Sub Station Design

download Sub Station Design

of 43

Transcript of Sub Station Design

  • 8/3/2019 Sub Station Design

    1/43

    SIEMENS

    PRESENTATION

    ONSUBSTATION DESIGN

    By

    Yuvaraj Patil

    I&S/WR

  • 8/3/2019 Sub Station Design

    2/43

    SUBSTATION DESIGN

    WHAT IS THERE IN SUBSTATION DESIGNING ??

    SLD

    EQUIPMENT LAYOUT

    BUSBAR ARRANGEMENTFAULT LEVEL

    TYPE OF CONSTRUCTION

    CREEPAGE AND CLEARANCE

    GROUNDING & LIGHTNING PROTECTION

    SAFETY INTERLOCKSOTHERS, e.g. LIGHTING AND CIVIL

  • 8/3/2019 Sub Station Design

    3/43

    SUBSTATION DESIGN CRITERIA

    FOLLOWING STUDIES ARE PERFORMED TO ESTABLISH THE

    DESIGN CRITERIA FOR A SUBSTATION

    1. LOAD FLOW STUDIES :

    - To determine the current carrying requirements of new s/s.- To determine the continuous and Emergency rating of

    equipment

    2. S.C.CALCULATION :

    - To permit the equipment to without damage, severe thermaland mechanical stresses of S.C. currents.

    - To provide adequate interrupting capability in CBs, strength

    in post insulators

    - Setting of protective relays

  • 8/3/2019 Sub Station Design

    4/43

    SUBSTATION DESIGN CRITERIA

    3. TRANSIENT STABILITY STUDY :

    Following factors affects the Stability of System.

    - Severity ofFault

    - Speed with which fault is cleared

    - Ties between the Machine and the System after the fault are

    cleared ( Which may weaken the system by operating more

    than one line due to not operation of primary relaying )

    4. TRANSIENT OVER VOLTAGE STUDY :

    - It is required to protect the equipments from Lightning Stroke

    and Switching Transient.

    -*-

  • 8/3/2019 Sub Station Design

    5/43

    SUBSTATION ARRANGEMENT ASPECTS

    1. System Security :

    - The ideal s/s is one where each circuit is controlled byseparate CB with facility for replacement of bus bar OR CB inthe event of fault or during maintenance.

    - Double Bus Bar system with Double CB arrangement is ideal.

    2. Operational Flexibility :

    - For efficient loading of Generators it is necessary to controlMVA and MVAR loading under all condition

    3. Simplicity of Protection Arrangement :

    - Where greater no of CB has to be tripped during faultcondition, protection arrangement becomes more complex.

    JERP is best example of complex Protection !!

  • 8/3/2019 Sub Station Design

    6/43

    SUBSTATION ARRANGEMENT ASPECTS

    4. Ability to Limit the S.C. Levels :

    - Any arrangement which incorporates means of providing a S/S

    into Two separate sections is suitable to Limit S.C levels.

    5. Maintenance Facilities :

    - Arrangement shall be suitable for the Planned or Emergency

    Maintenance .

    6. Ease of Extension ::

    - To add new bays there shall be space and expansion facilities.

    7. Site Considerations :

    - Where the area is limited, simple arrangement with least no of

    CBs.

  • 8/3/2019 Sub Station Design

    7/43

    Considerations for Choice of Busbar Arrangement

    A number of factors are to be considered while finalizing the Layout

    and Switching arrangements of S/S.

    Importance of Substation

    Reliability

    Redundancy

    Economics and availability of finance

    Availability of Space and Right Of Way for approaching

    lines

    Future Expansion

  • 8/3/2019 Sub Station Design

    8/43

    LineIsolator

    Bus

    Bus-Isolator

    Circuit-breaker

    Earthing-switch

    Protection-zone,busbar

    Protection-zone,line/trafo

    Line 2Line 1

    Single Bus System- Primary Components,

    Protection Zone

    Current

    Transformer

    PotentialTransformer

    Bus-EarthingSwitch

    Bus-PotentialTransformer

    Wave

    Trap

    LineIsolator

    Earthing-switch

    Wave

    Trap

    Surgearrester

    Transformer

  • 8/3/2019 Sub Station Design

    9/43

    Main & Transfer Bus ArrangementMain Bus

    x

    Transfer Bus coupler

    A Transfer Bus Coupler & All feeders need one additional isolator.

