Summer Intern report_Austin
-
Upload
sahana-muralidharaneit-cmit-leed-ga -
Category
Documents
-
view
177 -
download
0
Transcript of Summer Intern report_Austin
Submitted by Sahana Muralidharan
CVEN 684: PROFESSIONAL INTERNSHIP At Austin Bridge & Road, Irving
Submitted To
Dr. David Ford
Table of Contents
1.0 Introduction ............................................................................................................................... 1
2.0 Lessons learned ......................................................................................................................... 2
2.1 Update primavera schedule ................................................................................................... 2
2.2 Tilos software ........................................................................................................................ 2
2.2.1 FM 455 – Denton County project ................................................................................... 3
2.2.2 NTTA –DNT project ...................................................................................................... 5
2.2.3 SH 34 Kaufman project .................................................................................................. 5
2.3 Site Visit.................................................................................................................................... 6
2.3.1 SH 34 Kaufman project .................................................................................................. 6
2.3.2 FM 148 ......................................................................................................................... 13
3.0 Activities and responsibilities ................................................................................................. 17
4.0 Conclusion and Suggestions ................................................................................................... 18
List of Figures
Figure 1 Iron Wolf Crusher 1000 series ......................................................................................... 3
Figure 2 Time - Distance graph for FM 455 project ....................................................................... 4
Figure 3 Tilos schedule for SH 34 Kaufman project ...................................................................... 6
Figure 4 Low profile concrete barrier (LPCB) ............................................................................... 7
Figure 5 Placement of LPCB .......................................................................................................... 7
Figure 6 Link-Belt 248 Hylab 5 ...................................................................................................... 8
Figure 7 Trimble SPS320 Total Station .......................................................................................... 9
Figure 8 360-degree prism ............................................................................................................ 10
Figure 9 TSC3 Controller ............................................................................................................. 10
Figure 10 Belly Dump Truck ........................................................................................................ 11
Figure 11 CAT M series Motor Grader ........................................................................................ 11
Figure 12 Sheep Foot Roller ......................................................................................................... 12
Figure 13 Beam placement on the bridge ..................................................................................... 13
Figure 14 CTB Rutting ................................................................................................................. 14
Figure 15 Wirtgen W 210 ............................................................................................................. 14
Figure 16 Truck Haul .................................................................................................................... 15
Figure 17 Dry Cement Spreader ................................................................................................... 15
Figure 18 Cement Mixer ............................................................................................................... 16
Figure 19 Pug Mill ........................................................................................................................ 16
1
1.0 Introduction
Austin Industries is one of the nation’s largest US-based construction companies. It provides
services in nearly every type of Civil Construction work through three companies namely Austin
Bridge & Road (ABR), Austin Commercial and Austin Industrial. The company is a 100%
employee owned company since 2000 and has a history of about 100 years in the Industry. In the
heavy Industry, Austin Bridge & Road provides the following services:
Preconstruction
Design-build
Construction Management at-risk
General Contracting
Austin works on four core values namely Safety, Service, Integrity and Ownership. Majority of
the projects taken up by ABR lies in the State of Texas. But they have also carried out projects in
Arkansas, Oklahoma, Arizona, Missouri and North Carolina. Some of the typical projects
undertaken by the company are as below.
I-30 HOV/ Managed Lanes
Austin is the prime contractor for this 18-mile project which begins half a mile west of
Fielder Road in Arlington and extends to Dallas at Sylvan Avenue. The scope of the work
includes widening of existing I-30 to include HOV/ Managed lanes, wishbone ramps,
bridge widening and toll infrastructure.
North Tarrant Express Zone 2
This project includes major rehabilitation to a series of Highways that run between I-35
W and Industrial Boulevard in North Tarrant County. Scope of the project comprises the
construction of new direct connect ramps from SH 183 to SH 121, a new Murphy-West
park bridge, main lane reconstruction and frontage roads.
