STUDY ON THE EXPANSION OF RAIL TRANSPORT ......Feasibility Study for Promotion of International...
Transcript of STUDY ON THE EXPANSION OF RAIL TRANSPORT ......Feasibility Study for Promotion of International...
Feasibility Study for Promotion of International Infrastructure Projects
in FY2011
STUDY ON THE EXPANSION OF RAIL TRANSPORT
CAPACITY FOR ROCK PHOSPHATE,
THE KINGDOM OF MOROCCO
FINAL REPORT
【SUMMARY】
November 2012
Prepared for:
The Ministry of Economy, Trade and Industry
Prepared by:
PACIFIC CONSULTANTS CO., LTD.
HITACHI, LTD.
TOSHIBA CORPORATION
1. Background and Necessity of the Project
In the output of phosphorus (phosphate rock), which is one of the three major ingredients of fertilizers,
Morocco is world number 3 (26.6 million tons) after China and the United States. As the United States
and China have a large population and therefore have export restriction, Morocco leaves the two
countries far behind international distribution. OCP (royal Moroccan phosphates company), a
monopolistic firm in the phosphate rock industry, has approved a mid and long term plan to increase its
phosphate rock production capacity from the current 28 million tons to 5.5 million tons, anticipating the
rise in the international market. Currently, OCP depends on ONCF for almost 100% of the
transportation from three mines, out of the four developed by OCP, to the ports of embarkation.
ONCF has allocated 39 electric locomotives to the phosphate rock transportation and secured around 30
million tons of annual transportation capacity. However, it is required to establish a plan to increase its
transportation capacity to respond to OCP’s plan to increase its production to 5.5 million tons.
Out of the total of 39 electric locomotives for phosphate rock transportation, 30 locomotives were
produced and delivered jointly by Hitachi and Toshiba through a yen loan. Although it has been over
30 years since the delivery, they are still highly reliable and the quality is highly valued.
The purpose of the project is to propose the best portfolio of locomotives owned by ONCF (optimal
assets of locomotives with a combination of new electric locomotives and existing Japanese ones with
repair and life-prolonging measures through examination of proposals for repair and life-prolonging
measures of the existing cars and procurement of new ones both from technical and cost points of view,
after investigating the details of OCP’s phosphate rock production and ore transportation plans for the
increase of ONCF’s phosphate rock transportation capacity.
2. Basic Policy to determine the Project Scope of
Work To determine the contents of the project, the study is conducted with following basic policies.
Analyze future outlook of phosphate rock production in Morocco.
Sort out requirements for railway freight transportation based on the result of the transportation
demand forecast.
Examine measures to increase transportation capacity of electric locomotives of Japanese make.
Selection of the best portfolio with a combination of new electric locomotives and existing
Japanese ones with repair and life-prolonging measures.
3. Project Overview
3.1 Actual Conditions and Future Prospects of Railway
Transportation of Phosphate Rock
3.1.1 Vehicle Ownership
Out of the 89 electric locomotives owned by ONCF, 39 locomotives are operated mainly for the
transportation of phosphate rock. 30 of them were made in Japan and delivered between 1977 and
1987.
While the Japanese locomotives take an important role in the transportation of phosphate rock, one of the
most important export items for Morocco, the average age of the locomotives is about to reach 30 years
old, which is generally considered as the end of the life. Therefore, there have recently been cases
where the service of these locomotives is suspended due to breakdown and measures are required.
Table 3-1 List of Electric Locomotives Owned by ONCF (delivered in 1977 and later)
Model Year of
delivery
No. of
cars Power Max speed Use Manufacturer
E1100 1977 22 2,850 kW 100 km/h Phosphate rock Hitachi
Toshiba (truck etc.)
E1200 1982 8 2,850 kW 100 km/h Phosphate rock Hitachi
Toshiba (truck etc.)
E1250 1987 12 3,900 kW 160 km/h Passengers Hitachi
E1300 1991 18 4,000 kW 160 km/h Passengers Alstom
E1350 2000 9 4,500 kW 120 km/h Phosphate rock Alstom
E1400 2010 20 5,500 kW 160 km/h Passengers and
containers Alstom
Note) Rows with thick frames: Locomotives for phosphate rock transportation
Source: Study team
3.1.2 Actual Situation of Phosphate Rock Transportation
According to the interview with the person in charge of freight operation management at ONCF
Casablanca Engine Depot, the actual situation of phosphate rock transportation is as below.
23 trains on average, 25 at maximum, are in operation every day for phosphate rock transportation.
The breakdown of the phosphate rock trains are 15-16 trains between Khouribga and Casablanca
Port/Jorf Lasfar Port and 8-9 trains between Ben Guerir and Safi Port.
The weight of a train is 4,800t. The empty weight of a 60-car train is 960t and the phosphate rock
load capacity per train is 3,840t.
