. 8. Applicable standards, such as ASTM or Federal specification numbers. 9. Identification of deviations from Contract Documents. 10. Identification of revisions on resubmittals. 11. An 8"x3" blank space in lower right-hand corner for review stamps. D. Resubmission Requirements: 1. Make any corrections or changes in the submittals required by the Consultant and

resubmit until accepted. 2. Shop drawings and product data: a. Revise initial drawings or data and resubmit as specified for initial

submittal.

Page 43: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 01300 - 3

b. Indicate any changes that have been made, other than those requested by the Consultant.

3. Samples: Submit new samples as required for initial submittal. E. Distribution: 1. Distribute reproductions of approved shop drawings and copies of product data to

affected subcontractors and retain one copy for use at the job-site. 2. Distribute approved samples as directed. F. Consultant's Duties: 1. Review submittals with reasonable promptness and in accordance with schedule. 2. Review of separate item does not constitute review of an assembly in which item

functions. 3. Affix stamp and initials or signature, and indicate requirements for resubmittal or

acceptance of submittal. 4. Return submittals to the Contractor for distribution or for resubmission. G. Schedule of Values and pay applications: 1. Submit typed schedule on State Form SC7.2; Contractor's standard form or

media-driven printout will be considered on request. 2. Format: Table of Contents of this Project Manual.

3. Include in each line item a directly proportional amount of Contractor's overhead and profit.

H. Schedule of Submittals: The Contractor shall submit the submittals required by the

specifications. The Contractor shall develop a submittal schedule that confirms the submittals and the time frame for review by the consultants.

I. Construction Schedule: 1. The Contractor shall submit a critical-path method (CPM) construction schedule

prior to start of construction activities. The CPM schedule shall include notice to proceed, submittal activities, construction activities, change order work (when applicable), close-out, testing, demonstration, and acceptance. The CPM shall correlate specifically to the schedule of values line items and be cost loaded.

Float, slack time, or contingency within the schedule (i.e., the difference in time between the project's early completion date and the required contract completion date), and total float within the overall schedule, is not for the exclusive use of either the principal representative or the Contractor, but is jointly owned by both and is a resource available to and shared by both parties as needed to meet contract milestones and the contract completion date. The Contractor will be required to submit an as-built progress CPM schedule with each progress billing. This CPM schedule will be the basis for making progress payments. The level of detail and quantity of work activities in the CPM schedule should be negotiated with the principal representative prior to starting construction.

J. Progress Photos 1. The Contractor shall submit up to 12 - 3x4 inch progress photos with each

progress payment. The photos should demonstrate the work in place and be dated with a short description of the photographed item.

Page 44: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 01300 - 4

K. Coordination Drawings: 1. The Contractor shall submit coordination drawings with all mechanical, electrical,

fire protection, and building monitoring systems prior to the Consultant review of any shop drawings or submittals for work in those trades. Approval of required shops and submittals must be obtained prior to starting work, and must be obtained prior to approval of pay applications of the work. The drawings shall be created to include all trades on a particular level of the building on one drawing. Identify conflicts between the systems or between the systems and architectural elements such as ceiling heights, ceiling types, or walls. Conduit routing for electrical, mechanical, energy management system, and security trades shall be included. Identify potential solutions to the conflicts for the Consultant and Owner to review during the submittal process. Revise the coordination drawings to show any comments made during the submittal review process, and reissue for use by all affected trades, Owner and Consultant.

2. The Coordination drawings shall include sectional coordination documents. Identify elevations of systems A.F.F. (above finish floor) and component dimensions. Show elevations whenever component changes height.

L. Daily Reports 1. The contractor shall submit daily reports, due by 5 p.m. the following day. The

report should include weather, equipment, manpower count, subcontractors on site, short description of work for that day, inspections, visitors, items that may affect progress or quality of project.

M. Request for Information (RFI): 1. The Contractor will be responsible for submitting RFIs on AIA form G716 or

similar. The RFI should identify in writing any unclear, inconsistent, or conflicting item in the documents that could not be answered by thorough review by the Contractor or subcontractors. The RFI should include a description of the item and a proposed solution. The RFI should indicate schedule or cost impact, if any. Contractor shall be required to submit cost or schedule impact within seven days of receipt of the RFI response. Each RFI shall be numbered in sequence.

N. Weekly Logs: 1. The Contractor shall provide an updated RFI, change request, and submittal logs

at weekly construction meetings. Contractor shall provide a 2-week detailed construction schedule at the weekly construction meeting.

PART 2 - MATERIALS Not used. PART 3 - EXECUTION Not used.

END OF SECTION

Page 45: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

QUALITY CONTROL 01400 - 1

SECTION 01400

QUALITY CONTROL

PART 1 - GENERAL 1.01 SUPPLEMENTAL TESTING

If required, the following testing shall be performed at the expense of the contractor installing the material being tested:

A. Material Substitution: Any tests of basic material or fabrication equipment offered as a substitute for specified item on which a test may be required in order to prove its compliance with the specifications.

B. Mechanical/Electrical: Tests on mechanical and electrical systems required to insure

their proper installation and operation. C. Any test that fails shall be paid for by the installing contractor subject to the following

conditions: 1. Quantity and nature of tests will be determined by the Consultant. 2. All test shall be done in the presence of the Owner or his representative. 3. Proof of noncompliance will make the installing contractor liable for any corrective

action which the Owner feels is prudent including complete removal and replacement of defective material.

Nothing contained herein is intended to imply that the installing contractor does not have the right to have tests performed on any material at any time for his own information and job control so long as the Consultant or Owner does not assume responsibility for costs or for giving them consideration when appraising quality of materials.

D. The Consultant shall determine the type and number of tests to be performed on the

project. 1.02 TEST REPORTS

Reports of all tests made by testing laboratories shall distributed by the testing laboratory as follows: 1 copy - Contractor 1 copy - Applicable supplier or subcontractor 1 copy - Owner 1 copy - Consultant Other copies - as directed

1.03 QUALITY CONTROL SYSTEM A. General: The contractor shall establish a quality control system to perform sufficient

inspection and tests of all items of work, including that of all subcontractors, to ensure conformance to the Contract Documents for materials, workmanship, construction, finish, functional performance and identification. This control shall be established for all construction except where the Contract Documents provide for specific compliance tests by testing laboratories or Consultants employed by the Owner.

The quality control system is the means by which the Contractor assures that construction complies with the requirements of the Contract Documents. Controls shall be adequate

Page 46: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

QUALITY CONTROL 01400 - 2

to cover all construction operations and should be keyed to the proposed construction schedule.

B. The Contractor shall designate a quality control representative on staff to review the work

to insure compliance with the contract documents by weekly jobsite visits for observation. The designated employee shall not be involved in the performance of the work. The quality control representative shall review the work and make necessary corrections to bring the work into compliance prior to scheduling the Architect for the final punchlist review.

C. Records: The Contractor shall maintain correct records on an appropriate form for all

inspections and tests performed, instruction received from the Owner and actions taken as a result of those instructions. These records shall include evidence that the required inspections or tests have been performed (including type and number of inspections or tests, nature of defects, causes for rejection, etc.) proposed or directed remedial action, and corrective action taken. The Contractor shall document inspections and tests as required by each Section of the Specifications.

1.04 INDEPENDENT TESTING AGENCY SERVICES A. The Owner will employ and pay for the services of an independent Testing Agency to

perform the Inspections, special inspections, tests and other services when required by sections of the specification. Services shall be performed in accordance with requirements of governing authorities and with specified standards.

1. Contractor shall cooperate with Testing Agency personnel and shall furnish tools, sample of materials, design mixes, equipment and assistance as requested.

2. Contractor shall provide and maintain, for the sole use of the Testing Agency, adequate facilities for the safe storage and proper curing of concrete testing cylinders on the project site for the first 24 hours after casting as required by ASTM C 31, Method of Making and Curing Concrete Test Specimens in the field.

3. Contractor shall notify Testing Agency sufficiently in advance of operations to allow for completion of initial tests and proper assignment of inspection personnel.

4. Contractor shall notify the testing agency sufficiently in advance of cancellation of required testing operations. The Contractor shall assume responsibility for costs incurred due to the failure to provide such notice.

END OF SECTION

Page 47: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

TEMPORARY FACILITIES 01500 - 1

SECTION 01500

TEMPORARY FACILITIES

PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary

Conditions and other Division 1 Specification sections, apply to work of this section. 1.02 DESCRIPTION OF REQUIREMENTS A. This section of the General Requirements outlines the basic requirements for temporary

services, utilities, and facilities which will indirectly enable adequate construction progress and processes, and will accommodate other necessary activities at the project site except as otherwise indicated, the costs of providing and using temporary services are included in the Contract Sum.

1.03 QUALITY ASSURANCE A. Comply with governing regulations and utility company regulations and recommendations

for the construction of temporary facilities, including but not necessarily limited to, code compliance, permits, inspections, testing, and health and safety compliance.

1.04 SITE CONDITIONS A. Provide Temporary facilities and services at the time first needed at the site and maintain,

expand, and modify the facilities as needed throughout the construction period and do not remove until no longer needed.

PART 2 - EXECUTION 2.01 GENERAL A. Use qualified tradesmen for the installation of temporary facilities. Locate facilities where

they will serve the total project construction work adequately and result in minimum interference with performance of the work. Relocate, modify, and extend facilities as required during the course of the work to properly accommodate the entire work of the project.

2.02 TEMPORARY FACILITIES A. Temporary Water: Connect to existing water source as designated by the Owner for

construction operations. B. Temporary Telephone: Provide, maintain and pay for telephone service to field office at

time of project mobilization. If a mobile phone is designated as the field office phone then it shall be a local number.

C. Sanitary Facilities: Comply with governing regulations, including safety and health codes

for the type, number, location, operation, and maintenance of fixtures and facilities. Install sanitary facilities in available locations which will best serve the needs of personnel at the

Page 48: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

TEMPORARY FACILITIES 01500 - 2

project site. Toilet rooms in existing buildings or in new construction may not be used without written approval of the Owner.

D. Temporary Heat and Ventilation: Provide such OSHA approved heat and fuel, heating

units, equipment as necessary to provide the required environmental conditions and to protect the work from damage due to cold. Maintain equipment in a clean, safe condition.

E. Fire Extinguisher: 1. Except as otherwise indicated or required, comply with the applicable

recommendations of NFPA No. 10 "Portable Fire Extinguisher" for each area of each construction activity whenever combustible materials, flammable liquids, and similar exposures to possible fires are present.

2. Locate extinguisher where most convenient and effective for the intended purposes. Store combustible materials in recognized fire-safe locations and containers.

F. Protection 1. Barricades, Warning Signs, and lights: Comply with recognized standards and

code requirements for the erection of substantial and structurally adequate barricades wherever needed to prevent accidents and losses. Paint with appropriate colors, graphics and warning signs to inform personnel at the site and the general public where exposure exists of the hazard being protected. Provide lighting where appropriate and needed for the recognition of the facility, including flashing red lights where appropriate.

G. Temporary Enclosure: Wherever required, provide temporary enclosure of materials,

equipment, work in progress, and completed portions of work, so as to afford protection for both the work and employees.

H. Miscellaneous Facilities: 1. Provide ladders, ramps, and temporary stairs for access to all levels of the

construction for general access by all trades, Individual contractors and subcontractors shall furnish their own stepladders, scaffolds, staging, work platforms, and other facilities for use of their workmen and as necessary for safety of all personnel.

I. Field Office: 1. The Contractor shall provide and maintain a suitable temporary field office for his

own use. Offices and all other temporary structures shall be removed from the site upon completion of the work.

2. Temporary structures or storage used for storage and offices for contractors shall be located on the site in an orderly manner as determined by the Owner.

2.03 OPERATIONS AND TERMINATIONS A. Supervision: Enforce strict discipline in the use of temporary facilities at the project site.

Limit availability of facilities to essential and intended uses, so as to minimize waste and possibility of abuses and the resulting unsanitary and hazardous or dangerous conditions.

B. Maintenance: Operate and maintain temporary facilities in good operating condition

through the time of use and until removal is authorized. Protect from damage by freezing temperatures and similar elements at the site.

C. Termination and removal: At the time the need has ended for each temporary facility, or

when it has been replaced by authorized use of a permanent facility, or at the time of

Page 49: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

TEMPORARY FACILITIES 01500 - 3

Substantial completion, promptly remove the facility unless requested by the Consultant to be retained for a longer period of time. Complete or restore permanent work which may have been delayed or otherwise affected by the temporary facility. Replace work which cannot be satisfactorily restored. Except as otherwise indicated, the materials and equipment of temporary facilities remain the property of the contractors.

END OF SECTION

Page 50: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

MATERIAL AND EQUIPMENT 01600 - 1

SECTION 01600

MATERIAL AND EQUIPMENT

PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Products. 2. Transportation and Handling. 3. Storage and Protection. 4. Manufacturer's Instructions. 5. Product Options. 6. Products List. 7. Substitutions. 8. Systems Demonstration. B. Related Sections: 1. Section 01400 - Quality Control. 2. Section 01730 - Operation and Maintenance Data. 1.02 QUALITY ASSURANCE A. Conform to applicable specifications and standards. B. Comply with size, make, type and quality specified, or as specifically approved in writing

by the Consultant. C. Manufactured and Fabricated Products: 1. Two or more items of the same kind shall be identical, by the same manufacturer. 2. Equipment capacities, sizes and dimensions shown or specified shall be adhered

to unless variations are specifically approved in writing. 1.03 TRANSPORTATION AND HANDLING A. Arrange deliveries of products in accord with construction schedules, coordinate to avoid

conflict with work and conditions at the site. B. Promptly inspect shipments to assure that products comply with requirements, quantities

are correct, and products are undamaged. 1.04 STORAGE AND PROTECTION A. Store products in accordance with manufacturer' instruction, with seals and labels intact

and legible. B. Arrange storage to provide access for inspection. Periodically inspect to assure products

are undamaged, and are maintained under required conditions. 1.05 MANUFACTURER'S INSTRUCTIONS A. When Contract Documents require that installation of work shall comply with

manufacturer's printed instructions, obtain and distribute copies of such instructions to parties involved in the installation, including one copy to the Consultant and one copy to the Contractor.

Page 51: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

MATERIAL AND EQUIPMENT 01600 - 2

B. Perform work in accord with manufacturer's instructions. Do not omit any preparatory

step or installation procedure unless specifically modified or exempted by Contract Documents.

1.06 PRODUCT OPTIONS A. Products Specified by Reference Standards or by Description Only: Any product meeting

those standards. B. Products Specified by Naming One or More Manufacturers with a Provision for

Substitutions: Submit a request for substitution for any manufacturer not specifically named.

C. Consultant will review requests for substitutions with reasonable promptness, and notify,

by Addendum, of the decision to accept or reject the requested substitution. 1.07 PRODUCT LIST A. Within 15 days after signing of agreement, submit complete list of major products

proposed for use, with name of manufacturer, trade name, and model number of each product.

1.08 SUBSTITUTIONS

A. Will only be considered prior to bid or in the event that Equipment is not available.

1.09 SYSTEMS DEMONSTRATION A. Prior to final inspection, demonstrate operation of each system to Consultant and Owner. B. Instruct Owner's personnel in operation, adjustment, and maintenance of equipment and

systems, using the operation and maintenance data as the basis of instruction. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED

END OF SECTION

Page 52: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CONTRACT CLOSE-OUT 01700 - 1

SECTION 01700

CONTRACT CLOSE-OUT

PART 1 - GENERAL 1.01 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. The Contractor shall comply with procedures stated in the General Conditions of the Contract for Notice of Completion, Final Inspection, Notice of Substantial Completion and Notice of Acceptance.

B. Should the Architect/Engineer or the Principle Representative determine that the work is

not substantially complete, or the punch list items exceed 25, he will immediately notify the Contractor, in writing, stating reasons. After Contractor completes work, he shall resubmit certification and request for final inspection. The Contractor will be responsible for all costs beyond two Architect/Engineer walk-throughs.

C. Owner may occupy designated portions of the Project under provisions stated in the

General Conditions of the Contract. 1.02 CLOSE-OUT FORMS

The Architect/Engineer will complete the Notice of Approval of Beneficial Occupancy, Closing-out Checklist and Contract Close-out forms and forward them to the Contractor. Comply with procedures stated in General Conditions of the Contract.

1.03 FINAL SETTLEMENT AND PAYMENT A. Contractor shall comply with procedures stated in the General Conditions of the Contract

before final settlement and payment are made. B. The Contractor shall also submit the following prior to the final application for payment: 1. Contractor’s Affidavit of Payment of Debit and Claims: AIA G706. 2. Contractor’s Affidavit of Release of Liens (claims): AIA G706A, with: a. Consent of Surety to final payment: AIA G707 b. Contractor’s release of waivers of claims. c. Separate release of waivers of claims for subcontractors, suppliers and

others with claim rights, against property of owner, together with list of those parties.

1.04 GUARANTEE INSPECTION A. The Contractor shall comply with procedures stated in the General Conditions of the

Contract for Guarantee Inspections after completion of the work. 1.05 WARRANTIES AND SPECIAL GUARANTEES

The Contractor shall comply with procedures and criteria outlined in the General Conditions of the Contract for all warranties and special guarantees of the work.

1.06 OPERATING AND MAINTENANCE DATA A. Refer to Section 01730 - Operating and Maintenance.

Page 53: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CONTRACT CLOSE-OUT 01700 - 2

B. Mechanical - By Mechanical Contractor: See Division 15.

C. Electrical - By Electrical Contractor: See Division 16. 1.07 DEMONSTRATIONS A. Refer to Section 01730 - Operating and Maintenance B. Mechanical - By Mechanical Contractor: See Division 15 C. Electrical - By Electrical Contractor: See Division 16. 1.08 SPARE PARTS AND MAINTENANCE MATERIALS

A. Provide products, spare parts, and maintenance materials in quantities specified in each Section, in addition to that used for construction of work. Coordinate with Owner, deliver to Project site and obtain receipt prior to final payment.

B. At the completion of the project, all loose keys for hose bibs; adjustment keys and

wrenches for door closers and panic hardware; and keys for electric switches, electrical panels, etc., shall be accounted for by the Contractor and turned over to the Owner.

END OF SECTION

Page 54: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CLEANING 01710 - 1

SECTION 01710

CLEANING

PART 1 - GENERAL 1.01 CLEANING A. Clean-up During Construction: Each contractor shall keep the building and premises free

from all surplus material, waste material, dirt and rubbish caused by his employees or work, and at the completion of his work he shall remove all such surplus material, waste material, dirt and rubbish, as well as his tools, equipment and scaffolding, and shall leave his work clean and spotless, unless more exact requirements are specified. In case of dispute, the owner may remove all such items and charge the cost of such removal to the contractor.

Each sub-contractor shall perform his clean-up daily and shall transport his rubbish to an on-site location designated by the Contractor who will arrange for its removal.

B. Cleaners: With the exception of clean-up of the site and cleaning specifically assigned to

Contractors under various sections of the specifications, all final clean-up of exterior and interior of the building shall be done by professional cleaners.

C. Final Clean-up: 1. Exterior: In addition to items specified below, any new surfaces on exterior,

concrete, metal, etc., shall be carefully and thoroughly cleaned. 2. Glass: Both sides of all glass in work areas shall be carefully and thoroughly

cleaned by professional window cleaners and left absolutely clean and free from paint, grease, dirt, etc.

3. Hardware: Clean and polish all hardware and leave clean and free from paint, grease, dirt, etc.

4. Plumbing: Clean and polish all plumbing fixtures, fittings, and exposed plated piping. Leave clean and free from paint, grease, dirt, etc. Remove all labels.

5. Electrical: Clean and polish all electric fixtures, including glassware, switch plates, etc. and leave clean and free from paint, grease, dirt, etc.

6 Equipment: Carefully and thoroughly clean all items of equipment, mechanical, electrical, cabinets, ductwork, etc.

7. Floors: Thoroughly clean all floors. Vacuum and clean carpeting. Shampooing of pre-existing carpet is required once project is complete. Contractor is responsible for this.

a. Contractors are responsible for cleaning (stripping floors if necessary) then applying the required two coats of sealer and three coats of finish before releasing the building for occupancy. Facilities Management will provide a contact person for help concerning campus standards free of charge. Or Custodial floor care services may be sub-contracted out through Facilities Management's work order system.

b. Facilities Management Approved Sealers and Finishes for Vinyl Tile Flooring:

CU requires floor care products to be from the same product line. (Different brands may interact disastrously).

All of these products may be ordered through Construction Stores, but these products not stocked at Stores, please place orders at least two weeks in advance.

Page 55: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CLEANING 01710 - 2

JohnsWax Butchers: Airkeim: Strippers: Freedom Time Buster Air Strip Full Impact Sealers: Over & Under Iron Stone Laser, Gemini Technique Finishes: Show Place MainStay Laser, Gemini Above

Campus safety standards require at least TWO (2) coats of Sealer be applied to a cleaned floor, and at least THREE (3) coats of Finish must be applied on top of the sealer.

c. Floor Cleaning Procedures: 1. Sweep floor clean of debris

2. Cord off area if necessary 3. Put up Caution signs 4. Mix Stripper or Cleaning solution according to label 5. Apply solution to floor 6. Start setting up equipment 7. Place RED abrasive pad on buffer (buffer less than 300 rpms) 8. Begin stripping or cleaning floor working with buffer moving it side to side

across the floor. 9. Use HEPA filtered water vacuum to begin to suck up slurry*

*use of HEPA filtered water vacuum is required on existing floor tile which contains asbestos.

10. Apply additional coats of water and re-vacuum up floor 11. Mop floor with clean water, change rinse water often 12. Mop floor a second time 13. Mop floor to dry completely 14. Clean up equipment 15. Wash red pad with clean water.

d. Sealing Procedures: 1. Using a new mop head or clean wax mop and clean bucket, apply first

coat of approved sealer to floor 2. Allow floor to dry completely (at least 20 minutes) 3. Apply second coat of sealer 4. Allow floor to dry

e. Finishing (Waxing) Procedures: 1. Using a clean wax mop and bucket apply first coat of approved finish

(wax) 2. Allow floor to dry completely (at least 20 minutes) 3. Apply second coat of finish (wax) 4. Allow floor to dry completely (at least 20 minutes) 5. Apply third coat of finish (wax) 6. Allow floor to dry completely (at least 30 minutes) 7. Wash mop and bucket with clean water 8. If floor is dry - remove caution signs and open area up

f. Burnishing Procedures: The next working day 1. Sweep floor clean of debris 2. Spot mop floor to remove spots and dirt 3. Set up High Speed Burnisher to make for a safe environment 4. Start Burnishing. Walk forward in a straight line 5. At end of row, turn around and start forward again 6. Repeat steps 5 & 6 until finished 7. Clean up equipment and pad.

Page 56: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

CLEANING 01710 - 3

E. Completion: The entire work inside and out, and the entire premises shall be in first-class, clean condition upon completion before being accepted by the Owner.

END OF SECTION

Page 57: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

PROJECT RECORD DOCUMENT 01720 - 1

SECTION 01720

PROJECT RECORD DOCUMENT

PART 1 - GENERAL 1.01 SUMMARY A. This section describes the definitions, recording and maintenance requirements and the

submittal requirements for record documents. 1.02 DEFINITIONS A. The Project Record Documents are intended to indicate all changes and deviations from

the original contract documents and permanently record the “as-built” condition of material, equipment and structure. The project record documents shall include the contract drawings, project manual, addenda, change orders, modifications and clarifications, field directives, approved shop drawings, approved product data, manufacturer’s certificates and project test results.

1.03 SUBMITTALS A. Submit the project record documents in conformance with Section 01700 and prior to the

final applications for payment. The final application for payment will not be approved prior to the submittal of record documents.

1.04 QUALITY ASSURANCE A. The project record documents shall be updated at a minimum on a weekly basis and shall

be readily available for inspection by the owner and consultants. Maintain a separate set of complete documents for exclusive use of record documents and protect the documents from damage in a clean, dry location. Note: Progress applications for payment will not be approved if record documents are not current.

B. The record documents shall contain a clear, legible record of all detail and dimensional

changes and locate all concealed work including, but not limited to: 1. Interior and Exterior Utilities 2. Valves 3. Dampers 4. Controls 5. Junction Boxes 6. Clean-outs 7. Access Doors C. The project manual (specifications) shall indicate all manufacturers’ products complete

with catalogue number and trade name of products installed. All changes and corrections to the project manual shall be clearly indicated.

