System integration through...
Transcript of System integration through...
1
I Foro Internacional Ferroviario BCNRail
1/39
System integration through operability
BCN RAIL 2011 – November 29th
I Foro Internacional Ferroviario BCNRail
2/39
Introduction to EGIS
EGIS GROUP
EGIS RAIL
System integration through operability
Preamble
Lille Metro line 1 renewal Project presentation
System integration through operability requirements
Summary
System integration through operability
2
I Foro Internacional Ferroviario BCNRail
3/39
Introduction to EGIS – EGIS GROUP
System integration through operability
Consolidated Turnover > €800 M
-> of which 46 % abroad
-> in over 100 countries
11, 000 employees
-> 7, 000 in engineering
-> including 2, 500 international employees
Key figures
I Foro Internacional Ferroviario BCNRail
4/39
Introduction to EGIS – EGIS GROUP
System integration through operability
Key figures
3
I Foro Internacional Ferroviario BCNRail
5/39
Introduction to EGIS – EGIS GROUP
System integration through operability
Key figures
I Foro Internacional Ferroviario BCNRail
6/39
Introduction to EGIS – EGIS GROUP
System integration through operability
Markets & Skills
Engineering
Transport
Water & Environment
Industry, Energy & Civil Engineering
Building & Urban Development
Consulting & Design
Project Development & Turnkey Solutions
Operation & Road Users Services
4
I Foro Internacional Ferroviario BCNRail
7/39
Introduction to EGIS – EGIS RAIL
System integration through operability
Origins
1968: SEMALY is founded by the Lyon conurbation authorities
2007: SEMALY becomes part of the EGIS group as EGIS RAILEGIS RAIL
Lyon Metro Line CRack rail metro
First opening in 1974
Lyon Metro Line DRubber-tyred fully automated system
First opening in 1991
Lyon Metro Lines A&BRubber-tyred automated system
First opening in 1978
I Foro Internacional Ferroviario BCNRail
8/39
Introduction to EGIS – EGIS RAIL
System integration through operability
Key figures
300
500
271
100
2004 2007 2011
550
342
Workforce
30 M€
2004 2007 2011
115 M€
50
100
Consolidated Turnover
49 M€
5
I Foro Internacional Ferroviario BCNRail
9/39
Introduction to EGIS – EGIS RAIL
System integration through operability
From conceptual design to commissioning
Feasibility studies
Project Management
Preliminary and detailed designs
Tests & Commissioning
Construction Management
Assistance
Tender packages
Driverless Metro - Standard Metro - LRT - Tram-train Inter-city Railway - High Speed Lines - Buses
I Foro Internacional Ferroviario BCNRail
10/39
Preamble – Definitions
System integration through operability
SYSTEM INTEGRATION:System integration is the bringing together of various subsystems in order to ensure that they function together as a system.
OPERABILITY:Operability is the ability to keep an equipment, a system or a whole industrialinstallation in a safe and reliable functioning condition, according to pre-definedoperational requirements.
6
I Foro Internacional Ferroviario BCNRail
11/39
Preamble – Approach through operability requirements
System integration through operability
One of the keys to a successful System integration stands in the right definition of the System itself and therefore the functions it has to achieve…
Operationobjectives?
Constraints?
System preliminary definition
Costs?
Operability?
I Foro Internacional Ferroviario BCNRail
12/39
Lille Metro Line 1 renewal project – Lille’s situation
System integration through operability
Lille
Greater Lille Area• 85 districts• 1.200.000 inhabitants
7
I Foro Internacional Ferroviario BCNRail
13/39
Lille Metro Line 1 renewal project – Existing network and system
System integration through operability
The Transport Authority : LMCU (Lille Métropole Communauté Urbaine)
The Metro network :• Line 1: 13.5 kilometres, 18 stations – first commissioning in 1983• Line 2: 32 kilometres, 44 stations – first commissioning in 1989 (last extension in 2000).