A locomotive is operated for 1.5 cycles (1 cycle = from start point, Youssoufia, to end point).
The schedule of phosphate rock transportation is 6-7 days for a locomotive to pull freight cars, 1 day
for the push-pull operation from around Khouribga Station to the branch lines to the mines and
another extra day for rescue etc.
According to the interviews with the Freight Transportation General Manager of the Freight and
Logistics Bureau of ONCF and the Ben Guerir Office of OCP, the load capacity of phosphate rock
freight on the South Axis (Ben Guerir/ Youssoufia to Safi) is 3,600t/train. Therefore, we will use
this number for the following calculations.
Figure 3-1 Routes for Railway Transportation of Phosphate Rock
Source: Study team
ONCF has a plan to increase the operation to 19 round trips on North Axis and 10 round trips on
South Axis.
If the plan presented by the general manager in charge of phosphate rock transportation is
achieved, the transportation volume (mining volume) is estimated as below.
Table 3-2 Estimated Volume When Transportation Capacity Is Increased as Stated by General Manager
in Charge of Phosphate Rock Transportation in the Interview
Route No. of Trains/d Transportation
volume per train
No. of
operating
days
Estimated
transportation volume
(Estimated mining
volume)
Khouribga 19 3,800t 365
26.353M t/y
Ben Guerir 10 3,600t 13.14M t/y
Total 29 - - 39.493M t/y
Source: Study team
3.2 Outline of the Project
In this project, regarding the procurement of the required number of locomotives to increase railway
transportation capacity to meet the plan of future increase of phosphate rock production, we will set the
following three cases, and, through comparison, consider the most appropriate option (best portfolio) for
the procurement of locomotives for phosphate rock transportation.
(Scenarios for consideration)
Combination of rehabilitated locomotives and newly-built locomotives (Case 1) :Procure
rehabilitated locomotives of existing operable locomotives and make up for the gap with new
locomotives to secure the number of locomotives required by the beginning of 2020.
Use of new locomotives (Case 2): Procure as many new locomotives as possible by the
beginning of 2020 and make up for the gap with rehabilitation of existing operable
locomotives to secure the number of locomotives required by the beginning of 2015.
Combination of newly-built locomotives and rehabilitation (Case 3): Secure about half of the
locomotives required by the beginning of 2020 through rehabilitation and procure new
locomotives for the remaining half.
3.3 Project Costs Overview
The project costs of this project at 2011 are shown in Table 3-3 - Table 3-5.
Table 3-3 Project Cost (Case 1)
Initial Construction Cost 2014~2019 216 million US$
Additional Construction Cost 2030~2034 245 million US$
2046 35 million US$
2059~2061 93 million US$
2064 105 million US$
2075~2079 245 million US$
Source: Study team
Table 3-4 Project Cost (Case 2)
Initial Construction Cost 2014~2018 321 million US$
Additional Construction Cost 2048 139 million US$
2059~2063 321 million US$
Source: Study team
Table 3-5 Project Cost (Case 3)
Initial Construction Cost 2014~2018 253 million US$
Additional Construction Cost 2030~2033 163 million US$
2047 72 million US$
2059~2062 175 million US$
2063 67 million US$
2075~2078 163 million US$
Source: Study team
3.4 Preliminary Economic and Financial Analysis
3.4.1 Economic analysis
A comparative analysis of the costs and benefits both in the case of executing the project ("With
project") and not executing the project ("Without project") is carried out from the viewpoint of the
national economy. Costs of "With project" consist of investment costs (including additional iii
investment costs) and operation and maintenance (O&M) costs. The quantified benefits of Vehicle
Operating Cost (VOC) savings are estimated in the analysis.
The results of preliminary economic analysis are summarized in Table 3-6.
The EIRR obtained from the analysis is Case-1 40.4%, Case-2 34.4%, Case-3 36.3% . Compared with
the social discount rate of 5.2%, the project is deemed to be economically feasible.
Table 3-6 Results of Economic Analysis
(Social discount rate = 5.2%)
Case Economic Internal Rate
of Return (EIRR)
Benefit and Cost Ratio
(B/C Ratio)
Economic Net Present
Value (ENPV)
1 40.4% 9.3 24,010 million Yen
2 34.4% 9.0 23,830 million Yen
3 36.3% 8.9 23,820 million Yen
Source: Study team
3.4.2 Financial analysis
Financial Internal Rate of Return (FIRR) on Project (Project FIRR) from the viewpoint of efficiency of
investment is estimated as evaluation index. The Project FIRR is evaluated in comparison to the
Financial Opportunity Cost of Capital (FOCC). In the analysis, the Weighted Average Cost of Capital
(WACC) serves as a proxy for the FOCC combined with the financial sources. Table 3-7 shows the
results of financial analysis. As a result, the Project FIRR is found to be Case-1 37.3%, Case-2 36.4%,
Case-3 38.8% and is considered financially viable compared with 1.6% of WACC.
