STAGE I DESIGN REPORT PRELIMINARY STRUCTURE REPORT…€¦ · STAGE I DESIGN REPORT ... Recommended...

147
ROUTE 617 (BACKLICK ROAD) OVER CSX RAILROAD PROPOSED BRIDGE REPLACEMENT Fairfax County, Virginia Virginia Department of Transportation – Northern Virginia District State Project 0617-029-344, P101, C501, B642 Federal Structure Identification Number 25341 UPC Number 110156 STAGE I DESIGN REPORT PRELIMINARY STRUCTURE REPORT, PLANS, AND ESTIMATES Prepared for the Virginia Department of Transportation Northern Virginia District Structure and Bridge Division Project Manager and S&B Coordinator: Shahrad Behboodi Submitted by PRIME AE Group PRIME AE Group Project No. PEI-VAT1457 LOA04 November 18, 2016

Transcript of STAGE I DESIGN REPORT PRELIMINARY STRUCTURE REPORT…€¦ · STAGE I DESIGN REPORT ... Recommended...

ROUTE 617 (BACKLICK ROAD) OVER CSX RAILROAD PROPOSED BRIDGE REPLACEMENT

Fairfax County, Virginia

Virginia Department of Transportation – Northern Virginia District

State Project 0617-029-344, P101, C501, B642 Federal Structure Identification Number 25341

UPC Number 110156

STAGE I DESIGN REPORT PRELIMINARY STRUCTURE REPORT, PLANS, AND ESTIMATES

Prepared for the

Virginia Department of Transportation Northern Virginia District Structure and Bridge Division

Project Manager and S&B Coordinator: Shahrad Behboodi

Submitted by

PRIME AE Group PRIME AE Group Project No. PEI-VAT1457 LOA04

November 18, 2016

Stage I Bridge Report Summary Form

Project Name: Replacement of Rte. 617 (Backlick Road) over CSX Railroad Date: 11/18/2016

Fed Structure ID (New) TBD UPC: 110156

Fed Structure ID (Exist) 25341

State Project Number: 0617-029-344, P101, C501, B642

County of: Fairfax District: Northern Virginia

Facility Carried: Rte. 617 Over CSX Railroad

This project is programmed for Federal Aid. Funding Source: State

Federal Project Number: TBD Federal Oversight: TBD

Prepared for the

Virginia Department of Transportation

Structure and Bridge Division Shahrad Behboodi, S&B Coordinator & Project Manager, (703)-259-2304

Submitted by

Steve Mackey, PRIME AE Group (703)-364-5562

Recommended Bridge Structural Summary:

Superstructure: Type: Multi-beam steel plate girder with composite concrete deck Units: One simple span unit Span Layout: 135’-0” Skew Angle: 22° Material – Steel (ASTM A709 Grade 50W) Superstructure width has been selected using: P=24 ft. Left Shoulder=2 ft. Right shoulder=2 ft. Median= ft. A Design Exception is not required There is 1 lane in each direction.. Through lane width is 12'. Total Pavement +Shoulder Width – 28'-0" face-to-face of curb and rail Parapet or Rail Type - BR 27 series, 42” high, Test Level TL-4 Bridge Deck Width (Bridge Surface Width): 45'-2" Out to Out of Deck width Pedestrian and Bicycle facilities do not meet shown in Volume 5 Part 2 Chapter 20 A Design Waiver is required Transverse Joint Type(s) - Structure will be Jointless Structure meets requirements for a jointless structure shown in Volume 5 Part 2 Chapter 17. A Design Waiver is not required Deck Width meets limitations in I&IM 80, a Longitudinal Joint is not required. A Design Waiver is not required

Substructure: Proposed Abutment A Type – Semi-Integral with MSE Wall Proposed Abutment B Type – Semi-Integral with MSE Wall Proposed Pier Type(s) – N/A Piers N/A be designed for collision. Pier protection N/A required. Proposed Foundation: Deep foundations (piles)

Clearances: Minimum Vertical Clearance: - 24’-3” Minimum Horizontal Clearance: - 25’-0”

Bridge crosses Railroad track(s). Geometry allows for 3 track(s)

Preliminary Hydraulic Analysis: Freeboard above design flood (25 Year) – N/A If 100 year storm floods bridge include: N/A Return Period of roadway flood event: N/A years

Scour at this location has not been computed. Scour is not expected to effect foundation design. A Design Waiver is not required

Recommended Bridge Cost Summary:

Estimated Costs*: The costs below represent Structure and Roadway/MOT. Estimated Cost of recommended layout - $7,625,300 bridge+related cost impacts. Ratio of recommended layout to lowest cost alternative considered: 1.00 Cost/SF this layout: $1,250 for bridge+related cost impacts. Estimate is not based on Trnsport. The detailed cost estimate is not included with the supplemental data.

This recommendation is the lowest cost structure solution. Justification for a cost differential is not presented in the narrative appendix. (*Estimated Cost does include Preliminary and Construction Engineering as well as 20% Contingency.)

Bridge Alternatives Developed:

Bridge Alternative forms are attached. Bridge Alternatives are presented in the Stage I Report.

Special construction Considerations:

Aesthetics - Aesthetic requirements are not anticipated Stage Construction - Stage Construction is not anticipated

Roadway Coordination Data Summary

Data not shown is provided on roadway plans provided as supplementary data Recommended structure will not be functionally obsolete. Based on Roadway Plans dated: On Bridge

Current ADT(year): 2200 (2015) Design ADT(year): (Not Available)

% Trucks: 25% Design Speed: 30 mph Posted Speed: (35) mph, See Stage I Report for more details

Reduced Design Speed (if applicable) N/A Is the road carried on the NHS? No

Functional Classification: Urban Local Street Min. Design Standard: GS-8 Existing Dimensions 2' - 24' - 2' Proposed Dimensions 2' - 24' - 2'

Max Grade -7.00 % Profile type Hump Vert Curve Under Bridge N/A (if applicable)

Current ADT(year): ( ) Design ADT(year): ( )

% Trucks: Design Speed: mph Posted Speed: mph

Reduced Design Speed (if applicable) Is the road under on the NHS?

Functional Classification: Min. Design Standard: Existing Dimensions Proposed Dimensions

Max Grade % Profile type The geometrics of the road approaching the structure include the position and alignment of the approach guardrail, if applicable. When bridge is an overpass then lateral clearances beneath the structure constitute part of the control geometrics and must be shown. If an existing structure at this site is to remain in place, its primary geometrics and its dimensional relationship to the proposed structure are included in the data.

Recommended Bridge Geometrics Summary: Geometrics: This project must meet

Low Volume Road Standards RRR Stds VDOT Road Design Manual and AASHTO Green Book AASHTO Green Book only (First Cities)

PM 100 attached Scoping Report Attached Current Road Plans Attached

Roadway width conforms to Volume 5 Part 2 Chapter 6 File No. 06-02-07 which controls the design. A Design Waiver is not required.

Roadway includes provisions for bicycles, Roadway is a shared roadway no modification to geometrics is required Roadway is a signed shared roadway Bicycle Lane is designated by striping, signing and pavement markings. Parapets and lane widths conform to the requirements of Volume 5 Part 2 Chapter 6. A Design Waiver is not required.

Pedestrian facilities are included: Sidewalk(s) does not meet requirements of Volume 5 Part 2 Chapter 6 are met; a 54” crash tested railing has been provided. A Design Waiver is required.

Bridge is on horizontal curve or within 200ft of PC/PT: Stopping sight distances meet requirements of Volume 5 Part 2 Chapter 6.

A Design Waiver is not required. See the preliminary structure report for additional information regarding the Design Waiver.

