Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury...

24
Status of the CW ERL Cryomodule at Daresbury Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration

Transcript of Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury...

Page 1: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Status of the CW ERL Cryomodule at Daresbury

Shrikant PattalwarASTeC, STFC, Daresbury Laboratory (UK)

ERL-2013, September 9-13, Novosibirsk

On behalf of ERL Cryomodule Collaboration

Page 2: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Introduction

Design – Assembly

Offline Tests

Integration and Commissioning

Future Plans

OUTLINE

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 2

Page 3: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Introduction

The aim – To build and test the ERL Cryomodulewith beam on ALICE

Accelerator and Lasersin Combined Experiment

Dimensioned to fit on the ALICE ERL facility at Daresbury:– Same cryomodule footprint.– Same cryo/RF interconnects.– ‘Plug Compatible’ with

existing cryomodule

Introduction

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 3

Page 4: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Existing Cryomodule on ALICE

Parameter TargetFrequency (GHz) 1.3

Number of Cavities 2

Number of Cells per Cavity 7

Cavity Length (m) 0.807

Cryomodule Length (m) 3.6

R/Q (Ω) 762

Eacc (MV/m) >20

Epk/Eacc 2.23

Hpk/Eacc 46.9

CM Energy Gain (MeV) >32

Qo >1010

Qext 4 x 106 - 108

Max Cavity FWD Power (kW) 20 SW

Introduction -The ERL Cryomodule

CW-ERL Cryomodule

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 4

Page 5: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

1. High Power Input couplersCornell ERL injector coupler

2. Modified Saclay-II tunersWider aperture.Low voltage piezo cartridges.

3. HOM absorbersCornell ERL injector CM with

Ferrite Absorbers (@ 80K)

4. Several thermal transitions(intercepts) cooled by GHe

80-5-2 (K) 2-5-80 (K)2-5-80-5-2 (K)

2580

Introduction - Major Variations in the Design

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 5

Page 6: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

5. Radiation Shield, HOMs and thermal intercepts cooled with GHe

6. Additional thermal management scheme

7. Additional Instrumentation

Introduction - Major Variations in the Design

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 6

Page 7: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

• Check the cryogenic performance •Understand the processes and establish commissioning and operating procedures • Validate instrumentation• Make the task of integration with ALICE easier• Identify and resolve any unknown issues

Off-line Cold Tests

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 7

Page 8: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Parameters Measured* Specification

Static Heat Load at 80K (HOMs, Thermal shield and intercepts.)

~ 7 W 20W

Static heat losses for the cavities at 80K ~ 3.5 W 15 W at 4K

Delta T across thermal shield at equillibrium < 5K <10K

Delta T across the two cavities during cooldown

< 5K

< 5KCurrently 50K to 60K for ALICE

Cavity Temperatures

12 hrs

Calibration error

Off-line Cold Tests – with LN2

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 8

Page 9: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

• Lowest temperature ~ 8K • Large Temperature gradient between the two cavities• Helium Reservoirs do not fill together• .......• Most of the issues can be attributed to high static heat load

( ~ 50W ) present during the testsdue to non ideal conditions and floating components

• Heat leak will be much lower (< 5W) during actual operation

50

150

100

T_C1

Off-line Cold Tests – with LHe4

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 9

Page 10: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Integration and Commissioning – Installation on ALICE

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 10

Page 11: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

• Input He gas at 300 K, maximum 10 bar, 10 g/SLHe at 4 K

• Output He gas at 5 – 6 K, 5 W, ~ 5 barHe Gas at 80 – 90 K, 175 W, ~ 5 bar

• Only one control valve for the operation with HOMs as primary cooling load• Operation fully independent of ALICE Cryo-system (except for LHe and LN2 supply)

• Three main components – Heat Exchanger Box, A compound transfer Line (TLx), and a LHe transfer line (TLy)

Integration and Commissioning – COOL-IT(Providing Cooling Power at Intermediate Temperatures)

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 11

Page 12: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Additional port To feed new gas lines into the Cryomodule

Integration and Commissioning – Cooling Circuits

Two Cooling Circuit in Series ->> >> >> >>

Coupler Intercepts Cooled by Conduction

HOMs at 80-90 KHOM at 5-6K Shield 90-100 K

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 12

Page 13: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Concept Design Build

Integration and Commissioning – COOL IT evolution

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 13

Page 14: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

TCF 502K BOX 1500 L Dewar NEW LINACBOOSTER

COOL-IT

Integration and Commissioning

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 14

Page 15: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Preliminary cool down

•Cryomodule cooled to 2K•Static heat load measured at 2K~ 6W

Similar to previous cryomodule, Spec- 15W•Base heat load measured at 2K ~ 2.5 g/s

Similar to previous cryomodule•Intermediate Temperatures has been achieved with GHe using COOL-IT

Gas pressure ~ 2 barA•HOMs, coupler intercepts and thermal shield are connected in series