Table 3-7 Results of Financial Analysis
Case Financial Internal Rate
of Return (FIRR)
Weighted Average Cost
of Capital (WACC)
Financial Net Present Value
(FNPV)
1 37.3% 1.6% 822,250 million Yen
2 36.4% 1.6% 825,650 million Yen
3 38.8% 1.6% 821,820 million Yen
Source: Study team
3.5 Evaluation of Environmental and Social Impacts
3.5.1 Features of the Project
The Project is to rehabilitate and extend life of electric locomotives that are currently used for mineral
phosphate transportation and to introduce new electric locomotives to accommodate production increase
plan of the mineral resources in the future.
The motors used for the existing electric locomotives after the rehabilitation work for life extension and
those that are planned to be newly introduced are superior to DC motors that are currently used for the
existing locomotives in terms of power consumption and maintenance.
The project implementation shall have the following advantages:
Reduction of power consumption, which also results in reduction of greenhouse gas emissions
Reduction of failures of electric locomotives (improvement of operation rate)
Promotion of employment for rehabilitation and extension of life of existing locomotives and supply
of new locomotives
Increase in employment and GDP growth as a result of mineral phosphate production increase
planned by OCP
3.5.2 Project Effects of Environmental Improvement
(1) Study
Reduction of CO2 emissions of electric locomotives as a result of the Project implementation are
estimated. Estimation of CO2 emissions when all the railway transportation with the current electric
locomotives is replaced with truck transportation shows that the current railway transportation imposes
less environmental burden. The case study is shown as follows:
Case 1) Measurement of environmental advantage of current railway transportation
Truck
Transportation Assumption of 100% truck transportation
Railway
transportation
Assumption of 100% railway transportation
Assumption that all electric locomotives have DC motor
Source: Study team
Case 2) Measurement of environmental improvement effects of project implementation
Project is not
implemented
Assumption that all electric locomotives are not rehabilitated (DC motor)
Assumption that increased operations are replaced with truck transportation
Project is
implemented
Assumption of 100% railway transportation
Assumption that both rehabilitated and new locomotives have AC motor
Source: Study team
(2) Measurement of Project Effects of Environmental Improvement
Estimated CO2 emission by implementing of this project is about 76,000t-CO2/y. However, recently,
transaction price has been tumbling down. For example, as of July 2012, transaction price in
Nikkei-JBIC Carbon Quotation Index is 252 yen/t-CO2. This value is one fifth of transaction price as of
July 2011.
It will be difficult to apply this project to CDM from the aspect of yield.
Table 3-8 Measurement Results of Project Effects of Environmental Improvement
CO2 Emission
(t-CO2/y)
Present a. Transportation by Truck 490,055
(2012) b. Transportation by Railway 68,672
c. Environmental Contribution (=a-b) 421,383
Future d. NOT Implementing the project (Without Case) 140,580
(2020) e. Implementing the project (With Case) 64,239
f. Environmental Improvement (=d-e) 76,340
Source: Study team
4. Planned Project Schedule Figure 4-1 shows the planned project schedule.
Figure 4-1 Planned Project Schedule
Note: This table is shown the project schedule for 52 quantities of the
locomotives for both rehabilitation and new manufacturing.
Source: Study team
Des
ign
of
equ
ipm
ent
for
E1
200
,
E12
50
, an
d d
esig
n f
or
ou
tfit
tin
g
Equ
ipm
ent
man
ufa
ctu
rin
g f
or
mas
s p
rodu
cts
Man
ufa
ctu
rin
g f
or
pro
toty
pe
loco
Ap
pli
cati
on
of
yen
lo
an
New ManufactureRehabilitation
Ten
der
Pre
par
ato
ry S
urv
eyItem
Ou
tfit
tin
g f
or
mas
s p
rod
uct
s an
d
tran
sport
to t
he
Moro
cco
Des
ign
Ou
tfit
tin
g a
t lo
cal
Equ
ipm
ent
man
ufa
ctu
rin
g a
nd
tran
sport
to t
he
Moro
cco
Des
ign
and
man
ufa
ctu
rin
g o
f
equ
ipm
ent
for
E110
0 p
roto
typ
e,
and
des
ign
for
ou
tfit
tin
g
’20
’19
’18
’17
’16
’15
’14
’13
’12
Des
ign
of
equ
ipm
ent
for
E1
200
,
E12
50
, an
d d
esig
n f
or
ou
tfit
tin
g
Equ
ipm
ent
man
ufa
ctu
rin
g f
or
mas
s p
rodu
cts
Man
ufa
ctu
rin
g f
or
pro
toty
pe
loco
Ap
pli
cati
on
of
yen
lo
an
New ManufactureRehabilitation
Ten
der
Pre
par
ato
ry S
urv
eyItem
Ou
tfit
tin
g f
or
mas
s p
rod
uct
s an
d
tran
sport
to t
he
Moro
cco
Des
ign
Ou
tfit
tin
g a
t lo
cal
Equ
ipm
ent
man
ufa
ctu
rin
g a
nd
tran
sport
to t
he
Moro
cco
Des
ign
and
man
ufa
ctu
rin
g o
f
equ
ipm
ent
for
E110
0 p
roto
typ
e,
and
des
ign
for
ou
tfit
tin
g
’20
’19
’18
’17
’16
’15
’14
’13
’12 D
ec.