Data Sources: Data from the following sources was considered in the development of this report

Environmental Sources CE EA EIS other

L&D Sources Roadway Design Plans Traffic Engineering Reports

Surveys Bridge Situation Plan Topographic survey and bathymetric/hydraulic datum references Other survey information (scour, utility, etc.) Hydraulics/Hydrology

Bridge Sources Existing Bridge Plans (Insert Structure Number and Plan Number, Year Built) Existing Bridge Inspection Report(s) Other

Geotechnical sources Existing Geotechnical Information (From project site, nearby bridges, roadway

borings, geologic maps, etc.) Project Specific Geotechnical

Meeting(s) (Localities, District, Residency, etc.) (dates on for these are critical) Localities District Residency Other

Other Sources FHWA Recommendation (Rehabilitation vs. Replacement) Site Visit Other

Approval of Recommended Bridge:

Project Name Replacement of Rte. 617 over CSX Railroad Date: 11/18/2016

Fed Structure ID TBD UPC: 110156 Federal Oversight TBD

State Project Number: 0617-029-344, P101, C501, B642 Federal Project Number: TBD

County of: Fairfax District: Northern Virginia Funding Source: State

Facility Carried: Rte. 617 Over CSX Railroad

Recommended for Approval By:

Date: District Bridge Engineer Remarks:

Approved:

Date: Assistant State Structure and Bridge Engineer Remarks:

Approval not Required::

Date: State Structure and Bridge Engineer Remarks:

Approval not Required:

Date: FHWA Virginia Division Bridge Engineer Remarks:

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

i

TABLE OF CONTENTS 1.0  INTRODUCTION ............................................................................................................................... 1 

1.1  AUTHORITY .................................................................................................................................. 1 

1.2  PROJECT PURPOSE ................................................................................................................... 1 

1.3  ROADWAY FUNCTIONAL CLASSIFICATION INFORMATION .................................................. 1 

1.4  ROADWAY GEOMETRY .............................................................................................................. 1 

1.5  DATA SOURCES .......................................................................................................................... 2 

2.0  DESIGN CRITERIA ........................................................................................................................... 2 

3.0  SITE DESCRIPTION ......................................................................................................................... 2 

3.1  PROJECT LOCATION .................................................................................................................. 3 

3.2  GEOTECHNICAL DESCRIPTION ................................................................................................ 3 

3.3  UTILITIES ...................................................................................................................................... 5 

3.4  TRAFFIC IMPACTS AND MOT OPTIONS ................................................................................... 6 

3.5  ROADWAY DESIGN ..................................................................................................................... 8 

3.6  ENVIRONMENTAL ISSUES ....................................................................................................... 10 

3.7  HYDROLOGIC AND HYDRAULIC ISSUES ............................................................................... 10 

3.8  ROADWAY DRAINAGE .............................................................................................................. 10 

3.9  STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL, AND PERMITTING .. 11 

3.10  CULTURAL RESOURCES ......................................................................................................... 11 

3.11  RAILROAD ISSUES .................................................................................................................... 11 

3.12  CONSTRUCTABILITY ISSUES .................................................................................................. 12 

3.13  AESTHETIC CONSIDERATIONS ............................................................................................... 13 

4.0  REMOVAL OF EXISTING BRIDGE ................................................................................................ 13 

5.0  BRIDGE TYPICAL SECTIONS ....................................................................................................... 14 

6.0  BRIDGE PRELIMINARY DISCUSSION ......................................................................................... 15 

6.1  ALTERNATE 1 – 168’-0” SINGLE SPAN BRIDGE ON EXISTING ABUTMENT PILES ............ 16 

6.2  ALTERNATE 2 – 135’-0” SINGLE SPAN BRIDGE ..................................................................... 17 

6.3  ALTERNATE 3 – 182’-0” (45’-92’-45’) THREE-SPAN BRIDGE ................................................. 18 

6.4  ALTERNATE 4 – 135’-0” SINGLE SPAN BRIDGE UTILIZING ABC METHODS ....................... 19 

7.0  RECOMMENDED ALTERNATE ..................................................................................................... 21 

8.0  ENGINEER’S COST ESTIMATE .................................................................................................... 21 

9.0  SCHEDULE ..................................................................................................................................... 22 

ATTACHMENT 1 – PROJECT LOCATION MAP ATTACHMENT 2 – STAGE I PRELIMINARY ROADWAY SKETCHES ATTACHMENT 3 – STAGE I PRELIMINARY BRIDGE SKETCHES ATTACHMENT 4 – ENGINEER’S COST ESTIMATES ATTACHMENT 5 – STAGE I PRELIMINARY BRIDGE PLANS FOR RECOMMENDED ALTERNATE ATTACHMENT 6 – TRAFFIC IMPACT STUDY – EXECUTIVE SUMMARY ATTACHMENT 7 – ABC CONSTRUCTION TIME ESTIMATE OF ALTERNATE 4 ATTACHMENT 8 – STORMWATER COMPUTATIONS ATTACHMENT 9 – BRIDGE ALTERNATES MATRIX AND MOT OPTIONS MATRIX ATTACHMENT 10 – UTILITY CONFLICT MATRIX

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

1

1.0 INTRODUCTION

1.1 AUTHORITY

This study was authorized by the Structure and Bridge Division of the Virginia Department of Transportation (VDOT) as part of the design services for the replacement of Route 617 (Backlick Road) Bridge over CSX Railroad, Fairfax County (State Project No. 0617-029-344, P101, C501, B642). The VDOT Project Manager and Structure & Bridge coordinator is Shahrad Behboodi, and he can be contacted at VDOT’s Northern Virginia District at (703) 259-2304 and [email protected]. PRIME AE Group is to provide the Stage I bridge design services per Letter of Agreement No. 4, dated August 15, 2016 with VDOT.

1.2 PROJECT PURPOSE

The purpose of this project is to replace the existing two-lane prestressed concrete girder bridge that carries Backlick Road over CSX railroad with a bridge that accommodates the addition of a third CSX railroad track. Additionally, the new bridge will correct the existing substandard vertical clearance above the active CSX railroad tracks and increase the vertical clearance to accommodate the potential future electrification for the CSX railroad as part of the Atlantic Gateway Project, which includes the DC to Richmond Southeast High Speed Rail project. The new structure will be designed and constructed to meet current applicable standards.

The scope of work for this project consists of a Stage I preliminary structure report, with supporting documentation and recommendations for review. Preliminary roadway plans have also been developed for Backlick Road. The results of the preliminary design are discussed herein.

1.3 ROADWAY FUNCTIONAL CLASSIFICATION INFORMATION

The VDOT functional classification of Route 617 over CSX Railroad is Urban Local Street. The current average annual daily traffic (AADT) is estimated to be 2200 vehicles per day (from VDOT, Traffic Engineering Division 2015) with approximately 25% truck traffic. According to the VDOT standards for Urban Local Street the required design speed is 30 mph. The current posted speed limit along northbound Backlick Road at Cinder Bed Road is 35 mph.

1.4 ROADWAY GEOMETRY

The alignment along Backlick Road is assumed to run north-south for layout and reference purposes. Roadway plans have been prepared for four bridge alternates with consideration of three maintenance of traffic options. The existing horizontal alignment consists of a tangent section within the project limits with the exception of a curve on the northern end of the project where Backlick Road terminates into a private commercial property. The existing vertical alignment is on a large vertical curve over the existing bridge. The horizontal alignment will be maintained in the proposed condition and the vertical alignment will be raised to accommodate the required vertical clearance over the proposed location of the CSX tracks. Two vertical alignments have been evaluated that work in partnership with the proposed bridge alternates. The proposed Stage I roadway sketches are provided in Attachment 2 of this report.

The existing posted speed limit on Backlick Road northbound at Cinder Bed Road is 35 mph. However, per VDOT standards and as-builts (Project 0617-029-328, C501, B619) sheet 24 of 34, the design speed for this section of the roadway is 30 mph. Therefore, a design speed of 30 mph was used for the geometric design of the roadway.