END OF SECTION

Page 58: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

OPERATING AND MAINTENANCE 01730 - 1

SECTION 01730

OPERATING AND MAINTENANCE

PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. Compile product data and related information appropriate for the University of Colorado's

maintenance and operation of products furnished. B. Prepare operating and maintenance data as specified in this section and as referenced in

other pertinent sections of specifications. C. Instruct the University of Colorado, Facilities Management personnel in the maintenance

of PRODUCTS and in the operation of equipment and systems. 1.02 QUALITY ASSURANCE A. Preparation of data shall be done by personnel: 1. Trained and experienced in maintenance and operation of the described

products. 2. Completely familiar with requirements of this section. 3. Skilled as a technical writer to the extent required to communicate essential data. 4. Skilled as a draftsman competent to prepare required drawings. 1.03 SUBMITTALS A. Prepare data in the form of an instructional manual for use by the University of Colorado,

Facilities Management personnel. Quantities are listed in Part 1.07. B. Format: 1. Submit electronically in Portable Document Format (PDF) format as one

document, OCR (Optical Character Recognition) searchable, bookmarked according to the Construction Specifications Institute (CSI) standards.

2. Title shall be "OPERATING AND MAINTENANCE INSTRUCTIONS", and shall

include:. a. Name of project and date of completion (month and year). b. Project number. c. Identify of general subject matter covered in the manual (e.g.,

Architectural, Mechanical, Electrical and/or Civil). 1.04 CONTENT OF MANUAL A. An electronically-written table of contents shall be provided for each volume, arranged

according to CSI standards. Include the following: 1. Name of responsible installing principal contractor, address, and telephone

number. 2. A list of each product being included, indexed to the content of the volume. 3. List with each product, the name, address, and telephone number of: a. Maintenance contractor, as appropriate. b. Identity of the area of responsibility of each. 4. Identify each product by product name and other identifying symbols.

Page 59: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

OPERATING AND MAINTENANCE 01730 - 2

B. Product Data: 1. Local source of supply for parts and replacement. 2. Include only those sheets that are pertinent to the specific product, with the

following information. a. Clearly identify the specific product or part installed. b. Clearly identify the data applicable to the installation. c. Delete references to inapplicable information. C. Drawings: 1. Supplement product data with drawings as necessary to clearly illustrate: a. Relations of component parts of equipment and systems. b. Control and flow diagrams. 2. Coordinate drawings with information in project record drawings to ensure correct

illustration of completed installation. 3. Do not use project record drawings as maintenance drawings. D. Provide written text, as required, to supplement product data for the particular installation: 1. Organize in a consistent format under separate headings for different procedures. 2. Provide a logical sequence of instructions for each procedure. E. Provide a copy of each warranty, bond, and service contract issued. Provide information

sheets for the University of Colorado, Facilities Management's personnel and give: 1. Proper procedures in the event of failure. 2. Instances that might affect the validity of warranties or bonds. 1.05 MANUALS FOR ARCHITECTURAL MATERIAL AND FINISHES A. Submit copies (per schedule shown in paragraph 1.07) of complete manual in final form. B. Content for architectural products include applied materials and finishes. 1. Manufacturer's data, giving full information on products. a. Catalog number, size, and composition. b. Color and texture designations. c. Information required for reordering special manufactured products. 2. Instructions for care and maintenance: a. Manufacturer's recommendation for types of cleaning agents and

methods. b. Cautions against cleaning agents and methods that are detrimental to the

product. c. Recommended schedule for cleaning and maintenance. C. Content for moisture-protection and weather-exposed products: 1. Provide manufacturer's data, giving fully information on products. a. Applicable standards b. Chemical composition c. Details of installation 2. Provide instructions for inspection, maintenance, and repair.

Page 60: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

OPERATING AND MAINTENANCE 01730 - 3

1.06 MANUAL FOR NON-ARCHITECTURAL EQUIPMENT AND SYSTEMS A. Submit copies (per schedule) of complete manual in final form. B. Content for each unit of equipment and system, as appropriate shall contain: 1. Description of unit and component parts (Consultant-approved submittals).

a. Function, normal operating characteristics, and limiting conditions. b. Performance curves, engineering data, and tests. c. Complete nomenclature and Commercial number of all replaceable parts.

2. Operating Procedures: a. Start-up, break-in, routine, and normal operating instructions. b. Regulation, control, stopping, shutdown, and emergency instructions. c. Summer and winter operating instructions. d. Special operating instructions.

3. Maintenance Procedures: a. Routine operations. b. Guide to troubleshooting. c. Disassembly, repair, and reassembly. d. Alignment, adjustment, and checking.

4. Servicing and Lubrication Schedule, including a list of lubricants required. 5. Manufacturer's operating and maintenance instructions. 6. Description of sequence of operation by control manufacturer. 7. Original manufacturer's parts list, illustrations, assembly drawings, and diagrams

required for maintenance and replacement. a. Predicted life of parts subject to wear. b. Items recommended to be stocked as spare parts.

8. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage.

C. Content for each electric and electronic system, as appropriate, shall contain: 1. Description of system and component parts: a. Function, normal operating characteristics, and limiting conditions. b. Performance curves, engineering data, and tests. c. Complete nomenclature and Commercial number of replaceable parts. 2. Operating Procedures:

a. Routing and normal operating instructions. b. Sequences required. c. Special operating instructions.

3. Maintenance Procedures: a. Routing operations. b. Guide to troubleshooting.

c. Disassembly, repair, and reassembly. d. Adjustment and checking. e. Manufacturer's printed operating and maintenance instructions. f. List of original manufacturer's spare parts, manufacturer's current prices,

and recommended quantities to be maintained in storage. D. Prepare and include additional data when the need for such data becomes apparent

during instruction of the University of Colorado, Facilities Management's personnel.

Page 61: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

OPERATING AND MAINTENANCE 01730 - 4

1.07 OPERATION & MAINTENANCE MANUAL A. Operations and Maintenance Manuals – all disciplines – submit electronically in Portable

Document Format (PDF) format as one document, OCR (Optical Character Recognition) searchable, bookmarked according to the Construction Specifications Institute (CSI) standards.

1.08 SUBMITTAL SCHEDULE A. Submit one electronic copy to the Consultants and one to the University of draft of

proposed formats and outlines of contents upon completion of the submittal process. The Consultants and the University staff will review the draft and will submit comments through the consultants.

B. Submit electronic copies of complete manual(s) in final form 15 days prior to final

inspection or acceptance. Comments will be submitted after final inspection. C. Submit specified number of CDs or DVDs of approved data in final form prior to

acceptance. 1.09 INSTRUCTION OF UNIVERSITY OF COLORADO, FACILITIES MANAGEMENT PERSONNEL A. Fully instruct the University of Colorado, Facilities Management personnel's designated

operating and maintenance personnel in the operation, adjustment, and maintenance of all products, equipment, and systems as required elsewhere in the specification.

B. Operating and Maintenance manual may be required as the basis of instruction. PART 2 - MATERIAL Not Used. PART 3 - EXECUTION Not Used.

END OF SECTION

Page 62: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

COMMISSIONING REQUIREMENTS 01740 - 1

SECTION 01740

COMMISSIONING REQUIREMENTS

PART 1 - GENERAL 1.01 DESCRIPTION OF WORK

A. Prepare commissioning process based on the Commissioning Checklists found in the UCB Standards website:

https://www.colorado.edu/fm/planning-design-construction/design-construction/building-construction-standards B. Coordinate the requirements of Project Closeout and Operating and maintenance

sections that are part of Division 1. C. Schedule the required commissioning activities with the University of Colorado Facilities

Department and their consultants at least 72 hours prior to conducting Commissioning activities.

PART 2 - MATERIALS Not Used. PART 3 - EXECUTION NOT USED

END OF SECTION

Page 63: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

BASIC SITE MATERIALS & METHODS 02050 - 1

SECTION 02050

BASIC SITE MATERIALS & METHODS

PART 1 – GENERAL 1.01 SUMMARY A. Section includes: 1. Construction Storm Water Requirements 2. Post-Construction Storm Water Requirements B. Related Sections 1. Section 02200 - Earthwork 2. Section 02221 – Trenching, Backfilling, Compaction 1.02 QUALITY ASSURANCE A. All construction sites 1. All construction sites that disturb any land must take appropriate erosion control

and stormwater detention measures to contain water run-off from site. B. Construction sites – one acre and larger 1. All construction sites that are one acre and larger must prepare and submit a

Storm Water Management Plan (SWMP) for approval before any work begins. The SWMP must conform to all the requirements contained herein.

1.03 SUBMITTALS A. Storm Water Management Plan (SWMP)

Storm Water Management Plan (SWMP): Prior to any construction activity disturbing one acre of land or more, an approved SWMP and a Stormwater Permit for Construction Activity application from the Colorado Department of Public Health and Environment (CDPHE) are required. The SWMP shall be prepared in accordance with the CDPHE requirements for “Contents of the Stormwater Management Plan” and the UDFCD’s Urban Storm Drainage Criteria Manual, Volume 3, “Best Management Practices” (UDFCD Drainage Criteria Manual). Stormwater quality management and erosion control measures are to be constructed and maintained in accordance with the SWMP and the UDFCD Drainage Criteria Manual.

PART 2 – MATERIALS 2.01 Storm Water Management Plan A. Preparation Standards: Design of the SWMP and the Storm Water Quality and Erosion

Control Plan shall include the following elements: 1. Protection for adjacent properties (including public right-of-way) from erosion

and/or sediment deposition. 2. Protection for public streets from the deposit of sediment from run-off or vehicles

tracking mud at construction access routes. 3. Stabilization for all disturbed areas as defined in the UDFCD Drainage Criteria

Manual.

Page 64: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

BASIC SITE MATERIALS & METHODS 02050 - 2

4. Protection for all storm sewer inlets from the entry of sediment-laden water. 5. Long-term stability of cut and fill slopes and the successful establishment of

permanent vegetative cover on exposed soil. 6. The following standard notes:

a. “All temporary erosion control facilities shall be installed before any construction activities take place”.

b. “Solid waste, industrial waste, yard waste and any other pollutants or waste on any construction site shall be controlled through the use of BMP’s. Waste and/or recycling containers shall be provided and maintained by the owner or contractor on construction sites where there is the potential for release of waste. Uncontained waster that may blow, wash or otherwise be released from the site is prohibited. Sanitary waste facilitates shall be provided and maintained by the owner or contractor”.

c. “Ready-mixed concrete, or any materials resulting from the cleaning of vehicles or equipment containing or used in transporting or applying it, shall be contained on construction sites for proper disposal. Release of these materials is prohibited”.

d. “Cover shall be applied within 14 days to inactive soil stockpiles, and shall be maintained for stockpiles that are proposed to remain in place longer than 30 calendar days”.

e. “BMP’s shall be implemented to prevent the release of sediment from construction sites. Vehicle tracking of mud shall not be allowed to enter the MS4 or waters of the State. Sediment tracked onto public streets shall be removed immediately”.

f. “Techniques shall be used to prevent dust, sediment or debris blowing from the site”.

g. “Stormwater discharges from construction activities shall not cause or threaten to cause pollution, contamination or degradation of waters of the State”.

h. “All earth disturbances shall be designed, constructed and completed to limit the exposed area of any disturbed land to the shortest possible period of time”.

i. “Bulk storage structures for petroleum products and other chemicals shall have adequate protection so as to contain all spills and prevent any spilled material from entering the MS4 or waters of the State”.

j. Any disturbance to temporary and permanent BMP’s resulting from construction activity shall be repaired or replaced within 48 hours.

PART 3 – EXECUTION 3.1 PERMITTING A. Contractor shall develop the SWMP in accordance with all of the requirements herein and

utilizing the most recent SWMP guidance document prepared by the CDPHE and good engineering hydrologic and pollution control practices and submit to the University for approval.

B. Contractor shall apply for and obtain a CDPHE storm water general permit for

construction activities. Provide copies of the permit to the University prior to the start of construction operations.

Page 65: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set Project No. CP008128 6 August 2015

BASIC SITE MATERIALS & METHODS 02050 - 3

3.2 CONSTRUCTION A. The Contractor will be required to have the SWMP on site at all times and shall be

prepared to respond to maintenance of specific BMP’s. B. The Contractor shall inspect all BMP’s at least every 14 days and within 24 hours after

any precipitation or snow melt event that causes surface run-off. Inspections of BMP’s shall be conducted by an individual who has successfully completed formal training in erosion and sediment control by an organization acceptable to the University. A certification of successful completion of such training shall be provided upon request.

C. The Contractor shall amend the SWMP whenever there is a change in design,

construction, operation, or maintenance, which has an effect on the potential for discharge of pollutants to the MS4 or receiving waters, or if the SWMP proves to be ineffective in achieving the general objectives of controlling pollutants in stormwater discharges associated with construction activities.

D. Records of inspection are to be maintained on site with the SWMP. Inspection records

are to be available at the project site at all times and shall be made available to the University upon request.

E. Prior to commencement of work, all general contractors, subcontractors and utility

agencies shall obtain and comply with the approved, current SWMP for the project. 3.3 POST CONSTRUCTION

At the conclusion of all construction activities and as a part of construction close-out, contractor shall remove all temporary BMP’s and inactivate the stormwater permit.

END OF SECTION

Page 66: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 1

SECTION 02111

TREE AND PLANT PROTECTION

PART 1 - GENERAL

1.01 SUMMARY

A. This section includes:

1. Installation of Fencing.

2. Installation of Boxing.

3. Siltation Control.

4. Protection of Trees to Remain.

B. Related Sections Include the Following:

1. Section “Site Clearing” for site stripping, grubbing, stockpiling topsoil, and removal of

above- and below-grade improvements and utilities.

2. Section “Trenching and Backfilling” for soil materials, excavating, backfilling, and site

grading.

1.02 REFERENCES

A. ANSI Z133.1 Safety Requirements for Pruning, Trimming, Repairing, Maintaining, and

Removing Trees, and for Cutting Brush.

B. Council of Tree and Landscape Appraisers: Guide for Plant Appraisals, 9th edition (April 2000)

C. International Society of Arboriculture (ISA): Tree and Shrub Transplanting Manual.

D. National Arborist Association (NAA) Book of Standards, most recent edition.

1.03 DEFINITIONS

A. Tree Protection Fencing: Temporary fencing installed prior to site preparation and demolition

which protects a group of trees or shrubs.

B. Boxing: Temporary wood box form installed prior to site preparation and demolition which

protects individual trees and shrubs.

C. Root Pruning: Physical cutting of plant roots to minimize root damage and promote healing.

D. Construction Branch Pruning: Physical cutting of any branch which interferes with

construction.

1.04 SUBMITTALS

A. Comply with Section 01300. All submittals shall be accepted by the Landscape Architect in

writing before Work commences.

Page 67: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 2

B. Schedule: Submit construction schedule which includes time frame for work near existing

plant material. Provide transplanting and tree removal schedule including tree transplants and

locations. Obtain approval by Landscape Architect prior to beginning of transplanting work

and construction near restricted area.

C. Work Methods: Submit proposed methods and schedule for effecting tree and plant

protection for approval, including proposed methods, materials, and schedule for root

pruning, construction pruning, aeration, and subsequent tree fertilization. Mark plan location

of root pruning and siltation fencing in field with paint for approval by Landscape Architect.

Any root pruning which is required due to construction work adjacent to existing trees and

shrubs designated to remain shall occur any time ground can be worked except when tree or

shrubs are in leaf. Root pruning when tree or shrubs are in leaf may occur only with approval

by Landscape Architect.

1.05 QUALITY ASSURANCE

A. Comply with Division One.

B. Qualifications

1. Arborist: Company having adequate capacity and facilities to meet the specified

requirements. All tree pruning and cleaning shall be performed by a landscape

contractor with a minimum 5 years documented experience. Evidence to this effect shall

be provided by the supplier if required by the Architect.

C. Regulatory Requirements: City permits are necessary for pruning or removal of all trees in the

right-of-way.

D. Pre-Installation Conference

1. Conduct pre-installation conference prior to construction.

2. Attendance required by: Owner, Architect, Contractor(s), Manufacturer(s), /Supplier(s),

other parties who are involved.

1.06 PROJECT/SITE CONDITIONS

A. All plant materials to remain or be moved will be tagged by the Landscape Architect to assist

the Contractor in identifying the trees. Contractor to notify Landscape Architect seven (7) days

before tree relocation. All relocated plant material to be included in maintenance – see 1.7.

B. Maintain all plant materials within tree protection areas. Designated tree protection areas of

trees, shrubs, and grasses are to remain untouched and unharmed.

C. Construction activities, including stockpiling, in tree protection areas are prohibited.

D. Tree arborist shall determine and document value of each tree or other plant materials within

the limits of work line that is designated to remain. Contractor shall reimburse client for the

value of any of these trees or other plant materials that are lost or damaged during

construction.

Page 68: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 3

1.07 MAINTENANCE

A. Maintenance Services: Performed by a landscape contractor during construction and for the

first year after final completion of all site construction.

B. Maintenance Period: Begin maintenance immediately upon start of construction. Continue

maintenance until one year after final completion of all site construction.

C. Maintenance to Include:

1. Quarterly review and monitoring of tree conditions.

2. Maintaining guying and lighting protection. Repair or replace when required.

3. Water at a sufficient frequency to saturate root system and keep soil moist.

4. Pruning, including removal of dead of broken branches, and treatment of pruned areas

or other wounds.

5. Disease Control.

D. Protection: In accordance with paragraph 3.2 Preparation-B.

E. Root Zone Fertilization: Root zone fertilize all trees affected by construction. The first root

zone fertilization shall occur within 6 months after completion of site construction and the

second within 12 months. Use a liquid application with an 18 inch soil probe. Fertilization mix

shall be submitted to the Landscape Architect for acceptance prior to application.

F. Pesticides: Apply pesticides, with permission of owner, in accordance with manufacturer’s

instructions. Remedy damage resulting from improper use of pesticides.

G. Maintenance Reports: Provide maintenance report including date and detailed summary of

work completed on site, to the Landscape Architect after each maintenance visit.

PART 2 - PRODUCTS

2.01 TREE PROTECTION FENCING

A. Fencing: Galvanized chain link fencing, 6 ft. high.

1. Tree protection fencing is the property of the Contractor.

2. Gates at tree protection areas shall be 6'-0" width min. for maintenance vehicles and be

6'-0" ht. galvanized chain link fence.

B. Metal Fence Posts: 9 ft. galvanized steel posts, driven a minimum of 3 ft. into the ground.

Space 10 ft. o.c. maximum.

2.02 SILTATION CONTROL FENCING

A. Fencing: 30" height. Siltation fencing complying to local codes.

B. Posts: Attach to tree protection fencing.

Page 69: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 4

2.03 SOIL AMENDMENTS/MULCH

A. Organic compost: A-1 Premium 3 Organic Compost. Submit sample for Landscape Architect's

approval.

B. Wood Mulch: Washington Cedar Mulch.

PART 3 - EXECUTION

3.01 NEW CONSTRUCTION

A. Curb cuts should not be closer than the dripline of the tree without permission from the

Landscape Architect.

B. New sidewalks, paving or asphalt within the drip line of the tree must allow breathing space

for tree roots. The following should be used as a guideline: For trees up to 4 inches in trunk

caliper, 25 square feet of porous area is needed. For each additional 2 inches of tree caliper,

10 more square feet are needed.

C. Where grade change is required, the same area must be provided either by construction of a

drywell where the level is to be raised or by building a retaining wall where the level is to be

lowered. The grade within the drip line of the tree is not to be changed without Landscape

Architect approval.

D. Avoid cutting surface roots wherever possible. Sidewalks and paving levels would be

contoured sufficiently to avoid such cutting.

3.02 EXAMINATION

A. Verification Of Conditions: Examine areas and conditions under which the Work of this

Section will be performed. Report unsatisfactory or questionable conditions to the Landscape

Architect. Do not proceed with the Work until unsatisfactory conditions have been corrected.

Commencement of work implies acceptance of all areas and conditions.

B. Verify all utility locations in the field prior to digging.

3.03 PREPARATION

A. Marking of Construction/Demolition/Tree Preservation Limits

1. Clearly mark the tree protection fence locations, boxing, and all construction/demolition

limits in the field.

2. Mark individual tree root pruning areas and location of siltation fencing with paint.

3. Verify all trees to be removed, transplanted, or protected with Landscape Architect. Tag

all plant material with appropriate tags noting action to be taken with each plant.

4. Contact and accompany Landscape Architect on a joint review of

construction/demolition limits, tagging and painting prior to the installation of the tree

protection fencing and start work.

Page 70: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 5

5. Limit of construction is generally defined as the limit of demolition. Contractor to

immediately notify Architect if work will occur outside the construction/demolition

limits.

6. Contractor to verify limits of existing R.O.W. Contractor to obtain all necessary permits

from appropriate jurisdictions prior to commencing activity within the R.O.W.

3.04 INSTALLATION OF FENCING

A. Fencing: Install tree protection fencing prior to start of demolition work and clearing and

grubbing operations in accordance with the following:

1. Following approval of staking by the Landscape Architect, install fencing at the tree

protection areas.

2. Install fencing as approved. No fencing is allowed within three (3) feet outside the drip

line of trees.

3. Install posts 10'-0" o.c. maximum.

4. Install gates where noted on the plans.

3.05 SILTATION CONTROL

A. Fencing: Provide silt control at Tree Protection Areas by attaching silt fence to the uphill side

of the protective fencing. Place lower 6" of silt fence in trench below grade. Backfill trench.

B. Drainage: Maintain positive drainage from Tree Protection Areas. Divert runoff from site

around Tree Protection Areas.

3.06 ROOT PRUNING AND PROTECTION

A. Root Pruning

1. Prune roots where construction will sever roots.

2. Only clean cutting methods are acceptable. Root pruning is the physical cutting of tree

roots to minimize root damage and promote healing. Unsuitable means for root pruning

include trenching, vibrating plow, stump grinder. Any method which tears roots or

disturbs the soil beyond the grading limit is unacceptable.

3. Hand trim roots at trench walls. Make clean cuts through roots.

4. Prune tree roots to a depth no greater than required by construction excavation, by

approved means only. All roots shall be pruned by an approved method.

B. Backfill: Close trenches within 24 hours. Backfill root pruning trench with existing soil. Tamp

lightly to set soil.

1. When trench closing is not possible within 24 hours, protect trench side in accordance

with this Section.

C. Mulching: Apply wood mulch to a depth of 4 in. to 5 in. at minimum 10 ft. to 15 ft. radius

around tree to reduce compaction and increase moisture retention. Soil shall be kept moist in

root pruning areas.

D. Root Protection: If tree roots larger than two (2) inches in diameter are encountered with

digging or trenching, tunnel under for any improvements if possible. Dig trench by hand only.

1. Conform with paragraphs 3.6.A - 3.6.C this Section.

Page 71: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 6

2. Notify Landscape Architect to allow physical inspection of excavation around root zones

to determine damage and health of tree. Do not tear the roots out. Removal of two (2)

inches or larger diameter roots encountered during construction is not allowed without

permission of Landscape Architect.

3. Upon approval by Architect, wrap cut roots 2' and larger with burlap to prevent scarring

or excessive drying.

3.07 CONSTRUCTION BRANCH PRUNING

A. Prune any branches of trees to be preserved which interfere with construction only at the

direction of the Landscape Architect. Approval of all proposed pruning is required prior to

start of work. Pruning is an incidental pay item associated with the transplanting of existing

trees, the planting of new trees, and the care of existing trees to remain. Payments for such

incidental items shall be drawn from the project budget.

B. Remove any branches which are weak or dead.

C. Any pruning included as part of the project shall be done by a licensed tree company and in

accordance with good pruning practices as approved by the Landscape Architect. Pruning shall

maintain balance, form, and function of tree.

3.08 TEMPORARY TREE GUYING

A. Upon review of on-site root pruning and construction grading limits, the Landscape Architect

shall determine whether the existing trees designated to remain should be temporarily guyed.

B. Complete tree guying using materials and techniques designated by the Landscape Architect

in accordance with Section 02900 and complete in a timely manner.

3.09 AERATION

A. If areas inside the restricted area become compacted as determined by the Landscape

Architect, aerate to a 20 inch depth using an aeration "grow gun," avoiding damage to surface

absorbing feeder roots.