DFW Connector: Asphalt Paving
The eight-mile project involves rebuilding portions of four highways, two interchanges
and five bridges. The DFW Connector includes state highways 114 and 121 and adjacent
roadways located north of DFW Airport. Austin is responsible for producing and placing
all asphalt. The scope of work consists of priming the lime subgrade, constructing
temporary asphalt detours and placing 2.5 inch asphalt bond breaker.
2
My Internship with Austin Bridge & Road for the summer term extended from May 18, 2015 to
August 7, 2015. My only expectation from the Internship was to gain practical exposure in a
construction Industry and realize how the theory is put to practice. I was definitely in good hands
to achieve what I desired and more. I was working at the Irving, Dallas office and my work was
primarily in the scheduling department. Predominantly I worked with an emerging scheduling
software: Tilos 8.0. This software has its origins in Germany and is still in its early stages of
implementation in the United States. Detailed explanation of this software is in the following
sections. Apart from this, I also visited certain roadway projects to gain practical knowledge of
construction.
2.0 Lessons learned
2.1 Update primavera schedule
The scheduling managers at Austin use two databases for Primavera namely P6 Version 6 (P6V6)
and P6 Version 8 (P6V8). P6V8 is an online database but is not much different from the other
version. The company is slowly shifting all its work to P6V8 from P6V6. A month end update is
done to all projects that is on-going. I had an opportunity to do one such update. The project
manager for that project sent me a schedule with the actual dates and my role was to actualize the
dates for the completed activities and provide the manager with an updated schedule.
2.2 Tilos software
Tilos is a time-location planning software for managing linear construction projects, usually
infrastructure projects. The key benefit compared to Gantt chart is the flow of visual data in terms
of time and distance on one plan. The plot depicts on a single page all the activities that usually
runs for pages on a typical schedule. It not only simplifies the visualization process but also aids
in planning the resources. It evidently shows the flaws in a schedule and the crunch for resources.
It paints a better picture of a project when compared to pages of Primavera schedule.
Austin Bridge & Road bought a licensed version of this software to explore its possibilities and
ease of application to the projects. As the state still requires Primavera schedules, Tilos will not
replace it but would serve as a useful tool for the schedulers and the project managers to understand
the project better. As the software is new to the company, I got an opportunity to explore the
3
extents of its ability. I figured how to import P6 schedules into Tilos and create the time-location
graph. I compiled my understandings and created a user guide which explains the process of
creating a schedule in Tilos with screenshots. To test the extents of the software, I applied it to
projects of varying sizes and durations. The different projects are explained in detail as follows.
2.2.1 FM 455 – Denton County project
This project site lies in the Denton County, Texas and will reduce the risk of accidents on the
existing FM 455 road. The project scope includes 0.75 miles of pavement and 160 ft. of bridge
construction. The old roadway would be demolished after the traffic switches to the new roadway.
The project was commenced on April 6th, 2015 and the contract duration is 193 working days.
The project involves minning and excavating a hill which embanking near the bridge. The rock
encountered was tougher to break to the desired size with the available rock breaker equipment.
As the site experienced torrential rains and the required poduction rates were not met, the project
was delayed by 45 calender days. Austin decided that the monetary loss could be reduced if they
brought in a different equipment. Hence they brought in Iron wolf 1000 crusher (Figure 1) which
met the expected production rates and the project is trying to make up the loss of days.
Figure 1 Iron Wolf Crusher 1000 series
4
Tilos software was first applied to this project and the Time – Distance plot is as shown in Figure
2. The plan of the project is at the top of the graph and the stations are along the X- axis. The time
axis ascends as we move up on Y-axis. Each activity has a specific template and that has been
created in the software to be used globally across all projects. The schedule in Tilos can be created
either from scratch or by importing the activities from Primavera. As TxDot requires P6 schedules,
this plot in Tilos was created by importing the data from Primavera using Excel as a medium. The
graph readily shows all the activities occurring across the project at any instant of time. It can be
used as a planning tool to plan the resources at the start of the project.
Figure 2 Time - Distance graph for FM 455 project
5
2.2.2 NTTA –DNT project
The Dallas North Tollway project is located in Collin County, Texas. The project scope includes
widening of the on and off ramps for 2.38 miles and 0.12 miles of bridge. Engineer’s estimate for
the project is around 56 Million USD. Austin started the work on Jun 1st 2015 and the duration of
the project is 935 calendar days.
