T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.
-
Upload
diana-mckenzie -
Category
Documents
-
view
214 -
download
1
Transcript of T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.
![Page 1: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/1.jpg)
T-76.115 Project Review
TetrastoneProjext Planning Iteration
27.10.2003
![Page 2: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/2.jpg)
2
T-76.115 Project ReviewT-76.115 Project Review
Agenda
Project status (5 min) achieving the goals of the iteration project metrics
Used work practices (5 min)
Completed work (5 min) The results of this iteration will be presented
Plans for the next iteration (5 min) Tasks Features that will be implemented
Discussion
![Page 3: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/3.jpg)
3
T-76.115 Project ReviewT-76.115 Project Review
Status of planned goals of the iteration
Goals of the project from all perspectives
Customer’s goals – The customer has identified their main goals for the project and the information has bee delivered to the group
Goals can be found from the project plan
Group’s goals – The project group has agreed an certain set of common goals for the project.
Can be found form the project plan too.
Select and adapt work practices to be used in the project
Work practices used during the project have been defined and some have already been used.
There has been no need to use all defined practices yet
Make the contract with the customer Ok
![Page 4: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/4.jpg)
4
T-76.115 Project ReviewT-76.115 Project Review
Status of planned deliverables of the iteration
Project Plan OK and Accepted, but... Detailled tasks for iterations 2, 3 and Delivery will be updated during the
project.
Requirements document OK and Accepted both by the customer and the project group
Risk management plan Delivered together with the project plan
Use cases So far Use cases 1-15 defined All cases accepted by the customer Documented in the Requirements Specification
![Page 5: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/5.jpg)
5
T-76.115 Project ReviewT-76.115 Project Review
Realization of the tasks
Summary:
Planned 200 hours – realized only 161.5 38.5 hours were realized less than was planned Of course that is better than vice versa! Few tasks were underestimated
Requirements documentation Project Plan writing
Problems:
Hard to estimate all the tasks needed A lot of general work Project was just starting
Solution:
Defining the task more accurately More detailled plans in the next iterations
name realized planned
GE: Meetings (customer) 28.50 100
GE: Meetings (internal) 3.50 100
GE: Server installation and setup
11.00 15
Realized hours (other/ALL iterations' tasks)
Realized hours (PP iteration tasks)
name hours_done planned diff hrs_left
DS: Req. documentation
14.00 10 4 0.00
DS: Req. elicitation and analysis
6.50 10 -3.5 0.00
DS: Study domain RosettaNet
3.00 10 -7 0.00
DS: Study technology XML/.NET
3.50 10 -6.5 0.00
GE: Lectures 40.00 50 -10 0.00
GE: Meetings (mentor) 12.00 20 -8 0.00
PM: Define project goals 2.00 2 0 0.00
PM: Other project management
5.00 5 0 0.00
PM: Plan work methods and tools
5.00 15 -10 0.00
PM: Start and organize project
5.00 10 -5 0.00
PM: Write progress report 2.00 3 -1 0.00
PM: Write the project plan
19.50 15 4.5 0.00
TOTAL HOURS PLANNED
Total 161.50 200
Total hours realized in the PP-iteration
![Page 6: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/6.jpg)
6
T-76.115 Project ReviewT-76.115 Project Review
Working hours by person
Kjell had some extra work with the Req. Spec. as well did Mikko with the Project Plan.
Usually only some part of the group was in the meetings and that’s why not all the planned hours realized.
Plan in the beginning of this iteration Hours realized per member
MEMBER HOURS
Mikko 49.00
Kjell 39.50
Anssi 15.50
Kimmo 15.00
Henry 11.00
Mikael 24.50
Hanna 9.00
Less studying than was planned :(
Hours were a little bit over estimated
![Page 7: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/7.jpg)
7
T-76.115 Project ReviewT-76.115 Project Review
Changes to the project
So far no changes to the project has been made
So far no changes can be seen in the horizon
![Page 8: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/8.jpg)
8
T-76.115 Project ReviewT-76.115 Project Review
Risks
Risk management of this project is made by a separate risk management group
This group attendeeds course:T-76.633 Special Course in Software Engineering: Risk management
Risk have been identified and documented in the Risk Management Plan
What is the current situation regarding the risks?
