Table of Contents - Dell · 2020. 7. 8. · establish your current data center capabilities and set...
Transcript of Table of Contents - Dell · 2020. 7. 8. · establish your current data center capabilities and set...
2013 EMC Proven Professional Knowledge Sharing 2
Table of Contents Introduction ................................................................................................................................ 3
Innovation of the Data Center Upgrade Business ....................................................................... 4
Upgrades: The Human Effect ..................................................................................................... 5
Levels of Upgrade ...................................................................................................................... 5
Upgrade Types .......................................................................................................................... 7
Upgrade Challenges .................................................................................................................. 9
Key Steps in an Optimal Data Center Upgrade .........................................................................11
Data Center Upgrade Plan, Phases, and Process .....................................................................14
Using Virtualization When Upgrading the Data Center ..............................................................19
Disclaimer: The views, processes, or methodologies published in this article are those of the
author. They do not necessarily reflect EMC Corporation’s views, processes, or methodologies.
2013 EMC Proven Professional Knowledge Sharing 3
Introduction
Business climates changes, business models change, information technology certainly
changes, and data centers change. What? Data centers change? Yes. The view that the data
center is just a room or facility that is a large capital investment and built every 10 to 15 years
has indeed changed. This doesn’t mean throw more money into it with greater frequency.
Rather, it means approaching it in new ways and making intelligent decisions about the data
center. The data center strategy is just as important as the IT strategy it protects and provides
for and the business strategy that both empower.
Remember: “It’s not just your data center; it’s your business center”
This Knowledge Sharing article introduces innovation implementation theory to the EMC Proven
Professional body of knowledge and draws service delivery implications for implementing
effective IT upgrades within organizations.
2013 EMC Proven Professional Knowledge Sharing 4
Innovation of the Data Center Upgrade Business
Most companies hope to get the same service from their data centers as they were getting
some years back. Unfortunately, there are many obstacles to achieving that length of service. In
particular, some key components that data centers rely on are not designed to last that long. In
addition, rapidly changing data processing requirements demand that data centers remain
flexible and support greater rack densities. Massive data growth, tough economic conditions,
and physical data center limitations (power, heat, and space) exert extreme pressure on IT
infrastructures. Finding ways to take cost, complexity, and associated business risk out of the
data center without sacrificing service levels has become a major objective for almost every
enterprise.
Typical characteristics of degraded data centers include:
complex cabling
increase of unplanned data
legacy operating systems
old application versions
electrical and mechanical failures
degraded efficiency of power and cooling
aging equipment
lack of scalability and flexibility
changing regulatory compliance
out-of-date documentation
These types of data centers are more prone to local disasters, equipment failures, disk errors,
inefficient, poor output, more administrative and managerial overheads, heat up of apparatus,
and lower speed.
The world of technology has seen plenty of change in recent years. To keep up with it,
organizations with data centers that are 10 years of age or older should seriously consider
modernizing those facilities.
This article adopts data center upgrade as a program for innovation implemented within IT
organizations of businesses, for the purpose of enabling the organization’s information assets to
deliver strategic business benefits. It is about delivering business upgraded capabilities through
IT innovation.
2013 EMC Proven Professional Knowledge Sharing 5
This article views data center upgrade as a general program for business, technology, process,
and behavior innovation. Upgrade refers to the replacement of the product with the new version
of the same product in order to bring the system up to date or to improve its characteristics and
enabling the business to flexibly and quickly respond and deliver business services. Data center
upgrade impacts infrastructure, applications, and the user experience.
Upgrades: The Human Effect
Successful upgrades are brought about by deep organizational willingness to change at its
core—its approach, organization, and processes, its infrastructure and toolsets, and its
skillsets—and by the ability to address and stay focused on the many multiple threads of an
upgrade initiative until the desired end state is achieved. Some organizations that have
achieved a level of efficiency and maturity may not require a transformation, and some may
even choose to wash their hands of technology altogether and outsource to a third party. You
and your management should consider the following questions to help you determine if your
organization is a candidate for this journey:
Do you understand the profound opportunity inherent in a data center upgrade?
Do you understand the challenges ahead and are you ready to assume the risk?
Do you have the discipline to stick with an upgrade initiative even when progress and
benefits realized at any point are not up to expectations?
Do you have the strong sponsorship you need to support you throughout your journey?
Do you have the “can-do” culture to enable and sustain momentum and achieve your
upgrade goals?
Do you have the upgrade leadership in place?
Do you have the right staff to carry out this journey?
Levels of Upgrade
The levels of upgrade are defined based on the key business requirement and associated IT
challenges to determine where you want to focus your upgrade efforts first. You also need to
establish your current data center capabilities and set goals for your upgrade program.