Preliminary Field Inspection (PFI) plans are being developed by PRIME AE Group and will be submitted to VDOT after the submission of the final Stage I Design report. The PFI plans provide specific information regarding the approach roadway geometry.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

2

1.5 DATA SOURCES

The following data sources were used in the development of this report:

Existing As-builts (Year Built: 1998)

Structure Inspection Report, Agency ID 0296106-0000000025341 (02/27/2016)

Field notes and project meeting minutes

Structure Selection Report (by HDR Engineering, Inc., August 2016)

Rail Plan and Profile (provided by HDR Engineering, 08/16/2016)

GIS/LiDAR Data for Existing Topography (provided by VDOT)

DC to Richmond Southeast High Speed Rail Basis of Design Report (DPRT, 02/24/2016)

Fairfax County Parkway Corridor Study, Final (by Kimley Horn, September 2015)

Fairfax County Parkway Record Plans (Project No. R000-029-F49, PE 105

2.0 DESIGN CRITERIA

The following design criteria were used to develop the Stage I Report and preliminary bridge plans:

AASHTO LRFD Bridge Design Specifications, 7th Edition, 2014

VDOT Modifications to AASHTO LRFD Bridge Design Specifications (IIM-S&B-80.5) dated August 25, 2015

VDOT Road and Bridge Standards, Vol. I and Vol. II, 2016

VDOT Road and Bridge Specifications, 2016

VDOT Manual of the Structure and Bridge Division, Volume 5, Part 2 – Design Aids & Typical Details.

VDOT Road Design Manual, Vol. I (January 2005), revised July 2016

VDOT Drainage Manual, Adopted April 2002, latest revision Effective July 2016

VDOT Work Area Protection Manual (WAPM), 2011 and revised April 2015

CSXT Engineering and Operating Standards, November 2014

AREMA MRE 2014 Edition

Load and Resistance Factor Design

Design Capacity of HL-93 Loading and 75 psf Pedestrian Load

3.0 SITE DESCRIPTION

The existing bridge and approach roadway is a two-lane lane facility located in an industrial area. The roadway is classified as an Urban Local Street with a posted speed limit of 35 MPH. The roadway runs from north to south while the railroad also runs from north to south.

The existing 165 foot three-span structure was constructed in 1996, and consists of prestressed concrete I-beams on a 22-degree skew to normal. The existing bridge consists of three spans (45’-6”, 74’-0”, 45’-6”), as measured along the centerline of Rte. 617. The bridge carries two travel lanes of Rte. 617 (Backlick Road) and a shared use path over CSX Railroad. The stationing of the roadway along the bridge runs from Abutment A on the north end to Abutment B on the south end.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

3

The travel width of the existing bridge is approximately 30’-0” measured face-to-face of curbs with an out-to-out width of approximately 44’-10”. The shared use path (SUP) is 10’-6” wide and separated from the northbound lane by a barrier. There is no sidewalk next to the southbound lane.

There are no utilities attached to the existing bridge structure, but there are overhead utility lines parallel to and approximately 25 feet west of the bridge. There is also an underground fiber optic cable running parallel to the railroad located to the east of existing Pier 2. The land in the immediate vicinity of the project is generally wooded, however there are some industrial and commercial businesses located nearby.

3.1 PROJECT LOCATION

The bridge is located on Route 617 over CSX Railroad approximately 300 feet east of the Route 286 (Fairfax County Parkway) and Route 617 (Backlick Road) intersection in Fairfax County. The bridge is approximately 0.8 mile from Interstate 95 to the north. The project location map is provided in Attachment 1 of this report. The proposed bridge will be constructed in the same location as the existing bridge.

3.2 GEOTECHNICAL DESCRIPTION

Based on the data available in the existing as-built plans, including the existing boring logs, it has been determined that the substructure units for the new bridge replacement structure will be founded on deep foundations (most likely piles).

Per the existing as-built plans, the bridge is supported on HP12x53 piles. The average pile lengths for Pier 1 and Pier 2 are 23.6 and 26 lineal feet, respectively. The average pile lengths for Abutment A and Abutment B are 41.9 and 39.7 lineal feet, respectively.

The as-built plans indicate eight (8) borings were completed for the current bridge with the boring depths ranging from 45 feet to 80 feet. The prepared logs indicate the subsurface profile generally contains interlayered silt, clay, and sand with all borings terminated on dense or very hard strata conditions. All borings were terminated without refusal and no rock coring was performed. Seasonal ground water conditions in the area of the pier foundations was measured within the upper 3 feet; in the area of the abutment foundations, ground water was measured at various depths ranging from approximately 15 feet to 44 feet.

Based on the pile lengths and the reported subsurface conditions, all piles for the current bridge structure were driven to practical refusal.

Minimum Preliminary Geotechnical Scope of Work for Backlick Road Bridge Replacement:

1. The number of borings for bridge structure foundations should adhere to Chapter III of the VDOT Manual of Instructions (MOI). Abutment borings shall extend to a minimum depth of 80 feet or auger refusal with continuous SPT sampling performed in the upper 10 feet and at 5-foot interval, thereafter. Abutment borings may be terminated at 80 feet if “N” values are greater than or equal to 50 for 3 consecutive 5-foot sampling intervals. If auger refusal occurs, borings shall be extended a minimum depth of 10 feet using rock coring methods. Percent recovery, RQD, RMR value, rock type, joint/fracture conditions, etc. should be included.

Soil borings and testing for retaining walls should also be in accordance with Chapter III of the VDOT Manual of Instructions (MOI). Borings should extend to a minimum depth of 25 feet or auger refusal with continuous SPT sampling performed in the upper 10 feet and at 5-foot interval, thereafter.

Groundwater measurements and/or boring cave-in depths should be taken at completion and following minimum 24-hour stabilization period.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

4

Boring locations shall be surveyed and staked with lat/long coordinates and ground elevations.

2. Laboratory Analyses: Soil classifications (Atterberg Limits and Grain Size Analyses) performed for each soil

type encountered (minimum 10 analyses). Natural moisture analyses performed on all SPT samples. Standard Proctor(s) and soil classifications (Atterberg Limits and Grain Size Analyses)

analyses performed on representative samples that may be used for backfill of structures.

3. Notify Miss Utility or private locater to mark all underground utilities prior to subsurface investigation.

4. Minimum reporting requirements: A plan of boring locations. A log showing the strata encountered for each boring and N-values. Laboratory test data. Subsurface conditions – soil, rock, and groundwater. Preliminary foundation recommendations with respect to foundation type(s) and

bearing capacity, H-piles, drilled shafts, micro-piles, etc. MSE and/or retaining wall construction recommendations: bearing capacity, earth

pressures, backfill requirements, etc. Temporary shoring recommendations. Global slope stability analyses and slope construction recommendations. Groundwater control and dewatering recommendations. Estimated settlements for foundation structures. Estimated time-rate of settlement. Future construction considerations with respect to existing below grade foundations. Other relevant information specific to the site.

Recommended Preliminary Minimum Geotechnical Scope of Work for Backlick Road Roadway Improvements:

1. A minimum of 4 borings (1 in east bound and 1 in west bound lanes for each approach). Borings should extend to a minimum depth of 10 feet or auger refusal with continuous SPT sampling performed. Existing pavement sections (base stone and pavement thickness) should be verified.

Groundwater measurements and/or boring cave-in depths should be taken at completion and following minimum 24-hour stabilization period.

Boring locations shall be surveyed and staked with lat/long coordinates and ground elevations.

2. Laboratory Analyses: Natural moisture analyses performed on all SPT samples. Standard Proctor, soil classifications (Atterberg Limits and Grain Size Analyses), and

CBR analyses should be performed on representative samples that may be used for backfill of structures and bridge approach subgrades (minimum 2 samples).

3. Notify Miss Utility or private locater to mark all underground utilities prior to subsurface investigation.

4. Minimum reporting requirements: A plan of boring locations. A log showing the strata encountered for each boring and N-values. Laboratory test data.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

5

Subsurface conditions – soil, rock, and groundwater. Earthwork recommendations and fill placement requirements. New pavement design recommendations. Other relevant information specific to the site.