In an effort to understand the project better, the schedule was depicted using Tilos 8.0. From the
time-distance graph, the project managers could clearly see that there are on a tight schedule and
many activities are happening at the same period of time. The plot evidently showed that it is a
resource dependent job and the necessary number of crews should be made available to keep the
job running on time. The graph can also be used as a decision tool to demand the necessary
resources from the owner or from the management to complete the project on-time.
2.2.3 SH 34 Kaufman project
This project is a Greenfield project in Kaufman County, Texas. The project includes construction
of 4 lanes of an urban roadway with the Interchange at US 175. The total length of the project is
1.84 miles and it connects to existing SH 243 & FM 1836. The project manager Mr. Thomas Burr
wished to see the schedule in Tilos in order to check if the project is running on- time and to verify
the availability of the required resources. Figure 3 shows this project in Tilos. The project was
divided into 2 parts as SH34 and US 175 were crossing each other, hence depicting the activities
on a single time-distance graph would not be feasible. The plot shows the project as of June end
update and no prominent flaws were found in the schedule.
6
Figure 3 Tilos schedule for SH 34 Kaufman project
2.3 Site Visit
2.3.1 SH 34 Kaufman project
Construction work commenced on Jan 26, 2015 and the contract time is 24 months. Major
activities like concrete paving, bridge deck, MSE walls, earthwork, HMAC paving and milling are
self-performed by the company. There are five major subcontractors on this project working on
Drainage, Drilled shafts etc.
Despite the heavy rains and some issues like utility conflicts, this project is running on time with
no delays. Currently the project is in Phase 0 where they have closed a part of the frontage roads
on US 175 and are constructing the overpass on US 175. Meanwhile detour has been constructed
on FM 1836 and traffic has been switched to facilitate the milling of the asphalt pavement.
7
I was involved in this project for five days to get on-site experience and to visually realize the
activities that were in the schedule. My activities and learnings are as listed below:
a) Low profile concrete barriers (LPCB) (Figure 4) were used to divert the traffic into specific
lanes as well as to assure the safety of the cars from falling off the road. LPCB were used
in the detour that was constructed on FM 1836. As an intern I did the quantity take offs
using Bluebeam Revu software and ordered LPCB as required. Verified the quantities on
site too and monitored the placement of the LPCB (Figure 5) by the subcontractor.
Meanwhile made sure the flaggers were diverting the traffic well and removed the super
cones & barrels that were no longer needed.
Figure 4 Low profile concrete barrier (LPCB)
Figure 5 Placement of LPCB
8
b) Link-Belt 248 Hylab 5 (Figure 6) is a self-assembling lattice boom crane with 200 tons
capacity and boom length of 100ft. The crane reached the site by parts on eight 18 wheeler
trucks and was assembled on site without the use of another crane. The cabin with a part
of the boom were first set on the ground using the hydraulic jacks that are a part of the
body. The hook attached to this partial boom was then used to lift and fit the tracks and
counter-weights to itself. The boom was then lowered to the ground and the other parts
were attached to extend it to 100ft length. I got an opportunity to interact with the crane
operator and stand beside him to oversee the self-assembly of the crane. The experience
was both knowledgeable and exciting to me.
Figure 6 Link-Belt 248 Hylab 5
9
c) Survey on-site: Figure 7 shows Trimble SPS620 total station that was used for surveying
on-site. I had an opportunity to visit the site with the surveyor and was able to witness the
following features of the total station.
It facilitates operation by a single person and thus avoiding miscommunication as
well as delay.
It has lock on feature where it automatically finds the prism and locks on it, thus
easing the process of shooting the prism.
The prism (Figure 8) can be shot from all directions and a specific radio channel
can be chosen for its communication with total station. This avoids the total station
to pick up other reflecting objects on-site and allows it to spot the prism easily.
