Stewardship Oversight Committee Project Delivery Design & Construction Performance Measures May...
-
Upload
lauren-lawrence -
Category
Documents
-
view
218 -
download
0
Transcript of Stewardship Oversight Committee Project Delivery Design & Construction Performance Measures May...
Stewardship Oversight CommitteeStewardship Oversight Committee
Project Delivery Design & Project Delivery Design & ConstructionConstruction
Performance MeasuresPerformance Measures
May 2012
3rd QTR SFY 12
2
% of Projects On Time for PS&E Acceptance% of Projects On Time for PS&E Acceptance(Statewide)(Statewide)
Metric Definition: Project no greater than 90 days over the target PS&E Acceptance date. Target PS&E acceptance date is currently defined as the target bid let date minus 45 days.
75% 81% 86% 82% 91% 88% 91%84%0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2005 2006 2007 2008 2009 2010 2011 2012
% On
Tim
e for
PS&
E
Statew ide Target
Statewide Proj. Count 60 64 71 50 90 66 59 54
3rd QTR SFY 12
3
% of Projects On Time for NTP% of Projects On Time for NTP(Statewide)(Statewide)
Metric Definition: Percentage of projects which reached NTP before their target bid-let date + 147 days. (Actual NTP < (target bid let date + 90 window + 57 days for NTP) = “on time”)
76% 82% 80% 77% 86% 90% 92% 89% 88%86%0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
% O
n Ti
me
Statew ide
Target
Statewide Proj. Count 21 104 90 66 71 50 82 72 57 42
3rd QTR SFY 12
4
% Preliminary Engineering (PE)% Preliminary Engineering (PE)(Statewide)(Statewide)
Metric Definition: Percentage of Preliminary Engineering = Design Cost divided by Total Project Cost
6% 9% 10%
8% 11%
12%
11%
15%
16%
7%11%
15%
16%
7%7% 0%7% 1%
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
State 2003 State 2004 State 2005 State 2006 State 2007 State 2008 State 2009 State 2010 State 2011 State 2012
% P
E
ALL No ARRA ALL ARRA PROJECTS Target
ALL 126 106 97 66 73 64 106 88 92 33
No ARRA 126 106 97 66 73 64 99 86 91 33
ALL ARRA PROJ ECTS 7 2 1 0
3rd QTR SFY 12
5
% of Projects Awarded Within Engineering % of Projects Awarded Within Engineering Estimate (Statewide)Estimate (Statewide)
Metric Definition: % of Projects awarded at no greater than or less than 10% of the Engineering Estimate.
59% 50% 46% 52% 26% 33% 30% 49% 23%50%
-11% -9% -8%-16% -17%
-22% -21% -20% -18%-9%
-40%
-20%
0%
20%
40%
60%
80%
100%
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
% W
ithin
Estim
ate
Within 10% of Eng.est.FHWA Target
% of Eng. Est:
% Eng. Est: Target
Statewide Proj. Count 121 106 93 69 74 54 94 80 80 40
3rd QTR SFY 12
6
Project Delivery Performance Measures -- BidProject Delivery Performance Measures -- Bid
3rd QTR SFY 12
7CONSTRUCTION PROJECT VOLUME1. How much has ODOT's construction program paid contractors
per calendar year?
3rd QTR SFY 12
8
CONSTRUCTION PROJECT VOLUME2. What is the value of ODOT's construction program awarded
to Contractors to build construction projects per calendar year?
3rd QTR SFY 12
9CONSTRUCTION PROJECT VOLUME3. What is the number of construction program projects with on site work
(2nd Note) completed during the calendar year?
3rd QTR SFY 12
10
TIMELINESS4. What percent of ODOT construction program projects completed
on-site work before the original contract completion date, and
before 90 days after the original contract completion date ?
3rd QTR SFY 12
11
QUALITY
5. For construction projects involving pavement that were
completed during the calendar year, what was the final
average pavement smoothness index? (Smaller is better)
3rd QTR SFY 12
12ENVIRONMENTAL
7. How many letters of non-compliance did ODOT receive
from regulatory agencies on ODOT construction contracts?
(Source: Statewide Permits Program Coordinator)
3rd QTR SFY 12
13
CONTRACT ADMINISTRATION10. At what level are the Construction claims being settled
based on the number of claims?
3rd QTR SFY 12
14CONTRACT ADMINISTRATION11. For projects with final payment during the calendar year,
what is the percentage of total project expenditures
vs. original construction authorization?
3rd QTR SFY 12
15
CONTRACT ADMINISTRATION12a. For projects with final payment during the calendar year,
what percent of total project costs were [CE / (TOTAL - CE)]
construction engineering expenses on all projects?
3rd QTR SFY 12
16CONTRACT ADMINISTRATION
13. For projects with final payment during the calendar year,
what was the average number of days per project between
on site work complete and final payment for normal Contracts?
Year Final # PM # LPM # PM w/C Excluded
2006 55 9 1051
2007 57 12 927
2008 55 14 235
2009 48 15 431
2010 39 35 948
2011 47 57 2241
Excludes projects with plant establishments, unusual labor compliance disputes and projects with non typical disputes preventing final payment.
3rd QTR SFY 12
17Contract Administration
13. Average No of CCOs/EWOs Processed per Project for Projects Finalized (Third Note)
1514
14
13 13
9
10
0
2
4
6
8
10
12
14
16
2005 2006 2007 2008 2009 2010 2011
3rd QTR SFY 12
18Contract Administration
13. Average No Materials Exceptions Processed per Project for Projects Finalized (Third Note)
0
0
0
0
0
1
1
1
1
1
1
2012 2013 2014 2015 2016 2017 2018
NO DATA GATHERED PRIOR TO 2012
3rd QTR SFY 12
19
Pavement Preservation Lane Miles
0
200
400
600
800
1000
1200
1400
1600
1800
2005 2006 2007 2008 2009 2010 2011
Lan
e M
iles
Chip SealPaving
3rd QTR SFY 12
20
Percent NHS Mileage with IRI < 95 in/miPercent NHS Mileage with IRI < 95 in/mi● 2005 - 2009 Data based on FHWA Highway Statistics Series Table HM-47 as ● 2005 - 2009 Data based on FHWA Highway Statistics Series Table HM-47 as collected and reported under the HPMS program. collected and reported under the HPMS program. ● 2010 data from Oregon HPMS submittal.● 2010 data from Oregon HPMS submittal.