The combination of upgrade framework and maturity model such as those illustrated in Table 1
can help you evaluate your current capabilities—where you are today. An assessment of your
data center against this framework can enable you to have strategic discussions on the
2013 EMC Proven Professional Knowledge Sharing 6
business value of deploying new technologies to improve the current state of your IT
infrastructure and address cost issues, security risk, and operational agility.
Basic Standard Rationalized Dynamic
Customer and Service
Support technology always in "react"
mode
Service catalog established
Service catalog SLA reports to clients
Utilization-based chargeback
Allocation-based
chargeback Automated services
management
Organization and Process
No formal processes, procedures
Process efficiency baseline established
IT best practices documented,
measured
Continuous process improvement
Some best practice
processes documented
Managed automation
Automated management reports
RACI aligment Operation for
virtualization in place
Infrastructure and Toolsets
Technology "silos" supporting single
applications
Tiering, application alignment
Broader virtualization
deployed
Complete production virtualization
Many non-integrated tools
Availability alternatives assessed
Policy-based data classification
Multi-site load balanced DR
Targeted, policy-based archiving
Backup to disk, Optimization
Policy-based data mobility
Infrastructure consolidation
Limited virtualization
deployed
Backup architecture
rationalized
2013 EMC Proven Professional Knowledge Sharing 7
People
Employees support technologies without training experience
Career paths defined Strong retention through career
growth, mobility
Business requirements
gathering skills in IT
Skill set assessed,
training plan in place
Benefits Realization
IT viewed as cost center IT value
difficult to articulate
Lower-cost, efficient data centers
Energy related savings from virtualization
Agile infrastructure
Consistent IT
services across enterprise
IT service performance reports
IT service performance
Information pooled, available for re-use
Decision support enabled
Business intelligence enabled
Table 1
Upgrade Types
Not all data centers require the same type of upgrade. The need to upgrade depends upon the
key business requirement and bottleneck in achieving the business goals. Data center upgrades
are therefore categorized in various types depending upon the IT requirement. There can be
more than what is presented below but here are some of the major types of upgrades.
Site upgrade
Some data centers are required to shift or moved due to space limitations or cost
factors. In such scenarios, a site upgrade is necessary in which land evaluation, land
analysis, building evaluation, and space planning is required.
o In land evaluation, a comprehensive study of sites is provided, including
characteristics and utilities. Multiple sites are evaluated and ranked based on
location, environmental limitations, available utilities, and aesthetics.
o Land analysis provides an in-depth study of site conditions (surface and
subsurface), characteristics, and suitability.
o Building evaluation is required to analyze the suitability of an existing building.
o Space planning is also required in such cases for future business growth and
sustainability of the new shifted data center for many years.
2013 EMC Proven Professional Knowledge Sharing 8
Mechanical upgrade
Mechanical upgrade pertains to existing equipment, including air conditioning, cleansing
and distribution, water chillers, and heat rejection. The fire detection and suppression
equipment are the recommended setups for the upgrades, Mechanical upgrades also
include uninterruptible power supply and battery equipment.
Electrical upgrade
The electrical upgrade is generally observed in many of data centers due to growing
data and business demands. New hardware in the data centers typically consumes extra
power. This requires upgrade to power distribution units (PDUs) to deliver the required
outputs. Besides data centers, lighting and other areas for the data center and support
rooms also fall under this category. The electrical upgrade also covers safety, grounding,
and noise attenuation issues.
Network upgrade
Network upgrade includes upgrade of switches, modules, hubs, and network cables. The
continuous demand for a fast network and fast accessibility drives the need for the
network upgrade. Today, speed is the main concern in the data center. It has taken quite
a while but 10GbE has become the standard for data center network backbones.
Connectors, SFP, and modules also come into play under network upgrade.
Hardware upgrade
Hardware upgrade is required when the business demands increase from critical to
mission critical. Improvements to hardware lead to faster accessibility and less response
time for the users. Hardware upgrades include servers, storage, supporting systems,
desktops, etc. A server upgrade includes decommission of the old models and
commissioning of the new models with smart arrays and more advanced hardware.
Storage upgrades include upgrading the storage tiers from slow disks to faster disks.
Generally, chassis upgrade also comes under hardware upgrades.
Software upgrade
Software upgrades include firmware, drivers, tools, management consoles versions,
reporting software, alerts. etc. This type of upgrade is more frequent and required for
better output and to reduce bugs in the existing supporting software.
2013 EMC Proven Professional Knowledge Sharing 9
Upgrade Challenges
“The brick walls are there for a reason. The brick walls are not there to keep us out. The brick
walls are there to give us a chance to show how badly we want something. Because the brick
walls are there to stop the people who don’t want it badly enough. They’re there to stop the
other people” (by Randy Pausch, The last Lecture).
Data center upgrade projects are critical to the success of the initiatives that the upgrades
support; an enterprise-wide application upgrade, a data center consolidation, or an
infrastructure upgrade. Such upgrades impact business-critical data, applications, and systems,
and result in significant cost. The data center upgrade project itself possesses significant risks
and requires proper planning and attention to ensure success of the data up gradation and the
initiatives that it supports.