B. Inject filler material to hold aeration fractures open.

3.10 WATERING

A. Apply supplemental watering to a depth of 10-12" (18" max) with a deep root feeder if loss of

grasses or heating of the roots occurs during construction or as directed by Landscape

Architect. Approximately 100 gallons per tree shall be applied.

B. Contractor to water existing trees as determined by Landscape Architect to promote healthy,

thriving plant material.

C. Contractor and Landscape Architect to determine appropriate water pressure.

Page 72: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 7

3.11 EXCAVATION INSULATION

A. Provide mitigation from moisture and temperature fluctuations by pinning 3 layers of burlap

onto the entire face of excavations exposed for more than 24 hours.

B. Wet burlap insulation immediately following installation.

C. Keep moist for the entire period the excavation remains open.

D. Remove insulation prior to backfilling.

3.12 CHEMICALS, FERTILIZATION AND INSECT SPRAYING

A. No chemicals shall be applied or used around or near existing trees.

B. No fertilizers, insect sprays or other chemicals shall be applied before or during root or branch

pruning process.

3.13 CONCRETE WASHOUT

A. Provide concrete washout in areas which drain away from the Tree Protection Areas as

indicated on the Drawings. The Landscape Architect shall approve concrete washout area

prior to the start of any site work.

3.14 GRADING AT TREE PROTECTION AREAS

A. All grading within protected areas shall proceed only after review and approval by the

Landscape Architect.

B. All fill within protected areas must be approved by the Landscape Architect. Tamping of fill

earth shall be allowed; compaction of fill earth shall not be allowed. No "cutting" of grades in

root area shall be allowed.

3.15 FIELD QUALITY CONTROL/DAMAGE PENALTIES

A. Trees labeled as requiring "General Protection" or "Special Protection" adjacent to

construction areas and in other key locations are identified on the Drawings. Loss of any of

these trees due to Contractor neglect or improper construction activities will result in

liquidated damages for the assessed value of the tree as determined by a licensed arborist.

Damage to a portion of these trees will be assessed by the arborist and a portion of the

liquidated damages will be assessed to the Contractor. A list of tree values for the project will

be on file in the Landscape Architect's office. Any damaged tree not on this list shall be

evaluated by the Architect as necessary to comply with this penalty.

B. A fine of $1,000 will be levied against the Contractor for each incident of construction

(including construction traffic) inside tree protection areas.

C. Trees or roots visibly damaged will cause the Owner to withhold from the Contractor an

assessed amount conforming to the requirements stipulated above, for a period of two years.

Page 73: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 8

After that period the impact of the damage to any tree will be assessed by the Landscape

Architect.

D. If any trees or shrubs designated to be saved are damaged and replacement is required, a

number and diameter of trees or shrubs of the same species and variety, as specified by the

Landscape Architect, shall be furnished and planted by the Contractor. The total inch diameter

of the replacement trees or shrubs shall equal the diameter of the tree or shrub to be

replaced as measured by The Guide for Establishing Value of Trees and Other Plants,

published by the International Society of Arboriculture. The Contractor shall not be liable for

any loss or damage which occurs while the Contractor is complying with instructions given by

the Landscape Architect working on the Project.

3.16 ADJUSTING

A. Tree Protection Area Access: When construction traffic is unavoidable as concurred by the

Contractor and Landscape Architect the following procedure shall be followed:

1. Obtain approval from the Landscape Architect for Tree Protection Area access.

2. Install protective fencing by hand to delineate the construction corridor. Fencing

location must be approved on site by the Landscape Architect.

3. Install a 12" layer of wood chips overlaid with continuous 3/4" plywood sheets on the

existing grade for the entire area of the traffic route to allay rutting and slightly reduce

soil compaction.

4. Remove all materials and return area to preconstruction condition within one week of

the work.

B. Excavation Insulation: If in the Contractor's opinion, climate conditions do not necessitate the

installation of burlap insulation at an excavation, he may submit to the Landscape Architect a

written request to omit the burlap insulation. Submit request to the Landscape Architect 24

hours prior to excavation.

3.17 CLEANING

A. Removal Of Protection: Except as otherwise indicated or requested by Engineer, temporary

protection devices and facilities installed during course of the work shall be removed only

after all work which may injure or damage trees and plants are completed.

B. Removal: Remove all excess material during construction period and haul off-site.

C. Repair: Repair surface damage caused by fence posts. Restore to match surrounding

conditions.

3.18 PROTECTION

A. Protect planting areas and plants at all times against damage of any kind for the duration of

the maintenance. If any plants become damaged of injured, they shall be treated or replaced

as directed by the Landscape Architect at no additional cost to the Owner. The contractor shall

not be responsible for acts of vandalism or acts of God during the maintenance period.

B. Protect tree roots in accordance with paragraph 3.7 this Section.

Page 74: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM-M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TREE AND PLANT PROTECTION

02111 - 9

C. Branch Protection: Contact Landscape Architect if it appears that construction will damage to

the branches of any tree. The Landscape Architect will determine action to be taken. If

pruning is required, perform in accordance with paragraph 3.8 this Section.

END OF SECTION

Page 75: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 1

SECTION 321216

ASPHALT PAVING

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Specification Sections, apply to this Section.

B. Additional information concerning asphalt paving may be found on the civil drawings, in the

project geotechnical report and University of Colorado Boulder and City of Boulder construction

standards. In case of conflict between the drawings, jurisdictional criteria and the information

specified herein, the more stringent requirements shall govern.

1.02 SUMMARY

A. This Section includes the following:

1. Hot-mix asphalt paving.

2. Hot-mix asphalt patching.

3. Field Quality Control.

4. Weed Control.

B. Related Sections include the following:

1. Section "Earthwork" for soil materials, excavating, backfilling and site grading.

2. Section “Pavement Markings” for pavement striping and symbols.

C. References:

1. University of Colorado Boulder and City and County of Boulder Standard Specifications

for Design and Construction, latest edition.

2. Colorado Department of Transportation Standard Specifications for Road and Bridge

Construction, current edition and all appropriate standard special provisions.

1.03 DEFINITIONS

A. Hot-Mix Asphalt Paving Terminology: Refer to ASTM D 8 for definitions of terms.

B. CDOT: State of Colorado Department of Transportation.

C. CDOT Specifications: Colorado Department of Transportation Standard Specifications for Road

and Bridge Construction, current edition and all appropriate standard special provisions.

1.04 SYSTEM DESCRIPTION

A. Provide hot-mix asphalt paving in accordance with Section 401 of the CDOT Specifications.

1. Standard Specification: CDOT Specifications.

Page 76: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 2

2. Measurement and payment provisions and safety program submittals included in CDOT

Specifications do not apply to this Project.

1.05 SUBMITTALS

A. Product Data: For each type of product indicated, include technical data and tested physical

and performance properties.

B. Job-Mix Designs: For each job mix proposed for the Work.

C. Material Test Reports: For each paving material.

D. Material Certificates: Two (2) copies for each paving material, signed by providers.

E. Submit complete manufacture’s data for each product used and report manufacture’s safety

data sheets, method of application and location of application.

F. Recycled Asphalt Content Data Sheets: Recycled asphalt content data sheets must be submitted

to Parking and Transportation Services (PTS) for review and approval for any usage in parking

controlled areas. PTS may require that lower percentages of recycled content be used in certain

parking areas..

G. Weed Control Products: Submit complete manufacturer’s data for each product to be used.

H. Traffic Control Plan: Provide 2 copies of a temporary vehicular and pedestrian traffic control

plan for approval by the UCB Civil Engineer.

1.06 QUALITY ASSURANCE

A. Manufacturer and Installer Qualifications:

1. Manufacturer Qualifications: Engage a firm experienced in manufacturing hot-mix

asphalt similar to that indicated for this Project and with a record of successful in-service

performance.

2. Installer Qualifications: Engage an experienced installer who has completed hot-mix

asphalt paving similar in material, design, and extent to that indicated for this Project and

with a record of successful in-service performance.

B. Testing Agency:

1. All testing and inspections required herein will be performed by an independent testing

and inspection agency employed by the Contractor.

2. Notify the testing and inspection agency not less than 48 hours in advance of all work

requiring testing or inspection services.

C. Testing Requirements:

1. All testing and inspections required herein will be performed by an independent testing

and inspection agency employed by the Contractor. All documentation, including the

Compaction Test Reports shall be given to the Owner’s Representative at the end of each

working day, specifying road names and termini. Three core drill samples shall be taken

by the Contractor of each lot for quality control purposes. Contractor shall be responsible

Page 77: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 3

for any delay caused by the Contractor’s laboratory, which may affect the Contractor’s

work performance on the project. Contractor shall be responsible for any performance

on the project. Any retesting required due to failed test shall be paid by the Contractor.

2. Asphalt paving shall be tested for gradation, asphalt content, and in-place density in

accordance with the Colorado Department of Transportation’s “Standard Specifications

for Road and bridge Construction”. Latest Edition, and the current edition of CDOT Field

Materials Manual, whichever is more stringent.

3. Field-testing shall be performed by the paving Contractor’s certified nuclear gauge

operator and monitored by the Owner’s Representative. The Contractor’s nuclear gauge

operator shall be on site at all times when paving operations occur.

4. Notify the testing and inspection agency with adequate time in advance of all work

requiring testing or inspection services. In addition, Work shall not be allowed to be

placed if testing and inspection agency are not onsite for required services.

5. All test results shall be submitted to the Owner within 48 hours of the test.

6. Provide CU Parking services with Asphalt Density tests performed in parking areas, within

24 hours of the testing.

D. Preconstruction Conference: Conduct conference at Project site as directed by Owner’s

Representative. Contractor to comply with requirements, which may also be included in Section

"Project Management and Coordination."

1.07 PROJECT CONDITIONS

A. Environmental Limitations: Do not apply asphalt materials if subgrade is wet or excessively

damp or if the following conditions are not met:

1. Tack Coats: Minimum surface or air temperature in the shade of 60 deg F (15 deg C).

2. Asphalt Base Course: Minimum surface or air temperature in the shade of 40 deg F and

rising at time of placement.

3. Asphalt Surface Course: Minimum surface or air temperature in the shade of 50 deg F

and rising at time of placement.

B. Coordination and Scheduling:

1. Cooperate with other trades and arrange scheduling to avoid damage to other work,

including grading, site utilities and piping, exterior concrete, landscaping and irrigation

systems.

2. Before commencing pavement operations, ascertain that utility lines, site lighting and

wiring, piping, curb and gutter work, general grading and heavy trucking is complete so

that such operations will not damage paving work.

3. Mask off and protect exposed building surfaces and abutting concrete from damage or

staining by tack coat and paving operations.

PART 2 - PRODUCTS

2.01 DESIGN

A. The designer shall follow the recommendations of the geotechnical engineer with regard to

pavement design, including but not limited to asphalt cement type, subgrade thickness, and

Page 78: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 4

pavement thickness. If a geotechnical engineer has not been retained for the work, then the

minimum standards contained in this section shall be used.

B. Design Traffic: Shall be made based on specific traffic loadings or the geotechnical engineer’s

recommendations. In the absence of such information, the following recommended EDLA value

shall be used.

Road types EDLA Value

UCB campus collector streets 50

UCB campus drives 30

Parking lots and stalls 30

C. The asphalt material used shall be based on s SuperPave Gyratory Design Method.

D. Asphalt pavements may not be used in loading docks and high turning stress areas.

2.02 AGGREGATES

A. General: Use materials and gradations that have performed satisfactorily in previous

installations meeting the requirements of the CDOT Specifications.

B. Base Course Aggregate: Per section 703.03, Class 6, Colorado Department of Transportation

Specifications, and Geotech recommendations.

1. Minimum Thickness: 12”

C. Asphalt Concrete Aggregate: Use clean. Hard, durable particles of crushed stone, crushed slag,

crushed gravel, or natural gravel, Per Section 703.04, Colorado Department of Transportation

Specifications, Gradation SG(75) for base course and S(75) for surface course.

1. Minimum Thickness Over Aggregate Base: 5.5”

D. Mineral Filler: Limestone dust, Portland cement, or other inert material complying with ASTM

D242 or AASHTO M17.

2.03 ASPHALT MATERIALS

A. Asphalt Cement: The asphalt cement to be used on this project shall be PG 64-22 conforming

to the requirements of Subsection 702.01 of the CDOT Specifications.

1. Asphalt Cement:

a. For parking facilities: Use PG 64-22 conforming to the requirements of Section 702

of CDOT Specifications and ASTM D3381 or AASHTO M226 Table 1, Viscosity Grade

AC-10 or AC-20.

b. For all other locations: Use PG 58-28 conforming to the requirements of Section

702 of CDOT Specifications and ASTM D3381 or AASHTO M226 Table 1, Viscosity

Grade AC-10 or AC-20.

Page 79: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 5

B. Tack Coat: AASHTO M 140, emulsified asphalt or AASHTO M 208, cationic emulsified asphalt,

slow setting, diluted in water, of suitable grade and consistency for application.

C. Prime Coat: Cut back asphalt type, ASTM D2022 or AASHTO M82, MC 30, MC70, or MC-250.

D. Water: Potable.

E. Reclaimed Asphalt Pavement (RAP): Up to 20% RAP may be used in the mix design. Submit RAP

to UCB Parking Services for approval, per the submittals section.

2.04 MIXES

A. Hot-Mix Asphalt: Dense, hot-laid, hot-mix asphalt plant mixes. Furnish job-mix formulas for

each pavement type, conforming to the requirements of Subsection 401.02 of the CDOT

Specifications. Mix aggregates and bituminous materials in accordance with the requirements

of Subsection 401.15 of the CDOT Specifications. Use approved job mix formulas. Mix to comply

with the following requirements:

1. Provide mixes with a history of satisfactory performance in geographical area where

Project is located.

2. Base Course: Grading SG(75).

3. Surface Course: Grading S(75).

B. Emulsified-Asphalt: Shall conform to AASHTO M140 or M208 in accordance with Subsection

702.03 of the CDOT Specifications.

C. Mixes shall be designed for an Equivalent Single Axel Loading (ESAL) range of 0.3 to <3.0 million

ESAL’s (compaction level 2) and a seven (7) Day Average Design Air Temperature #39EC.

PART 3 - EXECUTION

3.01 PREPARATION

A. Verify that subgrade is unfrozen, free of water, snow, and ice otherwise in suitable condition to

support paving and imposed loads.

B. Proof-roll subbase using heavy, pneumatic-tired rollers to locate areas that are unstable or that

require further compaction. Scarify, regrade and recompact surface of subgrade that is

pumping or deforming as required to provide true levels, uniform slopes and proper total

thickness of paving as required in Section “Earthwork.”

C. Proceed with paving only after unsatisfactory conditions have been corrected.

D. Minimum temperature of surface or air shall be 60 degrees F and rising at time of placement.

E. Verify and maintain the existing drainage pattern(s) of each area to be milled, receive an overlay

or patch including special attention to infrastructure such as tie-ins, inlets, chase drains and

other identified patterns.

Page 80: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 6

3.02 PATCHING

A. Hot-Mix Asphalt Pavement: Saw cut perimeter of patch and excavate existing pavement section

to sound base. Excavate rectangular or trapezoidal patches, extending 12 inches into adjacent

sound pavement, unless otherwise indicated. Cut excavation faces vertically. Remove

excavated material. Recompact existing unbound-aggregate base course to form new subgrade.

B. Tack Coat: Apply uniformly to vertical surfaces abutting or projecting into new, hot-mix asphalt

paving at a rate of 0.05 to 0.2 gal./sq. yd. (0.2 to 0.8 L/sq. m).

1. Allow tack coat to cure undisturbed before applying hot-mix asphalt paving.

2. Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove

spillages and clean affected surfaces.

C. Patching: Partially fill excavated pavements with hot-mix asphalt base mix and, while still hot,

compact. Cold-mill adjacent pavement as indicated on the plans then. Cover asphalt base

course with compacted, hot-mix surface layer finished flush with adjacent surfaces.

3.03 COLD MILLING

A. Clean existing pavement surface of loose and deleterious material immediately before cold

milling. Remove existing asphalt pavement by cold milling to grades and cross sections indicated.

1. Mill to a depth of a minimum 2-inches.

2. Mill to a uniform finished surface free of gouges, grooves, and ridges.

3. Control rate of milling to prevent tearing of existing asphalt course.

4. Repair or replace curbs, manholes, and other construction damaged during cold milling.

5. Excavate and trim unbound-aggregate base course, if encountered, and keep material

separate from milled hot-mix asphalt.

6. Transform milled hot-mix asphalt to CDOT approved asphalt recycling facility.

7. Keep milled pavement surface free of loose material and dust.

3.04 JOINING TO EXISTING WORK:

A. When joining to existing work, the Contractor will mill a minimum of 2 feet into the existing

asphalt to apply a 2-inch overlay. Apply tack coat to exposed asphalt surfaces before placing

new pavement. Meet existing thickness or surface and base courses, but not less than specified

for new work.

B. Where new work joins existing asphaltic concrete paving on City of Boulder right-of-way,

comply with the requirements of City of Boulder authorities for surface and base course

thickness.

C. Contact surfaces of curbing, gutters, manholes, and other structures shall be painted with a

uniform coating of bituminous material prior to placing bituminous mixture against them.

3.05 REPAIRS

A. Contractor shall protect the pavement against damage from all causes associated with

construction activities. Any part of the pavement that is damaged shall be repaired or replaced

by and at the expense of the Contractor.

Page 81: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 7

B. Leveling Course: Install and compact leveling course consisting of hot-mix asphalt surface

course to level sags and fill depressions deeper than 1 inch in existing pavements.

C. Crack and Joint Filling: Remove existing joint filler material from cracks or joints to a depth of ¼

inch.

1. Clean cracks and joints in existing hot-mix asphalt pavement.

2. Use emulsified-asphalt slurry to seal cracks and joints less than ¼ inch wide. Fill flush with

surface of existing pavement and remove excess.

3. Use hot-applied joint sealant to seal cracks and joints more than ¼ inch wide. Fill flush

with surface of existing pavement and remove excess.

D. Hot-applied joint sealant being a single-component formulation complying with ASTM D 3405

or D1190.

1. Refer to CDOT Standard Specification, Section 702.06 for joint and crack sealant material

requirements.

2. Refer to CDOT Standard Specification, Section 408.01 and 408.03 for joint and crack

sealant installation requirements.

3.06 SURFACE PREPARATION

A. General: Shortly before paving, the pavement subgrade should be excavated and/or scarified

to a depth of at least 24 inches, moisture conditioned, and properly recompacted. Immediately

before placing asphalt materials, remove loose and deleterious material from substrate

surfaces. Ensure that prepared subgrade is ready to receive paving. Subgrade preparation

should extend the full width of the pavement from back-of-curb to back-of-curb.

1. Sweep loose granular particles from surface of unbound-aggregate base course. Do not

dislodge or disturb aggregate embedded in compacted surface of base course.

2. Contact surfaces of curbing, gutters, manholes and other structures shall be painted with

a uniform coating of asphalt cement prior to placing asphalt mixture against them.

B. Weed Control:

1. If vegetation exists on subgrade, remove surface vegetation within 3 days prior to

application of Casoron or apply “Roundup” at rates following manufacturer’s instructions.

2. Apply Casoron weed control at rate of 2.4 lbs per 100 sq.yds. for G-10 or 4.0 lbs. for W-

50. Apply by methods recommended by manufacturer.

3. Exercise care and be responsible for damage to vegetation outside area to be treated due

to careless or improper handling or use of weed control.

4. Conform to State and local requirements for use of agricultural chemicals.

C. Tack Coat: Apply uniformly to surfaces of existing pavement at a rate of 0.05 to 0.20 gal./sq.

yd. (0.2 to 0.8 L/sq. m).

1. Allow tack coat to cure undisturbed before applying hot-mix asphalt paving.

2. Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove

spillages and clean affected surfaces.

Page 82: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 8

3.07 SURFACE TREATMENTS

A. Fog Seals: Apply fog seal at a rate of 0.10 to 0.15 gal./sq. yd. (0.45 to 0.7 L/sq. m) to existing

asphalt pavement and allow to cure. With a fine sand, slightly dust areas receiving excess fog

seal.

B. Chip Seal: Apply emulsified asphalts in accordance with CDOT Section 702.03

3.08 HOT-MIX ASPHALT PLACING

A. Machine place hot-mix asphalt on prepared surface, spread uniformly, and strike off. Place

asphalt mix by hand to areas inaccessible to equipment in a manner that prevents segregation

of mix. Place each course to required grade, cross section, and thickness when compacted.

1. Place hot-mix asphalt base course in number of lifts and thicknesses indicated on the

plans or as directed by Geotechnical Report. Maximum lift thickness shall be 3-inches.

Minimum lift thickness shall be 1½-inches for Grading SX and 2-inches for Grading S.

2. Place hot-mix asphalt surface course in single lift. Maximum lift thickness shall be 2-

inches.

3. Spread mix at minimum temperature of 235 deg F (113 deg C) per in accordance with

Subsection 401.15 of the CDOT Specifications, Table 401-5.

4. Begin applying mix along centerline of crown for crowned sections and on high side of

one-way slopes, unless otherwise indicated.

5. Regulate paver machine speed to obtain smooth, continuous surface free of pulls and

tears in asphalt-paving mat.

B. Place paving in consecutive strips not less than 10 feet wide unless infill edge strips of a lesser

width are required.

1. After first strip has been placed and rolled, place succeeding strips and extend rolling to

overlap previous strips. Complete a section of asphalt base course before placing asphalt

surface course.

C. Promptly correct surface irregularities in paving course behind paver. Use suitable hand tools

to remove excess material forming high spots. Fill depressions with hot-mix asphalt to prevent

segregation of mix; use suitable hand tools to smooth surface.

3.09 JOINTS

A. Construct joints to ensure a continuous bond between adjoining paving sections. Construct

joints free of depressions with same texture and smoothness as other sections of hot-mix

asphalt course.

1. Clean contact surfaces and apply tack coat to joints.

2. Offset longitudinal joints, in successive courses, a minimum of 6 inches.

3. Offset transverse joints, in successive courses, 6 to 12 inches.

4. Construct transverse joints as described in AI MS-22, "Construction of Hot Mix Asphalt

Pavements."

5. Compact joints as soon as hot-mix asphalt will bear roller weight without excessive

displacement.

6. Compact asphalt at joints to a density within 2 percent of specified course density.

Page 83: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 9

3.10 COMPACTION

A. General: Begin compaction as soon as placed hot-mix paving will bear roller weight without

excessive displacement. Compact hot-mix paving with hot, hand tampers or vibratory-plate

compactors in areas inaccessible to rollers.

1. When paving surface temperature falls below 185 deg F (85 deg C) no further compaction

effort will be permitted unless approved.

B. Breakdown Rolling: Complete breakdown or initial rolling immediately after rolling joints and

outside edge. Examine surface immediately after breakdown rolling for indicated crown, grade,

and smoothness. Correct laydown and rolling operations to comply with requirements.

C. Intermediate Rolling: Begin intermediate rolling immediately after breakdown rolling while hot-

mix asphalt is still hot enough to achieve specified density. Continue rolling until hot-mix

asphalt course has been uniformly compacted to the following density in accordance with

Subsection 401.17 of the CDOT Specifications.

1. Pavement shall be compacted to a density of 92-96 percent of the maximum theoretical

density, determined according to Colorado procedure 51. Field density determination

will be in accordance with Colorado Procedure 44 or 81.

2. Owner will check compaction and compliance with design mix by cutting test plugs where

directed in accordance with ASTM D1559. Patch core holes. Owner will test for

compaction minimum of 92-96% of Marshall Design, aggregate gradation, voids and

percent asphalt.

D. Finish Rolling: Finish roll paved surfaces to remove roller marks while hot-mix asphalt is still

warm.

E. Edge Shaping: While surface is being compacted and finished, trim edges of pavement to proper

alignment. Bevel edges while asphalt is still hot; compact thoroughly.

F. Repairs: Remove paved areas that are defective or contaminated with foreign materials and

replace with fresh, hot-mix asphalt. Compact by rolling to specified density and surface

smoothness.

G. Protection: After final rolling, do not permit vehicular traffic on pavement until it has cooled

and hardened.