Final Geotechnical Scope of Work for Backlick Road Bridge Replacement:

Update and submit final report following review and comments pertaining to preliminary geotechnical report. Report to include:

Additional soil boring/testing results, if required. Final foundation recommendations. Procedures and monitoring criteria for installation of selected deep foundation system. Final revisions as necessary to address review comments.

All investigative procedures, laboratory analyses, and reporting requirements for subsurface investigations should adhere to applicable sections as outlined in Chapter III of the VDOT Manual of Instructions (July 2016). Any access to the CSXT right-of-way for soil borings, survey, or other data collection shall be coordinated directly with CSXT via the CSX website.

3.3 UTILITIES

The existing utilities shown on the plans were captured from the SU files provided by VDOT, field investigations, and the 1995 Fairfax County Parkway plans. The existing bridge does not carry or support any utilities, and there are unknown overhead utility lines parallel to and approximately 25 feet west of the bridge. Based on the field investigations, these lines are likely telephone and or cable TV. These lines run parallel to Backlick Road and are underground but then turn-up utility poles at the end of the bridge before crossing over the CSX Railroad. Based on the alternatives reviewed in this study, the overhead lines will likely require relocation to facilitate bridge construction but we will revisit in more detail when the utility designation is completed and an Alternate is selected.

There is also an underground fiber optic cable that runs parallel to the railroad tracks and is located approximately 10 feet south of existing Pier 2. The exact location of this utility is currently unknown, but a Utility Survey, including test pits, has been ordered. It is anticipated that relocation of this utility will be very costly and require a significant splice. It is known that the three span alternate will require this utility line to be relocated due to the proposed placement of the piers. The single span alternates can likely be constructed without impacting the line. The future grading of the embankment slope, which will occur when the existing tracks are shifted and the third railroad track is constructed, will possibly expose the fiber optic line and require it to be re-buried or relocated. There is a possibility that there are one or two additional underground utilities located adjacent to the railroad tracks. The existence and location of these other utilities will be determined with the Utility Survey. Only the utilities that interfere with construction of the bridge will be relocated to accommodate the bridge. Utility relocation will not be done for utilities that will be impacted by the track improvements.

After the utilities are designated and shown on the plans, a Utility Field Investigation (UFI) will be held to start relocation work if utility relocation is needed. Any pipeline/wireline facilities to be installed, modified, removed, or retired in place within the CSXT right-of-way must be coordinated directly with CSXT Property Services.

In addition, the roadway approach construction creates conflicts with existing lighting, signal hand boxes, traffic signal controller cabinets, and underground telephone. To assist VDOT review of the utilities, we have included a Utility Conflict Matrix (see Attachment 10) that indicates anticipated utility conflicts along the project limits. This will be updated upon receiving the Utility Designation File and used to establish future utility test pit locations.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

6

3.4 TRAFFIC IMPACTS AND MOT OPTIONS

Backlick Road at the crossing of the CSX railroad is a lightly travelled roadway with an Average Daily Traffic (ADT) of 2,200 vehicles per day (vpd). The peak hour volumes measured in September 2016 are generally less than 200 vehicles per hour (vph) for the peak direction.

The area that is served by Backlick Road is an industrial and commercial area with high truck volumes. Other than Backlick Road, access to the area is limited to Newington Road. Newington Road connects on the west through a one lane CSX underpass, and to the east through a residential neighborhood.

A traffic study was conducted, and submitted to the Department on October 6, 2016, to determine the congestion impacts of a full closure of Backlick Road at the CSX Railroad crossing versus the impacts with a multi-staged construction approach. The executive summary of the traffic study is included for reference in Attachment 6 of this report. The study concluded:

“Backlick Road at the bridge over CSX railroad is a lightly used local roadway. In addition, a large portion of the traffic on Backlick Road and Newington Road is external “cut through” traffic; some of this traffic will divert to other roadways during bridge construction.

Staged construction will allow traffic to continue over the CSX Railroad during construction. Two alternatives are possible with only minor impacts to traffic flow. However, staged construction will either necessitate one way operations or removing pedestrian access. Two way operations with pedestrian access is not feasible.

A full closure of the bridge is not expected to create significant congestion along the proposed detour route. Furthermore, conditions on Fairfax County Parkway and other primary routes are not expected to be significantly affected.”

At this time no decision has been made as to whether a full closure with detour or staged construction will be implemented. The Traffic Study analyzes the congestion impact of the full detour and staged construction options and is provided separately. This document shows plans for each of the options and summarizes the advantages and disadvantages of each.

There are three general Maintenance of Traffic (MOT) options; full closure with detour, staged construction with one lane and pedestrian access, and staged construction with two lanes open. The MOT option utilizing staged construction with one lane and pedestrian access was evaluated for two variants. Both variants of this option are discussed within this section of the report. The remainder of the report will refer to the three general MOT options. The following MOT options have been evaluated:

MOT Option A: Full Closure and Detour.

MOT Option B1: One Lane – Alternating Two-Way Traffic, with Pedestrian Access.

MOT Option B2: One Lane – Two-Way Traffic by time of day, with Pedestrian Access.

MOT Option C: Two Lanes, without Pedestrian Access.

MOT Option A: Full Closure and Detour.

To implement this option, a more extensive community outreach program will be necessary to inform Newington area businesses and the Newington residential area. A limited community has been conducted to date. Access to the spur from Backlick Road to Fairfax County will also be closed.

The detour from Fairfax County Parkway will be to Loisdale Road to Newington Road to Cinder Bed Road. This detour directs traffic through the CSX underpass on Newington Road.

The existing bike and pedestrian trail will not be maintained. The trail is lightly used and there are no residential bike and pedestrian generators located nearby. Bus service does not use

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

7

Backlick Road. This portion of the trail is part of a larger County network and it is possible that bike or hike hobbyists rely on the crossing.

To maintain pedestrian access over CSX Railroad three alternatives are available: Construct a temporary pedestrian bridge to the south (between Backlick and Fairfax

County Parkway); Provide a protected area in the shoulder of the Fairfax County Parkway for bike and

pedestrian use. Shuttle bike and pedestrian users around the construction.

Advantages of Option A: Reduced project duration and construction cost. Reduce risk and improved safety to construction workers and motorists. Reduced environmental impacts from less complicated construction and fewer

vehicles in construction area. Reduced construction cost due to reduced bridge width. Bridge width will be 45’ (+/-).

Disadvantages of Option A: Detour will have modest effect on area congestion (see Traffic Study). Lack of egress from Newington area. Egress will be limited to the CSX underpass or

the Newington residential area. No bike or pedestrian access.

MOT Option B1: One Lane – Alternating Two Way Traffic, with Pedestrian Access.

Each of the staged construction alternates consist of several bridge and roadway pavement phases. Preliminary plans of these phases are in Attachment 2.

Phase I will consist of demolition of a portion of the existing bridge and construction of a 27 foot (+/-) section of new bridge in the space of the demolition. In Phase II traffic will shift to the new 27-foot section of bridge and the remainder of the existing bridge will be demolished. Following demolition construction of the remainder of the new bridge will commence.

This staged option will require a temporary signal at each end of the bridge. Traffic will alternate between northbound and southbound. The type of actuation has not been determined. During low volume periods predetermined time splits will most likely be used.

Bike and pedestrian access will be maintained via a 5-foot sidewalk through the work zone.

Advantages of Option B1: Maintains bike and pedestrian access. No detour of traffic.

Disadvantages of Option B1: Increased risk to workers and motorists than detour. Longer project duration and greater construction cost than detour. Temporary traffic signal needed. Traffic heading southbound is expected to create queues that may block through traffic

on Fairfax County Parkway. Wider bridge width. The final bridge width will be 57 feet (+/-).