    In Thermax Project we are using this arrangement

    Transfer Bus

    x

    Line 1

    LineIsolator

    Earthing-switch

    WaveTrap

    Surgearrester

    TransferIsolator

    x

    Line 2

    LineIsolator

    Earthing-switch

    WaveTrap

    Surgearrester

    Transfer

    Isolator

    x

    Line 3

    Line

    Isolator

    Earthing-

    switch

    Wave

    Trap

    Surgearrester

    TransferIsolator

    CT CT CT CT

  • 8/3/2019 Sub Station Design

    10/43

    Ring or Mesh SystemLine 1

    Line 2

    Transformer 1 Transformer 2

  • 8/3/2019 Sub Station Design

    11/43

    Bus-disconnect

    Circuit-breaker

    CT

    VT

    Line-disconnect

    Earthing switch

    Bus Section-isolatorBus BBus A

    Surge arrester

    Earthing switch

    Single Bus with sectionaliser System- Primary

    Components,

    Over-lapping Protection Zone

    Bus PT 1 Bus PT 2

    To improve Reliability bus section isolator/CB is introduced

  • 8/3/2019 Sub Station Design

    12/43

    Bus-Isolators

    Circuit-breaker

    CT

    Bus I

    Bus II

    Bus-coupler

    Double Main Bus System

    or Main & Reserve Bus system

    LineIsolator

    Earthing-switch

    Transformer

    LineIsolator

    Earthing-switch

    WaveTrap

    Surgearrester

    Line 1

    Earthing-switch

    WaveTrap

    Surgearrester

    Line 2

    Bus-PT -I

    Bus-PT -II

    Bus-Earthing-I, II

  • 8/3/2019 Sub Station Design

    13/43

    Bus-Isolators

    Circuit-breaker

    CT

    Bus I

    Bus II

    Bus-coupler

    Double Main & Transfer Bus

    Arrangement (DMT)

    LineIsolator

    Earthing-switch

    WaveTrap

    Surgearrester

    Line 1

    Bus-PT -I

    Bus-PT -II

    Bus-Earthing-I, II

    Earthing-switch

    WaveTrap

    Surgearrester

    Line 2

    TransferBus-coupler

    TransferIsolator

    Almost all PGCIL 220kV substations use this arrangement

  • 8/3/2019 Sub Station Design

    14/43

    Bus A

    Bus B

    Q0 41

    Q0 42

    Q0 11

    Q0 13

    Q0 12

    For future use

    Bushing

    Bushing

    One and a Half Breaker

    Arrangement

    Almost all PGCIL 765kv,400kV substations use this arrangement

  • 8/3/2019 Sub Station Design

    15/43

    2000/1/1/1A

    Core Likeline 417

    Three Main & Transfer Bus Arrangement

    Practiced in Europe, Germany

  • 8/3/2019 Sub Station Design

    16/43

    245 kV Outdoor switchyard (AIS) Double busbars, classical layout

    1 Bus I 3 Bus-disconnector 5 CT 7 Line-disconnector with built-on earthing switch

    2 Bus II 4 Circuit-breaker 6 VT 8 Surge arrester

    245kV Switchyard Layout

    Almost all PGCIL 220kV substations use this arrangement

  • 8/3/2019 Sub Station Design

    17/43

    SUBSTATION DESIGN CONSIDERATIONS

    1. FAULT LEVEL :

    Expressed as MVA or kA and duration of 1-3 Sec.

    Depends on source impedance

    All CBs are to be rated for fault level

    Earth Switches for making fault level

    - All Bus bars, bus supports to be designed to withstand forcesdue to S.C

    2.SAFETY CLEARANCES :

    3. STRUCTURE :

    Why is it required ?

    To support and install Buses, electrical equipment and terminatetransmission line conductors.

    The structures may be of steel, RCC or wood

    They need foundation according to soil condition at site

  • 8/3/2019 Sub Station Design

    18/43

    SUBSTATION DESIGN CONSIDERATIONS

    Design of Structures are affected by :

    - Phase clearance

    - Ground clearance

    - Length and weight of buses and other equipment.