H. Erect barricades to protect paving from traffic until mixture has cooled enough not to become

marked.

3.11 INSTALLATION TOLERANCES

A. Thickness: Compact each course to produce the thickness indicated within the following

tolerances:

1. Base Course: Plus or minus ¼ inch.

2. Surface Course: Plus ¼ inch, no minus.

Page 84: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 10

B. Surface Smoothness: Compact each course to produce a surface smoothness within the

following tolerances as determined by using a 10-foot straightedge applied transversely or

longitudinally to paved areas:

1. Base Course: ¼-inch.

2. Surface Course: 3/16-inch.

3. Crowned Surfaces: Test with crowned template centered and at right angle to crown.

Maximum allowable variance from template is ¼-inch.

3.12 MANHOLE FRAME ADJUSTMENTS

A. Set frames for manholes and other such units within areas to be paved to ¼-inch minimum to

½-inch maximum below final grade as part of this work. Include existing frames or new frames

furnished under other sections of these specifications.

B. Set cover frames to ¼-inch below surface of adjacent pavement. Surround frames set to grade

with a ring of compacted asphaltic concrete base prior to paving. Place asphaltic concrete

mixture up to 1-inch below top of frame, slope to grade, and compact with hand tamping.

Adjust frames as required for paving.

C. Provide temporary closures over openings until completion of rolling operations. Remove

closures at completion of work.

D. Contractor shall provide manhole and valve risers.

3.13 TESTING REQUIREMENTS

A. All testing and inspections required herein will be performed by and independent testing and

inspection agency employed by the Contractor to perform field tests and inspections and to

prepare test reports. All documentation, including the Compaction Test Reports shall be given

to the Owner’s Representative at the end of each working day, specifying road names and

termini. Three core drill samples shall be taken by the Contractor of each lot for quality control

purposes. Contractor shall be responsible for any delay caused by the Contractor’s laboratory,

which may affect the Contractor’s work performance on the project. Any retesting required due

to failed test shall be paid by the Contractor.

1. Testing agency will conduct and interpret tests and state in each report weather tested

work complies with or deviates from specified requirements.

2. Additional testing and inspecting, at Contractor’s expense, will be performed to

determine compliance of replaced or additional wok with specified requirements.

B. Asphalt paving shall be tested for gradation, asphalt content, and in-place density in accordance

with the Colorado Department of Transportation’s “Standard Specifications for Road and Bride

Construction”, Latest Edition, and the current edition of CDOT Field Materials Manual,

whichever is more stringent.

C. Field-testing shall be performed by the paving contractor’s certified nuclear gauge operator and

monitored by the Owner’s Representative. The contractor’s nuclear gauge operator shall be on

site at all times when paving operations occur.

Page 85: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 11

D. Thickness: In-place compacted thickness of hot-mix asphalt courses will be determined

according to AST 3549.

E. Surface Smoothness: Finished surface of each hot-mix asphalt course will be tested for

compliance with smoothness tolerances.

F. In-Place Density: Testing agency will take samples of un-compacted paving mixtures and

compacted pavement according to ASTM D 979.

1. Reference maximum theoretical density will be determined by averaging results from four

samples of hot-mix asphalt-paving mixture delivered daily to site, prepared according to

ASTM D 2041, and compacted according to job-mix specifications.

2. In-place density of compacted pavement will be determined by testing core samples

according to ASTM D 1188 or ASTM D 2726.

a. One core sample will be taken for every 350 sq. yd. or less of installed pavement,

with no fewer than 3 cores taken.

b. Field density o in-place compacted pavement may also be determined by nuclear

method according to ASTM D 2950 and correlated with ASTM D 1188 or ASTM D

2726.

G. Asphalt Content and Gradation. Testing agency will take sample of un-compacted paving

mixtures at a minimum frequency of every 1,000 tons according to Colorado Procedure –

Laboratory CPL-5120 and Colorado Procedure CP-31

H. Remove and replace or install additional hot-mix asphalt where test results of measurements

indicate that it does not comply with specified requirements. Conforming to the specified

requirements will be in accordance with Subsection 105.03 of the CDOT Specifications.

I. All test results shall be submitted to the Owner within 48 hours of the test.

3.14 FIELD QUALITY CONTROL

A. Testing Agency: Contractor will engage a qualified independent testing and inspecting agency

to perform field tests and inspections and to prepare test reports.

1. Testing agency will conduct and interpret tests and state in each report whether tested

work complies with or deviates from specified requirements. In-place compacted

thickness will not be acceptable if exceeding following allowable variation from required

thickness.

a. Base Course: plus/minus 0.25”

b. Surface Course: +0.25”: (no minus)

B. Additional testing and inspecting, at Contractor's expense, will be performed to determine

compliance of replaced or additional work with specified requirements.

C. Thickness: In-place compacted thickness of hot-mix asphalt courses will be determined

according to ASTM D 3549.

D. Surface Smoothness: Finished surface of each hot-mix asphalt course will be tested for

compliance with smoothness tolerances. Owner will test finished surface of each asphaltic

concrete course for smoothness, using 10’ straightedge applied with, and right angles to

Page 86: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 12

centerline of paved area. Surfaces will not be acceptable if exceeding the following tolerance

for smoothness.

Wearing Course Surface: 0.1875”.

E. In-Place Density: Testing agency will take samples of un-compacted paving mixtures and

compacted pavement according to ASTM D 979.

1. Reference maximum theoretical density will be determined by averaging results from four

samples of hot-mix asphalt-paving mixture delivered daily to site, prepared according to

ASTM D 2041, and compacted according to job-mix specifications.

2. In-place density of compacted pavement will be determined by testing core samples

according to ASTM D 1188 or ASTM D 2726.

a. One core sample will be taken for every 350 sq. yd. or less of installed pavement,

with no fewer than 3 cores taken.

b. Field density of in-place compacted pavement may also be determined by nuclear

method according to ASTM D 2950 and correlated with ASTM D 1188 or ASTM D

2726.

F. Asphalt Content and Gradation. Testing agency will take sample of un-compacted paving

mixtures at a minimum frequency of every 1,000 tons according to Colorado Procedure –

Laboratory CPL-5120 and Colorado Procedure CP-31.

G. Remove and replace or install additional hot-mix asphalt where test results or measurements

indicate that it does not comply with specified requirements. Conforming to the specified

requirements will be in according with Subsection 105.03 of the CDOT Specifications.

3.15 DISPOSAL

A. Except for material indicated to be recycled, remove excavated materials from project site and

legally dispose of them in an EPA-approved landfill.

1. Do not allow excavated materials to accumulate on-site.

3.16 MEASUREMENT AND PAYMENT

A. At any time during the period of the contract, the Owner and/or Owner’s Representative may

increase, delete, or substitute tonnage and/or quantities listed herein.

B. Unless otherwise specified, payment will be made based upon the in-place quantities measured

by the Owner’s Representative and rounded to the nearest unit.

C. Hot Mix Asphalt pavements will be measured and paid for at the Contract unit price bid per ton

for the respective types of HMA. The payment will be full compensation for furnishing, hauling,

placing, testing (including field and laboratory), tack coat, labor, temporary traffic control,

equipment, tools and incidentals necessary to complete the work. Payment for line striping and

permanent pavement markings will be inclusive to the per ton price bid for HMA.

D. Geosynthtic waterproof paving mat will be measured and paid for at the Contract unity price

per SY as measured to the nearest .1’ and rounded to the nearest SY. The payment will be full

compensation for furnishing, hauling, placing, testing (including field and laboratory) tack

Page 87: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

ASPHALT PAVING

321216 - 13

coat/binders, labor, traffic control, equipment, tools and incidentals necessary to complete the

work.

END OF SECTION

Page 88: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 1

SECTION 321313

CONCRETE PAVEMENT

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Specification Sections, apply to this Section.

1.02 SUMMARY

This Section includes constructing exterior concrete paving on prepared subgrade or base

course in accordance with these specifications. This work shall be in conformity with the lines,

grades, thicknesses and typical cross-sections shown on the plans for the following:

1. Driveways and roadways.

2. Curbs and gutters.

3. Sidewalks, steps, ramps.

4. As detailed on the plans.

Related Sections include the following:

1. Section "Earthwork" for subgrade preparation, grading, and subbase course.

2. Section “Pavement Marking” for pavement striping and symbols.

3. Section “Pavement Joint Sealants” for expansion and contraction joints.

1.03 REFERENCES

University of Colorado Boulder and City of Boulder Standard Specifications for Design and

Construction, latest edition.

Colorado Department of Transportation Standard Specifications for Road and Bridge

Construction, current edition.

1.04 DEFINITIONS

Cementitious Materials: Portland cement alone or in combination with one or more of blended

hydraulic cement, expansive hydraulic cement, fly ash and other pozzolans, ground granulated

blast-furnace slag, and silica fume.

CDOT: State of Colorado Department of Transportation.

CDOT Specifications: Colorado Department of Transportation Standard Specifications for Road

and Bridge Construction, current edition.

ADA Handbook: Americans with Disabilities Act Standards for Accessible Design, U.S.

Department of Justice.

Page 89: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 2

ANSI A117.1: Standard for Accessible and Usable Buildings and Facilities, American National

Standard Institute.

Refer to ACI 301: (American Concrete Institute – Standard Specifications for Structural

Concrete), for additional definitions.

1.05 SUBMITTALS

Product Data: For each type of manufactured material and product indicated.

Design Mixes: For each concrete pavement mix, and includes alternate mix designs when

characteristics of materials, project conditions, weather, test results, or other circumstances

warrant adjustments.

Material Test Reports: From a qualified testing agency indicating and interpreting test results

for compliance of the following with requirements indicated, based on comprehensive testing

of current materials:

1. Aggregates.

2. Cement.

3. Admixtures.

Material Certificates: Signed by manufacturers certifying that each of the following materials

used in the project complies with requirements:

1. Cementitious materials and aggregates.

2. Steel reinforcement and reinforcement accessories.

3. Admixtures.

4. Curing compounds.

5. Applied finish materials.

6. Bonding agent or adhesive.

7. Joint fillers.

Field quality-control test reports.

Pavement Joint Layout Plan: Plan to show joint locations and typical dimensions for review and

approval by engineer.

Traffic Control Plan: For work in the public right-of-way. Including Pedestrian Control Plan.

Shop Drawings: Submit sections and details where not fully dimensioned on the drawings.

1.06 QUALITY ASSURANCE

Installer Qualifications: An experienced installer who has completed pavement work similar in

material, design, and extent to that indicated for this Project and whose work has resulted in

construction with a record of successful in-service performance.

Manufacturer Qualifications: Manufacturer of ready-mixed concrete products complying with

ASTM C 94/C 94 M requirements for production facilities and equipment.

Page 90: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 3

1. Manufacturer must be certified according to the National Ready Mix Concrete

Association's (NRMCA) Plant Certification Program.

Testing Agency Qualifications: An independent agency qualified according to ASTM C1077 and

ASTM E 329 for testing indicated, as documented according to ASTM E 548.

1. Personnel conducting field tests shall be qualified as ACI Concrete Field Testing

Technician, Grade 1, according to ACI CP-01 or an equivalent certification program.

Source Limitations: Obtain each type or class of cementitious material of the same brand from

the same manufacturer's plant and each aggregate from one source.

ACI Publications: Comply with ACI 301, "Specification for Structural Concrete," unless modified

by the requirements of the Contract Documents.

Concrete Testing Service: The Owner will engage a qualified independent testing agency to

perform material evaluation tests and to design concrete mixtures.

Preconstruction Conference: Conduct conference at project site as directed by Owner’s

Representative prior to start of construction. Contractor to comply with requirements, which

may also be included in Section “Project Management and Coordination.”

Regulatory Requirements:

Comply with University of Colorado Boulder and City of Boulder standards for sidewalks, curbs,

ramps, gutters, and driveway approaches or aprons, including standard dimensions, profiles,

thicknesses, reinforcing, and compressive strength. In the event of conflict between the

Contract Documents and the standards, the more stringent requirements will apply.

1. Comply with applicable requirements of ADA Handbook, ANSI A117.1, and local and State

codes and ordinances regarding walks, steps, ramps and curb ramps.

Record of Work: Provide record of time and date of placement, temperature, and weather

conditions.

1.07 PROJECT CONDITIONS

Traffic Control: Maintain access for vehicular and pedestrian traffic as required for other

construction activities.

Coordination and Scheduling: Coordinate with other trades and arrange scheduling to avoid

damage to other work including grading, site utilities and piping, asphalt paving, landscaping

and irrigation systems.

Field Measurements: Verify dimensions and existing conditions shown on the drawings by

taking field measurements prior to start of work. Report discrepancies to the Owner’s

Representative for clarification and make minor adjustments in layout as required by field

conditions and as approved by the Owner’s Representative, at no additional cost to the Owner.

Environmental Requirements: Perform work only under suitable weather conditions. Comply

with the environmental requirements of Section 3.6 for concrete placement.

Page 91: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 4

PART 2 - PRODUCTS

2.01 MANUFACTURERS

In other Part 2 articles where titles below introduce lists, the following requirements apply to

product selection:

Available Products: Subject to compliance with requirements, products that may be

incorporated into the Work include, but are not limited to, products specified.

Products: Subject to compliance with requirements, provide one of the products

specified.

Available Manufacturers: Subject to compliance with requirements, manufacturers

offering products that may be incorporated into the Work include, but are not limited to,

manufacturers specified.

Manufacturers: Subject to compliance with requirements, provide products by one of the

manufacturers specified.

2.02 FORMS

Form Materials: Plywood, metal, metal-framed plywood, or other approved panel-type

materials to provide full-depth, continuous, straight, smooth exposed surfaces.

Use flexible or curved forms for curves of a radius 100 feet or less.

Form-Release Agent: Commercially formulated form-release agent that will not bond with,

stain, or adversely affect concrete surfaces and will not impair subsequent treatments of

concrete surfaces.

2.03 STEEL REINFORCEMENT

Reinforcement Bars: CDOT Section 709 and ASTM A 615/A 615M, Grade 60, deformed. Cut

bars true to length with ends square and free of burrs.

Reinforcement Bars: ASTM A615 and Supplement 1, Grade 60, epoxy coated. Required for

entrance and exit points to parking facilities.

Joint Dowel Bars: Plain steel bars, CDOT Section 709 and ASTM A 615/A 615M, Grade 60. Cut

bars true to length with ends square and free of burrs.

Tie Bars: CDOT Section 709 and ASTM A 615/A 615M, Grade 60, deformed.

Welded with Fabric: ASTM A185 Supply 6”x6”/WL4xW1.4 in sheets minimum.

Supports for Reinforcement: Chairs, spacers, and other devices for spacing, supporting, and

fastening reinforcement bars, welded wire fabric, and dowels in place. Manufacture bar

supports according to CRSI's "Manual of Standard Practice" from steel wire, plastic, or precast

concrete or fiber-reinforced concrete of greater compressive strength than concrete, and as

follows:

1. Equip wire bar supports with sand plates or horizontal runners where base material will

not support chair legs.

Page 92: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 5

2.04 FIBER REINFORCEMENT

Fibrous reinforcement collated fibrillated, polypropylene fibers containing no reprocessed

olefin materials and having a tensile strength of 70,000 psi. Use 1.5 lbs per cubic yard of

concrete, mimimum. Subject to approval by Owner’s Representative.

2.05 EXPANSION JOINT FILLER

Sealed Joints: Preformed, compressible fiber or cork filler material complying with ASTM D1751

or D1752, Type II, guaranteed compatible with expansion joint sealant materials, ½-inches thick

unless otherwise indicated. Provide high-impact polystyrene removable “void cap” to create ½-

inches deep reveal for installation of sealant.

Self-Sealing Joints: Preformed, compressible asphalt fiber joint filler complying with ASTM

D994, ½-inches thick unless otherwise indicated. Do not use asphalt fiber filler in joints to

receive elastomeric joint sealants.

2.06 CONCRETE MATERIALS

Cementitious Material: Use the following cementitious materials, of the same type, brand, and

source throughout the Project:

1. Portland Cement: CDOT Section 701 and ASTM C 150, Type I/II.

Normal-Weight Aggregates: CDOT Section 703 and ASTM C 33, coarse aggregate, uniformly

graded. Provide aggregates from a single source.

Maximum Coarse-Aggregate Size: 3/4 inch nominal.

Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

Do not use fine or coarse aggregates containing substances that cause spalling.

Water: CDOT Section 712 and ASTM C 94/C 94M potable.

2.07 ADMIXTURES

General: Admixtures certified by manufacturer to contain not more than 0.1 percent water-

soluble chloride ions by mass of cement and to be compatible with other admixtures.

Air-Entraining Admixture: CDOT Section 711 and ASTM C 260.

Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with

other admixtures and to contain not more than 0.1 percent water-soluble chloride ions by mass

of cementitious material.

Water-Reducing Admixture: ASTM C 494/C 494M, Type A.

Retarding Admixture: ASTM C 494/C 494M, Type B.

Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D.

Water-Reducing and Accelerating Admixture: ASTM C494, Type E.

High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F.

High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type G.

Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II..

Page 93: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 6

Recycled Content: 100% post-industrial fly ash.

a. Up to 15%, by weight, of the portalnd cement may be substituted by fly ash.

Fly ash shall not be used in concrete for the following: sidewalks, curb ramps, curb and

gutters, valley gutters, cross pans, concrete paths, driveways, storm drainage structures,

and alley approaches.

Prohibited Admixtures: Calcium chloride or thiocyanate.

2.08 CURING MATERIALS: CDOT SECTION 711

Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing

approximately 9 oz./sq.yd. (305 g/sq.m) dry.

Moisture-Retaining Cover: ASTM C 171, waterproof paper, polyethylene film or white burlap-

polyethylene sheet.

Water: Potable.

Evaporation Retarder: Waterborne, monomolecular film forming; manufactured for application

to fresh concrete.

Clear Waterborne Membrane-Forming Curing Compound: ASTM C 309, Type I, Class B.

1. Provide material that has a maximum volatile organic compound (VOC) rating of 350 g/L.

White Waterborne Membrane-Forming Curing Compound: ASTM C 309, Type II, Class B.

1. Provide material that has a maximum volatile organic compound (VOC) rating of 350 g/L.

2.09 CONCRETE MIXTURES

Prepare design mixes, proportioned according to ACI 211.1 and ACI 301, for each type and

strength of normal-weight concrete determined by either laboratory trial mixes or field

experience.

Use a qualified independent testing agency for preparing and reporting proposed mix

designs for the trial batch method.

Do not use Owner's field quality-control testing agency as the independent testing

agency.

Proportion mixes to provide concrete with the following properties:

1. Compressive Strength (28 Days): 4,500 psi.

2. Modulus of Rupture (28 day): Minimum 650 psi.

3. Maximum Water-Cementitious Materials Ratio at Point of Placement: 0.45.

4. Slump Limit: 4 inches (100 mm).

5. Minimum 564 lb. Cement per cubic yard. (CDOT Class P)

Add air-entraining admixture at manufacturer's prescribed rate to result in concrete at point of

placement having an air content of approximately 6.0 percent.

Limit water-soluble, chloride-ion content in hardened concrete to 0.15 percent by weight of

cement.

Page 94: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 7

Chemical Admixtures: Use admixtures according to manufacturer's written instructions.

Use water-reducing admixture, plasticizing and retarding admixture in concrete, as

required, for placement and workability.

Use water-reducing and retarding admixture when required by high temperatures, low

humidity, or other adverse placement conditions.

Cementitious Materials: Limit percentage, by weight, of cementitious materials other than

portland cement according to ACI 301 requirements for concrete exposed to deicing chemicals.

2.10 CONCRETE MIXING

Ready-Mixed Concrete: Measure, batch, and mix concrete materials and concrete according to

ASTM C 94/C 94M. Furnish batch certificates for each batch discharged and used in the Work.

PART 3 - EXECUTION

3.01 EXAMINATION

Examine exposed subgrades and subbase surfaces for compliance with requirements for

dimensional, grading, and elevation tolerances.

Proof-roll prepared subbase surface below concrete pavements with heavy pneumatic-tired

equipment to identify soft pockets and areas of excess yielding.

1. Completely proof-roll subbase in one direction and repeat in perpendicular direction.

Limit vehicle speed to 3 mph (5 km/h).

2. Proof-roll with a loaded 10-wheel tandem-axle dump truck weighing not less than 15

tons.

3. Subbase with soft spots and areas of pumping or rutting exceeding depth of 1/2 inch

require correction according to requirements in Division 2 Section "Earthwork."

Subgrade shall be tested by Geotechnical Engineer and pass required tests prior to concrete

pavement placement.

Proceed with concrete pavement operations only after non-conforming conditions have been

corrected and subgrade is ready to receive pavement.

3.02 PREPARATION

Remove loose material from compacted subbase surface immediately before placing concrete.

3.03 EDGE FORMS AND SCREED CONSTRUCTION

Set, brace, and secure edge forms, bulkheads, and intermediate screed guides for pavement to

required lines, grades, and elevations. Install forms to allow continuous progress of work and

so forms can remain in place at least 24 hours after concrete placement.

Clean forms after each use and coat with form release agent to ensure separation from concrete

without damage.

Page 95: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 8

Forms shall have maximum deflection of ¼-inch and shall be straight and free from warp, with

maximum deviation from surface of 1/8-inch

3.04 STEEL REINFORCEMENT

General: Comply with CRSI's "Manual of Standard Practice" for fabricating reinforcement and

with recommendations in CRSI's "Placing Reinforcing Bars" for placing and supporting

reinforcement.

Clean reinforcement of loose rust and mill scale, earth, ice, or other bond-reducing materials.

Arrange, space, and securely tie bars and bar supports to hold reinforcement in position during

concrete placement. Maintain minimum cover to reinforcement.

Install welded wire fabric in lengths as long as practicable. Lap adjoining pieces at least one full

mesh, and lace splices with wire. Offset laps of adjoining widths to prevent continuous laps in

either direction.

Install fabricated bar mats in lengths as long as practicable. Handle units to keep them flat and

free of distortions. Straighten bends, kinks, and other irregularities, or replace units as required

before placement. Set mats for a minimum 12-inch overlap of adjacent mats.

3.05 JOINTS

General: Construct/install construction, isolation, expansion, and contraction joints and tool

edgings true to line with faces perpendicular to surface plane of concrete. Construct transverse

joints at right angles to centerline, unless otherwise indicated.

When joining existing pavement, place transverse joints to align with previously placed

joints, unless otherwise indicated.

Contractor to provide plan of joint placement for the Engineers approval.

The distance between joints shall not exceed in feet, maximum 10-foot joint spacing each

way.

Construction Joints: Set construction joints at side and end terminations of pavement and at

locations where pavement operations are stopped for more than one-half hour, unless

pavement terminates at expansion joints.

1. Contractor may utilize preformed galvanized steel or plastic keyway-section forms or

bulkhead forms with keys, unless otherwise indicated. Embed keys at least 1-1/2 inches

into concrete.

2. Continue reinforcement across construction joints, unless otherwise indicated. Do not

continue reinforcement through sides of pavement strips, unless otherwise indicated.

3. Provide tie bars at sides of pavement strips where indicated.

4. Keyed Joints: Provide preformed keyway-section forms or bulkhead forms with keys,

unless otherwise indicated. Embed keys at least 1-1/2 inches into concrete.

Expansion Joints: Form expansion joints of preformed joint-filler strips abutting concrete curbs,

catch basins, manholes, inlets, structures, walks, other fixed objects, and where indicated.

1. Locate expansion joints in pavement where indicated on plans.

2. Extend joint fillers full width and depth of joint.

Page 96: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 9

3. Terminate joint filler no less than 1/2 inch or no more than 1 inch below finished surface

for joint sealant.

4. Furnish joint fillers in one-piece lengths. Where more than one length is required, lace or

clip joint-filler sections together.

5. Protect top edge of joint filler during concrete placement with metal, plastic, or other

temporary preformed cap. Remove protective cap after concrete has been placed on

both sides of joint.

Contraction Joints: Form weakened-plane contraction joints, sectioning concrete into areas as

indicated. Construct contraction joints for a depth equal to at least one-fourth of the concrete

thickness, as follows:

Sawed Joints: Form contraction joints with power saws equipped with shatterproof

abrasive or diamond-rimmed blades. Cut 1/8-inch- wide joints into concrete when cutting

action will not tear, abrade, or otherwise damage surface and before developing random

contraction cracks.

