SWRO.ppt [Compatibility Mode]

download SWRO.ppt [Compatibility Mode]

of 29

Transcript of SWRO.ppt [Compatibility Mode]

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    1/29

    Surface Water Run-Off

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    2/29

    Sur 1 - Management of surface water run-off

    from developments

    To design surface water drainage for housing developments which

    avoid, reduce and delay the discharge of rainfall to watercoursesand public sewers using SuDS techniques. This will protect

    receiving waters from pollution and minimise the risk of flooding

    and other environmental damage in watercourses

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    3/29

    Assessor approach

    Not expected to know

    detail of this

    Engineer AQP who does

    this, knows SuDS

    Collating evidence

    Assessor needs basic

    understanding of

    principles only

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    4/29

    RAIN

    Stream or sewer

    Infiltration

    Surface water run off

    Green field site /

    pervious ground

    Sur 1 - Principles

    This is our concern

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    5/29

    Stream or sewer

    Infiltration

    No infiltration

    Surface water run off now

    greater as rain hitting house

    cannot infiltrate

    Sur 1 - PrinciplesRAIN

    Green field site /

    pervious ground

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    6/29

    Stream or sewer

    Sur 1 Possible Solutions Sustainable drainage systems

    (SuDs)

    Soakaway

    Water goes here

    instead of running off

    Run off is reduced to

    pre development level

    Permeable

    Paving

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    7/29

    Stream or sewer

    Sur 1 Possible Solutions Rainwater used in the

    dwelling

    Water goes here

    instead of running off

    Run off is reduced to

    pre development level

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    8/29

    SuDS Management Train

    Source control (where the rain falls) Soakaways

    Porous/permeable paving

    Roof water directed to garden

    Rainwater harvesting

    Green roofs

    Small swales and ponds

    Underground attenuation storage

    Site control (where the rain runs to) Swales

    Infiltration/detention basins

    Larger soakaways

    Regional control Balancing ponds and wetlands

    (to encourage a holistic thought process)

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    9/29

    Criteria Overview

    Use SuDS management train:

    1 Peak rate of run off No greater than pre developed site

    2A Volume of run off

    Additional volume entirely reduced Infiltration or other SuDS techniques non holding back solutions

    Must do this first, only move to 2B if 2A cannot be satisfied

    2B Volume of run off Reduce run off rate to limiting discharge

    Must do 2A first where possible

    Underground attenuation tanks possible solution here (not in 2A)

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    10/29

    Not acceptable in meeting 2A

    Source control (where the rain falls) Soakaways

    Porous/permeable paving

    Roof water directed to garden

    Rainwater harvesting

    Green roofs

    Small swales and ponds

    Underground attenuation storage

    Site control (where the rain runs to) Swales (in some cases)

    Infiltration/detention basins

    Larger soakaways

    Regional control Balancing ponds and wetlands

    Anything that

    holds water

    back will not

    comply with 2A

    egHolding ponds

    Oversized

    pipes with

    hydrobreak

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    11/29

    Details

    Mandatory requirements

    Appoint appropriately qualified person Professional or team of professionals

    Knowledge of

    Sites SWRO needs/opportunities SuDS based solutions (+ experience)

    Champion SuDS

    Provide robust hydraulic design calculations

    Report, flood risk assessment and drawings Covering all mandatory requirements

    In accordance with Development and Flood Risk: a practice guidecompanion to PPS25

    Concessions for smaller sites (see guidance)

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    12/29

    Peak Rate Run-off no greater Than pre development

    For 1 year and 100 year return period

    events

    5 l/s discharge is allowed Post development At a discharge point

    To avoid blockage

    These rules do not apply If no increase in impermeable areaor

    If criteria 2A (next) cannot satisfied

    Sur 1 Mandatory criteria 1- Peak run off rate

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    13/29

    If run off volume post

    development greater than pre

    (2A) Additional volume (m3) must

    be prevented from leaving site by SuDS techniquiqes

    Holding back soluitons do not comply

    100 year 6 hour event

    If no increase in impermeable,

    criteria met by default

    Sur 1 Mandatory criteria 2 - Volume of run off

    SuDs

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    14/29

    Unless A cannot be satisfied Responsibility of AQP to decide this

    Full justification must be provided

    In which case: (2B) the peak rate of run off must be reduced to:

    1 year peak flow rate

    Mean annual flood flow rate (Qbar)

    2 l/s/ha (max)

    No single discharge point need be < 5 l/s

    Sur 1 Mandatory criteria 2 - Volume of run off

    } whichever is higher= limiting discharge

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    15/29

    3. Designing for local drainage system failure

    Demonstrate that the flooding of the property would not

    occur in the event of the above

    Caused by Extreme rainfall

    Lack of maintenance

    Sur 1 Mandatory criteria 3 - Volume of run off

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    16/29

    Fag packet maths Poor sitedrainage

    Good site

    drainage

    Site size/increase in impermeable?