MOT Option B2: One Lane – Two Way Traffic by time of day, with Pedestrian Access.

This option is identical to MOT Option B1 with regards to the construction process; however, this option will not use a temporary signal. Traffic will travel southbound between 5am and 2pm and northbound during the remainder of the day.

Detours will be necessary for the direction of traffic not served. The detour will be the same as the detour for MOT Option A. Pedestrian access will be via a 5-foot sidewalk.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

8

Advantages of Option B2: Maintains bike and pedestrian access. Traffic heading SB not expected to queue or block Fairfax County Parkway traffic. No need for temporary traffic signal.

Disadvantages of Option B2: Detour by time of day necessary. Potentially confusing signing and marketing

necessary. Increased risk to workers and motorists than detour. Longer project duration and greater construction cost than detour. Wider bridge width. The final bridge width will be 57 feet (+/-)

MOT Option C: Two Lanes, without Pedestrian Access.

The construction process for this option is identical to the other staged alternates. However, traffic control is much simpler in that there is no need for a regular detour or a temporary signal.

This option uses the same general width of roadway for Phase II. As such there is not enough width for a bike pedestrian lane during Phase II. To maintain bike and pedestrian access, the same alternatives as shown in MOT Option A will be used.

Advantages of Option C: Best vehicular capacity over bridge; most similar to current conditions. Signing and marking less complicated.

Disadvantages of Option C: Increased risk to workers and motorists than detour. Longer project duration and greater construction cost than detour. No access for bike or pedestrians. Widest bridge width. Final bridge width will be 61 feet (+/-).

It is likely that there will be the need for a short term full closure of the roadway and bridge even with staged construction (MOT Options B and C). With Alternative 2 the profile is approximately 6 feet (+/-) above the current roadway. During phase 3 of the construction, 27 feet (+/-) of new bridge and adjacent roadway will be constructed. Both will be on the higher profile than the existing bridge and roadway.

Before traffic can be placed on the new bridge and roadway, a portion of the existing connector road will also need to be raised to prevent a drop off in grade. During this sub-phase, traffic will not be able to travel on the new bridge or the existing bridge.

The time to build up the roadway to eliminate the drop off will depend if this construction is temporary or permanent. It is expected that the full closure with staged construction will be more than 3 weeks.

3.5 ROADWAY DESIGN

A 30 mph design speed has been used for the geometric design of the roadway. However, since the posted speed limit of 35 mph is greater than the design speed due to the current roadway classification, a speed limit study should be considered.

Roadway Typical Section:

The roadway typical section consists of a normal crown with two 12’-0” lanes, 4’-0” paved and 4’-0” grass shoulders on the southbound roadway, and a 2’-0” combination curb and gutter on the northbound roadway. In addition, the existing 8’-0” wide shared use path (SUP) will be reconstructed with 3’-0” grass buffer behind the curb on the northbound roadway. The shared use path width will transition from 8’-0” along the roadway to 15’-6” on the bridge approaches.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

9

The basic roadway typical section is 30’-0” wide between the face of curb and edge of the paved shoulder. The bridge typical section is discussed in more detail in Section 5.0.

To validate the proposed typical section and roadway geometry, WB-67 truck turning simulations were performed using the Auto-Turn software. The turning movement wheel path for the worst case scenario is shown on the roadway plans (see Attachment 2). Large trucks traveling southbound are unable to clear their rear wheels without encroaching on the northbound lanes. The situation exists for all of the bridge alternates and is marginally improved for Alternate 2. Features to provide more room for southbound trucks will be added in final design. A wedge at the northwest corner of the bridge may be necessary.

The roadway typical section at both bridge approaches will vary from 28’-0” to 43’-6” depending on the maintenance of traffic (MOT) options used (see Table 3-1). The additional pavement width proposed for the MOT Options B and C will occur on the west side of the alignment and will improve the southbound truck turning movement from Fairfax County Parkway.

Maintenance of Traffic Options

Typical Section Clear Width at Bridge

Approaches (All Alternates)

Meets the Minimum Width Required for the

Proposed WB67 Truck Maneuvering?

Option A – Detour 28 ft.- 0 in. No. Wedge may be

required.

Option B – Staged Construction with One-Lane, Two-Way Traffic

38 ft.- 8 1/2 in. Yes, with widening to west

of current centerline.

Option C – Staged Construction with Two-Lane, Two-Way Traffic

43 ft.- 6 in. Yes, with widening to west

of current centerline.

Table 3-1

Horizontal and Vertical Alignments:

The proposed horizontal alignment will follow the existing alignment. It consists of a tangent section within the project limits followed by a 500 foot radii curve on the northern end of the project where Backlick Road terminates into a private commercial property. The existing horizontal alignment meets the AASHTO requirements.

The existing vertical alignment is on a large vertical curve, 480 feet, over the existing bridge. The post construction vertical alignment will be raised to provide for the required vertical clearance over the proposed location of the three CSX tracks. Two vertical alignments have been evaluated for the post construction condition: a) Optimum Profile and b) Higher Profile.

The Optimum Profile will correspond to Alternate 3 only due to a shallower superstructure depth requirement. The proposed Optimum Profile will consist of a 160-foot crest curve on the bridge with the tangents extending towards the north at a (+)1.1% grade and towards the south at a (-)6.5% grade. The proposed vertical alignment will meet the AASHTO and VDOT Road Design Standard GS-8. The Optimum Profile will be approximately 3’-6” higher than the existing profile near the south end of the bridge. The overall profile grades for the Optimum Profile will remain in the same direction as existing and will cause relatively less grading impacts on the roadside grading. The Optimum Profile will necessitate the roadway reconstruction of 25 feet on the north and 200 feet on the south along the Backlick Road. The remainder of the approach roadway, approximately 200 feet on the north and 100 feet on the south, and the entire Backlick Connector Road will be milled and overlaid.

The Higher Profile will correspond to Alternates 1, 2 and 4 due to the longer spans and deeper superstructure depth requirements. The proposed Higher Profile will consist of 250-foot crest curve on the bridge with the tangents extending towards north at a (+)1.0% grade and towards the south at a (-)7.0% grade. The proposed vertical alignment will meet the AASHTO and

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

10

VDOT Road Design Standard GS-8. The Higher Profile will be approximately 6’-0” higher than the existing profile near the north end of the bridge. Due to the substantial rise in elevation, the Higher Profile requires significant amount of roadway reconstruction and causes larger impacts on the roadside grading. Accordingly, the roadway reconstruction of 250 feet on north and 250 feet on south along Backlick Road will be required. The remainder of Backlick Road, approximately 50 feet on north and 100 feet on south will be milled and overlaid. The Backlick Connector Road profile will be raised as high as four feet adjacent to Backlick Road and therefore, it will be necessary to reconstruct the roadway between Fairfax County Parkway and Backlick Road.

Attachment 2 contains roadway plans for each of the Alternates. Two additional plans have been prepared for Alternate 3 to show the wider bridge required for MOT B and C. Attachment 2 also contains plans describing the MOT options.

3.6 ENVIRONMENTAL ISSUES

A typical structure replacement project is usually addressed with a Programmatic Categorical Exclusion (Cat 15) NEPA document. It is anticipated that this project will likely qualify for a PCE. The State Environmental Review Process (SERP) is not required since this is a federally eligible project.

Screening for potential asbestos-containing materials is strongly recommended prior to dismantling the existing bridge.

3.7 HYDROLOGIC AND HYDRAULIC ISSUES

There are no hydrologic or hydraulic issues for this bridge located over CSX Railroad.

3.8 ROADWAY DRAINAGE

Roadway grading has been evaluated for two different profiles: a) Optimum Profile and b) Higher Profile. Plans showing the proposed profiles are in Attachment 2.