Tied Contraction Joints: Install deformed bars and support assemblies at joints where

indicated.

3.06 CONCRETE PLACEMENT

Inspection: Before placing concrete, inspect and complete formwork installation,

reinforcement steel, and items to be embedded or cast in. Notify other trades to permit

installation of their work.

Remove snow, ice, or frost from subbase surface and reinforcement before placing concrete.

Do not place concrete on frozen surfaces.

Moisten subbase to provide a uniform dampened condition at the time concrete is placed. Do

not place concrete around manholes or other structures until they are at the required finish

elevation and alignment.

Comply with ACI 301 and ACI 304R requirements and recommendations for measuring, mixing,

transporting, and placing concrete.

Do not add water to concrete during delivery to the project site.

Do not add water to fresh concrete after testing.

Do not add water to concrete surface during finishing operations.

Deposit and spread concrete in a continuous operation between transverse joints. Do not push

or drag concrete into place or use vibrators to move concrete into place.

Consolidate concrete according to ACI 301 by mechanical vibrating equipment supplemented

by hand spading, rodding, or tamping. Use equipment and procedures to consolidate concrete

according to recommendations in ACI 309R.

Consolidate concrete along face of forms and adjacent to transverse joints with an

internal vibrator. Keep vibrator away from joint assemblies, reinforcement, or side forms.

Page 97: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 10

Use only square-faced shovels for hand-spreading and consolidation. Consolidate with

care to prevent dislocating reinforcement, dowels, and joint devices.

Screed pavement surfaces with a straightedge and strike off.

Commence initial floating using bull floats or darbies to form an open textured and uniform

surface plane before excess moisture or bleed water appears on the surface. Do not further

disturb concrete surfaces before beginning finishing operations.

Curbs and Gutters: Produce curbs and gutters to required cross section, lines, grades, finish,

and jointing as specified with expansion joints at intervals of approximately 100 feet and tooled

contraction joints at 10-foot intervals When automatic machine placement is used for curb and

gutter placement, submit revised mix design and laboratory test results that meet or exceed

requirements.

Walks: Sidewalks not subject to Vehicle Traffic and less than 8 feet in width: 6 inches thick with

Fibrous Mesh Reinforcemnet. Sidewalks subject to Vehicle Traffic or sidewalks greater than or

equal to 8 feet in width: 6 inches thick with rebar reinforcement. No. 4 base at 18 inches o.c.

both ways. Expansion joints at intervals of approximately 100 feet and tooled contraction joints

at intervals equal to width of walks or maximum 5-foot intervals. Tool edges to rounded profile

and finish as noted herein or shown on the drawings. Contractor may utilize sawed contraction

joints. Pitch walks ¼-inches per foot max for drainage unless otherwise indicated. All sidewalks

are to be ADA compliant.

Ramps: Construct ramps similar to walks. Comply with applicable ADA Handbook, ANSI A117.1,

and local and State codes, ordinances, and details including maximum allowable slope not to

exceed 1 foot vertical in 12 foot horizontal, with maximum rise not to exceed 30-inches between

level landings. Ramps shall include truncated domes per University of Colorado Boulder

Standards.

Steps: Minimum 6-inches thick at intersection of treads and risers, reinforced as indicated.

Slope treads ¼-inches to nosing, and tool nosings to uniform ½-inches radius. Finish as specified

below.

Paving: Drives where subject to vehicle traffic. Minimum 6-inches thick unless otherwise

indicated. Loading docks 8-inches thick. Provide expansion joints (1/4-inch minimum depth) as

indicated on the drawings, and contraction joints at a minimum 10-feet -0-inches EWW.

Reinforcing is required for all pavement subject to vehicular loads (including snow removal

vehicles). For 6-inch thick drives use No. 4 bars at 18 inches o.c. both ways. For eight-inch thick

laoding docks use No. 5 bars at 18 inches o.c. both ways. Place concrete paving over compacted

subgrade as specified in Section “Earthwork”. Provide minimum 1% slope for drainage unless

otherwise indicated.

Driveway Approaches: Minimum 6-inches thick, unless otherwise indicated or required by local

public works standards or building codes. Construct to radius of flare indicated, and taper or

warp into alignment with adjacent curbs, gutters, and walks. Place approaches over compacted

subgrade as specified in section “Earthwork.” Refer to drawing and details for any reinforcing

requirements.

Page 98: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 11

Slip-Form Pavers: When automatic machine placement is used for pavement, submit revised

mix design and laboratory test results that meet or exceed requirements. Produce pavement

to required thickness, lines, grades, finish, and jointing as required for formed pavement.

Compact subbase and prepare subgrade of sufficient width to prevent displacement of paver

machine during operations.

When adjoining pavement lanes are placed in separate pours, do not operate equipment on

concrete until pavement has attained 85 percent of its 28-day compressive strength.

Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from

physical damage or reduced strength that could be caused by frost, freezing actions, or low

temperatures.

1. When air temperature has fallen to or is expected to be 40 deg F, uniformly heat water

and aggregates before mixing to obtain a concrete mixture temperature of not less than

50 deg F and not more than 80 deg F at point of placement.

2. Do not use frozen materials or materials containing ice or snow.

3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or

chemical accelerators, unless otherwise specified and approved in mix designs.

4. Cease concreting when air temperature falls below 35 degrees F, and there is frost in

subgrade.

Hot-Weather Placement: Place concrete according to recommendations in ACI 305R and as

follows when hot-weather conditions exist:

1. Cool ingredients before mixing to maintain concrete temperature at time of placement

below 90 deg F. Chilled mixing water or chopped ice may be used to control temperature,

provided water equivalent of ice is calculated to total amount of mixing water. Using

liquid nitrogen to cool concrete is Contractor's option.

2. Cover reinforcement steel with water-soaked burlap so steel temperature will not exceed

ambient air temperature immediately before embedding in concrete.

3. Fog-spray forms, reinforcement steel, and subgrade just before placing concrete. Keep

subgrade moisture uniform without standing water, soft spots, or dry areas.

Wet-Weather Placement: Do not begin to place concrete while rain, sleet, or snow is falling

unless adequate protection is provided and, when required, acceptance of protection is

obtained.

3.07 FLOAT FINISHING

General: Do not add water to concrete surfaces during finishing operations.

Edging: Tool edges of pavement, gutters, curbs, and joints in concrete after initial floating with

an edging tool to a 1/4-inch radius. Repeat tooling of edges after applying surface finishes.

Eliminate tool marks on concrete surfaces.

Float Finish: Begin the second floating operation when bleed-water sheen has disappeared and

the concrete surface has stiffened sufficiently to permit operations. Float surface with power-

driven floats, or by hand floating if area is small or inaccessible to power units. Finish surfaces

Page 99: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 12

to true planes. Cut down high spots, and fill low spots. Refloat surface immediately to uniform

granular texture.

Medium-to-Fine-Textured Broom Finish: Draw a soft bristle broom across float-finished

concrete surface perpendicular to line of traffic to provide a uniform, fine-line texture.

Burlap Drag Finish: For use on curbs, roadways and streets only. Provide a course finish

by dragging a clean, unused, section of burlap fabric longitudinally across pavement.

3.08 CONCRETE PROTECTION AND CURING

General: Protect freshly placed concrete from premature drying and excessive cold or hot

temperatures. Maintain temperature of concrete at 50 degrees F or above for minimum of 5

days from placement.

Comply with ACI 306.1 for cold-weather protection and follow the recommendations of ACI

305R for hot-weather protection during curing.

Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy

conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing

operations. Apply according to manufacturer's written instructions after placing, screeding, and

bull floating or darbying concrete, but before float finishing.

Begin curing after finishing concrete, but not before free water has disappeared from concrete

surface.

Curing Methods: Cure concrete by moisture curing, moisture-retaining-cover curing, curing

compound, or a combination of these as follows:

1. Moist Curing: Keep surfaces continuously moist for not less than seven days with the

following materials:

a. Water.

b. Continuous water-fog spray.

c. Absorptive cover, water saturated and kept continuously wet. Cover concrete

surfaces and edges with 12-inch lap over adjacent absorptive covers.

2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover

for curing concrete, placed in widest practicable width, with sides and ends lapped at least

12 inches, and sealed by waterproof tape or adhesive. Immediately repair any holes or

tears during curing period using cover material and waterproof tape.

3. Curing Compound: Apply uniformly in continuous operation by power spray or roller

according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall

within three hours after initial application. Maintain continuity of coating and repair

damage during curing period.

3.09 PAVEMENT TOLERANCES

Comply with tolerances of ACI 117 and as follows:

1. Elevation: 1/4 inch.

2. Thickness: Plus 3/8 inch, minus 1/4 inch.

3. Surface: Gap below 10-foot- long, unleveled straightedge not to exceed 1/4 inch.

4. Lateral Alignment and Spacing of Tie Bars and Dowels: 1 inch.

Page 100: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 13

5. Vertical Alignment of Tie Bars and Dowels: 1/4 inch.

6. Alignment of Tie-Bar End Relative to Line Perpendicular to Pavement Edge: 1/2 inch.

7. Alignment of Dowel-Bar End Relative to Line Perpendicular to Pavement Edge: Length of

dowel 1/4 inch per 12 inches.

8. Joint Spacing: 3 inches.

9. Contraction Joint Depth: Plus 1/4 inch, no minus.

10. Joint Width: Plus 1/8 inch, no minus.

3.10 FIELD QUALITY CONTROL

Testing Agency: Owner will engage a qualified testing and inspection agency to sample

materials, perform tests, and submit test reports during concrete placement.

Testing Services: Testing of composite samples of fresh concrete obtained according to

ASTM C 172 shall be performed according to the following requirements:

Testing Frequency: Obtain at least 1 composite sample for each 50 cu. yd. or fraction

thereof of each concrete mix placed each day.

a. When frequency of testing will provide fewer than five compressive-strength tests

for each concrete mixture, testing shall be conducted from at least five randomly

selected batches or from each batch if fewer than five are used.

Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample,

but not less than one test for each day's pour of each type of concrete mix. Perform

additional tests when concrete consistency appears to change.

Air Content: ASTM C 231, pressure method; one test for each composite strength test,

but not less than one test for each day's pour of each type of concrete mix.

Concrete Temperature: ASTM C 1064; one test hourly when air temperature is 40 deg F

and below and when 80 deg F and above, and one test for each set of composite strength

specimens.

Compression Test Specimens: ASTM C 31/C 31M; one set of four standard cylinders for

each compressive-strength test, unless otherwise indicated. Cylinders shall be molded

and stored for laboratory-cured test specimens unless field-cured test specimens are

required.

Compressive-Strength Tests: ASTM C 39; one set for each day's pour of each concrete

class exceeding 5 cu. yd., but less than 25 cu. yd., provide at least two tests for every 100

cu.yd., (one set for each 50 cu. yd.). One specimen shall be tested at 7 days and two

specimens at 28 days; one specimen shall be retained in reserve for later testing if

required.

When strength of field-cured cylinders is less than 85 percent of companion laboratory-

cured cylinders, current operations shall be evaluated and corrective procedures shall be

provided for protecting and curing in-place concrete.

Strength of each concrete mix will be satisfactory if average of any 3 consecutive compressive-

strength tests equals or exceeds specified compressive strength and no compressive-strength

test value falls below specified compressive strength by more than 500 psi (3.4 MPa).

Test results shall be reported in writing to Owner’s Representative, concrete manufacturer,

engineer and Contractor within 24 hours of testing. Reports of compressive-strength tests shall

contain Project identification name and number, date of concrete placement, name of concrete

Page 101: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING

321313 - 14

testing and inspecting agency, concrete type and class, location of concrete batch in pavement,

design compressive strength at 28 days, concrete mix proportions and materials, compressive

breaking strength, and type of break for both 7- and 28-day tests.

Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be

permitted by Owner’s Representative, but will not be used as the sole basis for approval or

rejection.

Additional Tests: Testing agency shall make additional tests of the concrete when test results

indicate slump, air entrainment, concrete strengths, or other requirements have not been met,

as directed by Owner’s Representative. Testing agency may conduct tests to determine

adequacy of concrete by cored cylinders complying with ASTM C 42, or by other methods as

directed.

Remove and replace concrete pavement where test results indicate that it does not comply with

specified requirements. Any concrete surfaces displaying holes or honeycombs will be removed

and replaced.

Additional testing and inspecting, at Contractor’s expense, will be performed to determine

compliance of replaced or additional work with specified requirements.

3.11 REPAIRS AND PROTECTION

Remove and replace concrete pavement that is broken, damaged, or defective, or does not

meet requirements in this Section. Saw cuts are to be made on existing concrete joints only.

Drill test cores where directed by Owner’s Representative when necessary to determine

magnitude of cracks or defective areas. Fill drilled core holes in satisfactory pavement areas

with portland cement concrete bonded to pavement with epoxy adhesive.

Protect concrete from damage. Exclude traffic from pavement for at least 14 days after

placement. When construction traffic is permitted, maintain pavement as clean as possible by

removing surface stains and spillage of materials as they occur.

Maintain concrete pavement free of stains, discoloration, dirt, and other foreign material.

Sweep concrete pavement not more than two days before date scheduled for Substantial

Completion inspections.

END OF SECTION

Page 102: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

SITE CLEARING

311000 - 1

SECTION 311000

SITE CLEARING

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 1 Specification Sections, apply to this Section. Meet Colorado University

specifications and requirements at a minimum.

1.02 SUMMARY

A. This Section includes the following:

1. Protecting existing trees, shrubs, groundcovers, plants, grass, and other vegetation to

remain or as designated by Owner.

2. Removing existing trees, shrubs, groundcovers, plants, grass, and other vegetation, as

required for new construction within the limits of construction as shown on design

documents.

3. Clearing and grubbing.

4. Stripping and stockpiling topsoil.

5. Removing above- and below-grade site improvements.

6. Disconnecting, capping or sealing, abandoning site utilities in place, and removing site

utilities.

B. Related Sections include the following:

1. Section “Trenching and Backfilling” for soil materials, excavating, backfilling, and site

grading.

2. Section “Temporary Erosion and Sedimentation Control” for storm water erosion and

sediment mitigation.

3. Section “Tree and Plant Protection” for the protection of existing trees and plants onsite.

1.03 DEFINITIONS

A. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and

clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than

underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than

2 inches (50 mm) in diameter; and free of subsoil and weeds, roots, toxic materials, or other

nonsoil materials.

B. Tree Protection Zone: Area surrounding individual trees or groups of trees to be protected

during construction, and defined by the drip line of individual trees or the perimeter drip line of

groups of trees, unless otherwise indicated.

Page 103: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

SITE CLEARING

311000 - 2

1.04 MATERIAL OWNERSHIP

A. Except for stripped topsoil or other materials indicated to be stockpiled or to remain on Owner's

property, cleared materials shall become Contractor's property and shall be removed from

Project site.

1.05 SUBMITTALS

A. Photographs or videotape, sufficiently detailed, of existing conditions of trees and plantings,

adjoining construction, and site improvements that might be misconstrued as damage caused

by site clearing.

B. Record drawings, identifying and accurately locating capped utilities and other subsurface

structural, electrical, and mechanical conditions. Information required may also be included in

Section "Project Record Documents."

1.06 QUALITY ASSURANCE

A. Preconstruction Conference: Conduct conference at Project site as directed by Owner’s

Representative prior to start of construction. Contractor to comply with requirements, which

may also be included in Section "Project Management and Coordination."

1.07 PROJECT CONDITIONS

A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied

or used facilities during site-clearing operations.

1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities

without permission from Owner and authorities having jurisdiction.

2. Provide alternate routes around closed or obstructed traffic ways meeting local

requirements and Owner’s approval.

B. Improvements on Adjoining Property: Authority and permits for performing indicated removal

and alteration work on adjacent rights-of-way shall be obtained by Contractor.

1. Do not proceed with work on adjoining property until written authority is obtained.

C. Protect improvements on adjacent and Owner’s property.

D. Salvable Improvements: Carefully remove items indicated to be salvaged and store on Owner's

premises where indicated.

E. Utility Locator Service: Notify utility locator service for area where Project is located before site

clearing. Primary and secondary locating of utilities is the Contractor’s responsibility.

F. Do not commence site clearing operations until temporary erosion and sedimentation control

measures are in place. Contractor is responsible for SWMP through the State prior to

construction and throughout the project.

G. Restore damaged improvements to their original condition, as acceptable to parties having

jurisdiction.

Page 104: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

SITE CLEARING

311000 - 3

PART 2 - PRODUCTS

2.01 SOIL MATERIALS

A. Satisfactory Soil Materials: Requirements for satisfactory soil materials are specified in Section

“Trenching and Backfilling” (PART 2 – PRODUCTS).

2.02 LEED REQUIREMENTS

A. Materials/products shall contain the maximum amount of recycled content allowed that retains

material integrity.

B. Preference shall be given to materials that are manufactured, harvested, extracted, mined,

quarried, etc. within a 500 mile radius of the project site.

PART 3 - EXECUTION

3.01 PREPARATION

A. Protect and maintain benchmarks, survey control points, monuments, property line pins and

other reference points from disturbance during construction. If disturbed or destroyed, restore

or replace at no cost to Owner.

B. Provide erosion control measures to prevent soil erosion and discharge of soil-bearing water

runoff or airborne dust from leaving project site.

C. Locate and clearly flag trees and vegetation to remain or to be relocated.

D. Protect existing site improvements to remain from damage during construction.

1. Restore or replace damaged improvements to their original condition, as acceptable to

Owner.

3.02 TREE PROTECTION

A. Erect and maintain temporary fencing around drip line of individual trees or around perimeter

drip line of groups of trees to remain before starting site clearing. Remove fence when

construction is complete.

1. Do not store construction materials, debris, or excavated material within fenced area.

2. Do not permit vehicles, equipment, or foot traffic within fenced area.

3. Maintain fenced area free of weeds and trash.

B. Do not excavate within tree protection zones, unless otherwise indicated.

C. Where excavation for new construction is required within drip line of trees, hand clear and

excavate to minimize damage to root systems. Use narrow-tine spading forks, comb soil to

expose roots, and cleanly cut roots as close to excavation as possible.

1. Cover exposed roots with burlap and water regularly.

Page 105: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

SITE CLEARING

311000 - 4

2. Temporarily support and protect roots from damage until they are permanently relocated

and covered with soil.

3. Coat cut faces of roots more than 1-1/2 inches (38 mm) in diameter with an emulsified

asphalt or other approved coating formulated for use on damaged plant tissues.

4. Cover exposed roots with wet burlap to prevent roots from drying and backfill with soil

as soon as possible.

D. Repair or replace trees and vegetation indicated to remain that are damaged by construction

operations, in a manner approved by Owner’s Representative.

1. Employ a qualified arborist, licensed in jurisdiction where Project is located, to submit

details of proposed repairs and to repair damage to trees and shrubs.

2. Replace trees that cannot be repaired and restored to full-growth status, as determined

by the qualified arborist.

3.03 UTILITIES

A. Contractor will locate, identify, arrange for disconnect and seal or cap off utilities indicated to

be removed before site clearing.

1. Verify that utilities indicated as abandoned have been disconnected and capped before

proceeding with site clearing.

2. Arrange with utility companies having jurisdiction to shut off indicated utilities.

B. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless

permitted under the following conditions and then only after arranging to provide temporary

utility services according to requirements indicated:

1. Notify Owner’s Representative not less than two days in advance of proposed utility

interruptions.

2. Do not proceed with utility interruptions without Owner’s Representative’s written

permission.

3. Provide bypassing or alternate utility as necessary to facilitate construction.

C. Excavate for and remove underground utilities indicated to be removed.

D. After removal of underground utilities, as indicated, properly cap and/or plug existing lines to

remain in accordance with authorities having jurisdiction.

3.04 CLEARING AND GRUBBING

A. Remove obstructions, shrubs, grass, and other vegetation to permit installation of new

construction. Removal includes digging out stumps and obstructions and grubbing roots.

1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated.

2. Cut minor roots and branches of trees indicated to remain in a clean and careful manner

where such roots and branches obstruct installation of new construction.

3. Grind stumps and completely remove roots, obstructions, and debris extending to a depth

of 18 inches (450 mm) below exposed subgrade.

4. Use only hand methods for grubbing within drip line of remaining trees.

5. Chip removed tree branches, stockpile in areas approved by Owner’s Representative, and

dispose of off-site.

Page 106: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

SITE CLEARING

311000 - 5

B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless

further excavation or earth moving is indicated.

1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches, and

compact each layer to a density equal to adjacent original ground.

3.05 TOPSOIL STRIPPING

A. Remove shrubs before stripping topsoil.

B. Strip topsoil to whatever depths are encountered or as determined by Geotechnical Engineer

in a manner to prevent intermingling with underlying subsoil or other waste materials.

1. Remove subsoil and nonsoil materials from topsoil, including trash, debris, weeds, roots,

and other waste materials.

C. Stockpile topsoil materials away from edge of excavations without intermixing with subsoil.

Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust.

1. Limit height of topsoil stockpiles to 72 inches unless authorized by Owner’s

Representative.

2. Do not stockpile topsoil within drip line of remaining trees.

3. Dispose of excess topsoil as specified for waste material disposal.

4. Stockpile surplus topsoil to allow for respreading a thicker layer of topsoil.

3.06 SITE IMPROVEMENTS

A. Remove existing above and below grade improvements as indicated and as necessary to

facilitate new construction.

B. Remove slabs, paving, curbs, gutters, and aggregate base as indicated on plans.

1. Existing full-depth joints shall coincide with line of demolition, neatly saw-cut length of

existing pavement to remain before removing existing pavement. Saw-cut faces vertically.

2. Paint cut ends of steel reinforcement in concrete to remain to prevent corrosion.

C. Remove existing fill.

3.07 DISPOSAL

A. Disposal: Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials,

and waste materials including trash and debris, and legally dispose of them off Owner's

property.

1. Separate recyclable materials produced during site clearing from other nonrecyclable

materials. Store or stockpile without intermixing with other materials and transport them

to recycling facilities.

END OF SECTION

Page 107: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 1

SECTION 331100

WATER UTILITY DISTRIBUTION PIPING

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 1 Specification Sections, apply to this Section.

B. Additional information concerning water distribution systems may be found on the civil

drawings. In case of conflict between the drawings and the information specified herein, the

more stringent requirements shall govern.

1.02 SUMMARY

A. This Section includes water-distribution piping and specialties outside the building for the

following:

1. Fire-service mains.

2. Public water mains.

B. Work Included: Excavation, exploratory excavation (pothole), backfill, bedding, soil

stabilization, ground water removal, connection to existing mains, and installation of pipe,

thrust blocks, thrust restraints, valves, fittings, valve boxes, and all necessary appurtenances.

Also includes removal and replacement of existing paving or concrete where required, haul and

import of adequate backfill material to meet compaction requirements and removal of existing

thrust blocks where necessary. Includes abandonment of valves and existing mains as required.

C. Related work:

1. Section "Site Clearing" for temporary utilities and support facilities may be included.

2. Section “Earth Moving” for soil materials, site grading, site excavation and filling.

3. Section “Trenching and Backfilling” for excavating and backfilling of utilities.

4. Section “Asphalt Paving” pavement patching over trenches.

5. Section “Concrete Paving” for concrete structures, concrete materials and exterior

concrete paving or walks.

6. Section “Temporary Erosion and Sedimentation Control” for erosion and sedimentation

control measures.

7. Section “Tree and Plant Protection” for the protection of existing trees and plants onsite.

1.03 DEFINITIONS

A. Fire-Service Main: Exterior fire-suppression water piping that is brought within the building.

B. Public Water Main: Exterior domestic-water service piping.

C. The following are industry abbreviations for pipe materials:

1. DIP: Ductile iron pipe.

Page 108: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 2

D. Trench Excavation: Excavation of all material encountered along trench.

E. Rock Excavation: All excavation for trenching is included under trench excavation.

F. All items under this section shall, at a minimum, conform to:

1. The most recent City of Boulder Design and Construction Standards are incorporated by

reference into the University’s Standards. When there is a conflict between standards,

the more stringent requirement shall apply. The University’s Civil Engineer must approve

in writing any deviation from these standards prior to construction.

2. The most recent International Plumbing Code.

3. The most recent International Building Code.

4. NFPA Compliance: Install fire protection water systems in accordance with NFPA 24

“Standard for the Installation of Private Fire Service Mains and Their Appurtenances.”