Ten
der
pre
par
atio
n
enfo
rcem
ent
Appra
isal
(Sep
t.)
Exchange
of
No
te,
Lo
an A
gre
em
ent
(Oct
.)
Ten
der
(Ja
n.)
Co
ntr
act
(Feb
.)
9m
on
th f
or
man
ufa
ctu
re,
1.5
mon
th f
or
tran
spo
rt
per
4 l
oco
moti
ve
3 m
on
th f
or
4 l
oco
E1100
Des
ign/M
anu
fact
ure
/Tra
nsp
ort
/Outf
itti
ng
/Tes
t ru
n
E1200
E1250
Aft
er c
erti
fica
tio
n,
sequenti
all
y
Manu
fact
uri
ng/O
utf
itti
ng/T
ransp
ort
atio
n
3 m
on
th f
or
4 l
oco
3 m
on
th f
or
4 l
oco
Des
ign/M
anu
fact
ure
/T
ransp
ort
/Outf
itti
ng
/T
est
run
Dec
.
Ten
der
pre
par
atio
n
enfo
rcem
ent
Appra
isal
(Sep
t.)
Exchange
of
No
te,
Lo
an A
gre
em
ent
(Oct
.)
Ten
der
(Ja
n.)
Co
ntr
act
(Feb
.)
9m
on
th f
or
man
ufa
ctu
re,
1.5
mon
th f
or
tran
spo
rt
per
4 l
oco
moti
ve
3 m
on
th f
or
4 l
oco
E1100
Des
ign/M
anu
fact
ure
/Tra
nsp
ort
/Outf
itti
ng
/Tes
t ru
n
E1200
E1250
Aft
er c
erti
fica
tio
n,
sequenti
all
y
Manu
fact
uri
ng/O
utf
itti
ng/T
ransp
ort
atio
n
3 m
on
th f
or
4 l
oco
3 m
on
th f
or
4 l
oco
Des
ign/M
anu
fact
ure
/T
ransp
ort
/Outf
itti
ng
/T
est
run
5. Technical Advantages of Japanese Companies Japanese manufacturers that are considering participation in the Project has supplied a total of 42 electric
locomotives to ONCF in three deliveries; 22 E1100 locomotives in 1977, 8 E1200 locomotives in 1982
and 12 E1250 locomotives in 1987.
Currently, out of the 89 electric locomotives owned by ONCF, 42, nearly half, are Japanese-made. There
are 22 E1100 electric locomotives, which is the biggest force among the 6 types of electric locomotives
owned by ONCF. (The second biggest force is 20 E1400 locomotives made in France.)
The two Japanese electric locomotive manufacturers who are considering participation in the Project
have ensured high reliability and safety of the railway vehicles delivered to customers inside and outside
Japan.
Based on the knowhow accumulated in Japan about the development and production of railway vehicles,
they develop and produce train vehicles for export. They can also deal with projects that require
compliance with international standards such as UIC (International Union of Railways) standards and
EN (European Standard), and specifications and safety performance required by the country of delivery
and the route of use.
Considering their past deliveries to ONCF from 1977 and recent order receipts from and deliveries to
other foreign countries, it is deemed that the companies have advantage in the supplier selection for
rehabilitation of existing Japanese electric locomotives and manufacturing of new ones for Morocco.
6. Project Location Map
Figure 6-1 Project Location Map
Source: Illustrated by Study Team based on OCP (Office Chérifien des Phosphates; The national Moroccan
phosphates company) publications, ONCF publications.
Main rock phosphate mines
Khouribga, Benguerir, Youssoufia
Main ports of shipment
Casablanca, Jorf Lasfer, Safi
Coastal fertilizer plant
Jorf Lasfer, Safi
Railway lines for
transportation of rock phosphate
Khouribga – Casablanca
Khouribga – Jorf Lasfer
Benguerir – Youssoufia – Safi
Jorf Lasfer
Casablanca
Safi
Khouribga
Benguerir
Youssoufia