The Optimum Profile will correspond to proposed bridge Alternate 3 only due to a shallower superstructure depth requirement. The optimum profile will cause minimal grading impacts north of the proposed bridge however; it will necessitate roadway reconstruction of approximately 200 feet on the south end of the bridge. The road side grading will require fill along both sides of the roadway and cut into the existing embankment east of Backlick Road at the south end of the project. The overall grading and drainage pattern will remain the same as existing with exception of reconstruction of the curb inlet located just north of the proposed bridge. A roadside drainage ditch will be re-graded along the southbound side of Backlick Road south of the proposed bridge and will tie back to existing at the south end of the project. Remainder of the project grading will tie to existing with either cut or fill slopes and will outfall to existing outfalls.

The Higher Profile will correspond to proposed bridge Alternate 1, 2, and 4, which have deeper superstructure depth requirements. The Higher Profile requires significant grading and fill for approximately 250 feet on both north and south sides of the proposed bridge. The road side grading will require mostly fill along both sides of the roadway and cut into the existing embankment east of Backlick Road at the south end of the project. Also, due to the raised roadway profile, a highpoint is created near the north end of the bridge and therefore, there will be a slight change in drainage areas within the project limits. Accordingly, a new storm drain system will be required along Backlick Road on the north side of the proposed bridge. A roadside drainage ditch will be re-graded along southbound Backlick Road on the south side of the proposed bridge and will tie back to existing at the south end of the project. Remainder of the project grading will tie to existing with either cut or fill slopes and will outfall to existing outfalls.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

11

3.9 STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL, AND PERMITTING

Stormwater Management has been evaluated according to the VDOT Drainage Manual and Instruction and Information Memorandums IIM-LD-195.9, IIM-LD-242.5 and IIM-LD-251.3. Since the project disturbs more than 2,500 SF of land, stormwater management and erosion and sediment control permit will be required according to the Virginia Stormwater Management Handbook (2011) and July 1, 2014 Stormwater Regulations.

Accordingly, the post construction stormwater quality will be addressed by the purchase of nutrient credits. Preliminary runoff reduction analysis has been performed and summarized in Table 3-2. Refer to Attachment 8 for a detailed analysis. The post construction stormwater quantity requires 10-yr peak discharges to pre-existing conditions or lower. The increased runoff in post construction condition will be attenuated by the installation of check dams in roadside ditches along southbound Backlick Road on the south side of the bridge and a stormwater control structure in the existing low laying area located north of the Connector Road between Fairfax County Parkway and Backlick Road.

This project disturbs more than one acre of land therefore, Virginia Pollutant Discharge Elimination System (VPDES) will be required.

Design Alternate 

MOT Option Total Land Disturbance 

(LOD) 

Qualified for Nutrient Credits? 

(< 5 Acres LOD) 

Nutrient Credits Required 

(Phosphorous Reduction (Lb./Year) 

1  A  1.90  Yes  0.49 

A  1.96  Yes  0.50 

B  2.07  Yes  0.60 

C  2.08  Yes  0.65 

A  1.74  Yes  0.48 

B  1.72  Yes  0.60 

C  1.73  Yes  0.65 

4  A  1.96  Yes  0.50 

Table 3-2

3.10 CULTURAL RESOURCES

There are no known cultural resource sites within the project limits. This bridge does not meet the age criteria to qualify as a historic property. Modern buildings and associated infrastructure dominate the immediate landscape.

3.11 RAILROAD ISSUES

The proposed bridge will be designed to accommodate the installation of a new third mainline track and a minor shift in the location of the two existing mainline tracks. The centerline to centerline of the existing tracks through the project vicinity will be approximately 14’-0”, and the centerline of the new track will be located 15’-0” to the east of the existing northbound mainline track. The addition

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

12

of this third track will result in a substandard horizontal clearance (less than 10 feet) at Pier 2 of the existing bridge, and therefore the pier must be removed to rectify the clearance issue. The standard horizontal clearance for CSXT is typically 25’-0” or greater; however, horizontal clearances of less than 25’-0” but greater than 18’-0” with a crash wall are acceptable pending CSXT approval. For this project the standard 25’-0” minimum horizontal clearance will be provided.

Furthermore, the current vertical clearance of the existing bridge over the railroad tracks is substandard at 22’-8”. The standard vertical clearance that needs to be provided, measured from top of high rail to lowest point of structure in the horizontal clearance area which extends 9’-0” to either side of the track centerline, is 23’-0”. However, as part of the requirements for the DC to Richmond Southeast High Speed Rail, the minimum vertical clearance that needs to be provided is 24’-3”. This 1’-3” increase from the CSXT standard will provide the necessary clearance to allow for the potential future electrification of the tracks.

The location of this bridge is over one of the busiest corridors of CSX Railroad that services numerous CSXT freight trains and Amtrak passenger trains. There are an estimated 78 trains per day so the available times for overhead demolition and construction will be highly dependent on the train schedule. CSXT is contractually obligated to maintain the Amtrak schedule. In order to maintain this schedule, construction will need to be coordinated accordingly and with consideration to the varying frequency of the CSXT freight trains.

3.12 CONSTRUCTABILITY ISSUES

The estimated time for construction of the proposed bridge will depend on the preferred method of construction. Currently there are three methods of construction under consideration: normal routine construction, staged construction, and accelerated bridge construction (ABC). The proposed bridge will be constructed in the same location as the existing bridge, though the footprint of the bridge may be slightly wider and/or longer as required for each alternate.

A construction duration of 7-11 months is estimated if normal routine construction methods are used. The duration of construction will be shortest for the single span alternates and will be longer for the three span alternate due to the need to fully demolish the existing piers as well as construct the new piers.

A construction duration of 13-16 months is estimated if staged construction methods are used. Similar to normal routine construction, the duration will be shortest for the single span alternates and longest for the three span alternate.

Finally, it is estimated that accelerated bridge construction methods can reduce the duration of construction of the single span alternate by approximately 1 month assuming a full bridge closure. Accelerated bridge construction methods were not evaluated for the stage construction options as directed by the Department.

Regardless of the method of construction, the erection of the new bridge will be greatly impacted by the volume of freight trains and passenger trains operating daily the tracks. Additionally, the availability of CSXT flaggers is very limited in this corridor. A flagger must be on site during construction, particularly for work over the track, so it will be important to coordinate the construction schedule with CSXT to minimize the need for flaggers and optimize the available work window around the train schedule. A CSXT flagger may be required for any work which requires entry onto the CSX track, and all work to be performed within 50 feet of the centerline of the track. The contractor must plan and perform the work in a manner such that the CSX tracks remain fully capable of carrying rail traffic throughout the work period and rail traffic is not delayed or otherwise impacted due to the work being performed.

Access to both sides of the proposed bridge will be achieved from the existing roadway approaches and right-of-way. Temporary construction clearances will not be allowed. The contractor shall not

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

13

be permitted to use the CSXT right-of-way for storage of materials or equipment during construction. The CSXT right-of-way must remain clear at all times.

At a minimum, there will be approximately 2’-0” between Stage I construction and Stage 2 demolition for the staged construction alternates. This should provide adequate space for temporary shoring, forming of the new abutments and piers (if utilized), and erection of the new superstructure.

There are overhead utility lines and at least one underground fiber optic cable in the area that may need to be relocated. The drainage ditches adjacent to the CSX tracks are to be restored to the original condition after construction.

3.13 AESTHETIC CONSIDERATIONS

There are no specific aesthetic requirements for the proposed bridge.

4.0 REMOVAL OF EXISTING BRIDGE

The removal of the existing Route 617 bridge will be completed in either one operation or in multiple phases of demolition depending on the MOT option selected for construction. The demolition will be in accordance with VDOT Specifications and CSXT Standards.

