STIP Process Presentation
Lindsey Bruer
December 2018
![Page 2: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/2.jpg)
What is the STIP?
2
![Page 3: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/3.jpg)
How is it developed?
• Projects are selected by all of the following Central Office, Districts, Jointly and by ATPs
3
Central Office Districts Jointly ATPs
HSIP Non-NHS Pavements NHS Pavements Local Road & Bridge
Rail Safety Non-NHS Bridges NHS Bridges Transportation Alternatives
Rest Areas Roadside Infrastructure Transit (sometimes)
Noise Walls Preventive Maintenance
Historic Properties
Other Solicitations
![Page 4: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/4.jpg)
4
Priority Network for Investment:National Highway System (NHS)
![Page 5: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/5.jpg)
STIP timeline
5
Timeframe Activity
December District Funding Targets Announced
Jan - Feb Districts & CO Identify & Update Projects
March D8 Shares Draft ATIP with ATP
March – April Time for Public Input on Draft Projects & RDC Input Meetings
April ATP Meeting Vote to Approve Draft ATIP
April 15th District ATIPs Due to Central Office
Summer Final Edits to the STIP are Made
Fall The STIP is Submitted to FHWA & FTA
Mid-Fall/Early Winter STIP is Approved by FHWA & FTA
![Page 6: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/6.jpg)
ATP 8 ATIP
12/14/2018 6
![Page 7: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/7.jpg)
Statewide STIP
12/14/2018 7
![Page 8: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/8.jpg)
Can the STIP be changed?
• Yes
•Administrative Modifications
• Formal Amendments
8
![Page 9: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/9.jpg)
Formal Amendments
9
![Page 10: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/10.jpg)
Administrative Modifications
10
![Page 11: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/11.jpg)
Use of Scores & Transparency
• Based on legislative requirements, MnDOT will post:
• Criteria and methodology for all project selection processes
• Scores for all projects selected and evaluated but not selected
• The score assigned to candidate projects will be a key factor in project selection, but not all factors are quantifiable.
• When a high scoring project is not selected or when a lower scoring project is selected, MnDOT will provide a short explanation of the reasoning
11
![Page 12: STIP Process Presentation - Minnesota Department of ... Process Pres… · STIP Process Presentation Lindsey Bruer December 2018. What is the STIP? 2. How is it developed? •Projects](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fd5896ed3ddbc40c720161d/html5/thumbnails/12.jpg)
Questions?
Lindsey Bruer
District 8 Planning Director
320-979-5534