S. No. Types of Risks/Challenges
1 Information Growth
2 Infrastructure Complexity and Interdependencies
3 Different Geographies
4 Unexpected or Extended Downtime
5 Performance
6 Heterogeneous Data Center Vendors
7 Funding the project
8 Out-of-date documentation
9 Risk of downtime during construction
10 Code compliance
11 Other (Stability/KT)
12 Do not know/NA
Information growth and infrastructure complexity: Today’s complex environment—including
ever-increasing information growth, number of vendors and applications being deployed,
2013 EMC Proven Professional Knowledge Sharing 10
applications becoming Tier 1, and complex infrastructures—drive higher cost and risk. While IT
organizations work to deliver specific service requests with innovation, speed of delivery,
flexibility, and cost-effectiveness, they must also concentrate on addressing the specific
upgrade challenges listed here to ensure that they continue to manage complexity and reduce
risk.
Unexpected or Extended Downtime: Detailed and careful planning needs to take place to
clearly identify windows in which downtime is acceptable and ensure that no data is lost. For
data migration projects that include mission-critical business data, the risk of impacting sales
operations is high; the loss of availability or access to the data could directly impact the profit
and loss of the business. Trends in compute architectures and the adoption of virtualization
have increased the number of applications running on a single host. This has resulted in
decreasing maintenance windows where the downtime to a host can result in multiple significant
application outages.
Performance: Discussions with any customer regarding data center upgrade will always raise
two major questions:
1. Will performance be affected during migration activity?
2. Will all of my data remain available and accessible to users during the upgrade process?
These factors need to be kept in mind when designing an upgrade activity. It has been observed
during every upgrade that these two will impact your business every now and then both in terms
of cost performance and data availability.
Heterogeneous Data Center Vendors: It is rare to find a customer using only one data center
technology in its infrastructure. In heterogeneous data center environments, a number of factors
need to be considered while upgrading equipment from old to newer versions. These factors
vary depending upon downtime availability, technology, and cost.
Funding the project: Before data center managers can update a computing facility, they must
first persuade senior executives to fund and authorize such a project. That means building a
detailed and persuasive business model complete with concrete ROI calculations. Without prior
experience, however, assembling such facts and figures can be difficult.
Out-of-date documentation: Retrofitting an older data center’s electrical or mechanical
systems haphazardly can result in overloads and other dangerous conditions. To prevent such
2013 EMC Proven Professional Knowledge Sharing 11
problems from occurring, facilities managers need access to complete and accurate blueprints
of the data center’s existing electrical or mechanical infrastructure. Unfortunately, many
companies neglect to keep those documents up to date.
Risk of downtime during construction: Few companies can afford to take a data center
offline for months at a time during upgrades. Yet replacing electrical and mechanical systems in
a live, production environment without affecting availability can be a demanding task and
requires careful planning.
Code compliance: Data center operators must verify that any changes they make to a facility’s
electrical or mechanical systems comply with current arc flash safety requirements. However,
conducting thorough arc flash studies without jeopardizing critical workloads requires specific
engineering knowledge and skills.
Key Steps in an Optimal Data Center Upgrade
Data center upgrade projects are complex projects that pose significant cost and risk. To
successfully complete a data migration project, organizations must develop a comprehensive
plan encompassing people, processes, and technology. There are many steps for data center
upgrade but most critical stages are overviewed here:
Assembling the right project team
This is the first and most important stage for any data center upgrade. The project team for the
data center upgrade should include all relevant stakeholders from within the organization as well
as a complete set of appropriate vendor partners. Internal stakeholders should be in agreement
with respect to goals and objectives of the project, and there should be no organizational silos
between the IT and facilities departments. Make sure that vendor partners under consideration
have documented proof of having successfully completed similar projects under similar
circumstances in the past.
Assessment and planning
Initial investigation of any project is key to achieve successful completion. The homework gives
you an idea of the limitations and risks associated with the project. Before commencing a data
center upgrade, organizations should create a complete list of their facility’s limitations and
identify multiple options for overcoming them. There are numerous possible solutions to any
given data center problem, and evaluating all of them is the best way to ensure that you select
2013 EMC Proven Professional Knowledge Sharing 12
the best approach available for your specific needs. A vendor such as EMC with expertise in
data center modernization can help identify appropriate options to study.
Establishing the business care
Once they’ve identified potential options, businesses must weigh their costs and benefits and
then decide which make the most sense to pursue. Based on that analysis, managers can then
prepare a business case for securing adequate funding.
Note that while cost saving and return on investment are likely to figure prominently in the
business case for a data center upgrade project, non-fiscal considerations are often important
as well. For example, sometimes the strongest justification for a data center upgrade is that it
will be impossible to accomplish your organization’s long-term strategic goals without it.