Regardless of the method of construction, the railroad tracks will need to be protected at all times from falling debris during the removal of the overhead bridge and from any debris rolling down the side slopes or otherwise coming into the area around the tracks which could affect train operations. According the CSXT Criteria for Overhead Bridges, a protection shield erected from the underside of the bridge over the track area must be provided to catch falling debris. The protection shield should be supported from the girders and will be designed for a minimum of 50 pounds per square foot plus the weight of the equipment, debris, personnel, and other loads to be carried. The construction and application of the protection shield will need to be evaluated to ensure it will have no impacts on the already substandard vertical clearance of the existing bridge.

The deck will be removed by cutting it in sections and lifting each section out. Large pieces of the deck are not to be allowed to fall on the protection shield. Additionally, a ballast protection system consisting of geofabric or canvas may need to be placed over the track to keep the ballast clean. The system will extend along the track structure for a minimum of 25’-0” beyond the limits of the demolition work. For the alternates that do not require the pier footing to be removed, the pier columns will be removed to the maximum extent possible, but not less than three feet below the final finished grade or two feet below the base of rail, whichever is lower. The other alternates will require the entire pier footing to be removed. Sheeting may be required for pier removal, but it is not anticipated that the necessary excavation will encroach on the CSXT Theoretical Live Load Zone of Influence for the recommended alternate. This will need to be re-evaluated if a different alternate is preferred by the Department.

All existing abutment and pier piles are to remain in place if it is anticipated that they will not obstruct construction of the new foundations. Where possible, the existing piles are to be re-used for the foundations of the new substructure units. The piles that are to be re-used may require testing to assess their condition. The location of the piles that are to be re-used is discussed for each alternate in further detail within the Bridge Preliminary Discussion (Section 6.0) subsections.

The removal schedule will need to be coordinated with CSXT as the times available for overhead demolition are highly dependent on the train schedule. All of the removal work within the track area will need to be performed during the available time windows when the trains are not passing the site. This was previously discussed in Sections 3.9 and 3.10 of this report.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

14

5.0 BRIDGE TYPICAL SECTIONS

The proposed bridge typical sections are established based on existing roadway and traffic conditions, the VDOT Roadway Design Manual, and VDOT S&B Division Manual – Volume V, Part 2. The typical sections were discussed and decided in a meeting held with representatives from NOVA District Structure and Bridge, Location and Design, and Traffic Engineering on September 29, 2016.

Construction phasing will affect the overall width of the bridge. If traffic is maintained over the bridge throughout the construction project the southbound shoulder width will be wider than 2’. This is due to the need to increase the bridge width through the various stages of construction and demolition.

The typical sections consist of two 12 foot lanes with two 2 foot shoulders and a 15’-6” shared use path and buffer space area. The shared use path and buffer space area will be adjacent to the northbound travel lane and consist of an 8 foot shared use path (SUP), buffer areas on both sides of the path, curb, and barrier. A physical barrier will not be required between the roadway and the shared use path because the distance from the face of the curb to the edge of the shared use path meets the required minimum of 5’-6”. In order to reduce the out-to-out width of the bridge, the SUP has been reduced from 10 feet to 8 feet. This matches the path on the adjacent roadway. A design waiver will be required in accordance with IIM-LD-227.9 and the Manuals of the Structure and Bridge Division, Volume V Part 1.

The typical sections have a normal cross slope with 2% slope on each side of the point of finished grade on the bridge. The slope on the SUP/sidewalk will be 1% sloping toward the bridge deck travel lanes. A 3’-6” 1-rail (BR27C-12) barrier on the southbound lane and a 4’-6” 3-rail (BR27C-15) barrier used as a traffic barrier on the far outside of the structure were selected to satisfy the crash test level (TL-4) and rail height requirements for the proposed bridge. The 3-rail barrier will be mounted on top of the sidewalk. A pedestrian fence that meets VDOT and CSXT specifications will be attached to the outside of barrier on each side of the bridge. See figure 5.1 for the proposed bridge typical section for all alternates if MOT Option A is used.

Figure 5-1

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

15

There are three Maintenance of Traffic (MOT) options. The advantages and disadvantages of each are discussed in Section 3.4. The impact of each on the width of the bridge is as follows.

MOT Option A: Full Closure and Detour.

For the MOT option utilizing a full bridge closure with a detour for the duration of construction, the proposed curb to face of railing width is 24’-0” and the out-to-out width is 45’-2”. The centerline of the bridge will be offset approximately 7’-9” to the east of the roadway centerline.

Bike and pedestrian access will not be provided in this option. See Section 3.4 for a discussion on options to provide bike and pedestrian access.

MOT Option B: One Lane – Alternating Two-Way Traffic, with Pedestrian Access.

For the MOT option utilizing staged construction with one lane open and alternating two-way traffic, the proposed curb to face of railing width is 39’-8½” and the final out-to-out width is 56’-10½”. The centerline of the bridge will be offset approximately 1 foot to the east of the roadway centerline.

This option will use one 14-foot lane and a 5-foot sidewalk during construction. The wider 14-foot lane is necessary to accommodate the large trucks that use the bridge. The existing 8-foot shared use path will be reduced to a 5-foot sidewalk and separated from traffic by a barrier. Bolt-down single-faced barriers will be used during construction.

MOT Option C: Two Lanes, without Pedestrian Access.

For the MOT option utilizing staged construction with two lanes open and no pedestrian access, the proposed curb to face of railing width is 43’-6” and the final out-to-out width is 60’-8”. The centerline of the bridge will be coincident with the roadway centerline. This option will use two 11-foot lanes with 1-foot shy for each lane during construction and will not provide access for pedestrians or bicyclists. Bolt-down single-faced barriers will be used during construction.

Bike and pedestrian access will not be provided in this option. See Section 3.4 for a discussion on alternatives to provide bike and pedestrian access. The construction cost for a temporary pedestrian bridge was not estimated for this report.

The high point of the roadway is located on the bridge for all alternates. The BR27C railing on the southbound lane and curb and gutter on the northbound lane will provide a continuous curb line to direct stormwater off of the bridge. Currently, there will be no utilities carried on the proposed bridge. The vertical and horizontal alignment has been established to meet the proper sight distance and ride-ability requirements for a 30 MPH design speed.

6.0 BRIDGE PRELIMINARY DISCUSSION

The following four bridge replacement alternates were evaluated for this report:

Alternate 1: 168-foot single span steel plate girders with composite concrete deck on existing abutment piles.

Alternate 2: 135-foot single span steel plate girders with composite concrete deck on new abutments.

Alternate 3: 182-foot three-span steel plate girders with composite concrete deck on new abutments and piers.

Alternate 4: 135-foot single-span straight steel plate girders with composite concrete deck on new abutments utilizing Accelerated Bridge Construction Methods (ABC).

These alternates have been studied with consideration to the three maintenance of traffic options previously defined in this document. See Section 3.4 for a detailed description of the advantages and disadvantages of the evaluated MOT options. Alternates 1 & 4 were only studied assuming a

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

16

full closure with detour. Alternates 2 & 3 were studied for all three MOT options. This is discussed in more detail below.

Sketches showing a plan, elevation, and typical section of each alternate are provided in Attachment 3 of this report.

In addition to the alternates above, others were considered as well. Raising the bridge by jacking the superstructure and utilizing the existing abutments and piers was considered but eliminated because of insufficient horizontal clearance from the centerline of the proposed new track to the face of the existing pier. A through-girder option was considered but eliminated due to the fracture critical nature of the structure.

Shared Use Path:

The span lengths for all alternates were evaluated to ensure that there is sufficient clearance to accommodate a potential future shared use path (SUP) in addition to the three CSX railroad tracks. It has yet to be determined if a future SUP will be located under the bridge, but the Department has instructed that the bridge layout shall not preclude the future construction of an SUP adjacent to the railroad tracks. The speculative location of the SUP will be to the east of the of railroad tracks. The position of the SUP will be within CSXT right-of-way and will therefore require CSXT’s approval. CSXT policy is to not permit parallel bicycle/pedestrian paths. If any such trail were to be considered, CSXT will require safety measures such as fencing and signage.

