Steering Committee Meeting Sunflower Project Statewide Financial Management System Update
description
Transcript of Steering Committee Meeting Sunflower Project Statewide Financial Management System Update
Steering Committee Meeting
Sunflower ProjectStatewide Financial Management System Update
September 11, 2009
2
Today’s Topics
• Project status and activities – Kent
• IV&V Report – Peggy
• Change control – Peggy
• Agency Interactions, Timelines & Upcoming Events – Gary
• Agency Reporting Strategy and Approach – Gary
• Measuring Progress – Gary
• Remaining Issues and Challenges – Gary
3
Project Timeline
August September October November December January February March
Config
ure
Syste
m, D
evelo
p M
ods
Develo
p Rep
orts,
Buil
d an
d Tes
t
Inte
rface
s, R
un D
ata
Conve
rsion
s
Begin
Syste
m T
estin
g
Agenc
y Role
Map
ping
Build Phase Test Phase
Busine
ss P
roce
ss W
orks
hops
Inte
rface
Tes
ting
Begin
User A
ccep
tanc
e
Testin
g
4
Completing:• defining and loading configuration values• change requests for remaining software mods• data conversion templates• security role definitions• functional designs for modifications
Continuing:• functional designs for reports • formulating preliminary cutover plan• support for training development and BPWs
Project Status & Activities – Finance Team
5
• Completed demos to facilitate agency decisions on de-commissioning systems (KDOR, SRS, KWP, Aging)
• Monitoring progress of agencies and completion of assignments• Five agencies are of concern; meeting with agencies’
leadership to resolve
• Conducted 12 of 18 business process workshops with agencies
• Developing training materials
• Continuing to recruit trainers, facilitators and facilities
• Evaluating help desk software and developing support processes
Project Status & Activities – Enterprise Readiness Team
6
• Developing technical designs and coding mods
• Developing remaining interfaces (mostly internal)
• Developing technical designs and coding reports
• Building and maintaining environments
• Implementing data warehouse including security based on requirements provided by functional team and agencies
• Beginning work on disaster recovery plan – will be working closely with DISC and A&R
Project Status & Activities – Tech Team
7
• A&R/DISC performing modifications to SHARP including data conversion – saving State approximately $200K
• Working with IBARS vendor to design modifications to support new chart of accounts
• Developing options for SHARP performance testing
Project Status & Activities – Central Systems
8
• Monthly forums to address issues and communicate with agencies for interfaces and conversions
• Continuing to review project plans to assess agencies’ progress and communicate early identification of problems
• Provided three briefings to DoA personnel
• Finalizing logistics with Washburn for remedial accounting course for agency personnel
• Determining the funding mechanism to support the services provided by the Service Center
• State “all hands” meeting held on August 28th
Project Status & Activities – Miscellaneous
9
• 3rd scheduled IV&V project review (Sys Test Labs – Denver)
• One week prep, one week on-site, one week to draft report
• Interviewed 32 project and non-project personnel
• Reviewed 35 documents (deliverables, risk log, issue log, project plan, status reports, requirements matrix, test scripts, etc.)
• Overall project health rated as “very good”
• Several recommendations provided:• Finalize status of remaining requirements prior to testing (7 out of 3,056
need to be to be approved and 72 out of 3,056 waiting approval)• Need to freeze agency-specific requirements• Improve configuration management plan for code migrations
IV&V Review, Findings and Recommendations
10
Change orders approved since last Steering Committee meeting
Change Control
No change requests over $50K since last meeting
Credits of $124K for change orders since last meeting
Change Request Tracking Report/Enhancement and Mod Effort vs Cost
Approval Date by CCB
Steering Comm.