The Trimble TSC3 controller (Figure 9) is a hand held device which is used to
communicate with Trimble GNSS receivers cable free via Bluetooth wireless
technology. Both Trimble total station and GPS devices can be operated using this
controller and it measures quickly and accurately.
Once the total station finds the target prism and locks on it, it automatically takes
measurements in direct and reverse mode to finally give the coordinates for the
point on which it has been centered.
Figure 7 Trimble SPS320 Total Station
10
Figure 8 360-degree prism
Figure 9 TSC3 Controller
Being a Teaching Assistant for CVEN 303: Surveying lab, I could realize the extent to
which the technology has advanced in this field. The equipment are way more sophisticated
than the ones that are used in the class but follows the same basic principles of
measurement. I was impressed by the advancement and was able to capture videos to show
my students how surveying is done in the real world. I had an amazing opportunity to visit
the site with an experienced surveyor who taught me how to stake out points for the face
of the retaining walls.
11
d) Certain equipment that were used on this site were new to me. They were used to backfill
the abutment on the north side of the bridge. Figure 10 shows a belly dump truck that
transported the dirt from a nearby site to the project site. The truck dumps the dirt from the
bottom and hence it saves time to load the dirt on site.
Figure 10 Belly Dump Truck
After the dirt was dumped for the backfill, a CAT M series motor grader (Figure 11) was used to
spread the dirt evenly throughout the area. The motor grader, frequently known as ‘The Blade’,
can move and rotate the blade in all 3 directions. This aggressive blade angle allows material to
roll more freely along the blade for better material control. Supplementary devices like GPS can
be attached to the blade and programmed to grade to the final cross-section required.
Figure 11 CAT M series Motor Grader
12
Usually rollers are used to compact the dirt to the desired relative density. On this site, apart from
the rollers, ABR also had sheep foot rollers (Figure 12) for the same purpose. The advantage of
this sheep foot is that it provides a higher compaction as it pushes the soil in with its sheep’ foot
like projections. While pushing the soil in, the roller also vibrates providing a higher density soil.
Figure 12 Sheep Foot Roller
e) Beam Setting: The overpass on US 175 consisted of 4 spans and 20 beams in each span.
The average length of the beam is around 85ft with the maximum length being 93ft. The
beams on each span were done one at a time, hence takes 4 days to place all the beams. As
of August 7th 2015, beams on two spans have been placed. As the frontage roads are already
shut down for construction, Austin had to stop and regulate traffic when the beams were
placed in the span just above US 175. To lift this 10,000 lbs heavy beam, two Link-Belt
248 Hylab 5 were used as shown in Figure 13.
13
Figure 13 Beam placement on the bridge
The beam were precast and arrived on 20 separate 18-wheelers. Lifting and placing each beam
took around 15 minutes, hence around 5 hours to complete placing beams for one span of the
bridge. There were two crews standing on the caps on either side of the span, to hold and position
the beam in place. This task called for extreme coordination between the two crane operators and
the workers placing the beam. All safety precautions were necessarily taken and hence was
executed efficiently without any accidents.
2.3.2 FM 148
This is one other construction project in Kaufman County carried out by Austin Bridge & Road.
The scope of the project includes 7.5 miles of milling, Cement treated base, chip seal and HMAC.
Work started on Jan 10, 2014 and the contractual duration of the project is 12 months. About one
month into the project they uncovered saturated clayey soil while milling. When the pavement was
laid, the proposed typical section failed and TXDOT stopped time due to the failing subgrade
(Figure 14). In the 1-mile stretch of road that had been “opened up”, ABR tested new design ideas
given by TXDOT, repaired potholes, and chip sealed all under force account payment. On March
23, 2015 TXDOT issued a new design that allowed ABR to continue work on the 1-mile of
roadway that was initially started. Contractor has submitted a re-design proposal, along with a
price for the new contract items associated and is waiting for TXDOT to make a decision on the
remaining 6 miles of the job.
