Start with a Vision in Mind BP Greater Plutonio Project
description
Transcript of Start with a Vision in Mind BP Greater Plutonio Project
Start with a Vision in MindStart with a Vision in MindBP Greater Plutonio ProjectBP Greater Plutonio Project7th April 2005
PELC Conference 2005
Andy TillAngola DCT Program ManagerBP Exploration
2
BackgroundBackground
Block 18 – 6 deepwater fields operated by BPFPSO – Floating production, storage & offloading vessel300m Long , 250kbbls / dayEPCm contract with Kellogg Brown & Root, UKFPSO Hull built by Hyundai Heavy Industries, KoreaFirst Oil Q2 2007BP investment of $3.3b
3
Learning CycleLearning Cycle
PlanningStandardsSpecifications
DoingContractsData Collection Tools
ReflectingAssuranceAudit
LinkingCleansingCorrectionVision
Planning
4
GPP Information management GPP Information management (Planning)(Planning)
Define Statement of Requirements during early stages of project (pre-feed)
Agree standards i.e. ISO 15926Agree project data and document requirements
Write the requirements in to the contractHandover requirements (Responsibilities / Accountabilities)Detailed standards (numbering / handover)
Clear Data ModelEarly Visibility of Data
5
Core Data ModelCore Data Model
6
Data CollectionData Collection (Doing) (Doing)
ICT
Phasset
Oracle Data Vault
Document Vault
Document Vault
Documentu
m
KBR
Oracle Data Vault
Supplier Electronic Documents
SDRL Document Register
EIHS Templates and SDRL Data Requirements
Import or Data Entry
Document Posting/ Review
Suppliers
Propid
P-H
Document Meta-Data
Engineering Data & Relationships
Supplier SDRL Documents
- Processes
V
7
Close collaboration with: (Reflecting)Close collaboration with: (Reflecting)
KBR – EPCm ContractorPearson-Harper – Validation and Content & Data Collection ToolAveva – 3D Model & Engineering Portal
People Process
Technology
8
The Learning Cycle (Revised)The Learning Cycle (Revised)
9
What is your paradigm?What is your paradigm?
Electronic Data & DocumentsSingle windowGlobal Access
10
Status of deliverablesStatus of deliverables
11
ConclusionConclusion
Write requirements in to the contract (2 Years 3 months to polish the data)Comprehensive information set available for HUC and Operations (required detail in EIHS) Confidence the information set will be complete for 1st Oil (data has been validated)Any electronic system is only as good as the data entered (consistency and cleansing)Angola has only scratched the surface of possibilitiesHave a Vision
People Process
Technology
12