5. Contractor must obtain a permit to operate valves or hydrants from the University of

Colorado at Boulder Utilities and Engineering Division. Where valves or hydrants are

owned by a utility other than the University, Contractor must contact the owning utility

and follow that utility’s regulations for operating valves and hydrants.

6. Operation of Water System must at all times remain under the supervision of the

University of Colorado at Boulder.

7. Use the Technical Drawings as shown in the construction drawings.

1.04 SUBMITTALS

A. Product Data: For the following:

1. Piping specialties.

2. Fittings.

3. Valves, valve boxes, and accessories.

B. Field Quality-Control Test Reports: From Contractor.

C. Test Reports: Submit two (2) copies of laboratory gradation tests for bedding and trench

stabilization materials.

D. Permits: Submit copies of all permits issued for project. Contractor is responsible for obtaining

all applicable utility agency, City, County, and State Permits for the project.

E. Certificates: Submit two (2) copies of acceptance from Health Department prior to placing

water system in service.

F. Locates: Contractor must submit two (2) copies of utility locate drawings/receipts prior to

beginning construction.

G. As-Builts: Provide Engineer with copies of redlined, as-built plans upon completion of

construction. Horizontal and vertical information is to be certified by a Professional Land

Surveyor.

Page 109: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 3

1.05 QUALITY ASSURANCE

A. Product Options: Drawings indicate size, material profiles, and dimensional requirements of

piping and specialties and are based on the specific system indicated.

B. Regulatory Requirements:

1. Comply with University of Colorado Boulder Standards.

2. Comply with requirements of utility company supplying water, including tapping of water

mains and backflow prevention.

3. Comply with standards of authorities having jurisdiction for potable-water-service piping,

including materials, installation, testing, and disinfection.

4. Comply with standards of authorities having jurisdiction for fire-suppression water-

service piping, including materials, hose threads, installation, and testing.

C. Piping materials shall bear label, stamp, or other markings of specified testing agency.

D. Comply with FMG's "Approval Guide" or UL's "Fire Protection Equipment Directory" for fire-

service-main products.

E. NFPA Compliance: Comply with NFPA 24 for materials, installations, tests, flushing, and valve

supervision for fire-service-main piping for fire suppression.

1.06 DELIVERY, STORAGE, AND HANDLING

A. Preparation for Transport: Prepare valves according to the following:

1. Ensure that valves are dry and internally protected against rust and corrosion.

2. Protect valves against damage to threaded ends and flange faces.

3. Set valves in best position for handling. Set valves closed to prevent rattling.

B. During Storage: Use precautions for valves according to the following:

1. Do not remove end protectors unless necessary for inspection; then reinstall for storage.

2. Protect from weather. Store indoors and maintain temperature higher than ambient dew-

point temperature. Support off the ground or pavement in watertight enclosures when

outdoor storage is necessary.

C. Handling: Use sling to handle valves if size requires handling by crane or lift. Rig valves to avoid

damage to exposed parts. Do not use stems as lifting or rigging points.

D. Deliver piping with factory-applied end caps. Maintain end caps through shipping, storage, and

handling to prevent pipe-end damage and to prevent entrance of dirt, debris, and moisture.

E. Protect stored piping from moisture and dirt. Elevate above grade. Do not exceed structural

capacity of floor when storing inside.

F. Protect flanges, fittings, and specialties from moisture and dirt.

G. Store plastic piping protected from direct sunlight. Support to prevent sagging and bending.

Page 110: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 4

1.07 PROJECT CONDITIONS

A. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless

permitted under the following conditions and then only after arranging to provide temporary

utility services according to requirements indicated:

1. Notify Owner’s Representative not less than two days in advance of proposed utility

interruptions.

2. Do not proceed with utility interruptions without Owner’s Representative written

permission.

B. Environmental Requirements: Except by specific written authorization, cease concreting when

descending air temperature in shade and away from artificial heat falls below 35 degrees F. and

there is frost in subgrade. When concreting is permitted during cold weather, temperature of

mix shall not be less than 60 degrees F. at time of placing. The Contractor shall protect fresh

uncured concrete surfaces from rain and snow. Equipment is not permitted on concrete until

its design strength is obtained.

C. Immediately pump or bail out water found in excavations, whether rain or seepage.

Coordination and use of electric power is the Contractor's responsibility. Excavations must be

kept free from water at all times.

D. It shall be the responsibility of the Contractor to take all measures and furnish all equipment

and labor necessary to control the flow, drainage and accumulation of water as required to

permit completion of the work under this section to avoid damage to all work at no additional

cost to the Owner.

E. It shall be the responsibility of the Contractor to take all measures and furnish all material,

equipment, and labor necessary to provide adequate backfill material as specified herein.

F. Water Service shall remain operational at all times until service change over is completed.

Provide Owner with water as needed during outages.

1.08 PROJECT RECORD DOCUMENTS

A. Maintenance of Documents: Store documents apart from drawings used for construction. File

submitted documents in accordance with the specification's section numbers. Maintain

documents in a clean, dry legible condition and in good order. Do not use record documents for

construction purposes.

B. Recording: Label each document "PROJECT RECORD" in neat, large, printed letters. Record

information concurrently with construction progress. Do not cover work until required

information is recorded. Marking of project records shall be legible and with a dark pen or

pencil. Ink shall not be water based due to easy smearing. Mark drawings to record actual

construction including field dimensions, elevations, details, changes made by a modification,

details not on original drawings, horizontal and vertical locations of underground utilities, and

appurtenances referenced to a minimum of two permanent surface improvements, and depths

of various elements of work in relation to project datum. All horizontal and vertical information

is to be certified by a licensed Professional Land Surveyor.

Page 111: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 5

C. Submission: Accompany submittal with transmittal letter in duplicate containing date, project

title and number, Contractor's name, address and telephone number, title and number of each

record document, and signature of Contractor or his authorized representative. Contractor shall

submit two drawings and certified by a licensed Professional Land Surveyor depicting all as-built

information to the Engineer.

1.09 PROTECTION

A. Barricades and Safety Provisions: Place and maintain until completion of work adequate

barricades, construction signs, warning lights and guards to avoid property damage and protect

persons from injury. Flares with open flames will not be permitted. Protect all materials,

equipment, pipe and earth piles that may serve as hazards to vehicular or pedestrian traffic by

barricades or guards and warning lights.

B. Shoring: Provide and maintain all sheeting, shoring, and bracing required to safely retain earth

banks. Protect adjoining grades and structures from caving, sliding, erosion or other damage,

and suitable forms of protection against bodily injury; all in accordance with applicable codes

and governing authorities.

C. Do not remove any sheeting unless the pipe strength is sufficient to support the trench loads

based on trench width measured to the back of sheeting. Remove sheeting and shoring

gradually as excavation backfilling progresses to protect the construction or other structures,

utilities or property. Do not attempt removal of sheeting in one operation after backfilling is

complete.

D. All work must comply with latest OSHA requirements.

E. Utilities: Protect from damage existing utility lines shown on drawings or locations of which are

made known to contractor prior to work and utility lines constructed during construction

operations of the project. Hand excavate within six inches of known piping or objects to prevent

damage from equipment. Before commencing work, obtain information concerning location,

type, and extent of concealed existing utilities on the site and adjacent properties. Repair

damage to utilities at no cost to the Owner.

F. Granular Fill: Protect existing granular fill adjacent to existing structures from dirt that would

impede free drainage. Remove and replace any portions of granular fill that become

contaminated with dirt.

G. Drainage: Maintain the excavations and site free from water throughout the work. Remove any

water encountered in the trench to provide firm subgrade, to permit joints to be made dry at

the final grade, and to prevent entrance of water into the pipeline. Accomplish the foregoing

by the use of sumps and gravel blankets, well points, or drainlines. Contractor shall obtain all

permits associated with dewatering.

Rock, gravel, and other appurtenances used to keep trenches free from water or used to add

support to installed piping is considered incidental to construction and all costs shall be the

responsibility of the Contractor.

Page 112: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 6

H. Survey Control Monuments and Range Boxes: Protect existing survey control monuments from

damage. Contractor will be responsible for replacement or repair of any monument damaged

or destroyed. Replacement of monuments must be performed by a qualified land surveyor.

1.10 COORDINATION

A. Coordinate connection to water main with University of Colorado Boulder Facilities and City of

Boulder Water Department as applicable.

PART 2 - PRODUCTS

2.01 PIPING MATERIALS

A. Ductile-Iron Pipe And Fittings sizes 3-inches – 42-inches

1. Mechanical-Joint, Ductile-Iron Pipe: AWWA C151, thickness Class 52 with cement-mortar

lining, AWWA C104 with mechanical-joint, bell- and plain-spigot end.

a. Mechanical-Joint, Ductile-Iron Fittings: AWWA C110, pressure rating 250 psi,

ductile- or gray-iron standard pattern or AWWA C153, ductile-iron compact

pattern.

b. Glands, Gaskets, and Bolts: AWWA C111, ductile- or gray-iron glands, rubber

gaskets, and high-strength, low alloy steel bolts such as Cor-Ten.

c. All fittings cement – mortar lined, AWWA C104.

d. Bituminous outside coating one mil thick.

2. Push-on-Joint, Ductile-Iron Pipe: AWWA C151, thickness Class 52 with cement mortar

lining, AWWA C104 with push-on-joint, bell- and plain-spigot end unless grooved or

flanged ends are indicated.

a. Push-on-Joint, Ductile-Iron Fittings: AWWA C110, ductile- or gray-iron standard

pattern or AWWA C153, ductile-iron compact pattern.

b. Gaskets: AWWA C111, rubber.

c. Cement mortar lined, AWWA C104.

d. Bituminous outside coating one mil thick.

2.02 PIPING SPECIALTIES

A. Mechanical Joint Restraint

1. General: All mechanical joint restraints shall be incorporated in the design of a follower

gland. The gland shall be manufactured of ductile iron conforming to ASTM A536.

Dimensions of the gland shall be such that it can be used with the standardized

mechanical joint bell and tee-head bolts conforming to AWWA C111 and C153.

2. Description: The restraint mechanism shall consist of numerous individually activated

gripping surfaces to maximize restraint capability. The gripping surfaces shall be wedges

designed to spread the bearing surfaces on the pipe. Twist-off nuts, sized same as tee-

head bolts, shall be used to insure proper actuating of restraining devices. When the nut

is sheared off, a standard hex nut shall remain.

3. Pressure: The mechanical joint restraint device for ductile iron pipe shall have a working

pressure of at least 250 psi with a minimum safety factor of 2.

Page 113: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 7

4. Acceptable Manufacturer: The mechanical joint restraint devices shall be of the type

listed below or equal, and approved by City of Boulder Water Department prior to

bidding:

For Ductile Iron Pipe:

EBAA Iron, Inc. Megalug 1100 series (4-inches – 12-inches)

Uni-Flange Series 1400 (4-inches – 12-inches)

2.03 CORROSION-PROTECTION ENCASEMENT FOR PIPING

A. Encasement for Underground DIP Piping: AWWA C105, PE film, Type I, Class A, Grade E-1 (ASTM

D1248), 1200 lbs per square inch minimum tensile strength, minimum 300% elongation, 800

v/mil thickness minimum dielectric strength, minimum thickness, tube or sheet.

2.04 GATE VALVES AND ISOLATION VALVES

A. AWWA, Cast-Iron Gate Valves:

1. Nonrising-Stem, Metal-Seated Gate Valves: 3-inches – 12-inches size AWWA C500,

parallel seats, gray- or ductile-iron body, and bonnet; with fully bronze mounted double-

disc gate, bronze gate rings, bronze stem, and stem nut. Valves shall be furnished with 2-

inch square wrench nuts. The wrench nut shall comply with 3.15 of AWWA C500. Stem

seal shall consist of O-rings in accordance with 3.12 of AWWA C500. The valves shall open

by turning counter clockwise.

a. Minimum Working Pressure: 200 psig.

b. End Connections:

1) Mechanical Joint: All components of this type of joint shall conform to

AWWA C111. The tee-head bolts and hexagon nuts shall be fabricated from

a high-strength, low alloy steel known in the industry as Cor-Ten, Usually,

ductile iron Durabolt or equal.

c. Interior Coating: Complying with AWWA C550.

d. Bolting Material: Bonnet and gland bolts and nuts shall be either fabricated from a

low alloy-steel for corrosion resistance or electro plated with zinc or cadmium. The

hot dip process in accordance with ASTM A153 is not acceptable.

2. Nonrising-Stem, Resilient-Wedge Gate Valves: AWWA C509, gray- or ductile-iron body

and bonnet; with bronze or gray- or ductile-iron gate, resilient seats, bronze stem, and

stem nut. Valve stem shall have a minimum yield strength of 40,000 psi, minimum

elongation of 2-inches of 12%, and shall be per ASTM A276, type 304 or 316; or AISI 420.

Wrench nuts in accordance with 4.11 of AWWA C509. Stem seal shall consist of two (2)

O-rings in accordance with Section 4.8 of AWWA C509. The valves shall open by turning

counter clockwise.

a. Minimum Working Pressure: 200 psig.

b. End Connections:

1) Mechanical Joint: All components of this type of joint shall conform to

AWWA C111. The tee-head bolts and hexagon nuts shall be fabricated from

a high-strength, low alloy steel known in the industry as Cor-Ten Usalloy,

ductile iron Durabolt or equal.

c. Interior Coating: Complying with AWWA C550.

Page 114: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 8

d. Bolting Material: Bonnet and gland bolts and nuts shall be either fabricated from a

low alloy-steel for corrosion resistance or electro-plated with zinc or cadmium. The

hot-dip process in accordance with ASTM A153 is not acceptable.

2.05 GATE VALVE ACCESSORIES AND SPECIALTIES

A. Valve Boxes: Comply with AWWA M44 for cast-iron valve boxes. Include extension of length

required for depth of burial of valve, plug with lettering "WATER.” Valve boxes shall be the

three-piece adjustable screw type. The top section shall be 16-inches long. The following

pattern is acceptable, 5 ¼-inch diameter with 1/16-inch minimum thickness.

2.06 MORTAR

A. Masonry mortar shall be Type S conforming to ASTM C270.

The mortar shall consist of one part cement, 0.15 part lime, and three parts sand, measured by

volume. The cement, lime, and sand shall be first mixed dry to a uniform color in a suitable box

or batch mixer and then mixed with water thoroughly; the water being added gradually until

the required consistency is obtained. Mortar shall be mixed in batches of such size as will be

used immediately. Retempered mortar, or any mortar which has been mixed for more than one-

half hour shall not be used. When mortar is molded into briquettes one square inch in cross-

section, it shall attain an ultimate tensile stress of 125 pounds per square inch after one day in

air and six days in water, and 175 pounds per square inch after one day in air and twenty-seven

days in water.

PART 3 - EXECUTION

3.01 EARTH MOVING

A. Refer to Division 31 Section "Trenching and Backfilling" for excavating, trenching, and

backfilling.

B. Exploratory Excavation: It shall be the Contractor's responsibility to excavate and locate all

existing utilities which may affect construction of the water facilities. All exploratory excavations

shall occur far enough in advance to permit any necessary relocation to be made with minimum

delay and to verify existing vertical and horizontal location to determine alignment for the

proposed water line. All costs incurred by the Contractor in making exploratory excavations

shall be considered to be included in the unit price bid for constructing each section of water

line or the associate structures.

Page 115: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 9

C. Unstable Trench Bottom

Where trench does not have sufficient strength to support pipe and bedding, use one of

following methods to repair trench bottom as approved by the Geotechnical Engineer. A

minimum depth of repair is 2-feet.

1. Embankment: Clear and strip existing surface of all unacceptable material. Place

embankment material agreed to by Engineer, compact to 95% ASTM D698.

2. Aggregate Trench Bottom, percent by weight passing square mesh sieves: 1-½”, 90-100;

3/4", 50-90; No. 4, 30-50; No. 200, 3-12.

3.02 PIPING APPLICATIONS

A. General: Use pipe, fittings, and joining methods for piping systems according to the following

applications.

B. Transition couplings and special fittings with pressure ratings at least equal to piping pressure

rating may be used in applications below, unless otherwise indicated.

C. Do not use flanges, unions, or keyed couplings for underground piping.

D. Flanges, unions, keyed couplings, and special fittings may be used, instead of joints indicated,

on aboveground piping and piping in vaults.

3.03 JOINT CONSTRUCTION

A. Make pipe joints according to the following:

1. Ductile-Iron Piping, Gasketed Joints for Water-Service Piping: AWWA C600 and

AWWA M41.

2. Ductile-Iron Piping, Gasketed Joints for Fire-Service-Main Piping: UL 194.

3. Dissimilar Materials Piping Joints: Use adapters compatible with both piping materials,

with OD, and with system working pressure.

B. Pipe Jointing:

1. General: Cut pipe for inserting valves, fittings, or closure pieces in neat and workmanlike

manner with no damage to pipe or lining. Leave smooth end at right angles to axis of pipe.

2. Mechanical Joints: Thoroughly clean last 8-inches of spigot and inside bell to remove oil,

grit, tar, and other foreign matter. Coat spigot and gasket with solution furnished by pipe

manufacturer. Slip cast-iron gland on spigot end of pipe with lip extension of gland toward

spigot end. Coat gasket with joint lubricant and place on spigot end of pipe to be laid, with

thick edge toward gland.

Push entire section forward to seat spigot in bell of pipe in place. Press gasket into place

within bell, even around entire joint. Move ductile-iron gland along pipe into position for

bolting all nuts with suitable torque wrench. Alternately tighten nuts 180 degrees apart

to produce equal pressure on all parts of gland.

Pipe Size Bolt Size Range of Torque

Inches Inches Ft.-Lb.

Page 116: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 10

3" 5/8 45 - 60

4"-24" 3/4 75 – 90

3. Push-on Joints: Thoroughly clean exterior 4-inches of pipe spigot and inside of adjoining

bell to remove all oil, grit, tar, and other matter. Place gasket in bell with large round side

of gasket pointing inside pipe bell. Apply thin film joint lubricant over gasket's entire

exposed surface. Wipe spigot end of pipe clean and insert into bell to contact gasket.

Force pipe into bell to manufacturer's jointing mark.

4. Flanged Joints: Thoroughly clean faces of flanges of all oil, grease, and other material.

Thoroughly clean rubber gaskets and check for proper fit. Assure proper seating of flanged

gasket. Tighten bolts so pressure on gasket is uniform. Use torque wrenches to insure

uniform bearing. If joints leak when hydrostatic test applied, remove and replace gaskets

and retighten bolts.

C. Thrust Restraint: Install in accordance with City of Boulder Standards and drawings. Removal

of existing thrust blocks and rodding is the sole responsibility of the Contractor. Any damage

caused by the removal of thrust blocks, regardless of size, or rodding shall be paid for by

Contractor.

3.04 PIPING INSTALLATION

A. General: Deliver, handle, store, and install in accordance with the pipe manufacturer's

recommendations and the applicable paragraphs of AWWA C600, AWWA C603, and ASTM

D2321.

Carefully examine all pipe and fittings for cracks and other defects. Groove in bells of ductile

iron pipe to be full and continuous or be rejected. Remove all foreign matter from interior and

ends of pipe and appurtenances before lowering into trench. Carefully lower all pipe, fittings,

valves, and hydrants into trench piece by piece to prevent damage to pipe materials, protective

coatings, and linings. Do not dump into trench. If pipe cannot be lowered into trench and into

place without getting earth into it, place heavy, tightly woven canvas bag over each end and

leave in place until joints are made. During pipe laying, place no debris, tools, clothing, or other

materials in pipe.

Keep trenches free from water during pipe laying and jointing. Dewatering of trench considered

as incidental to construction and all costs included in contract prices. When pipe laying is not in

progress, close open ends of pipe by watertight plug, or other means approved by Engineer.

Dewatering shall be accomplished by the use of well points, sump pumps, rock or gravel drains

placed below subgrade foundations, or subsurface pipe drains. All water shall be disposed of in

a suitable manner without being a menace to public health or causing public inconvenience. No

water shall be drained into other work being completed or under construction. Obtain all

necessary permits for dewatering.

The dewatering operation shall continue until such time as it is safe to allow the water table to

rise in the excavations. Pipe trenches shall contain enough backfill to prevent pipe floatation.

Page 117: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 11

Water shall not be allowed to rise until the concrete has set a minimum of twenty-four (24)

hours, and the forms have been removed. Water shall not be allowed to rise unequally against

unsupported structural walls.

B. Deflection of Pipe: Do not exceed deflection limits for each type of pipe as allowed by the City

of Boulder or the pipe manufacturer.

C. Water-Main Connection: Tap water main according to requirements of the City of Boulder

Water Department and of size and in location indicated.

D. Make connections larger than 2-inches with MJ Tee. Valves shall be placed on each leg of the

Tee, as shown on the construction plans.

E. Install underground piping with restrained joints at horizontal and vertical changes in direction.

Use restrained-joint piping, thrust blocks, anchors, tie-rods and clamps, and other supports.

3.05 ANCHORAGE INSTALLATION

A. Install anchorages for tees, plugs and caps, bends, crosses, valves, and hydrant branches.

Include anchorages for the following piping systems:

1. Gasketed-Joint, Ductile-Iron, Water-Service Piping: According to AWWA C600.

2. Gasketed-Joint, PVC Water-Service Piping: According to AWWA M23.

B. Apply full coat of asphalt or other acceptable corrosion-resistant material to surfaces of

installed ferrous anchorage devices.

3.06 VALVES AND HYDRANTS

A. Carefully inspect valve before installation. Clean interior. Operate valve to determine parts in

proper working order, with valves seating and drain valve operating properly. Set plumb and

securely brace into place. Valve boxes centered and plumb over the operating nut. Valve boxes

supported by bricks or other means to prevent any shock or stress transmitted to pipe or valve.

Set valve box covers to just below subgrade level to prevent damage during construction of

surfacing if applicable. Adjust to grade of surfacing.

B. AWWA Gate Valves: Comply with AWWA C600 and AWWA M44. Install each underground valve

with stem pointing up and with valve box.

3.07 SANITARY SEWER CROSSING

A. Normal conditions: Whenever possible lay water mains over sanitary sewers to provide vertical

separation of at least 18-inches between invert of water main and crown of sewer.

B. Unusual Conditions: If above separation cannot be met, use following:

1. Sewer passing over or less than 18-inches under water main.

a. One continuous length of watertight pipe 20' long centered on water main. Joints

between different pipes encased in concrete 6-inches thick and extending 6-inches

either side of joint: or

Page 118: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 12

b. Sewer pipe encased in 6-inches concrete around pipe, and extend 10' either side of

water main.

2. Water mains passing under sewers: If vertical separation less than 18-inches provide

structural support for sewer.

3.08 UTILITIES ENCOUNTERED

Protection of all existing gas, water, sewer services, drains, cable, telephone lines, and electric

lines encountered during construction is the Contractor's responsibility. If utilities are disturbed,

they shall be maintained and/or restored to original condition at the Contractor's expense.

Backfill around utilities shall be adequately compacted to assure permanent stability. Flow fill

is to be used under existing utilities where a new utility line has been installed.

3.09 FIELD QUALITY CONTROL

A. Piping Tests: Conduct piping tests before joints are covered and after thrust blocks have

hardened sufficiently. Fill pipeline 24 hours before testing and apply test pressure to stabilize

system. Use only potable water.

B. Notify UCB Inspector at least 24 hours in advance of pipe being laid in any trench. Cover no

pipes until observed by Engineer. Notify Engineer at least 48 hours before pipe is to be tested.

All water mains are to be disinfected, flushed, and hydrostatically tested per the City of Boulder

Regulations.

C. Hydrostatic Testing:

1. General: Make pressure and leakage tests on all newly laid pipe. Test two or more valved

sections not to exceed 1000 feet. Test first section of pipe laid to verify if watertight. Lay

no additional pipe until first test section has passed tests.