Note also that many utilities, government, and regulatory bodies offer financial incentives to data
centers that significantly improve their energy efficiency. Though no comprehensive catalog of
such programs exists at present, an experienced vendor can help businesses determine which
offers are applicable to their initiative. Be advised that many rebate programs require
organizations to apply for and receive that rebate before any construction work commences.
Setting project objectives
After receiving funding approval, data center managers should create a list of goals and
success criteria for their effort that clearly specifies not only which infrastructure changes are
within the project’s scope but which are not as well.
Creating a project plan
The next step is to prepare a thorough plan of action, including a realistic schedule. In addition,
a well-written project plan should:
Indicate precise steps for minimizing disruption to production workloads during
upgrades, assuming the data center must remain operational throughout that process.
List potential issues that could arise while work is underway and define contingency
measures for addressing them. What will you do if an electrician accidentally severs the
building’s main circuit, for example or your facility temporarily loses connectivity? Finding
solutions to such problems before they arise can save precious time later.
2013 EMC Proven Professional Knowledge Sharing 13
Executing the plan
To ensure quality results, businesses should work only with contractors that have exceptional
project management abilities and a demonstrated history of completing similarly ambitious
efforts on time and under budget. It is also important to make certain that the project manager
holds meetings at frequent and regular intervals to ensure that the project is following the
agreed upon schedule and that issues are addressed promptly.
Updating blueprints
Though a largely administrative step in the retrofit process, updating the data center’s blueprints
is an important best practice that will make life significantly easier for future IT and facilities
managers. To ensure that revised drawings are as accurate as possible, organizations should
hire an engineer or draftsman to assist them.
Conducting tests
The commissioning process for an upgraded data center should include careful testing of any
system that has been changed, added, or replaced. Such tests should assess modified
components both individually and collectively. For example, if an organization updated its UPS
hardware, deployed new PDUs, and installed aisle or rack containment cooling, it should
confirm that each of those systems functions properly on its own and then verify that they also
work correctly together by subjecting them to various simulated workloads.
Validating results
Before putting their upgraded data center into production, companies should return to the goals
and objectives they defined earlier and validate that they’ve achieved all of them. This should be
a rigorous and objective evaluation of the modernized facility’s real-world performance and
capabilities, executed with the assistance of a knowledgeable vendor consultant.
Performing an arc flash hazard analysis
If a data center retrofit included electrical changes, checking the revised infrastructure for
compliance with current arc flash safety codes is critical. An arch flash hazard analysis can help
uncover arc flash risks and identify appropriate mitigation strategies. Data centers should
always conduct hazard studies in partnership with a qualified power systems engineer.
2013 EMC Proven Professional Knowledge Sharing 14
Data Center Upgrade Plan, Phases, and Process
Any upgrade process is complex, involves multiple phases, and requires coordination and
planning at the technology, process, and business level. This section describes the phases of
the data up gradation project.
Phase 0: Assessment
Phase 1: Planning and design
Phase 2: Change control
Phase 3: Up gradation execution
Phase 4: Post-upgradation review
Phase 0: Assessment
The first phase of the upgrade process involves defining scope and requirements and
performing a preliminary analysis of the current environment to determine the level of
conformance to the supported standards. During this phase, also select the appropriate
migration methodology based on the defined requirements. Effort spent during the assessment
phase results in the following benefits:
Safe, structured upgrade solutions that minimize risk
Repeatable and predictable results
Process tailored to the specific requirements of the lines of business
Efficient execution of the project by the shared data center management teams
Numerous data upgrade technologies and methodologies are available. Business requirements
dictate the most appropriate methodology to deploy for a specific project. To determine the
appropriate approach, it is important to perform a preliminary analysis that involves gathering
the following information:
Quantity of equipment to be upgraded
Gather the specific information regarding the number and specifications of the
devices which need to be upgraded. If they are firmware, drivers, or management
console software, check the compatibility and interoperability of each other with the
hardware and software.
2013 EMC Proven Professional Knowledge Sharing 15
Application availability
The amount of application downtime for an application often determines the
appropriate upgrade method. Many hardware and software supports upgrade without
any downtime. These types of hardware have the characteristics which we generally
called “failover”. Vendors providing systems which have two or more processing
units are pro-actively designed to have upgrade facilities without any downtime.
Best Practice: Online upgrades introduce additional risk that must be weighed
against the impact of application availability. The best practice is to check the failover
and failback capability of the system before starting any upgrade activity in off-peak
hours and to perform offline upgrade whenever failover is not possible.
Allocation requirements
Allocation requirements define the extra devices required to support the system so
that it does not collapse during upgrade. For example, the support of the pillars
required when you are upgrading or renovating the roof of your house. The allocation
requirement should be addressed in the planning phase.
