Status Report of BepiColombo MPO
Transcript of Status Report of BepiColombo MPO
BepiColombo: ESA – JAXA mission to explore Mercury
Status Report of BepiColombo MPOStatus Report of BepiColombo MPO
Harri Laakso and Johannes BenkhoffESA/ESTECNoordwijk, The Netherlands
SERENA Team Meeting, 24-27 August 201011 / 14
Noordwijk, The Netherlands
BepiColombo - dual spacecraft missionMercury Planetary Orbiter (MPO)• 3-axis stabilized spacecraft on
polar orbit optimized for study of the planet itself
• 400x1500 km• 400x1500 km• 2.3 hr period
Mercury MagnetosphericOrbiter (MMO)• Spin-stabilized spacecraft on polar
orbit optimized for study of the magnetosphere
• 400x12000 km
SERENA Team Meeting, 24-27 August 20102
• 400x12000 km• 9.2 hr period
• avoid exact 1:4 synchronisation of MPO/MMO for science reasons
� Launch: 19 July 2014 on Ariane 5� 6.3 year cruise to Mercury by electric
SERENA Team Meeting, 24-27 August 20103
Rocket: Ariane 5 ECATotal Launch mass: 4200 Kg
� 6.3 year cruise to Mercury by electric propulsion
� Earth, 2 Venus, 4 Mercury flybys/gravity assists
Arrival at Mercury
� Arrival in November 2020
� Gravity capture into Mercury orbit � chemical propulsion
� Final Mercury orbit adjustment� Final Mercury orbit adjustment
� Injection of the MPO and MMO into their respective orbits
� Start of science mission: Feb 2021
� Prime mission through Feb 2022� Extended mission through Feb 2023
SERENA Team Meeting, 24-27 August 20104
Project Schedule
SERENA Team Meeting, 24-27 August 20105
� TOP PRIORITY: To keep the schedule for launch in 2014� Hardware procurement ongoing in support of STM and ETB
integration in 2010� Schedule margins for P/L are decreasing
BepiColombo Status
� Schedule margins for P/L are decreasing� STM delivery due 1 Sep 2010
• all compatible (with adjusted dates)
� EM delivery due 1 Aug 2010
• one instrument compatible with this; the rest marginal or non-compliant
� EM campaigns close to STM activities – manpower issues
SERENA Team Meeting, 24-27 August 20106
� FM delivery due 26 Jan 2012
• all P/L marginal; few already known non-compliant
STM/EM AIV ActivitiesMPO mock-up
� MPO Mock-up ready for AIT
� Instrument support required for EM AIV
� The initial setup comprises:
� MPO P/L (one at a time)MPO P/L (one at a time)
� OBC, SSMM, MPO-RIU
� POWER FE (instead of PCDU)
� See parts 12 and 16 in EID-C for the
format/content of
test procedures
� Both STM and EM
SERENA Team Meeting, 24-27 August 20107
� Both STM and EM
integrations start
in Sept 2010
� Instrument I/F temperatures � out of specification temperature for some instruments at perihelion;
e.g. Strofio by 6ºC at PH
� Particle contamination from MLI
BepiColombo Payload Issues
� Particle contamination from MLI� Power
� 140/180 Watts to operate all payload cannot be guarantee at all times
within a Mercury Orbit
� Perihelion power problems reported earlier may have disappeared,
details to be presented in SWT (Graz)
� Data Downlink baseline 1550 Gbits/year
SERENA Team Meeting, 24-27 August 20108
� Data Downlink baseline 1550 Gbits/year� Note: D/L needs power (another ground station would increase D/L, but
would require twice as much power, and if limited power available, …)
Science Activity Timeline
45
135
BC#2 – night to day terminator
(20 days)
Flip-over Flip-over
BC#1 – perihelion
(16 days)
Eclipses start 2 days
before this season and
end 2 days after
BC#3 – aphelion
(32 days)
• Eclipses occur
during all of this
season (max 42
min)
Flip-over Flip-over
SERENA Team Meeting, 24-27 August 20109
225315
BC#4 – day to night terminator
(20 days)
• Flip-over (~30 min)
in eclipse
Science profile / downlink / SSMM
297.9414
16
18
300
350
400
Sciene data profile DL capabilityPeripelion AphelionStart science @ 19.02.2021 SSMM nominal operationSSMM 10d non coverage
D/L Capability and SSMM Usage
Best D/L rates
2
4
6
8
10
12
Gb
it p
er d
ay
50
100
150
200
250
Dat
a in
SS
MM
(G
bit
s)
SERENA Team Meeting, 24-27 August 201010
0
2
01.0
1.20
21
02.0
4.20
21
02.0
7.20
21
01.1
0.20
21
01.0
1.20
22
02.0
4.20
22
0
50
� collect instrument operation information from the teams � build up a database of all payload operations and measurements
we plan to perform
MPO Science Operations Activities
� based on these information, the following activities done by the SGS� science activity plan� baseline analysis (study various operational cases in order to
deal with operational constrains or reduced resources)� defining a planning concept� defining a data handling and archiving concept
SERENA Team Meeting, 24-27 August 201011
� defining a data handling and archiving concept
BC-MESSENGER Joint Activities
� Standing invitations to team meetings
� BC: Sendai ‘08, Blois ‘09, Seggau Castle ‘10
� MESSENGER: Boulder ‘08; Providence ‘09, Columbia ‘09, Cambridge ‘10� MESSENGER: Boulder ‘08; Providence ‘09, Columbia ‘09, Cambridge ‘10
� BC-MESSENGER Workshops (annual/biannual)
� 1st workshop on “The surface composition of Mercury from UV-Vis-IR”, University of Parma, Italy, 3-5 June 2009
� 2nd workshop on “Exploring Magnetosphere-Exosphere Coupling at Mercury”, Boulder, USA, 2-5 Nov 2010
� Co-Organize Mercury sessions at major science conferences:
� EUROPLANET, COSPAR, EGU, AGU
SERENA Team Meeting, 24-27 August 201012
� EUROPLANET, COSPAR, EGU, AGU
Summary
�BepiColombo spacecraft development on track and on schedule for a launch in 2014
�First hardware has been build and will be tested after summer �First hardware has been build and will be tested after summer 2010
�Science Operations Concept under development
SERENA Team Meeting, 24-27 August 201013