Approval CR # CR Description Total Hours
Accenture Hours per
CRState Hours
per CR Total $ Cost
Accenture hours 71%
Contractual
State hours 29%
Contractual Contractual $
due
Overpayment / (Underpayment)
due to State hours
7/14/2009 N/A CR 88 1099 Processing for BPC 90 90 0 $ 17,505.00 64 26 12,428.55$ 5,076.45$ 7/21/2009 N/A CR 85 SHaRP Integration Mods 935 187 748 $ 36,371.50 664 271 129,118.83$ (92,747.33)$
8/4/2009 N/A CR 59 Outbound PO Receipt Interface Identifies 1 contingency interface needed by state hospitals8/4/2009 N/A CR 96 Voucher Origin Approvals 218 218 0 $ 42,401.00 155 63 30,104.71$ 12,296.29$
8/19/2009 N/A CR 53 Wildlife & Parks requirements Add Wildlife & Parks requirements to the RTM and identify 1 contingency interface8/19/2009 N/A CR 89 RTM updates Confirm updates to the RTM8/19/2009 N/A CR 97 Deposit Adjustment Approval 26 26 0 $ 5,057.00 18 8 3,590.47$ 1,466.53$ 8/19/2009 N/A CR 87 Remove Portal (257.07) (257.07) $ (50,000.00)
9/1/2009 N/A CR 8 Amends CR 8 originally approved 3/31/09 - deletes 3 complex and 2 average contingency reports9/1/2009 N/A CR 75 Amends CR 75 originally approved 6/23/09 - deletes 1 complex and 2 average contingency reports
9/1/2009 N/A CR 91 SHARP Conversion support $ 46,680.00
9/8/2009 N/A CR 83 Delivered Reports Identifies 81 delivered reports
9/8/2009 N/A CR102 Addl Interfund Training Design 80 80 0 $ 15,560.00 57 23 11,047.60$ 4,512.40$ 9/8/2009 N/A CR105 Cancel Deliverable 86 $ (73,716.00)
Total Hours/Dollars Used 20,278 16,407 4,089 3,191,161.50$ 14,580 5,955 Total Possible Hours/Dollars 19,130 3,720,785.00$
Remaining Mod Hours/Dollars 2,723 529,623.50$
Reserve created by de-scoped items 1,825 408,135.50$
Use Reserve for Payroll SME & SHARP Conversion (978) (190,190.00)$
Total "Bucket" dollars 847 217,945.50$
Percentage of effort by "team" 81% 20% 72% 29%
includes eGrants analysis, Purchasing modules,decrease in FARMS effort, RE Mgmt, Portal, Directory Interface, Portal Pack. Treasury Build/Unit Test
240 hours max for mock conversions, dry run testing & deployment
11
Change Control – Remaining Balance
• Balance of hours for customizations (including all customizations discussed today)
• Total Accenture hrs used = 16,407 (15,806 July)
• Total available contract hrs = 19,130
• % Used = 86% (83% last month)
• % Remaining = 14% (2,723 hours)
12
CR Req’d Estimated Cost
• Interfund Process – creating groups for notifications Yes < $30K
• Travel and Expense – payment method Yes $10K
• Travel and Expense - decentralizing Travel and Expense set up for traveler and approval Yes $40K
Data Warehouse• SHARP HR/Payroll data Yes TBD• Financial data Yes TBD
Note: May need additional CRs to address new or previously unidentified requirements that don’t surface until testing
Change Control – Remaining CRs
13
• Meetings held with agencies:• Health Policy Authority
• Department of Revenue
• State Treasurer
• KU and KUMC (separately)
• Regents (collectively)
• SRS & State Hospitals
• Wildlife and Parks
• Corrections
• KPERS
• and many others
Agency Interactions
14
Conversion and Interface Timelines
2009Apr/May/Jun Jul/Aug/Sep Oct/Nov/Dec
Agency Interface/System Modifications
Connectivity Testing
Conversion Build and Unit TestConversion Build and Unit Test
Conversion Assembly Test
Conversion Assembly Test
Mock 1 Conversion Test
Mock 1 Conversion Test
Extract Conversion DataExtract Conversion Data
Conversion Data CleansingConversion Data Cleansing
InterfaceTesting Cycles
15
Upcoming Events
September Monthly Conversion Technical Meeting
Business Process Workshops
Change Agent Network Meeting #5 – 09/30
Data Warehouse Advisory Group – 09/26
October Monthly Interface Technical Meeting
16
Agency Reporting Strategy & Approach
Objective: Identify and resolve critical agency reporting gaps
• Background • Over 150 reports will be available for agency use at go-live
• However, some agencies may have reports or data feeds that will not be fully replaced by the new reports
• Developed an approach to address and resolve go-live agency reporting gaps
• Piloting this approach with several large agencies (SRS, KDOR, DOL) prior to rolling out Statewide
17
Step 1 – Agencies list reports that are critical to perform the agency’s Day 1, go-live business processes
Step 2 – Agencies compare reports identified in Step 1 with list of reports available in SMART and identify reporting gaps
Step 3 – Sunflower Project Team reviews agencies’ high priority reporting gaps to determine if:
• A delivered report meets the reporting need• If a report can be built by the agency in the data warehouse• If a report is not available in the data warehouse and will need to be developed
by the Project Team• Team will document their determination for each reporting gap and return the
information to the agency
Note: Medium and low priority reporting gaps will be addressed after go-live using a process to be determined
Agency Reporting Strategy & Approach
18
If a report can be built by the agency in the data warehouse:
• Agency identifies at least one agency person to build and test these reports prior to go-live
• Agency report developer attends mandatory training on the data warehouse and the reporting tool
• Agency report developer will have access to a report development lab to create and test their reports
• Agency must have sufficient data in the system to develop their reports (interface testing, conversion, on-line entry)
• Agency develops lower priority reports after go-live
Agency Reporting Strategy & Approach
19
Measuring Progress
• Tech Team (Accenture and State) are working OT
• No impact on key milestones or the “go-live” date
Scope Element07/09Status
09/09Status Detailed Status/Corrective Actions
Test Scripts Cycles 1 and 2 Yellow Complete
Configuration Data Entry Green Yellow Finance Team is approximately 60% complete vs. 80% planned. Finance Team is dedicating time to complete remaining tasks over next 2 weeks.