2. Furnish following equipment and materials for tests, unless otherwise directed by

Engineer:

3. 1 Graduated containers

4. 2 Pressure gauges

5. 1 Suitable hose and suction pipe as required

6. Testing Procedure: Test each 1000 feet of line installed while trench is partially backfilled

and joints are left exposed for examination for leaks. Do not conduct pressure tests until

48 hours after placement of concrete thrust blocks. After pipe has been partially

backfilled, slowly let water into line. Vent to allow air in line to be released. Flush line as

necessary for cleaning. Leave water in line for 24 hours prior to pressure test. Test at 1-1/2

times working pressure, calculated for low point of test section, or 150 psi, whichever is

greater. Valve off pump and hold pressure in line for test. Test for two hours or as agreed

to by Engineer. At end of test, operate pump until test pressure is again attained. Calibrate

container of water for pump suction to determine amount of water to replace leakage.

7. Leakage Allowance: Leakage is quantity of water necessary to refill line at end of test

period. No installation will be accepted until leakage is less than:

ALLOWABLE LEAKAGE PER 1000' OF PIPE IN GPH

Avg. Test Nominal Pipe Diameter - in.

Page 119: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 13

Pressure

psi 6 8 10 12 18

200 0.64 0.85 1.06 1.28 1.91

175 0.59 0.80 0.99 1.19 1.79

150 0.55 0.74 0.92 1.10 1.66

125 0.50 0.67 0.84 1.01 1.51

100 0.45 0.60 0.75 0.90 1.35

For pipe with 18' nominal lengths. To obtain recommended allowable leakage for pipe

with 20' nominal lengths, multiply the leakage calculated from the table by 0.9. If pipeline

under test contains sections of various diameters, allowable leakage will be sum of

computed leakage for each size. Reduce allowable leakage proportionately for sections

less than 1000 ft.

D. Prepare reports of testing activities.

3.10 FLUSHING AND DISINFECTING

A. General: In accordance with AWWA C601. Acceptable chlorine disinfectants are calcium

hypochlorite granules, sodium hypochlorite solutions, and calcium hypochlorite tablets.

B. Chlorine-Water Solution Method:

Chlorine Required to Produce 25 Mg/L Concentration

in 100 feet of Pipe - by Diameter

Pipe 100 Percent 1 Percent

Diameter Chlorine Chlorine Solution

In. Lb. Gal.

4 .013 .16

6 .030 .36

8 .054 .65

10 .085 1.02

12 .120 1.44

16 .217 2.60

Induce chlorine solution into pipe line at a continuous feed rate to attain a concentration of 25

Mg/L free chlorine.

C. Tablet Method: May not be used on solvent welded plastic pipe. May be used only when all

foreign materials have been kept out of pipe. If ground water has entered pipe during

installation and tablets have been installed, flush main and use chlorine-water solution method.

Do not use if temperature is below 5 degrees C. Place tablets with non-toxic adhesive in each

pipe length in top of pipe in accordance with following table:

Page 120: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 14

Number of 5-g Hypochlorite Tablets

Required for Dose of 25 mg/L*

Pipe Length of Pipe Section, ft.

Diameter 13 18 20 30 40

in. or less

4 1 1 1 1 1

6 1 1 1 2 2

8 1 2 2 3 4

10 2 3 3 4 5

12 3 4 4 6 7

16 4 6 7 10 13

D. Chlorination Test: Assure valves are closed on existing system to prevent chlorine solution

flowing into existing system. Retain 25 mg/L chlorinated water in pipe line for minimum of 24

hours. During retention period operate all valves and hydrants to disinfect. At end of 24 hour

period, chlorine in system to be no less than 10 mg/L throughout length tested. When section

being tested meets 10 mg/L chlorine after 24 hours, flush main. Water samples taken shall show

no coliform organisms. If water in pipe does not meet the governing health agency

requirements, repeat disinfection procedure, at Contractor's expense, until requirements are

met. Furnish acceptance forms from governing agency to Engineer.

3.11 IDENTIFICATION

A. Underground Line Marker:

1. During backfilling and top-soiling of underground piping, install continuous underground

line markers, located at two (2) depths, 1’ below grade and 2’ above pipe.

2. Manufacturer’s standard permanent, bright-colored, continuous-printed tape with

metallic core, intended for direct-burial service; not less than 6” wide x 4 mils thick.

Furnish blue tape with black printing reading “CAUTION WATER LINE BURIED BELOW.”

B. Non-Metallic Piping:

1. If non-metallic piping is used then provide tracer wire and test stations in compliance with

COB’s Design and Construction Standards.

2. Tracer wire shall be 12 gauge type UF, 600V single strand copper wire. Splices in tracer

wires shall be “3M” Type DBY-6 low voltage for direct bury, and shall be waterproof gel

type connectors.

3. Tracer wire test stations shall be C.P. Mini Box stations measuring 2-1/2 inches in

diameter and 18 inches high, or an approved equal.

*Based on 3.25 g available chlorine per tablet, any portion of tablet rounded to next higher number.

Page 121: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

WATER UTILITY DISTRIBUTION PIPING

331100 - 15

3.12 OPERATION OF VALVES

Contractor is responsible for operating any valves necessary to complete project. Contractor is

required to provide Owner 24 hours notice prior to said operation. Valves shall be tagged “Out

of Service” until the water system is operational. It is the responsibility of the Contractor to

notify the City of Boulder Fire Department regarding the location of the tagged hydrants.

3.13 CLEANUP AND RESTORATION

Restore all pavements, curbs, gutters, utilities, fences, irrigation ditches, yards, lawns, and other

structures or surfaces to condition equal to or better than before work began, and to

satisfaction of Engineer. Deposit all waste material in designated waste areas. Grade and shape

disposal site. Complete topsoil and reseeding of site, if required. Where disposal sites are not

designated, remove, and dispose of all waste material off site.

END OF SECTION

Page 122: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 1

SECTION 312333

TRENCHING AND BACKFILLING

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Specification Sections, apply to this Section.

B. Additional information concerning trenching and backfilling may be found on the civil drawings,

in the University of Colorado Boulder specifications and City of Boulder. In case of conflict

between the drawings, jurisdictional criteria and the information specified herein, the more

stringent requirements shall govern.

1.02 SUMMARY

A. This Section includes the following:

1. Excavating and backfilling for utility trenches.

2. Excavating and backfilling trenches within building lines.

B. Related Sections include the following:

1. Section "Site Clearing" for site stripping, grubbing, stripping, and stockpiling topsoil, and

removal of above- and below-grade improvements and utilities.

2. Section “Temporary Erosion and Sedimentation Control” for erosion and sediment

control.

3. Section “Tree and Plant Protection” for the protection of existing trees and plants onsite.

C. Shoring Design: Provide the services of a professional engineer to design all shoring, bracing,

and underpinning required to protect the safety of workers and integrity of adjacent existing

structures or other improvements.

1.03 DEFINITIONS

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to

support sides of pipe.

2. Final Backfill: Backfill placed over initial backfill to fill a trench.

B. Base Course: Course placed between the subbase course and hot-mix asphalt paving.

C. Bedding Course: Course placed over the excavated subgrade in a trench before laying pipe.

D. Borrow Soil: Satisfactory soil imported from off-site for use as backfill approved by Geotechnical

Engineer.

Page 123: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 2

E. Unclassified Excavation: Removal of all material of whatever-character required for the work

encountered above subgrade elevations and to lines and dimensions indicated, including

boulders.

F. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated

lines and dimensions as directed or approved by Owner’s Representative and the testing and

inspections agency to correct unsatisfactory conditions. Authorized additional excavation and

replacement material will be paid for according to Contract provisions for changes in the Work.

G. Bulk Excavation: Excavation more than 10 feet in width and more than 30 feet in length.

H. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and

dimensions without direction by Owners Representative. Unauthorized excavation including

disposition of overexcavated materials and other work resulting from slides, cave-ins, swelling,

upheaval, or remedial work, as well as remedial work directed by Owners Representative, shall

be without additional compensation.

I. Subbase Course: Course placed between the subgrade and base course for hot-mix asphalt

pavement, or course placed between the subgrade and a cement concrete pavement or a

cement concrete or hot-mix asphalt walk.

J. Subgrade: Surface or elevation remaining after completing excavation, or top surface of a fill

or backfill immediately below subbase, drainage fill, or topsoil materials.

K. Utilities: Includes on-site underground pipes, conduits, ducts, and cables, as well as

underground services within buildings.

1.04 SUBMITTALS

A. Product Data: For the following:

1. Each type of plastic warning tape.

B. Samples: Contractor to submit representative samples of all materials proposed for use in

bedding and trench backfilling operations to the testing and inspections agency for analysis and

determination of compliance with the requirements specified herein.

C. Material Test Reports: Six (6) copies provided by Owner from a qualified testing agency

indicating and interpreting test results for compliance of the following with requirements

indicated:

1. Classification according to ASTM D 2487 of each on-site or borrow soil material proposed

for fill and backfill.

2. Laboratory compaction curve according to ASTM D 698 for each on-site or borrow soil

material proposed for fill and backfill.

D. Pre-Excavation Photographs or Videotape: Show existing conditions of adjoining construction

and site improvements, including finish surfaces that might be misconstrued as damage caused

by earthwork operations. Submit before earthwork begins.

Page 124: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 3

1.05 QUALITY ASSURANCE

A. Testing Agency:

1. All testing and inspections required herein will be performed by an independent testing

and inspection agency employed by the owner.

2. Notify the testing and inspection agency not less than 48 hours in advance of all work

requiring testing or inspection services.

B. Regulatory Requirements: Comply with all applicable requirements of the Occupational Safety

and Health Administration and local and State rules, regulations, and ordinances concerning

shoring, bracing, or sloping of excavations and safety of workers. Safety of workers is the

responsibility of the Contractor.

C. Coordination: Coordinate scheduling and procedures for trench excavation, bedding, and

backfilling with other Sections whose work relates to or is affected by this work.

D. Pre-Construction Conference: Conduct conference at Project site as directed by Owner’s

Representative prior to start of construction. Contractor to comply with requirements, which

also may be included in Section "Project Management and Coordination."

E. Testing and Inspection:

1. Conform testing and inspection of backfill to the requirements of this section. Make in

place density tests at intervals and locations as directed by the Owner’s Representative.

2. All tests required for preliminary review of materials shall be made by an acceptable

independent testing laboratory at the expense of the Contractor. Two (2) initial gradation

tests shall be made for each type of pipe bedding, fill or backfill material, and one (1)

additional gradation test shall be made for each additional 500 tons of each material.

Retests of samples failing initial tests shall be at the expense of the Contractor. Initial

moisture density (Proctor) tests sand relative density tests on the materials, and all in

place field density tests shall be made at the expense of the Owner.

1.06 PROJECT CONDITIONS

A. Existing Utilities: Locations, sizes and depths or invert elevations of existing utilities as shown

on the drawings are based on information provided by others, and are believed to be correct,

but may not be absolutely so. Such information is therefore presumed only as approximations

and should be verified prior to construction. Do not interrupt utilities serving facilities occupied

by Owner or others unless permitted in writing by Owner’s Representative and then only after

arranging to provide temporary utility services according to requirements indicated.

1. Notify Owner’s Representative not less than two (2) days in advance of proposed utility

interruptions.

2. Do not proceed with utility interruptions without Owner’s Representative's written

permission.

3. Contact utility-locator service for area where Project is located before excavating.

4. Provide potholing of utilities to determine existing conflicts. Notify Owner’s

representative of conflicts prior to construction.

Page 125: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 4

B. Existing Bench Marks: Carefully preserve and maintain existing bench marks, monuments,

property line pins, and other reference points. If disturbed or destroyed, restore or replace

them at no additional cost to the Owner.

C. Verification of Existing Conditions: Visit the site prior to submission of bids. Verify existing

conditions, elevations, and utility locations. In the event of discrepancies between existing

conditions and those indicated on the Contract Documents or survey, contact the Owner’s

Representative for clarification.

D. Sleeving: Verify all required utility sleeving is installed and properly located and supported prior

to backfilling.

1.07 WARRANTY

Settlement in backfill, fill or in structures built over backfill or fill, which may occur within the

specified project warranty period, shall be corrected at no cost to the Owner. Any structures

damaged by settlement shall be restored to their original condition by the Contractor, at no

cost to the Owner.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Bedding Material within Building Lines.

1. Granular bedding material for Ductile Iron Pipe shall be washed chips, of 3/8” nominal

size in accordance to the above gradations below:

Sieve Size or Designation Maximum Particle Size (in.)

1/2” 100%

3/8” 85-100%

No. 4 10-30%

No. 8 0-5%

General Note: Flow Fill is required under any civil utility which is excavated under or is placed

on disturbed soils.

B. Flow Fill

1. Low Strength Concrete (LSC) or Controlled Low Strength Material (CLSM) is defined as

flow fill in these standards.

2. Materials, batching, mixing, and delivery shall be in accordance with the Colorado

Department of Highways Standard Specifications for Road and Bridge Construction and

shall meet the specific requirements outlined in the City of Boulder’s Design and

Construction Standards, Section 9.02.

3. The desired 28-day compressive strength is between 50 to 150 psi.

C. Utility Trench Backfill Materials:

1. Existing soils obtained from trench excavations, including granular or aggregate base

course from removed pavements, broken and pulverized claystone or claystone-

sandstone bedrock may be used for backfilling trenches, provided it meets any special

Page 126: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 5

requirements of the Utility Agency and Geotechnical Engineer. Bedrock must be

processed and broken or pulverized so that the maximum particle or fragment size does

not exceed two-inches (2-inches).

D. Unsuitable Utility Trench Materials: Materials unsuitable for bedding and backfilling include

highly organic soils, ASTM D2487 Group PT topsoil, and soils containing roots, vegetable matter,

trash, and debris.

2.02 ACCESSORIES

A. Shoring and Bracing: Provide all materials for shoring and bracing, such as sheet piling, uprights,

stringers, and cross-braces, in good and serviceable condition, as required for safety and by

governing authorities.

B. Detectable Warning Tape: Acid- and alkali-resistant polyethylene film warning tape

manufactured for marking and identifying underground utilities, a minimum of 6 inches (150

mm) wide and 4 mils (0.1 mm) thick, continuously inscribed with a description of the utility;

colored as follows:

1. Red: Electric.

2. Yellow: Gas, oil, steam, and dangerous materials.

3. Orange: Telephone and other communications.

4. Blue: Water systems.

5. Green: Sewer systems.

6. Purple: Non-potable water systems.

PART 3 - EXECUTION

3.01 EXAMINATION

A. Verification of Conditions: Examine areas and conditions under which the work of this Section

will be performed. Do not proceed with the work until unsatisfactory conditions have been

corrected. Commencement of work implies acceptance of all areas and conditions.

3.02 PREPARATION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by

settlement, lateral movement, undermining, washout, and other hazards created by earthwork

operations.

B. Preparation of subgrade for earthwork operations including removal of vegetation, topsoil,

debris, obstructions, and deleterious materials from ground surface is specified in Section "Site

Clearing."

C. Protect and maintain erosion and sedimentation controls, which are specified in Section

"Temporary Erosion and Sediment Control," during earthwork operations.

D. Existing Utilities:

Page 127: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 6

1. General: Location of existing utilities shown on the plans are approximate only. The

Contractor shall be responsible to locate all existing underground utilities in areas of the

work. Provide potholing for all utilities to verify conflict does not exist. If utilities are to

remain in place, provide protection during excavation and backfilling operations. Should

uncharted or incorrectly charted piping or other utilities be encountered during

excavations, consult the Owner’s Representative immediately for direction. Cooperate

with the Utility Agency in keeping respective services and facilities in operation. Repair

damaged utilities to the satisfaction of the Utility Agency.

2. Active Utilities: Do not interrupt existing utilities serving facilities occupied and used by

the Owner or by adjacent properties, except when permitted in writing by the Owner’s

Representative, and then only after acceptable temporary utility services have been

provided. Remove or relocate utilities only as indicated or specified.

3. Inactive Utilities: Report inactive or abandoned utilities encountered in excavating or

grading operations, and remove, plug, or cap as required.

E. Protection of Persons and Property:

1. Provide all necessary measures to protect workmen and passersby. Barricade open

excavations occurring as part of the work, as required by municipal or other authorities

having jurisdiction.

2. Protect adjacent streets, structures, and other improvements from damage caused by

settlement, undermining, washout, and other hazards created by trench excavations.

F. Protect subgrades and trench bottoms soils against freezing temperatures or frost. Provide

protective insulating materials as necessary.

G. Cold Weather Work: Prevent frost from entering bearing strata upon which construction will

taken place or in areas where fill will be placed in that season.

3.03 DEWATERING

A. Prevent surface water and subsurface or ground water from entering excavations, from ponding

on prepared subgrades, and from flooding Project site and surrounding area.

B. Provide and maintain pumps, well points, sumps, suction and discharge lines, and other

dewatering system components necessary to convey water away from excavations and to

collection or runoff areas. Establish and maintain temporary drainage ditches and diversions

away from trench excavations. Do not use trench excavations as temporary drainage ditches.

C. Protect subgrades from softening, undermining, washout, and damage by rain or water

accumulation.

1. Reroute surface water runoff away from excavated areas. Do not allow water to

accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.

2. Install a dewatering system to keep subgrades dry and convey ground water away from

excavations. Maintain until dewatering is no longer required.

3. Obtain and comply with all provisions of the Colorado Department of Public Health and

Environment, Water Quality Control Division, Construction Dewatering Permit.

Page 128: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 7

3.04 SHORING AND BRACING

A. Provide shoring and bracing of excavations as required for safety and by governing authorities.

Carry down shoring and bracing as excavation progresses. Maintain shoring and bracing in

excavations regardless of time period excavations will be open.

3.05 PAVEMENT REMOVAL AND REPLACEMENT

A. Where trenches or other utility excavations are made in existing paved areas, saw-cut pavement

at a neat, clean edge or at existing joints for concrete pavements to create a clean break line.

Cut pavement a minimum of 12-inches beyond trench width on each side of trench; remove

and dispose of existing surface course and aggregate base course, leaving a 12-inches wide

undisturbed subgrade lip on each side of trench.

B. After trench has been backfilled and compacted, place new pavement in accordance with

applicable requirements of Sections 321216 and 321313 as applicable, for Asphaltic or Portland

cement concrete pavement and in accordance with Authorities having jurisdiction.

3.06 EXPLOSIVES

A. Explosives: Do not use explosives.

3.07 EXCAVATION FOR UTILITY TRENCHES

Flow Fill is required under all existing utilities that are excavated under and all new utilities that are

placed on disturbed soils or beneath building foundations.

A. Excavate trenches to indicated gradients, lines, depths, and elevations.

1. Beyond building perimeter, excavate trenches to allow installation of top of pipe below

frost line.

B. Excavate trenches to uniform widths to provide the following clearance on each side of pipe or

conduit. Excavate trench walls vertically from trench bottom to 12 inches (300 mm) higher than

top of pipe or conduit, unless otherwise indicated on the drawings.

C. Clearance: 12 inches each side of pipe or conduit.

1. Slope sides of trenches or provide shoulders in accordance with OSHA requirements and

as required by Utility Agency standards.

2. Continuously monitor cut slopes and trenches for distress or movement. Provide all

necessary shoring and bracing required to protect the life and safety of workmen

performing excavation or installing piping or conduit.

D. Trench Bottoms: Excavate trenches a minimum of 4 inches deeper than bottom of pipe

elevation to allow for bedding course. Hand excavate for bell of pipe.

1. Excavate trenches 6 inches deeper than elevation required in rock or other unyielding

bearing material to allow for bedding course and backfill with a 6-inches layer of crushed

stone or gravel prior to installing pipe.

Page 129: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 8

3.08 BEDDING OF PIPES:

A. After completion of trench excavation and before installation of piping, install not less than 6-

inches of approved bedding material in trench bottom for support of pipe. The moisture content

of the material shall be from 1 percent below to 3 percent above the optimum. Dig bell holes in

bedding deep enough to provide a minimum of 2-inches clearance between the bell and

bedding material. Fully support pipe on bedding material for the full length of the pipe barrel.

B. After pipe is adjusted for line and grade, and all jointing is complete, carefully place and tamp

bedding material under the haunches of the pipe and in the previously dug bell holes.

C. Install bedding in separate loose lifts, not to exceed 6-inches of loose depth, except that the

first loose lift shall not be higher than the pipe centerline to a minimum depth of 12-inches

above top of pipe prior to starting placement of compacted backfill. Lightly compact or tamp

bedding material in a manner to avoid displacement of or damage to the pipe.

D. If the granular bedding does not meet filter criteria for the enclosing soils, then non-woven filter

fabric (e.g., Tencate Mirafi® 140N, or the equivalent) should be placed around the bedding to

reduce migration of fines into the bedding, which can result in severe, local surface settlements.

3.09 STORAGE OF SOIL MATERIALS

A. Stockpile borrow soil materials and excavated satisfactory soil materials in approved locations

without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent

windblown dust.

1. Stockpile soil materials away from edge of excavations. Do not store within drip line of

remaining trees.

3.10 UTILITY TRENCH BACKFILL

Flow Fill is required under all existing utilities that are excavated under and all new utilities that are

placed on disturbed soils or beneath building foundations.

A. After installation of utility piping or lines have been completed, locations recorded, trash or

other debris removed from excavations, and bedding placed and approved, backfill promptly as

work and weather conditions permit. Do not backfill trenches until all required pipe system tests

and inspections have been made, unless partial backfilling is required to restrain pipe under test

pressures. Use care in backfilling to avoid damage or displacement of pipe systems.

B. Place backfill on subgrades free of mud, frost, snow, or ice.

C. Place and compact bedding course on trench bottoms and where indicated. Shape bedding

course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings,

and bodies of conduits.

D. Place backfill materials in layers not more than 8-inches in loose depth for material compacted

by heavy compaction equipment, and not more than 4-inches in loose depth for material

compacted by hand operated tampers. Use hand held tools or compacting devices for trench

Page 130: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 9

backfill, until a minimum compacted thickness of 3-feet -0-inches above top of pipe is achieved.

Mechanical or power compactors may be used thereafter.

E. Before compaction, moisten or aerate each layer of backfill to specifications.

F. Compact each layer to not less than 95% of maximum standard Proctor density (ASTM D698).

Thoroughly compact by means of mechanical tampers areas which cannot be properly

compacted by means of rolling equipment. The material shall be from 1 percent below to 3

percent above the optimum moisture content.

G. Backfill to subgrade elevation shown for finish grading, topsoil placement, or paving.

H. Place and compact initial backfill of satisfactory soil, free of particles larger than 1 inch in any

dimension, to a height of 12 inches over the utility pipe or conduit.

1. Carefully compact initial backfill under pipe haunches and compact evenly up on both

sides and along the full length of utility piping or conduit to avoid damage or displacement

of piping or conduit. Coordinate backfilling with utilities testing.

I. Backfill voids with satisfactory soil while installing and removing shoring and bracing.

J. Place and compact final backfill of satisfactory soil to final subgrade elevation.

K. Install warning tape directly above utilities, 12 inches below finished grade, and 6 inches below

subgrade under pavements and slabs.

L. Unless otherwise authorized by the UCB Civil Engineer flowable fill shall be used for backfill

under high traffic asphalt roadways. This includes, but is not limited to, any asphalt areas on

18th Street, Colorado Avenue, Kittredge Loop Road, Discovery Drive, Euclid Avenue,

Wardenburg Drive, and Baker Drive.

M. The Contractor may request approval of alternate means of compaction. Such request must be

submitted to the Owner’s Representative in writing and the approval will be made by the

Owner’s Representative in writing. Use of specified or approved compaction methods does not

relieve the Contractor from providing a complete project meeting the intent of the Design and

Construction Standards.

N. When directed by the Owner’s Representative, the Contractor shall excavate backfilled trenches

for purposes to perform compaction tests at locations and depths determined by the Owner’s

Representative. The Contractor shall be responsible for reinstalling and compacting the test

excavation at no additional cost to the Owner.

3.11 PLACEMENT OF FLOW FILL

A. Sufficient mixing capacity shall be provided to permit the flow fill to be placed continuously,

without interruption.

B. Flow fill shall be thoroughly mixed prior to discharging to ensure a uniform product. Agitation

is required during transportation and waiting time to ensure that the material is in suspension

when placed.

Page 131: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 10

C. Flow fill shall be discharge from the mixer into the trench to be filled, or by other methods

approved by the Owner’s Representative.

D. The flow fill shall be placed continuously and brought up uniformly to a point a minimum of 1-

inch above adjacent surfaces (trench walls) to ensure proper drainage of bleed water away from

the trench.

E. Flow fill shall be vibrated during and after placement to accelerate the bleeding and evaporation

of water and to improve consolidation of the material.