14
Figure 14 CTB Rutting
The contactor milled out the 1 mile of the pavement that failed using an asphalt milling equipment
Wirtgen W 210 (Figure 15). The position of the blade and the depth of the cut are fed into the Total
Station and communicates with the GPS installed on the equipment. The values are also displayed
on a screen which can be manually overridden by a personnel. This versatile milling machine is
track-driven and has a cutting depth of 13 inches.
Figure 15 Wirtgen W 210
15
As the milling operation was carried out, the debris was thrown on to a conveyor belt and was
directed into a truck that was positioned in front of it (Figure 16). The arm of the milling equipment
could swing to exactly position the arm on top of the truck.
Figure 16 Truck Haul
After Asphalt was removed, the subgrade was treated with cement. Figure 17 shows a dry cement
spreader that was used to spray the cement in the desired portion of the pavement.
Figure 17 Dry Cement Spreader
16
The cement was then mixed into the subgrade to stabilize and strengthen the base. The mixer as
shown in Figure 18 mixes the cement and the soil beneath it to achieve a cement treated base.
Figure 18 Cement Mixer
Subsequently flex base is placed on top of the cement treated base. For flex base, an equipment
called Pug mill (Figure 19) was used and it mixed crushed concrete, water and cement. This
mixture was the filled into the belly dump- trucks and was transported to the site. The haul time to
the site and back to the Pug mill site took around one hour and there were totally 7 trucks that were
used on site.
Figure 19 Pug Mill
17
The next day, asphalt would be poured on the top of this flex base and a Hot-mixed Asphalt
(HMA) pavement would be laid. This entire process was repeated every four days to lay the
pavement in parts as they had to handle the existing traffic.
3.0 Activities and responsibilities
My activities and responsibilities as a scheduling Intern at ABR were not confined just to
scheduling but are listed as follows.
1. Interacted with the project manager to update the primavera schedule.
2. Visited FM 455 project to review the schedule and understood the practical problems faced
during the execution of the project.
3. Visited IH 30 project as a part of Intern site visit and gained a clear understanding of the
activities involved in a bridge construction.
4. Attended video conferences with Tilos software experts and gained in depth knowledge in
its working.
5. Drafted the plan for a project in AutoCAD to simplify the process of planning and
estimating.
6. Understood the working of the company by reading their TAW2 manual that explains the
Austin Way of working.
7. Created a user manual explaining in detail the procedure to create a schedule in Tilos 8.0.
8. Using a profile diagram, estimated the quantity take-offs for excavation and embankment.
9. Familiarized more with design-build and design-bid-build project delivery methods.
10. Learnt to update a schedule in Primavera on a monthly basis for real life projects.
11. Carried out quantity take offs for the low profile concrete barrier and monitored its
placement on site.
12. Understood how traffic switching and stripping is done in practice. Attended the training
for flaggers by which I realized the importance of safety in the field.
18
4.0 Conclusion and Suggestions
Internship at ABR was truly a remarkable experience, training me both on and off site. Apart from
their work, I also learned how a team works in unison and how to balance work and life. I was
amazed by the work culture in the company and is reflected at any place across projects. I gained
hands-on experience with the scheduling software Tilos corroborated with the site experience I
acquired during the Job-site tours.
CVEN 641: Construction Engineering Systems provided a basis of scheduling in primavera. This
base knowledge eased the process of understanding the working of the new software. Equipment
productivity was dealt in CVEN 639: Methods Improvement Construction Engineers, which I was
able to practically comprehend on site. I travelled in the belly dump- truck to actually realize the
haul time taken and the difficulties faced in maneuvering from and to the project.
In conclusion, the experience developed me and academically well as personally. It definitely
served as platform to develop my skills and knowledge. After this experience, I have few
suggestions to the department. Kindly consider the following suggestions and it would help the
up-coming batches of students.
1. Tilos is a German software and is slowly trending in the Industry. Basic knowledge about
this software can be included in the curriculum which will open more opportunities for the
students.
2. Internship is the best way to gain practical knowledge and to understand how the theory is
put into practice. But unfortunately all students don’t get this opportunity. My personal
suggestion would be to include site visits to the on-campus projects in the curriculum. This
opens the student’s view of the construction Industry and the learning would be much more
practical.