    Design Load on Girders shall include :

    - Conductor tension

    - Earth wire tension

    - Weight of Insulators and Hardwares

    - Erection load ( approx. 350 kg)

    - Weigh of man & tools to work ( aprox. 200kg)- Wind load

    - Impact load, if any during operation of equipment.

    - Walkway if any.

    ( BSP Project we are providing the same)

  • 8/3/2019 Sub Station Design

    19/43

    SUBSTATION DESIGN CONSIDERATIONS

    4. Recommended Standard Bay Widths :

    a. 400kV feeder Bays - 27m

    b. 400kV Transformer Bays - 20m ( per phase)

    c. 220kV Feeder Bays - 17m

    d. 110kV Feeder Bays - 10m

    e. 110kV Transformer Bays - 10m

    f. 66kV Bays - 8m

    g. 22kV Bays - 3.8mh. 11kV Bays - 3.5m

  • 8/3/2019 Sub Station Design

    20/43

    SUBSTATION DESIGN CONSIDERATIONS

    Normally adopted phase spacings are :

    Sr. No. Voltage Level (kV) Spacing (m)

    1 11/22 1.3

    2 33 1.5

    3 66 2.0 to 2.2

    4

    110 2

    .4

    to3

    .0

    5 220 4.5

    6 400 7.0

  • 8/3/2019 Sub Station Design

    21/43

    BUS DESIGN

    Present day trend is to use Rigid bus rather than strain bus due to

    can be constructed at lower profile.

    are aesthetically pleasing.

    corona level is lower.

    1. Construction of Rigid Bus : Aluminum bus materials used for rigid bus may be of different

    shapes.

    They may be round tubing's, channels, angles or integral web

    designs.

    Round tubing used in all voltage levels.

    Square/channel tubing is used only at lower voltages.

    Angle bus used only at distribution voltages.

    Integral web bus is structurally strong and is used for high current and

    long spans generally at lower voltage.

  • 8/3/2019 Sub Station Design

    22/43

    BUS DESIGN

    Design considerations of Rigid Bus :

    Bus must carry the expected maximum load current withoutexceeding the temp. limit .

    The capacity of bus shall be checked for max. temp. under S.C.

    conditions.Shall be designed to take vibration induced by the action of

    50Hz current.

    Shall be designed to take the vibration due to wind flowingacross the tubing.

    It should withstand the S.C. force.

    for HV and EHV S/S the diameter of bus should be checked forcorona discharge.

    The bus support system must be capable to to take weight oftubing, damping material, wind on tubing, S.C. force calculated.

  • 8/3/2019 Sub Station Design

    23/43

    BUS DESIGN

    2. Design considerations of Strain Bus :

    Widely used in most of the station due to ease of construction.

    Even in station where Rigid bus is predominant, some spans willbe invariably of strain bus construction.

    The design followed is based on simple sag-tensioncalculations.

    The down drops from strain bus appear as a concentrated load.

    Depending on length and weight of dropper, tension on bus willvary considerably.

    Where bundled conductors are used in strain bus, the type of

    spacer may have an influence on resulting tension. If rigid spacers are used, then during S.C., the two conductors

    will attempt to draw together and cause increases tension onstrain bus

  • 8/3/2019 Sub Station Design

    24/43

    ACCESSORIES REQUIRED FORBUS CONSTRUCTION

    RIGID BUS :

    1. BPI

    2. Aluminium Tubular pipes for bus

    3. Welding Sleeves of equivalent dia for Al Bus.

    4. BPI clamp for fixing tubular pipe to the insulator5. Inter connector for Al tube to strain Bus

    6. Corona bells for the free ends of right bus.

    STRAIN BUS :

    1. Insulator strings2. ACSR conductor of right choice

    3. Hardware fittings for tension points.

    4. Arcing horns

    5. Corona rings

  • 8/3/2019 Sub Station Design

    25/43

    ACCESSORIES REQUIRED FORBUS CONSTRUCTION

    6. Sag compensating spring.

    7. Suspension clamps with accessories for jumper connection

    points.