Performance impact
Upgrades involve blocking of functionality for a certain time so that it performs better
than before. However, doing so can impact performance of the host, array, network,
and fabric. This impact must be considered.
Best Practice: Schedule the upgrade when performance demand is not required.
Scheduling requirements
Depending on the criticality of current operations, maintenance or cutover windows
may be small. Some techniques allow upgrades to occur over an extended period
with actual cutover being performed during the next scheduled maintenance window.
Rollback plan
To reduce the risk to the business, a detailed outline of a working backout plan is
required before beginning the upgrade. When upgrading the hardware, ensure that
older hardware is available so that you can roll back or degrade the system to it if the
2013 EMC Proven Professional Knowledge Sharing 16
new hardware does not work. When upgrading the software, ensure that older
versions of drivers and firm ware are available so that you roll back or degrade to the
older versions if the upgraded version does not work.
Phase 1: Planning and design
During this phase of a migration project, a detailed design and timeline are developed based on
requirements identified during the analysis. Completion of this planning and design phase is
required for any well-developed change management process. This phase consists of
developing an implementation plan that includes not only the specific details of the project but
also an analysis of future requirements based on possible growth of the application. A solution
design must document the upgrade method as well as an environmental assessment to ensure
that the solution meets defined business requirements.
Some of the information identified and documented during this phase includes:
Interoperability and compatibility check of existing hardware or software with the new
one in the system
Pre-requisites of the new hardware/software
Bottleneck in the system
Power and cooling requirements for the new system
Physical connections requirement
Fabric connections
Software versions and licensing
Hardware and software support with extended warrantee, if required.
A macro view takes into account the complex nature of data upgrades and the impact on shared
resources, including server load, network bandwidth, storage array, power devices, chilling
towers, and impact on operational schedules. All have an impact on the amount of data flow.
Proper solution design allows proper sizing of resource requirements and sets the expected
project duration. This is critical to project success.
Criteria for success are defined during the planning phase and validated with the stakeholders.
These criteria fall into two categories: data integrity and performance. Obviously, data integrity
is paramount for any data migration project. A team that includes the application stakeholders
must first define a test plan.
2013 EMC Proven Professional Knowledge Sharing 17
This plan could be simple, such as performing flash test or successfully starting the application
after new installation; however, more comprehensive testing to validate dataset consistency
between interrelated application data is more likely required. In addition, current performance
benchmarks should be established during the planning phase and revalidated during post-
upgrade phase. Capturing the output performance and/or IOSTAT is recommended for at least
one day prior to upgrade so that the results can be compared with post-upgrade performance.
Best Practice: if the proposed solution includes a new technology or technique that has not
been deployed previously in the production environment, a best practice is to validate the
approach in a proof-of-concept exercise in a non-production environment. This minimizes risk,
and benchmarked transfer rates can be used to set appropriate expectations.
Phase 2: Change control
Data center upgrade projects must conform to the change management process. The following
is a summary of the change management components:
Risk assessment
A critical component of change management is a full risk assessment. Risk assessment
is the analysis of what can go wrong, how to prevent it, and how to mitigate the impact
resulting from a failed change. This analysis should be documented and include a
tested back out plan.
Upgrade plan
This is a review of the upgrade implementation plan that was created during the
planning and design phase. This outlines the current and target environment and
includes a step-by-step process.
Prerequisites and dependencies
Prerequisites such as site support engagement, vendor, and parts availability should be
documented and planned for.
Timeline and schedule
If the current operations are critical, the timeline and schedule will need to be well
defined in order to meet limited maintenance or cutover timeframes. Ensure that backup
plans are prepared in the event that an implementation needs to be backed out.
Resource plan
The plan should include human resource availability, skills, and ownership.
2013 EMC Proven Professional Knowledge Sharing 18
Phase 3: Upgrade execution
In this phase, the plan developed during the design phase is implemented. General upgrade
implementation best practices includes:
As a first step, perform a full backup of all data involved.
Review detailed procedures. A scripted methodology is the preferred approach.
Ensure that support needs are defined and available and that back out plans are as well
understood as the data upgrade plans.
Conduct a pilot upgrade or execute advanced testing whenever possible. A test before
a scheduled event can be extremely valuable.
Perform the consistency check.
Follow the test plan and document everything! The highest risk in upgrading the system
is incompatibility issues occurring even though they were compatible in vendor’s guide.
If the plan is documented and explicitly followed, this risk can usually be mitigated. It is
critical to have the customer sign off on each upgraded and tested data source before
moving to the next data source.
Escalate issues promptly. It may seem easier to wait before asking for help, in the hope
that the problem can be resolved. However, if behavior that is not within the plan is
observed, it is important to involve the support system to ensure that help is available
when needed, especially if the staff involved has little experience performing data center
upgrades.
Phase 4: Post-migration review
Confirm that there is no quality-of-service impact during the post-migration phase. Complete the
following actions:
Capture performance statistics and compare them with pre-upgrade benchmarks.