• Circuit 1: Tin ~ 89K , Tout ~ 99K• Circuit 2: Tin ~ 13.5K , Tout ~ 15.5K

•Pressure stability at 2K (30mbar) ±0.05 mbar

Further optimisation is in progress

Cryomodule

COOL‐IT

TCF 50

2K  Box

Dewar

Integration and Commissioning – ALICE Cryogenics

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 15

Page 16: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

COOL DOWN to 2K295 K

2.0 K

Cryogenic (Pressure) Stability at 2K

Liquid Helium levels in Reservoirs Cavity 1

Cavity 2

Cavity 1 Cavity 2

Cavity 1 Cavity 2

Level Control Valve

130 K2 ½ days to 130 K

15 hrsto 4K

3 hrs to 2K

3K/hr (Cooling only by radiation and conduction through supports)

Service Reservoir

Integration and Commissioning – CM Cryogenic Performance

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 16

Page 17: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

• Static heat load measured with all the input valves closed to ensure that only the boil off from the cryostat is measured

• 0.6 g/S total mass flow Linac + Booster0.3 g/S per module~6.2 W per cryomodule

Integration and Commissioning – CM Static Heat Load at 2K

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 17

Page 18: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

• Linac 1 • Linac 2

• Cavity tuner operation verified• Tuning achieved• Tuning range ±350 kHz• Qext adjusted• Full extent of adjustment to be

determined

Previous mechanical issue

Integration and Commissioning – Cavity Frequency

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 18

Page 19: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

• Original Linac• The microphonics were tested in

CW mode, open loop operation. • Cavity was driven by signal

generator • A Hittite phase detector was used

to measure the phase difference between the cavity probe signal and the system generator signal.

• New ERL Linac• The new ERL cavities were driven

with a CW wave from the digital LLRF system. The cavity probe signal is then mixed with the forward RF signal and filtered by a low pass filter.

• The cavities have been analysed in self excited loop and open loop operations.

Based on the LLRF4 development board, designed by Larry Doolittle of LBNL

Integration and Commissioning – Microphonic Tests

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 19

Page 20: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

• Open loop operation, strong resonances have been observed at:-1Hz, 7Hz , 21.5Hz, 23.5Hz, 35Hz, 48Hz, 68Hz, 71Hz, 78Hz, 82Hz, 98Hz, etc.

• Loop closed, resonances remain at 1Hz, 37.5Hz, 50Hz and its side bands.

Detuning peaks at 22Hz, 70Hz,63Hz,139Hz,386Hz.

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1-2

-1.5

-1

-0.5

0

0.5

1

1.5

t(s)

Ph

i(de

gre

es)

Linac Cavity II Static Frequency Detuning Measurement

0 50 100 150 200 250 300 350 400 450 50010

-4

10-3

10-2

10-1

100

frequency(Hz)

FF

T(p

ha

se)

Linac Cavity II Microphonics Spectrum 70Hz22Hz

139Hz 386Hz

0 50 100 150 200 250 300 350 400 450 500-120

-110

-100

-90

-80

-70

-60

-50

-40Cavity II Microphonics detuning measurement

frequency (Hz)

ampl

itude

(dB

)

closed loop measurement

open loop measurement

Integration and Commissioning – LINAC Cavity 2

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 20

Page 21: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Integration and Commissioning – Cryogenic Performance

Parameter Unit Measured Value

Spec

Base temperature K 2.0 2.0Static heat load W 6.2 15 Single shot mode at 2KStatic base heat load g/S 2.5 1.5 With flash gas (additional heat

leak from external components)Pressure stability mbar ±0.05 ±1.0 at 2KHOM Intercepts K 13.5 < T < 15.5 < 20 CKT -1 at GHe 2.0 barAHOM Intercepts K 89 < T < 99 < 90 CKT -2 at GHe 2.0 barAShield K 89 < T < 99 < 90 CKT -2 at GHe 2.0 barACavity Frequency GHz 1.3 1.3Tuning range KHz ±350Dynamic performance to be measuredStatic performance similar to ALICE LINAC

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 21

Page 22: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Integration and Commissioning – Status

Held up due to major blockage in helium liquefier (TCF 50).

Operation expected to resume inmid October

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 22

Page 23: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

Evaluation Programme:-•Establish gradient and Q0•Measure Lorentz force detuning at high gradient •Performance measurements with piezo tuners •Determine DLLRF control limitations wrt Qext•Evaluate the effect of beam loading with DLLRF, piezo control for various Qextlevels under pulsed and CW conditions•Characterise cavities in CW mode at high gradient:

– Evaluate thermal transients across cavity string and 2-phase line

Cryomodule installed on ALICE

Integration and Commissioning – Future Plan

ERL’13 September 9-13, 2013, BINP- Novosibirsk Shrikant Pattalwar 23

Page 24: Status of the CW ERL Cryomodule at Daresbury · Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) ERL-2013, September 9-13, Novosibirsk On behalf of ERL Cryomodule Collaboration.

2007

2012

2010

2009

2010

2010

2011

Thank You

2013