VAL System :• Rubber-tyred• Specific track design• Light metro• Unattended Train operation• Common OCC for both lines• Interchangeable Rolling stock (VAL206 and VAL208)
I Foro Internacional Ferroviario BCNRail
14/39
Lille Metro Line 1 renewal project – Line 1 route
System integration through operability
8
I Foro Internacional Ferroviario BCNRail
15/39
Lille Metro Line 1 renewal project – Key features
System integration through operability
• 13.5 kilometres (inc. 9 km underground), 18 stations
• PSD at each platform
• Stations equipped for 26-meters trains operation but constructed to accommodate 52-metres trains (CW)
• Two passenger connections with Line 2
• Transfer track with line 2
• Operation centralized at the OCC
• 53 VAL208 trains (26m long, and 2.08m wide)
• Track heating equipment on exterior sections
I Foro Internacional Ferroviario BCNRail
16/39
Lille Metro Line 1 renewal project – Operation performance
System integration through operability
• Commercial operation from around 5:15am to 1:00am (Day+1)
• Commercial Speed: 32 km/h
• Peak periods: 6:55am to 7:25am, and 4:40pm to 5:10pm
• Minimum operational headway: 60 seconds
• Train capacity (4 pax/m²): 156 passengers
• Commercial operation range exceptionally extended to 44 hours
• Four provisional terminus
• Line capacity (4 pax/m²): 8500 PPHPD
9
I Foro Internacional Ferroviario BCNRail
17/39
Lille Metro Line 1 renewal project – Project objectives
System integration through operability
• Additional access creation to some stations
• Increase depot capacity
• Station platform modification to accommodate the 52-m trains: PSD, cameras, Finishings, etc.
• Power Supply and Tunnel Ventilation adaptation to new operation configuration
• Double train capacity by doubling their length:New RS order : new 52-m trains or 26-m trains that can be coupled
/
Twenty-six existing VAL208 26-m trains will be coupled
Increase the system capacity to at least 15.300 PPHPD
I Foro Internacional Ferroviario BCNRail
18/39
Lille Metro Line 1 renewal project – Project objectives
System integration through operability
• Replace the ATC (including ATO/ATP functions)
• Replace pneumatic PSD with electric ones
• Replace Power Supply equipments
• Replace Low Voltage Distribution Panels
• Replace Tunnel ventilation and smoke exhaust systems
• Adapt the stations to match the upgraded standards regarding in particuliaraccess for disabled people.
• Replace the system supervision (ATS, SCADA, CCTV and Communication means)
Replace/Modernize all obsolete equipmentsAdapt the stations to match nowadays accessibility standards
10
I Foro Internacional Ferroviario BCNRail
19/39
Lille Metro Line 1 renewal project – Project objectives
System integration through operability
• On-board CCTV
• Limitation of train stoppings in interstation
• Mixed fleet operation (simultaneous operation of 52-m and 26-m trains)
• Improvement of operation of provisional terminus: • Simplify stteing and cancellation procedures• Bidirectional operation on one terminus
• Automatic anouncements on incidents
• Realtime stopping point selection from OCC
• Information on train stopping in interstation
Implement new functions
I Foro Internacional Ferroviario BCNRail
20/39
Lille Metro Line 1 renewal project – Project objectives
System integration through operability
Line 1 possible extension
1 or 2 additional stations after C.H.R. B-CALMETTE terminus
11
I Foro Internacional Ferroviario BCNRail
21/39
Lille Metro Line 1 renewal project – Major constraints
System integration through operability
• Operation must not be disturbed at any time
• Level of safety must be maintained
• Inconvenience to passengers should always be minimized
• Train detection system cannot easily be reused
• Existing wayside VAL equipment is very sensitive to unexpected train movements, and to unequipped trains (ie. trains without VAL on-board equipment).