F. Flow fill shall not be placed on frozen ground.

G. Flow fill shall be protected from freezing until it has hardened.

H. Flow fill mixing and placement may be started if weather conditions are favorable, when the air

temperature in the shade and away from artificial heat is at least 34 degrees Fahrenheit and

rising. Mixing and placing shall stop when the air temperature in the shade and away from

artificial heat is 38 degrees Fahrenheit or less and falling, and in no care shall flow fill be placed

with the air temperature is lower than 34 degrees Fahrenheit.

I. It shall be the Contractor’s responsibility to ensure that the backfilled trench is not exposed to

vehicular traffic loads until such time that the fill material has sufficiently cured to support the

anticipated vehicle loads. Prior to reopening the roadway to normal traffic, the Contractor shall

subject the fill material to a vehicular test load that is reasonably representative of the ultimate

loading anticipated. When the fill material supports such vehicular test load without apparent

deformation, said fill material shall be deemed sufficiently cured to permit reopening of the

roadway to normal traffic.

3.12 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified independent geotechnical engineering testing

agency to perform field quality-control testing.

B. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with

subsequent earthwork only after test results for previously completed work comply with

requirements.

C. Testing agency will test compaction of soils in place according to ASTM D 1556, ASTM D 2167,

ASTM D 2922, and ASTM D 2937, as applicable. Perform field moisture tests in accordance with

ASTM D3017. Tests will be performed at the following locations and frequencies at a minimum:

1. Trench Backfill: The density tests shall be performed during backfilling at specified depths

in the trench to ensure that the required density and moisture is obtained throughout.

For trenches less than 30-inches in depth, density tests shall be taken within 18-inches

above the top of pipe or conduit and at the surface/toplift as a minimum. For trenches

greater than 30-inches in depth, density tests shall be taken within 18-inches of the top

of the pipe or conduit, and at 2-foot vertical intervals to the top of the trench with the

final test at the surface/toplift. For utility mains conduct one (1) set of tests per 100 feet

of linear trench at specified depths and for service lines conduct one (1) test per every

Page 132: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TRENCHING AND BACKFILLING

312323 - 11

service line per utility type at specified depths. At a minimum, test intervals and quantities

shall meet or exceed the requirements of the local utility agency.

D. When testing agency reports that backfills have not achieved degree of compaction specified,

scarify and moisten or aerate, or remove and replace soil to depth required; recompact and

retest until specified compaction is obtained.

3.13 PROTECTION

A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep

free of trash and debris.

B. Repair and reestablish grades to specified tolerances where completed or partially completed

surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent

construction operations or weather conditions.

1. Scarify or remove and replace soil material to depth as directed by Owner’s

Representative; reshape and recompact.

C. Where settling occurs before Project correction period elapses, remove finished surfacing,

backfill with additional soil material, compact, and reconstruct surfacing.

1. Restore appearance, quality, and condition of finished surfacing to match adjacent work,

and eliminate evidence of restoration to greatest extent possible.

3.14 CLEANING AND ADJUSTMENT

A. Cleanup: Remove excess materials not required for backfilling purposes, including excess spoil

material, accumulated debris, and rubbish from site. Burning of waste material is prohibited.

3.15 RESTORATION

A. Adjacent Improvements: Restore all yards, lawns, irrigation systems and other structures or

surfaces to condition equal to or better than before work began.

3.16 DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Disposal: Remove surplus satisfactory soil and waste material, including unsatisfactory soil,

trash, and debris, and legally dispose of it off Owner's property.

END OF SECTION

Page 133: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TEMPORARY EROSION AND SEDIMENTATION CONTROL

312500 - 1

SECTION 312500

TEMPORARY EROSION AND SEDIMENTATION CONTROL

PART 1 - GENERAL

1.01 Contractor is responsible for any unintended flooding damage on-site and in neighboring areas

as a result of erosion control measures.

1.02 RELATED WORK

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Specification Sections, apply if provided, to this Section.

B. Additional information concerning temporary erosion and sedimentation control may be found

on the civil drawings and University of Colorado – Boulder Specifications and City of Boulder

construction standards. In case of conflict between the drawings, jurisdictional criteria and the

information specified herein, the more stringent requirements shall govern.

C. Additional information concerning erosion control may be found in the SWMP, Storm Water

Management Plan.

1.03 SUMMARY

A. Work Included. Furnish, install, maintain, and remove temporary erosion and sedimentation

controls as shown on the drawings or specified herein, or as required to complete the work.

Provide documentation as required by University of Colorado – Boulder and/or LEED

requirements, as applicable.

B. Related Sections include the following:

1. Section "Site Clearing" site stripping, grubbing, stripping, and stockpiling topsoil, and

removal of above- and below-grade improvements and utilities.

2. Section “Earthwork” for soil materials, site excavating, filling and grading.

3. Section “Trenching” for excavating and backfilling of utilities.

C. Permits and Fees: Obtain and pay for all permits and fees required for the work of this section,

including erosion and sediment control and water quality permits required by the authority

having jurisdiction and the Colorado Department of Public Health and Environment, Water

Quality Control Division.

D. Erosion Control: The Erosion and Sedimentation Control Drawings included in the Contract

Documents is the minimum requirement to be implemented. Provide additional control as

necessary to meet applicable criteria.

1.04 DEFINITIONS

A. Backfill: Soil material used to fill an excavation.

Page 134: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TEMPORARY EROSION AND SEDIMENTATION CONTROL

312500 - 2

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to

support sides of pipe.

2. Final Backfill: Backfill placed over initial backfill to fill a trench.

B. Unclassified Excavation: Removal of all material of whatever character required for the work

encountered above subgrade elevations and to lines and dimensions indicated, including

boulders.

C. Fill: Fill is all material placed to raise the grade of the site or to backfill excavation, upon which

the Soils Engineer has made sufficient tests and observations to enable him to issue a written

statement that, in his opinion, the fill has been placed and compacted in accordance with the

requirements of these specifications.

D. BMP: Best Management Practice. Erosion and sediment control devices, which may consist of

silt fence, sediment control logs, crates, filter fabric, riprap, etc.

E. SWMP: Storm Water Management Plan. Identifies BMPs, which are erosion and sediment

control measures for the project.

F. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and

electrical appurtenances, or other man-made stationary features constructed above or below

the ground surface.

G. Subgrade: Surface or elevation remaining after completing excavation, or top surface of a fill

or backfill immediately below subbase, drainage fill, or topsoil materials.

H. Utilities: Include on-site underground pipes, conduits, ducts, and cables, as well as underground

services to buildings.

1.05 SUBMITTALS

A. Submittal Procedures: All submittals are to be made to the Owner’s Representative. If provided

refer to section “Submittal Procedures.”

B. Product Data: Submit manufacturer’s published descriptive literature and complete

specifications for manufactured products specified herein and utilized on the project.

1. Geotextiles.

2. Erosion Control Fabric.

C. Storm Water Management Plan:

1. The Contractor is responsible for obtaining all required permits including a General Permit

application for Storm Water Discharges associated with construction activities at least ten

(10) days prior to start of construction. Permits are to be filed with the Colorado

Department of Public Health and Environment, Water Quality Control Division.

2. Contractor shall have the Storm Water Management Plan (SWMP) and report available

on-site at all times.

3. The Storm Water Management Plan should be reviewed and modified as part of the

overall process of assessing and managing storm water quality issues at the site. Erosion

and sediment control measures outlined in the report are intended as the minimum

Page 135: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TEMPORARY EROSION AND SEDIMENTATION CONTROL

312500 - 3

requirement for the construction of this project as anticipated at the time of design.

Additional measures are to be implemented and updated in the SWMP per authority

having jurisdiction, as necessary and as required.

1.06 QUALITY ASSURANCE:

A. Regulatory Requirements: Comply with applicable local, State and Federal ordinances, rules

and regulations concerning sedimentation control and storm water runoff.

B. In case of conflict between the above codes, regulations, references and standards and these

specifications, the more stringent requirements shall govern.

C. Preconstruction Conference: Conduct conference at Project site as directed by Owner’s

Representative prior to start of construction. Contractor to comply with requirements, which

may also be included in Section "Project Management and Coordination."

1.07 PROJECT/SITE CONDITIONS

A. Existing Conditions: Verify all existing conditions affecting the work of this section prior to

submitting bids or proposals. Additional compensation will not be allowed for revisions or

modification of work resulting from failure to verify existing conditions.

1.08 WARRANTY

A. Temporary Erosion and Sediment Control measures shall be maintained until permanent

measures are in place. All damaged, disturbed or devices filled with sediment, which may occur

within the specified project warranty period, shall be corrected at no cost to the Owner. Any

devices damaged by erosion or sediment shall be restored to their original condition by the

Contractor, at no cost to the Owner.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Erosion and Sedimentation Control Materials: Provide one or more of the following materials,

as shown on the plans or as applicable for site conditions:

1. Sand bags.

2. Sediment control logs.

3. Silt fences.

4. Temporary seeding.

5. Biodegradable wood excelsior, straw, or coconut-fiber mat enclosed in a

photodegradable plastic mesh.

6. Drainage geotextile.

7. Other materials proposed for use on-site.

Page 136: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TEMPORARY EROSION AND SEDIMENTATION CONTROL

312500 - 4

PART 3 - EXECUTION

3.01 PREPARATION

A. General:

1. Determine the existing ground elevations, drainage patterns, and changes to such

patterns during excavation in order to satisfactorily plan and provide materials for

adequate erosion and sediment control devices.

3.02 TEMPORARY EROSION AND SEDIMENTATION CONTROL

A. Provide temporary erosion and sedimentation control measures to prevent soil erosion and

discharge of soil-bearing water runoff or airborne dust to adjacent properties and rights-of-way

according to requirements of authorities having jurisdiction.

B. Inspect, repair, and maintain erosion and sedimentation control measures during construction

until permanent vegetation has been established.

C. Remove erosion and sedimentation controls, and restore and stabilize areas disturbed during

removal.

D. Secure grading permit from agency having jurisdiction prior to commencing grading operations.

3.03 EXAMINATION

A. Verification of Conditions: Examine areas and conditions under which the work of this section

will be performed. Do not proceed with the work until unsatisfactory conditions have been

corrected. Commencement of work implies acceptance of all areas and conditions.

3.04 INSTALLATION

A. Erosion and Sedimentation Control Devices. Erosion and sedimentation control measures to be

taken during construction include, but are not necessarily limited to the following:

1. Apply soil stabilization within 14 days to all disturbed areas that are to be dormant for a

period longer than 30 calendar days after reaching grade. Stabilize soil with mulch

anchored per criteria of authorities having jurisdiction. Temporarily revegetate areas that

will remain in an interim condition for more than sixty (60) days.

2. Roads and parking areas indicated to be paved may be covered with an appropriate

aggregate base course in lieu of mulch. Temporary mulching or aggregate base course is

not required if final pavement construction will take place within 30 days after grading to

final contours.

3. Soils that will be stockpiled for more than 30 days must be mulched and seeded within 14

days after stockpile construction.

4. Prevent sediment from leaving the project site by installing a silt fence or other BMPs as

indicated on the plans. Protect existing storm inlets adjacent to the site by an approved

gravel filter.

5. Locate stone stabilization pads at all points of vehicular ingress and egress to the

construction site.

Page 137: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TEMPORARY EROSION AND SEDIMENTATION CONTROL

312500 - 5

6. Provide temporary erosion controls consisting of berms at the top of slopes and

interceptor ditches at ends of berms and at those locations which will eliminate or

minimize erosion during construction, along with temporary seeding, temporary

diversion, chutes, and down pipes and lining of water courses.

7. Temporary sedimentation controls shall consist of silt dams, traps, silt fence, barriers, and

appurtenances at the top of spoil and borrow area slopes and where runoff water exits

the site.

8. Maintain the available silt holding capacity of silt dams, fence traps, and barriers until no

longer needed. The sediment capacity of sediment retainage areas shall be at a minimum,

the capacity shown on the plans in conformance with Urban Drainage Criteria Manual,

Volume 3. Prior to removal, obtain concurrence of the Owner and Engineer.

9. Remove accumulated sediment and debris from a BMP when the sediment level reaches

one-half the height of the BMP, or at any time the sediment or debris adversely impacts

the functioning of the BMP.

10. The erosion/sediment control plan shows the minimum required for the project. If it

becomes apparent that additional controls are necessary, the Owner’s Representative

shall be notified and with approval of the Owner’s Representative additional controls shall

be installed.

B. Chemicals and Pollutants:

1. Store construction materials and chemicals that could contribute pollutants to the runoff

within an enclosure, container, or dike located around the perimeter of the storage area,

to prevent discharge of these materials into runoff from the construction site.

2. Locate areas used for collection and temporary storage of solid and liquid waste away

from the storm drainage system. Provide covering or fencing as required to prevent

windblown materials; construct perimeter dike to contain liquid runoff. These measures

may not be necessary if materials are immediately placed in covered waste containers.

3. Perform equipment maintenance in designated areas using measures such as drip pans

to control petroleum products spillage.

4. Immediately clean up and properly dispose of spills of construction related materials such

as paints, solvents, or other chemicals.

C. Final Stabilization and Long-Term Management: University of Colorado – Boulder Standards

shall be met.

1. Final stabilization shall be achieved through permanent vegetation and landscaping after

construction of all buildings and paved surfaces.

2. With approval of University of Colorado – Boulder Facilities Management, temporary

erosion and sediment control measures may be removed within 30 days after final site

stabilization is achieved or after temporary measures are no longer needed.

D. Inspection and Maintenance: Inspect erosion and sediment control measures weekly during

construction. In addition, inspect all facilities immediately after any significant runoff or

snowmelt which results in runoff. Repair or otherwise mitigate any damage to the erosion and

sediment control facilities at no additional cost to the Owner.

3.05 CLEANING

Page 138: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

TEMPORARY EROSION AND SEDIMENTATION CONTROL

312500 - 6

A. Removal of Controls: Remove controls upon completion of that portion of the work for which

controls were furnished. Leave the site and work area in a clean condition.

END OF SECTION

Page 139: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING JOINT SEALANTS

321373 - 1

SECTION 321373

CONCRETE PAVING JOINT SEALANTS

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section includes the following:

1. Expansion and contraction joints within cement concrete pavement.

2. Joints between cement concrete and buildings and structures.

3. Surface preparation including primers.

4. Joint backup material.

B. Related Sections include the following:

1. Section "Cement Concrete Pavement" for constructing joints in concrete pavement.

2. Section “Asphaltic Concrete Pavement” for constructing new asphalt adjacent to existing

cement concrete pavement.

1.03 REFERENCES

A. University of Colorado Boulder and City of Boulder Standard Specifications for Design and

Construction, latest edition.

B. Colorado Department of Transportation Standard Specifications for Road and Bridge

Construction, current edition.

1.04 SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Product Certificates: For each type of joint sealant and accessory, signed by product

manufacturer.

C. Compatibility and Adhesion Test Reports: From sealant manufacturer, indicating the following:

1. Materials forming joint substrates and joint-sealant backings have been tested for

compatibility and adhesion with joint sealants.

2. Interpretation of test results and written recommendations for primers and substrate

preparation needed for adhesion.

D. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified

testing agency, for sealants.

Page 140: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING JOINT SEALANTS

321373 - 2

E. Warranty: As required by – Warranty Section: Contractor agrees to repair or replace joint

sealers (including labor, materials, and any necessary associated costs) which fail to perform as

watertight joints; or fail in joint adhesion, cohesion, abrasion resistance, weather resistance,

extrusion resistance, migration resistance, stain resistance or general durability; or appear to

deteriorate in any other manner not clearly specified by submitted manufacturer’s data as an

inherent quality of material for exposure indicated. Provide warranty signed by Installer and

Contractor.

1.05 QUALITY ASSURANCE

A. Requirements of Regulatory Agencies: Work under this section shall be subject to all applicable

provisions of federal, state, and local rules and regulations.

B. Applicator: Company specializing in application of sealants with five (5) years minimum

experience and be acceptable to manufacturer. Manufacturer’s field representative shall visit

site and make suggestions.

C. Adhesion Tests: Prior to any sealant application, perform adhesion tests as directed by sealant

manufacturer’s technical representative.

D. Source Limitations: Obtain each type of joint sealant through one source from a single

manufacturer.

1.06 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to Project site in original unopened containers or bundles with labels

indicating manufacturer, product name and designation, color, expiration date, pot life, curing

time, and mixing instructions for multi-component materials.

B. Store and handle materials to comply with manufacturer's written instructions to prevent their

deterioration or damage due to moisture, high or low temperatures, contaminants, or other

causes.

1.07 PROJECT CONDITIONS

A. Install sealant materials in strict accordance with all safety and weather conditions

recommended by manufacturer, product literature, or Material Safety Data Sheets. Do not

proceed with installation of sealants under adverse weather conditions, or when temperatures

are below or above manufacturer’s recommended limitations for installation. Proceed only

when forecasted weather conditions are favorable for proper cure and development of high-

early bond strength. Wherever joint width is affected by ambient temperature variations, install

elastomeric sealants only when temperatures are in lower third of manufacturer’s

recommended installation temperature range.

Page 141: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING JOINT SEALANTS

321373 - 3

PART 2 - PRODUCTS

2.01 MATERIALS, GENERAL

A. Compatibility: Provide silicone joint sealants, backing materials, and other related materials

that are compatible with one another and with joint substrates under conditions of service and

application, as demonstrated by joint-sealant manufacturer based on testing and field

experience.

B. Colors of Exposed Joint Sealants: As selected by Architect from manufacturer's full range.

2.02 SILICONE JOINT SEALANTS

A. Single-component formulation complying with ASTM D 6690 or D1190.

1. Refer to CDOT Standard Specification, Section 705.01 and 705.09 for joint and crack

sealant material requirements.

2. Refer to CDOT Standard Specification, Section 412.18 for joint and crack sealant

installation requirements.

2.03 JOINT-SEALANT BACKER MATERIALS

A. General: Provide joint-sealant backer materials that are non-staining; are compatible with joint

substrates, sealants, primers, and other joint fillers; and are approved for applications indicated

by joint-sealant manufacturer based on field experience and laboratory testing.

B. Round Backer Rods for Hot-Applied Sealants: ASTM D 5249, Type 1, of diameter and density

required to control sealant depth and prevent bottom-side adhesion of sealant.

C. Backer Strips for Hot-Applied Sealants: ASTM D 5249; Type 2; of thickness and width required

to control sealant depth, prevent bottom-side adhesion of sealant, and fill remainder of joint

opening under sealant.

2.04 PRIMERS

A. Primers: Product recommended by joint-sealant manufacturer where required for adhesion of

sealant to joint substrates indicated, as determined from manufacturers recommendations.

PART 3 - EXECUTION

3.01 EXAMINATION

A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with

requirements for joint configuration, installation tolerances, and other conditions affecting

joint-sealant performance.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

Page 142: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING JOINT SEALANTS

321373 - 4

3.02 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to

comply with joint-sealant manufacturer's written instructions.

B. Joint Priming: Prime joint substrates where indicated or where recommended in writing by

joint-sealant manufacturer, based on preconstruction joint-sealant-substrate tests or prior

experience. Apply primer to comply with joint-sealant manufacturer's written instructions.

Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining

surfaces.

3.03 JOINT DESIGN

A. Sealant depth is measured at the center (thin) section of sealant bead.

B. Install sealants to depths and widths as recommended by sealant manufacturer or as shown on

the drawings. Also, conform to the following general limitations if not in conflict with sealant

manufacturer’s recommendations.

1. For sidewalks, pavements and similar joints subject to traffic and other abrasion and

indentation exposures, fill joints to a depth equal to 75% of joint width, but neither more

than 5/8 inch deep nor less than 3/8 inch deep.

2. For normal moving joints not subject to traffic, fill joints to a depth equal to 50% of joint

width, but neither more than 5/8 inch deep nor less than ¼ inch deep.

3. Depth of sealant must not exceed width of joint.

4. Sealant joints shall not be less than ¼ inch in width and ¼ inch in depth.

5. Sealant joints shall not exceed 2 inches in width in a single application.

3.04 SURFACE PREPARATION

A. Preparation work shall result in clean surfaces in all areas where sealant is to be adhered. Such

surfaces shall be free of any old sealant, contaminants and impurities which are deleterious to

bonding or adhesion of primers or sealant.

B. Clean ferrous metals of all rust, mill scale, and coatings by wire brush or grinding. Any

equipment used to remove rust shall be free of oil contaminants.

C. Wire brush masonry joint surfaces, then blow clean with oil free compressed air.

D. Apply primer per manufacturer’s recommendations. Allow primer to dry prior to applying

sealant.

E. Do not caulk joints until they are clean, dry, and free of dust, loose mortar, old sealant, foreign

matter, or other bond inhibiting materials, and in compliance with requirements of

manufacturer of materials, details shown on drawings, and specific requirements of other

sections of specifications.

3.05 JOINT BACKING

A. Use joint backing to control depth of joint to specified thickness.

Page 143: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING JOINT SEALANTS

321373 - 5

B. Select joint backing size to allow for 25% compression of backing when inserted into joint.

C. Where shown on drawings where depth of joint will not permit use of joint backing, or wherever

recommended by sealant manufacturer, install bond-breaker tape to prevent three-sided

adhesion.

D. Do not leave voids or gaps between ends of joint backing units.

3.06 APPLICATION/INSTALLATION OF JOINT SEALANT

A. Apply sealants neatly, in a good and workmanlike manner which meets following minimum

requirements or standards. Specific instructions of manufacturer must also be followed.

B. Apply sealant using a gun with proper size nozzles. Use sufficient pressure to fill all voids and

joints solid to backup material, with complete wetting of all joint bond surfaces.

C. Applied sealant shall form a full, smooth, uniform bead, free of ridges, wrinkles, sags, air pockets

and embedded impurities.

D. After joint has been completely filled with sealant, neatly tool joint sealant to eliminate air

pockets or voids, and to provide a smooth, slightly concave, neat appearing finish, with sealant

surface slightly below adjoining surfaces. Wetting of finished surface will not be allowed.

E. Where horizontal joints are located between a horizontal surface and vertical surface, fill joint

to form a slight cove, so joint will not trap moisture and dirt.

F. Protect adjacent surfaces and systems from sealant material. Use masking tape where required

to prevent contact of sealant with adjoining surfaces which otherwise would be permanently

stained or damaged by such contact or by cleaning methods required to remove sealant smears.

Remove tape immediately after tooling without disturbing joint seal.

G. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint

sealants as applicable to materials, applications, and conditions indicated.

H. Tooling of Non-Sag Sealants: Immediately after sealant application and before skinning or

curing begins, tool sealants according to requirements specified below to form smooth, uniform

beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion

of sealant with sides of joint.

1. Remove excess sealants from surfaces adjacent to joint.

2. Use tooling agents that are approved in writing by joint-sealant manufacturer and that do

not discolor sealants or adjacent surfaces.

I. Provide joint configuration to comply with joint-sealant manufacturer's written instructions,

unless otherwise indicated.

J. Provide recessed joint configuration for silicone sealants of recess depth and at locations

indicated.

Page 144: TABLE OF CONTENTS DIVISION 1 - GENERAL …pix.ghphipps.com/projects/2015/15.0630/ProjDocs/01 - Bid Documents... · Project No. CP008128 ... TABLE OF CONTENTS DIVISION 1 - GENERAL

CAMP – Fire Sprinklers Upgrades (CLRE & DEN) Ph 1 of 5 (CM M081M4) Construction Document Set

Project No. CP008128 6 August 2015

CONCRETE PAVING JOINT SEALANTS

321373 - 6

3.07 CLEANING

A. Clean off excess sealants or sealant smears adjacent to joints as the Work progresses by

methods and with cleaning materials approved by manufacturers of joint sealants and of

products in which joints occur.

3.08 PROTECTION

A. Protect joint sealants during and after curing period from contact with contaminating

substances and from damage resulting from construction operations or other causes so sealants

are without deterioration or damage at time of Substantial Completion. If, despite such

protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint

sealants immediately and replace with joint sealant so installations with repaired areas are

indistinguishable from the original work.

3.09 JOB SITE CLEAN-UP

A. Sealant applicator must remove all excess materials from job site.

B. Leave all surrounding areas where joint sealant has been applied free of excess sealant, debris

and foreign substances.

END OF SECTION