Functional Design Reports Yellow Yellow Finance Team is approximately 50% complete vs. 80% planned. Finance Team continuing to work on report designs, but focus is on mod designs due to impact on testing. Additional reports added to queue (not included in stats). Report design and development will be an on-going challenge.
Functional Design Modifications
Green Green Finance Team has been focusing on designs for mods for past 1.5 months – 95% complete vs. 98% planned. This activity was falling behind schedule since last SC meeting but corrective action was taken to regain the schedule.
Interface Design Phase 1 Green Complete
Interface Design Phase 2 Red Yellow Tech Team is approximately 75% complete vs. 85% planned.
Data Conversion Yellow Yellow Tech Team is approximately 35% complete vs. 82% planned. There are 9 conversion programs: 3 in review, 5 in development, 1 not started. Testing schedule is staggered to accommodate staggered development
Business Process Workshops
Green Green
Training Phase 1 Green Complete
Training Phase 2 Green Green
20
Remaining Issues and Challenges
• Technical resources barely adequate to complete remaining development work in scheduled timeframe
– Accenture brining on additional technical resources– State re-assigning team member from coordinator role to developer role– Making minor changes to testing schedule to accommodate late mods
• Finance Team continues to be stretched and will remain very busy for next 6-8 months
• In general, most agencies continue to be good partners – complete assignments, provide feedback and attend meetings and workshops
– Small number of agencies consume inordinate amount of time– Review status reports each month and follow-up on issues– Large interfacing agencies (KDOT, SRS, KDOR and KHPA) are making good
progress on system modifications and interface development– Approximately 50% of agencies are behind schedule in asset conversions
• Continue to retain 2 months of schedule contingency for disaster recovery testing and operational readiness testing
21
Recently Resolved Issues and Challenges
• Data warehouse team lacked project management, technical resources and functional support
• Corrective actions taken over past two months:– Replaced key consultant– Brought in a senior manager and developed detailed project plan– Reviewed resource requirements– Adding additional data modeler and Business Intelligence consultant– State coordinating scope definition and security requirements
22
Questions and Answers
??For additional information on the project, please seethe project website: http://da.ks.gov/smart
23
Authority for Change Requests
Change Request
Authority Cost Impact Scope Impact Impact on PS Code
Base
Schedule Impact Agency Impact Law, Reg, Policy Impact
Level 1Executive Sponsors TBD TBD Any change affecting
the “Go-live” dateTBD Any changes affecting
laws, regulations or other non-A&R policies
Level 2Steering Committee Changes over $50K “Significant” impact on
project scope (+/-)TBD Recommends changes
to Executive Sponsors
Level 3FMS Mgmt Team (CCB) Changes under
$50K“Moderate” impact on project scope (+/-)
All mods approved by FMS Mgmt Team
Any change affecting KITO milestones or other key (internal management) milestones
Any decisions/ changes “adversely” affecting agencies
Any changes affecting A&R policies and procedures
Level 4 ManagersAll changes affecting cost (+/-) approved by FMS Mgmt Team
“Minor” impact on project scope (+/-)
“Minor” impact on project activities that do not adversely impact a milestone
Configuration decisions benefiting agencies that do not impact cost or do not impact a milestone