I Foro Internacional Ferroviario BCNRail
22/39
Lille Metro Line 1 renewal project – Major constraints
System integration through operability
• Conversion of Line 1, to a more efficient and modern line, closer to the needs of passengers and Operation staff
• Renewal of operating systems, without disruption of service, and maintaining the security level
• Implementation and commissioning of a new UTO ATC replacing an existing UTO ATC
a World first…
• Replacement of PDSs, on a line already in UTO
a World first…
12
I Foro Internacional Ferroviario BCNRail
23/39
Lille Metro Line 1 renewal project – Major steps
System integration through operability
Rehearsal on the test track at 4 Cantons Depot
Test Track will be equipped with the new wayside ATC and OCC equipments
Two existing trains will be equipped with the new on-board ATC equipment
No change in Operation of Line 1
I Foro Internacional Ferroviario BCNRail
24/39
Lille Metro Line 1 renewal project – Major steps
System integration through operability
Existing situation
13
I Foro Internacional Ferroviario BCNRail
25/39
Lille Metro Line 1 renewal project – Major steps
System integration through operability
Renewal Step 1
Installation of temporary OCC
Installation of the new PSD
Operation supervised from the existing OCC
Tests of new equipments from temporary OCC
Operation with existing trains and equipments
I Foro Internacional Ferroviario BCNRail
26/39
Lille Metro Line 1 renewal project – Major steps
System integration through operability
Renewal Step 2
26-m trains operated with new ATC
Stations with new accesses and all necessary equipments
New platforms operated with new PSD
Operation & tests supervised from temporary OCC
Fitting out of old platforms (new PSD and all necessary equipments)
Refurbishing of existing OCC
14
I Foro Internacional Ferroviario BCNRail
27/39
Lille Metro Line 1 renewal project – Major steps
System integration through operability
Final situation
New platform fitted for commercial operation (New PSD)
New OCC
New Equipements52-m/26-m trains mixed operation with new ATC
Platforms equipped for full length operation
Operation supervised from the refurbished OCC
I Foro Internacional Ferroviario BCNRail
28/39
System integration through operability requirements
System integration through operability
Focus…
• Why do operablity requirements need to be taken into account in System integration?
• What can new technologies bring to enhance the System’s operability?
15
I Foro Internacional Ferroviario BCNRail
29/39
System integration through operability requirements
System integration through operability
Taking into account operability requirements when designing the System:
System detailed
definition
I Foro Internacional Ferroviario BCNRail
30/39
System integration through operability requirements
System integration through operability
Example: Passenger exchange management
Centralized HMI (OCC)
Local HMI
16
I Foro Internacional Ferroviario BCNRail
31/39
System integration through operability requirements
System integration through operability
Frequent centralized HMI operability issues (1)
• Abilty to manage degraded modes
• HMI integration
I Foro Internacional Ferroviario BCNRail
32/39
System integration through operability requirements
System integration through operability
Frequent centralized HMI operability issues (2)
• Understandable information
• Crucial commands availability and accessibility
17
I Foro Internacional Ferroviario BCNRail
33/39
System integration through operability requirements
System integration through operability
Frequent local HMI operability issues
• Local HMI protection
• Local HMI accessibility
• Local HMI centralized supervision
I Foro Internacional Ferroviario BCNRail
34/39
System integration through operability requirements
System integration through operability
New technologies enhancing System operability (1)
• Provisional Terminus management:
- Allowing one shot tunbacks
Earlier retrun to depot
- Reducing setting and cancellation durations
18
I Foro Internacional Ferroviario BCNRail
35/39
System integration through operability requirements
System integration through operability
New technologies enhancing System operability (2)
• Increasing provisional services possibilities
Normal Operation
Existing situation
New possibilities
I Foro Internacional Ferroviario BCNRail
36/39
System integration through operability requirements
System integration through operability
New technologies enhancing System operability (3)
• Undesirable train stopping prevention
19
I Foro Internacional Ferroviario BCNRail
37/39
System integration through operability requirements
System integration through operability
New technologies enhancing System operability (4)
• Unexpected train stopping
I Foro Internacional Ferroviario BCNRail
38/39
System integration through operability requirements
System integration through operability
Conclusion
• Operability requirements to be taken into account in the System’s design in order to ensure a successful integration
• Operability requirements must be considered at the equipment level but above all at the System’s level
• New technologies allow operability improvements
20
I Foro Internacional Ferroviario BCNRail
39/39
System integration through operability
Thank you for your [email protected]