Stream Companies Paid Search Process & Improvements North Hills Toyota – Pittsburgh, PA.
Stream Improvements Have Started!
Transcript of Stream Improvements Have Started!
The Montgomery County
Department of Environmental Protection (DEP) is restoring and stabilizing
the Hollywood Branch stream channel from Midland Rd to Cannon Rd.
WSSC is also making improvements in this area at the same time. The
State Highway Administration is improving the lower portion of
Hollywood Branch downstream of Cannon Rd as a separate project.
DEP will arrange a meeting with neighbors for each work area as
the project progresses. This will be an opportunity to meet the
project team, discuss construction details within that area, and
learn about the project in general. Please contact Jennifer St. John
below to confirm your interest and contact information.
Stream Improvements Have Started! STARTED
HOLLYWOOD BRANCH STREAM RESTORATION From Midland Rd
to Cannon Rd
Watershed Management Division Montgomery County Department of Environmental Protection 255 Rockville Pike, Suite 120 Rockville, MD 20850 www.montgomerycountymd.gov/dep
May - Jun 2014 (Phase 1)
Survey/ S i te set up /
Bu i ld access roads
Jun - Oct (Phase 2)
In-stream work
Oct - Dec 2014 (Phase 3)
P l ant ings / Cleanup
TENTATIVE SCHEDULE
MAY 2014
Meet the Project Team!
See Reverse Side for More Details!
Jennifer St. John, Watershed Planner 240-777-7740 office
301-674-8348 mobile [email protected]
Project Webpage: www.montgomerycountymd.gov/DEP/Restoration/hollywood-branch.html
Project Contact:
11
22
33
Watershed Management Division Montgomery County Department of Environmental Protection 255 Rockville Pike, Suite 120 Rockville, MD 20850 www.montgomerycountymd.gov/dep
APPROXIMATE TIMING
Jun to Sept 30 2014
*Work i n the s t r eam i s
r egu l a ted b y the MD Dept o f
Env i ronmen t (MDE) .
*Our pro j e c t i s l im i ted by a
s t r eam c lo sure per iod f rom
Oc t 1 to Apr i l 30 .
*We p l an to mob i l i ze mu l t i p l e
c rews i n order to f in i sh the
p ro je c t w i th in 2014 and , i f
n ece s s ar y , reque s t an
ex ten s ion o f work w i th i n the
MDE c lo sure per iod .
*Howeve r , i t i s pos s ib l e th a t a
por t i on o f the work w i l l
n eed to be comp le ted i n
Sp r i ng 2015 .
*Rega rd l e s s , p l a n t i n g s and
c l e anup work w i l l s t i l l o ccur
w i t h in comp le ted a re a s and
un f i n i shed ar ea s s t ab i l i z ed .
INSTREAM WORK
Project Work Areas
WORK HOURS (construct ion tra f f i c & no i se)
Mon-Fri 7:00am - 4:00pm Weekends & Hol idays* 9:00am - 4:00 pm *The County may author ize
work outs ide o f regu lar hours on rare occas ions when there have been
s ign i f i cant weather de lays
Jennifer St. John, Watershed Planner 240-777-7740 office
301-674-8348 mobile [email protected]
Project Webpage: www.montgomerycountymd.gov/DEP/Restoration/hollywood-branch.html
Project Contact:
Jun to Aug 2014
Aug to Sept
Sept to Oct
Temporary Access
1
2
3
4
5
6
HOLLYWOOD BRANCH STREAM RESTORATION