Perform project cleanup by removing the tools utilized during upgrade.
Decommission the original source of data.
Review issues that occurred during the upgrade, the manner in which they were
handled, and the results.
Provide a functional overview regarding the end state of the upgraded data environment.
Examples include addresses, sizes, access speeds, and the names of the data sources
that have changed that can impact operations.
Update documentation.
2013 EMC Proven Professional Knowledge Sharing 19
Using Virtualization When Upgrading the Data Center
Your business is facing an interesting challenge when it comes to designing your enterprise
data center. The previous method of having servers support each office no longer really delivers
an effective or secure solution. What are some of the things you should consider as you plan
your updated data center? The first thing to consider should be the operating needs of the
business. Next, it is important to determine if virtualization is a viable option. Another area for
the leadership to study is how redundancy of computer components helps or hurts the business.
Finally, the executive team should study if using a cloud service provider can deliver the needed
resources safely and at a substantially reduced cost. With these issues in mind, management
can design the data center to benefit the business.
Far too often, the business creates a data center that does not support the strategy. This
potentially leads to higher operating costs and missed opportunities. For example, a month ago
we met with a large insurance company that decided to open several new branch offices. Each
office has a server and these feed to the central data center for backup and archive services,
but not for data sharing. When speaking with the executive team it became clear that they
lacked an operational vision for how the data center should operate in support of their growth
strategy. This lack of planning led the IT department to plan the technology to support the
strategy by putting servers in each location. The IT department needs leadership to design the
best solution to support the vision or old methods will continue to hamstring opportunities.
The next thing to consider is the role of virtualization. Today’s data center can potentially reduce
hardware costs through creating several virtual servers on a single physical server. Where once
there were many servers scattered through the country, an enterprise can now work with fewer
servers in a central data center, substantially reducing risk and costs. This method requires
running virtualization software such as Microsoft’s HyperV or VMware’s VCloud. Some
2013 EMC Proven Professional Knowledge Sharing 20
important things to consider are the cost of the virtualization software and the technical skill
required to run a virtualized data center. It is also critical to make sure that sufficient bandwidth
exists at both the data center and remote locations.
Recent data center upgrade case studies have shown that virtualization has played a significant
role for migrating data in terms of various factors such as eliminating the need for third party
tools, reducing downtime, application availability, least impact, performance maintenance during
upgrade, re-use of existing assets, and so on.
Key benefits of using a virtualization approach are:
Reduce number of servers
Partitioning and isolation, the characteristics of server virtualization, enable simple and
safe server consolidation. Through consolidating, the number of physical servers can be
greatly reduced, bringing benefits such as reduced floor space, power consumption, and
air conditioning costs. However, it is essential to note that even though the number of
physical servers is greatly reduced, the number of virtual servers to be managed does
not change. Therefore, when virtualizing servers, installation of operation management
tools for efficient server management is recommended.
2013 EMC Proven Professional Knowledge Sharing 21
Reduce TCO
Server consolidation with virtualization reduces costs of hardware, maintenance, power,
and air conditioning. In addition, it lowers the Total Cost of Ownership (TCO) by
increasing the efficiency of server resources and operational changes, as well as
virtualization-specific features. As a result of today’s improved server CPU performance,
a few servers have high resource-usage rates but most are often underutilized.
Virtualization can eliminate such ineffective use of CPU resources, plus optimize
resources throughout the server environment. Furthermore, because servers managed
by each business division's staff can be centrally managed by a single administrator,
operation management costs can be greatly reduced.
Improve availability and business continuity
One beneficial feature of virtualized servers not available in physical server
environments is live migration. With live migration, virtual servers can be migrated to
another physical server for tasks such as performing maintenance on the physical
servers without shutting them down. Thus, there is no impact on the end user. Another
great advantage of virtualization technology is that its encapsulation and hardware-
independence features enhance availability and business continuity.
Increase efficiency for development and test environments
At system development sites, servers are often used inefficiently. When different
physical servers are used by each business division's development team, the number of
servers can easily increase. Conversely, when physical servers are shared by teams,
reconfiguring development and test environments can be time- and labor-consuming.
Such issues can be resolved by using server virtualization to simultaneously run various
operating system environments on one physical server, thereby enabling concurrent
development and test of multiple environments. In addition, because development and
test environments can be encapsulated and saved, reconfiguration is extremely simple.
Improve availability of your virtual environment
The impact of a failure in a physical server can increase after virtualizing and
consolidating servers. To prevent such problems, vendors provide Cluster solutions and
other products for improving the availability of virtual servers.
2013 EMC Proven Professional Knowledge Sharing 22
Integrated management of mixed virtual environments
For objectives such as reducing costs and saving space, it is expected that virtualization
will spread rapidly and companies will be managing various mixed virtualization
environments. This raises the issue of how to consolidate management of different
virtual environments.