    8. Rigid or flexible spacers ( For bundle conductor bus)

    9. Parallel Groove clamps (PG Clamps) suitable for the ACSR forjumper and dropper connections.

    10. Tee Clamps for droppers. (With suitable sizes).

    11. Clamp to connect droppers, jumpers and interconnections to

    the equipment and on BPI

  • 8/3/2019 Sub Station Design

    26/43

    SUBSTATION EARTHING

    Purpose :

    In ungrounded system, it will be inherently coupledcapacitively to the earth th system capacitance. During groundfault, the charging current will rise to 3 times the Zerosequence current, develops high value of voltage.

    so earthing is required to

    1. Limit the transient overvoltages caused by restricting the

    ground current.2. Safety to the personnel working in the maintenance.

    3. Fast and selective clearing of ground fault to limit the damageto the equipment.

  • 8/3/2019 Sub Station Design

    27/43

    SUBSTATION EARTHING

    Following steps are involved in Design of Earthing System.

    1. Soil investigation.

    2. Determination of maximum ground current

    3. Preliminary designing of grounding system

    4. Calculation of resistance of grounding system

    5. Calculation of maximum grid potential rise.

    6. Calculation of step and touch voltages.

    7. Correction of preliminary design.

    A continuous earth conductor is placed around the

    perimeter of yard to enclose as much ground as possible toavoid current concentration.

    Within the grid conductors are laid in parallel lines and atuniform spacing along the rows of structure and equipment.

  • 8/3/2019 Sub Station Design

    28/43

    SUBSTATION EARTHING

    The earthing material should have

    High conductivity

    Low underground corrosion

    GI material is used for earthing and size of conductor should be

    such that

    It has thermal stability to flow the ground fault current

    It should last at least for 50 years without causing break in the

    ground circuit due to corrosion

    It should be mechanically strong.

  • 8/3/2019 Sub Station Design

    29/43

    INSTRUMENT TRANSFORMER

    Instrument Transformers are used to provide the exact

    proportion of the high voltage and current within the substation

    at a level suitable for metering, relaying and control.

    Voltage Transformers :

    VT may be of Electromagnetic or Capacitor type.When high level of accuracy is required then Electromagnetic

    type is used.

    All voltage transformers are required to comply with one of the

    classes in Table 8.1.

  • 8/3/2019 Sub Station Design

    30/43

    VOLTAGE TRANSFORMER

    For protection purposes, accuracy of voltage measurement

    may be important during fault conditions, as the system voltage

    might be reduced by the fault to a low value. Voltage

    transformers for such types of service must comply with the

    extended range of requirements set out in table 8.2

  • 8/3/2019 Sub Station Design

    31/43

    VOLTAGE TRANSFORMER

    Voltage Factors :

    The value Vfin Table 8.2 is an upper limit of operating voltage,expressed in per unit of rated voltage. This is important for correct relayoperation and operation under unbalanced fault conditions onunearthed or impedance earthed systems,. Voltage factors, with the

    permissible duration of the maximum voltage, are given in Table 8.3.

  • 8/3/2019 Sub Station Design

    32/43

    VOLTAGE TRANSFORMER

    Protection of Voltage Transformers

    o Voltage Transformers can be protected by H.R.C. fuses on the

    primary side for voltages up to 66kV. Fuses do not usually have

    a sufficient interrupting capacity for use with higher voltages.

    o In some cases protection on the primary is omitted. The

    secondary of a Voltage Transformer should always be protected

    by fuses or a miniature circuit breaker (MCB).

  • 8/3/2019 Sub Station Design

    33/43

    CURRENT TRANSFORMER

    CURRENT TRANSFORMER

    The current transformers may be either of bushing type or wound

    type.

    CT should be selected with a rating 25% greater than the max

    current that is likely to flow during normal operation.Protective CT should have high saturation factor.

    The secondary circuit must not be interrupted while the primary

    winding is energized. The induced secondary e.m.f. under these

    circumstances will be high enough to present a danger to life and

    insulation.Protection class current transformers must retain a reasonable

    accuracy up to the largest relevant current. This value is known

    as the accuracy limit current

    The ratio of the accuracy limit current to the rated current is

    known as the 'accuracy limit factor

  • 8/3/2019 Sub Station Design

    34/43

    CURRENT TRANSFORMER

    The accuracy class of protection current transformers is shown in Table

    Class PS Current Transformers

    The classification of Table 5 is only used for overcurrent protection

    PS commonly used with unit protection schemes

    Knee point is a key factor in the PS class CT

  • 8/3/2019 Sub Station Design

    35/43

    POWER TRANSFORMER

    RATINGS :

    Transformer ratings shall be such that the transformer can

    deliver its rated current under steady loading conditions without

    exceeding the limits of temperature-rise specified in IS : 2026 (

    Part II ) - 1977* assuming that the applied voltage is equal to therated voltage and that the supply is at rated frequency.