Materialized risks - None New risks identified - Basically all, since they have only now been identified
![Page 9: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/9.jpg)
9
T-76.115 Project ReviewT-76.115 Project Review
Work practices
So far the following practices have been used: Time reporting Documentation and document delivery Meetings Communications Risk management Etc.
The practices have been found good, since: They provide methods to easier control the project Bring consistency into the documentation, meetings, communications etc. They somewhat tell everybody what to do and what are the responsibilities
The practices used will be updated during the project if: Some practive does not suite to the group or the customer Someone comes with an idea of a new practice Some practice could be better
![Page 10: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/10.jpg)
10
T-76.115 Project ReviewT-76.115 Project Review
Example: Communications
The rules for communications was first published: E-mail conversations is done via [email protected] address Documents will be published in the group’s homepage
www.hut.fi/~mpsavola/Tetrastone Project manager / Account manger hadles the communications between the
group and the customer Document templates were published
The rules have been used so far quite succesfully Everybody knows the rules Document outlook is consistent Information is delivered to all stakeholders
Negative experiences Communications within the group could be done more efficiently The e-mail based communications delay is sometimes quite high Every body should have access to the WWW-pages
Summary The documentation practice is very usefull The practice will not be modified
![Page 11: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/11.jpg)
11
T-76.115 Project ReviewT-76.115 Project Review
Results of the iteration
The project group was succesfully formed
The group managed to get an agreement of the subject
And the group got the subject they wanted.
A first contact and a communications chain between the customer and the group was established
The domain and case were presented by the customer and understood by the project group
’Physical’ results: Project Plan Requirements Specification Risk Management Plan
![Page 12: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/12.jpg)
12
T-76.115 Project ReviewT-76.115 Project Review
Example: Project plan
Introduction Tells the background of the project and introduces the case
Stakeholders and Staffing Tells who are participating in the project
Goals and Criterion What is the wanted outcome End and about criteria
Resources and Budget How much resources can be used? And what resources are available
Work practices and tools How will different tasks be done during the project
Phasing How is the project divided in the timeline
Risk management plan Risks, propabilities and countermeasures
![Page 13: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/13.jpg)
13
T-76.115 Project ReviewT-76.115 Project Review
Example: Architecture overview
![Page 14: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/14.jpg)
14
T-76.115 Project ReviewT-76.115 Project Review
Plan for the next iteration Goals
Map almost all of the requirements To get better understanding of the
system Some code written Detailed design of support
functions and PIP document processor
Detailed design of data base and file system
Deliverables Updated Project Plan Updated Requirements
Specification Technical specification Test cases Test report and test log Progress report
Customer deliverables Initial version of the GUI Use cases 01-06 (UC-06 initially) Database and file systems
name effort responsible
DO: Updating requirement specification 5 kpholmbe
DS: GUI design 10 hniveri
DS: Technical specification 30 ALL
DS: Technical specification writing 10 ALL
GE: Meetings (customer) 20 ALL
GE: Meetings (internal) 20 ALL
GE: Meetings (mentor) 10 ALL
IM: Database and file system 20 ALL
IM: GUI implementation 20 hniveri
IM: Use Case 1 5 ALL
IM: Use Case 2 5 ALL
IM: Use Case 3 15 ALL
IM: Use Case 4 15 ALL
IM: Use Case 5 15 ALL
IM: Use Case 6 15 ALL
PM: Other Project planning 10 mpsavola
PM: Personal SE practice 20 ALL
PM: Progress report 5 mpsavola
PM: Project review and preparation 10 mpsavola
PM: Updating project plan 5 mpsavola
PM:Plan the next iteration 5 mpsavola
TE: Designing test cases 5 ALL
TE: Testing 20 ALL
TE: Writing test cases and log 5 ALL
![Page 15: T-76.115 Project Review Tetrastone Projext Planning Iteration 27.10.2003.](https://reader036.fdocuments.in/reader036/viewer/2022082819/56649f1d5503460f94c34b82/html5/thumbnails/15.jpg)
15
T-76.115 Project ReviewT-76.115 Project Review
Thank you
Any questions?