    Pre dev peak run off rate 1 / 100 yr

    1 Required post dev run off rate 1 / 100 yr

    2A Peak flow rate increase due to dev. (pre

    SuDs) 1 / 100 yr

    Additional volume to be dealt with by non holding

    back method (for 100 year event of 6 hours)

    Equivalent to cube tank side length of

    2B 1 yr peak pre dev. flow rate

    Qbar

    2 l / s / ha

    Limiting discharge rate

    Rate difference from 100 peak rate post dev.

    Additional volume to be dealt with in any way

    Equivalent to cube tank side length of

    2 ha / yes 2 ha / yes

    5 / 10 l/s

    5 / 8 l/s

    4 l/s

    3.51 m

    2x60x60x6 =

    43,200 litres

    5 l/s

    4 l/s

    4.76 m

    108,000

    5 l/s

    22 / 44 l/s

    4x60x60x6 =

    86,400 litres

    4 / 8 l/s

    20 / 40 l/s

    4.42 m

    20 l/s

    18 l/s

    4 l/s

    20 l/s

    24 l/s

    518,400

    8.03 m

    20 / 40 l/s

    4 l/s

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    17/29

    Information required

    A lot of detail Confirmation of qualifications of consultant

    Report

    Permeable/impermeable areas pre and post development

    If impermeable increased, report to include:

    Permeability characteristics of site

    Inc infiltration tests where appropriate

    Peak run off rate calculations for 1 and 100 year events

    Methods used to reduce run off

    Volume of run off pre, post development and with proposed

    mitigation etc

    FRA

    Drawings

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    18/29

    Special Cases

    Min flow rate set by sewerage undertaker

    Max flow rate set by sewerage undertaker

    Derelict sites

    Planning Consent pre dates Code requirement

    Infrastructure in place before Code requirement enforced Planning Authority require a non-compliant flow rate

    Supplementary guidance for Wales will be published byWAG

    For further guidance visit www.breeam.org/cshguidance

    http://www.breeam.org/cshguidancehttp://www.breeam.org/cshguidance
  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    19/29

    Assessing tips?

    Assessment methodology Useful step by step approach

    Calculation procedures Key publications

    Allowance for climate change (post development only) Greenfield sites

    calc method varies with size

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    20/29

    Using SUDS to improve quality of rainwater discharged or

    protect quality of receiving water

    Ensure no discharge for rainfall up to 5mm (1 credit) and/or

    Run off from all hard surfaces receive treatment (1 credit) In accordance with SuDS Manual

    To minimise pollution

    2 CreditsSur 1 Optional credits

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    21/29

    Default Cases Rainwater discharges directly into a tidal estuary or the sea

    Credits withheld if development goes against EnvironmentAgency recommendations

    Sur 1 - Management of surface water run-off

    from developments

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    22/29

    Examples

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    23/29

    Remineder of main requirements

    There are two key aspects to consider when

    assessing surface water run-off in the Code:

    Peak rate of runoff

    Ensuring the peak rate of runoff is no greater

    post development than it was pre development

    Volume of runoff

    Ensure that the post development volume ofrunoff is no greater than it was predevelopment

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    24/29

    Watercourse or sewer

    Possible solutions to deal with volume where

    infiltration techniques are possible on site

    Soakaway

    Water infiltratesrather than

    running off

    Run-off is reduced to

    pre-development level

    Green roof

    Permeable

    Paving

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    25/29

    Watercourse or sewerSome of the run-off

    infiltrates rather than

    running off

    Volume of run-off reduced

    with some residual run-offremaining

    Swales

    Holding Pond

    Possible solutions where additional volumes ofrunoff are low, but infiltration rates are alsovery low (such as sites with clay soils),

    therefore only partial infiltration is possible

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    26/29

    Example

    Site has the following characteristics

    Low permeability on the site pre development (therefore small

    additional volume of runoff caused by the new development)

    Additional Volume of Run-off: 6m3

    Fairly large open space

    Surface SuDS were the cheapest option and were able to deal with all

    the additional volumes of runoffPost development volume of runoff was no greater than pre development

    WetlandSwale

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    27/29

    Watercourse or sewer

    Possible solutions where infiltration is not at all

    feasible on the site

    Water collected in the Rainwate

    Harvesting System rather than r

    Runoff is reduced to

    pre-development level

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    28/29

    Watercourse or

    sewer

    Possible solutions can be a combination of both

    infiltration and Rainwater Harvesting where there is alarge volume to attenuate

    Water collected in the

    harvesting system rather

    than running off

    Runoff is reduced to

    pre-development level

    Permeable

    Paving

  • 8/10/2019 SWRO.ppt [Compatibility Mode]

    29/29

    Example

    Greenfield site pre development

    Additional Volume of Run-off: 25m3

    Holding Pond/Swales were not an option due to size of site

    RWH tank installed below the small communal garden

    Permeable paving installed on the front drives

    Permeable Paving

    Communal Rainwater Harvesting Tank

    Communal garden

    Additional Volume entirelyreduced.

    RWH tank sized to also

    deal with holding back

    the run off for the 100 year

    event before then being

    discharged at the Limiting

    Discharge rate