    SERVICE CONDITIONS :

    Transformers complying with IS-2026 are suitable for operation

    continuously at their ratings, provided the temperature of thecooling air or water does not exceed any of the reference

    ambient temperatures specified

  • 8/3/2019 Sub Station Design

    36/43

    POWER TRANSFORMER

    kVA Ratings:

    kVA ratings for three-phase transformers are given in below table

    For single-phase transformers intended for use in three-phase

    banks, the kVA ratings are one-third of the values in Table 2.

  • 8/3/2019 Sub Station Design

    37/43

    POWER TRANSFORMER

    Operation at Other than Rated Voltage :

    - A transformer built in accordance with IS-2026 may beoperated at its rated kVA at any voltage within +/- 10 percent ofthe rated voltage of that particular tap.

    - The transformer shall be capable of delivering rated current ata voltage equal to 105 percent of the rated voltage.

    Operation at Rated Frequency :

    The frequency for A transformer built in accordance with IS-2026 standard shall be 50 Hz with tolerance of +/- 3 percent.

    Temp Rise:

    The transformer shall confirm to the requirements oftemperature rise specified in IS : 2026 (Part II)

  • 8/3/2019 Sub Station Design

    38/43

    POWER TRANSFORMER

    Insulation Levels :

    The insulation levels shall be in accordance with IS : 2026 (Part

    III)- 19777.

    Terminal markings, tappings and Connections :

    The terminal markings, tapings and connections shall be in

    accordance with IS : 2026 ( Part IV )-1977

    Requirement with regards to Ability to withstand S.C.

    Transformers shall be designed and constructed to withstand

    without damage the thermal and dynamic effects of external

    short circuit under the conditions specified in IS:2026.

  • 8/3/2019 Sub Station Design

    39/43

    POWER TRANSFORMER

    CRITERIA FOR SELECTION OF POWER TRANSFORMERS

    ( ABOVE 1600kVA)Ratings :

    o The secondary no-load voltage should be specified 5percent more than the nominal voltage to compensate the

    transformer regulation partly.o For transformers requiring to be operated in parallel, the voltage

    ratio should be selected in accordance with guidelines given inIS : 10028 ( Part 2 )-1981*.

    Taps :

    o On-load tap changers on HV side should be specified,

    wherever required.o The total number of taps should be 16 in steps of 1.25 percent..

    Off-circuit taps, when specified, should be in the range of 2.5percent and +/- 5 percent provided on the HV side.

  • 8/3/2019 Sub Station Design

    40/43

    POWER TRANSFORMER

    Connection Symbol :

    o The preferred connections for two winding transformers up

    to 66 kV high voltage ( HV ) side rating are delta/star ( Dyn ) and

    star/star ( YNyn ). For higher voltages, connections star/star

    (YNyn) or star/delta ( YNd ) may be preferred.o The selection of connection group should be made taking into

    consideration the requirements of parallel operation with other

    transformers

    Impedance :

    o The transformer impedance is decided taking into Considerationthe secondary fault levels and the voltage dip.

    o typical impedance values are given IS : 2026 ( Part 1 )-19777.

  • 8/3/2019 Sub Station Design

    41/43

    POWER TRANSFORMER

    Termination Arrangement :

    o Primary and secondary terminals may be bare bushings,

    cable boxes or bus trunking depending upon the method of

    installation.o It is preferable to specify disconnecting chamber between

    transformer terminals and cable box to facilitate disconnection of

    transformer.

  • 8/3/2019 Sub Station Design

    42/43

    OTHER DEVICES AND EQUIPMENTS

    Due to the time constraint following devices/equipments

    are not covered in detail !!!

    Circuit Breakers

    Isolator and earth Switch

    LABattery and battery Charger

    ACDB

    DCDB

    AHU for Control room

    Control & Relay Panel

  • 8/3/2019 Sub Station Design

    43/43

    SIEMENS

    THANK YOU

    For your Patience !