Some vendors provide integrated virtualization management software which enables
centralized control of multiple virtualized environments, including VMware vSphere and
Hyper-V, from an integrated view. It also consolidates management of hardware such as
physical servers, networks, and storage, therefore providing the whole picture of your IT
system to increase operating efficiency.
Reallocation of workloads to eliminate inefficient operation and shut down
unnecessary servers
Virtualization vendors provide some specific integrated software which adopts an
effective energy-saving policy. The software autonomously detects server operating
status and consolidates loads to run on as few physical servers as possible. Physical
2013 EMC Proven Professional Knowledge Sharing 23
servers that are no longer being used will then be shut down. When the load increases,
physical servers that are not running will be restarted. The software can constantly
optimize operations and reduce power consumption.
Consolidated management of patch application and application updating
Operating system patches and application updates can be distributed in batches by job
group or for the system as a whole. It is also possible to deploy software on multiple
servers at one time when setting up a system.
2013 EMC Proven Professional Knowledge Sharing 24
Schedule resource allocation
It is possible, for example, to change a system configuration as previously defined to
optimize resource allocation to meet changes in server load during the day and at night.
Schedules and specific configurations can be easily changed via integrated view.
Single management interface
Managing hundreds of physical servers in the data center is the difficult and erroneous
task to maintain their performance. Jumping from one server to another every time is not
possible when maintaining hundreds of physical servers. Virtualization provides a
centralized single management interface which helps to manage all the machines
through one console. The tab on each virtual machine provides the entire information of
that machine and will look like a inventory management console.
2013 EMC Proven Professional Knowledge Sharing 25
OpEx and CapEx savings
Below are the several areas where organizations can achieve OpEx savings:
It is quite clear then that organizations are achieving a wide range of outcomes that drive
OpEx savings. They are increasing flexibility and agility, reducing downtime (and the
costs of lost productivity), reducing administration and management costs, solving
problems faster, achieving better disaster recovery and availability, and more—all areas
that directly reduce operational costs. Moreover, most organizations are achieving
several of these outcomes simultaneously, further increasing their opportunities for
OpEx reduction.
On the CapEx side, it’s easy to identify the dollar savings because Server Virtualization
helps eliminate infrastructure, or avoid the cost of additional infrastructure.
Typically, a company preparing to start a number of new projects with out-of-scope
dependencies would plan to purchase enough equipment to build out a new environment
for each project. With Service Virtualization, the need for those new environments
disappears, as does the cost of purchasing that equipment. Virtualize them and have the
system under test hit the virtual services. Performance testing is another area where
Service Virtualization can make a big difference. Companies don’t like spending the
millions of dollars that are needed to build out performance testing environments,
conversely they don’t like having their web site down. In today’s environment, minutes
equate to millions of dollars in lost revenue and tarnished reputations.
What if you already have the hardware you need and are more concerned about quality
and efficiency?
2013 EMC Proven Professional Knowledge Sharing 26
Quality is important for a number of reasons, however, let’s think about the people costs
associated with fixing bugs in production. Once a bug is found in production, how many
people need to be involved to assess/identify the issue? BA’s, SA’s, Developers from
multiple teams, etc. That gets expensive quickly.
Service Virtualization helps you identify these defects earlier because now you can
simulate all of the dependencies that you could not access previously. Finding those
defects up front means fewer defects in QA and Production. The idea is to increase
defect identification in development (i.e. “cheap” defects) and reduce the “expensive”
defects in QA, which equates to fewer defects in production. Fewer defects means FTEs
can be repurposed for other projects, or provide products to market faster. In addition, a
more effective offshore model can be implemented, with less downtime and more
productivity. Quality and efficiency are both served.
Service Virtualization gives you the ability to address both your CapEx and OpEx
challenges. Start with one and it will undoubtedly lead you to the other.
Another important issue when considering replacing servers is the role of redundancy. Five to
ten years ago, the concept of redundancy made sense as a lost hard disk or drive controller
effectively shut down the server. Today the main problem with this concept, at least from a
multi-server data center standpoint, is that computers, not components, are the
redundancy. Since each machine works as part of the whole, stripping out redundant
components substantially reduces cost. However, this approach can lead to additional risk if too
few servers make up the data center.
When planning your data center and server replacement policy, one concept to keep in mind is
using a cloud server solution to deliver the enterprise’s computing needs. In a cloud
environment, the provider virtualizes the physical servers to maintain high utilization and ensure
that each client has the computing resources necessary to support the business. Cloud server
providers build servers to reduce the cost by stripping out unnecessary redundancy while
employing virtualization managers to keep the servers running at high utilization and putting
data on multiple drives to keep it safe.
Your business can no longer effectively compete without seriously considering the role of the
server today. Your data center must support your strategy; but this requires looking at
leveraging today’s technology and understanding available options such as virtualization and
2013 EMC Proven Professional Knowledge Sharing 27
reducing hardware costs. To succeed however, you need to consider if the costs of owning and
operating an internal data center are substantially lower than outsourcing to a cloud provider.
There are other issues to consider, such as data security and data center location, but if profits
and cash flow are critical, outsourcing could provide a critical edge over your competition. In the
end, however, it is essential that the executive team ensure IT supports the vision, not the other
way around.
Data Center Activity - Customer Scenario: The success story
Project Summary: In late 2011, XYZ completed a significant data center upgrade, overhauling
one of the company’s Tier-1 data centers and focusing on one of many areas where XYZ is
implementing innovative solutions to help reduce the company’s environmental impacts. As a
global leader in design and engineering software, XYZ has developed many of the software
products used to plan, design, build, and manage more energy-efficient and sustainable
buildings and infrastructure. With the completion of the project, XYZ hoped to demonstrate that
its dedication to the environment extends to its own operations. Data centers are currently the
single largest source of IT-related emissions at XYZ. In 2011, they were responsible for almost
four percent of XYZ’s total carbon footprint; approximately 1,870 metric tons of carbon dioxide.
Objective: Make a parallel data center that would replace more than 85 percent of the existing
technology stack and move from a Solaris-based system to Linux and Windows.
Risks and Challenges
The center’s house numerous mission-critical core business applications. If those
applications stop, XYZ stops.
Low-efficiency power and cooling equipment.
Complex cabling.
Lack of flexibility and scalability.
Consuming more space.
The solution
Virtualization of severs.
Using smart storage allocation system such as SSDs and FAST.
Automatic provisioning.
2013 EMC Proven Professional Knowledge Sharing 28
Sell the unwanted hardware which are serviceable and recycle the rest through a
certified green recycler. (A good practice. The equipment will go through its full life and
not create any waste.)
The result
IT infrastructure costs reduced by 15 percent of the company’s IT infrastructure budget.
Zero waste. 100 percent of decommissioned equipment recycled.
75 percent reduction in physical servers.
62 percent reduction in energy use.
2013 EMC Proven Professional Knowledge Sharing 29
Conclusion
It has taken quite a while but 10 GbE has become the standard for data center network
backbones. Compared to the adoption rate for earlier versions of high-performance Ethernet, 10
GbE has experienced a glacial rate of acceptance, which brings us to an interesting point.
Back in September, the Ethernet Alliance held a plugfest event for 40 GbE and 100 GbE
equipment as a way of showing how close to reality these newer high-performance backbones
actually were, and in November, at Supercomputing 2010, CommScope and Cisco
demonstrated a viable networking ecosystem using their equipment to support 40 and 100 GbE
connectivity. Earlier in 2010, AT&T completed live field trials using Cisco equipment
implementing a 100 GbE networking environment.
So what does this mean to your data center? Generally, purchasers of networking backbone
infrastructure equipment would have looked to future-proof their purchases by looking for
chassis and equipment that were upgradeable to the next level of performance standards. But,
there are a number of other factors to consider beyond performance.
It's likely that since your last infrastructure refresh the issue of green computing has come up;
it's only in the last few years that this has become a major issue, and if you are moving toward
the end of your equipment cycle, your existing networking hardware likely predates the push to
energy efficiency as a major concern.
So what do you plan on looking for in your next generation backbone equipment? Energy
efficiency and power management goes pretty much without saying, but do you plan on
investing in 10 GbE now, and upgrade to 40 or 100 GbE in the near term? Are you considering
just waiting on greater availability of the faster technologies and replace from your core outward
with the fastest currently supported backbone? Do you have the wiring plant in place to support
the higher performance networking? Are there changes that need to be made to your
environment to prepare the way for a new, maximum performance backbone?
I talk to various different data center administrators and I get a wide variety of answers and a lot
more expressions of concern over the direction they need to take to replace their data center
backbone infrastructure. Let me know the decision points for your choices were and I'll spread
the word.
2013 EMC Proven Professional Knowledge Sharing 30
References
1. Key points to consider when upgrading or designing a new Datacenter or Server room
by John Caughell on 17/08/11 at 9:53 pm.
2. EMC Corporation. “What you need to know about Data Center Transformation: What
you need to know about Data Center Transformation. H5786.” EMC Perspective.
September 2008.
EMC believes the information in this publication is accurate as of its publication date. The
information is subject to change without notice.
THE INFORMATION IN THIS PUBLICATION IS PROVIDED “AS IS.” EMC CORPORATION
MAKES NO RESPRESENTATIONS OR WARRANTIES OF ANY KIND WITH RESPECT TO
THE INFORMATION IN THIS PUBLICATION, AND SPECIFICALLY DISCLAIMS IMPLIED
WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE.
Use, copying, and distribution of any EMC software described in this publication requires an
applicable software license.