As currently planned, all alternates provide a clearance of at least 15’-0” from the outer most rail of the tracks to the face physical separation barrier. According to Table A-5-12 of the VDOT Roadway Design Manual, a 15’-0” minimum clearance is recommended in constrained areas with heavy rail traffic (over 11 trains per day). The width of the potential future SUP is assumed to be 14’-0” in accordance with VDOT standards.

6.1 ALTERNATE 1 – 168’-0” SINGLE SPAN BRIDGE ON EXISTING ABUTMENT PILES

This bridge structure consists of a 168’-0” single span steel plate girders on a 22-degree skew to normal. The seven girders are spaced at 6’-8” with uniform deck overhangs, diaphragms, and a cast-in-place composite deck slab. The proposed curb to face of railing width is 24’-0” and the out-to-out width is 45’-2”. The deck slab has a minimum thickness of 8½”. The web depth of the plate girder section is 54 inches and the total girder depth is 58 inches.

The substructures will be new semi-integral cast-in-place concrete abutments constructed utilizing the existing abutment piles. The existing 3 span structure will be removed including both abutment concrete pile cap portions. A new row of piles will be installed behind the existing piles and the new semi-integral reinforced concrete abutment will be constructed. The existing pier caps will be demolished and the columns will be removed to approximately three feet below the proposed ground. Following construction of the bridge, the embankment slope and railroad ditches will be graded to match the existing condition. The substructures will be designed to accommodate a 1.5:1 slope for the future condition when railroad construction is completed. This slope is necessary in order to maintain the location of the existing abutments without creating the need to construct MSE walls. The slope may expose the existing fiber optic line and will therefore require the line to be buried or relocated.

This alternate is not recommended because the plate girders were designed assuming a reduction of the required LRFD span-to-depth ratio of approximately 85% while meeting all the other design criteria. The span-to-depth criteria is related to the stability of the structure during construction, the limitation for the live load deflection, and the effective “springiness” of the superstructure. Since this bridge carries a high percentage of heavy vehicles and is shared with pedestrians and cyclists it is strongly recommended that the span-to-depth criteria should not be relaxed.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

17

The decision to analyze this alternate with a reduced span-to-depth ratio was made after it was determined that sufficient vertical clearance over the railroad could not be provided without severe impact to the intersection of Backlick Road and the Fairfax County Parkway connector road. The required depth for a girder designed in accordance with all LRFD criteria is 69½ inches, which is approximately 11½” larger than the girder design using a reduced span-to-depth ratio. In order to accommodate the resulting increase in superstructure depth, the roadway will need to be raised to a height that will exceed the allowed vertical curve of Backlick Road.

This alternate was only evaluated for a full closure with a detour since it is not recommended to design the beams to 85% of the required span-to-depth ratio.

6.2 ALTERNATE 2 – 135’-0” SINGLE SPAN BRIDGE

This bridge structure consists of a 135’ single span steel plate girders on a 22-degree skew to normal. The substructures are new semi-integral cast-in-place concrete abutments on two rows of piles constructed behind MSE walls. Semi-integral abutments with MSE walls were selected for the cost development of this alternate because 30’-0” or taller MSE walls are more economical and can be constructed more quickly and cheaply than cast-in-place concrete abutments of similar height. However, if MSE walls are not permitted for use within the CSXT right-of-way, then full-height semi-integral abutments will be required. The cost of using full-height abutments was evaluated in case MSE walls are not approved for use by CSXT or if the potential addition of future tracks dictates the use of the abutments as crash walls due to horizontal clearance issues. The resulting increase in the total estimated cost is approximately $380,000. The use of full-height abutments will also likely require the relocation of the underground fiber optic line, which will add significant cost to the project.

Following construction of the bridge, the embankment slope and railroad ditches will be graded to match the existing condition. The substructures will be designed to accommodate a 2:1 slope, in accordance with CSXT standards, as needed for the future condition when railroad construction is completed. This slope may expose the existing fiber optic line and will therefore require the line to be buried or relocated. The abutments have a skew of 22 degrees and will have U-back wingwalls to support the required fill.

The location of this bridge provides more horizontal clearance than required from the centerline of the new CSX railroad track and will likely not require the fiber optic line to be relocated. Additionally, by locating the new abutments between the existing abutments and piers, the substructure can be constructed without requiring the full removal of the pier footings or the extraction of the existing steel piles. The existing pier caps and abutments will be demolished, and the columns of the pier will be removed to approximately three feet below the proposed ground.

Alternate 2A: Full Closure and Detour.

The superstructure consists of six plate girders spaced at 7’-10” with uniform 2’-9” deck slab overhangs, cross frames, and a cast-in-place composite deck slab. The proposed curb to face of railing width is 24’-0” and the out-to-out width is 45’-2”. The deck slab has a minimum thickness of 8.5 inches. The web depth of the plate girder section is 54 inches and total girder depth is 57⅜ inches.

The estimated time for construction of this alternate is approximately 8-9 months, using normal, routine construction methods.

This is the recommended alternate. This alternate requires the least cost and shortest construction time, unless ABC methods are utilized. This alternate is roughly the same width as the existing bridge and is approximately 30 feet shorter, thereby reducing the overall footprint of the bridge.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

18

Alternate 2B - Staged Construction: One Lane – Alternating Two-Way Traffic, with Pedestrian Access.

The superstructure consists of six plate girders spaced at 7’-5½” with uniform 2’-4” deck slab overhangs, cross frames, and a cast-in-place composite deck slab. The proposed curb to face of railing width is 39’-8½” and the final out-to-out width is 56’-10½”. The deck slab has a minimum thickness of 8.5 inches. The web depth of the plate girder section is 54 inches and total girder depth is 57⅜ inches.

The estimated time for construction of this alternate is approximately 13-15 months, using staged construction methods.

This alternate is not recommended. Although staged construction will allow the bridge to remain open to traffic, it will also result in an increased construction duration. The overall cost of the project will also increase when compared to Alternate 2A. Finally, the bridge will remain open to pedestrian use but will require bicycles to use a suitable detour.

Alternate 2C - Staged Construction: Two Lanes, without Pedestrian Access.

The superstructure consists of six plate girders spaced at 7’-10” with uniform 2’-11” deck slab overhangs, cross frames, and a cast-in-place composite deck slab. The proposed curb to face of railing width is 43’-6” and the final out-to-out width is 60’-8”. The deck slab has a minimum thickness of 8.5 inches. The web depth of the plate girder section is 54 inches and total girder depth is 57⅜ inches.

The estimated time for construction of this alternate is approximately 13-15 months, using staged construction methods.

This alternate is not recommended. Although staged construction will allow the bridge to remain open to traffic, it will also result in an increased construction duration. The overall cost of the project will also increase when compared to Alternate 2A. Finally, this alternate will require the use of a detour or construction of a temporary bridge for maintenance of pedestrian/bicycle traffic.

This alternate was also preliminarily examined as a 110’ simple span steel girder bridge. However, a decision was made to increase the length of the bridge from 110’ with intent to avoid potential conflict with the existing pier footings piles, stay away from the existing underground fiber optic cable, and reduce the fill needed to construct the bridge. The span length can be further reduced if CSXT permits the use of crash walls, but this is unlikely and will also result in conflicts with the existing substructures.

6.3 ALTERNATE 3 – 182’-0” (45’-92’-45’) THREE-SPAN BRIDGE

The bridge structure consists of a three span steel plate girders with span arrangement of 45’-0” - 92’-0” - 45’-0” on a 22-degree skew to normal. The substructures include new integral cast-in-place concrete abutments on one row of piles and new multi-column piers. The north abutment will be constructed utilizing the existing abutment piles and Pier 1 will be constructed utilizing the existing pier piles. The existing three-span structure will be removed entirely except for the existing piles and the Pier 2 footing, which can remain since it does not impact the future condition. New piles will be driven for the south abutment, Pier 2, and the widened portions of the north abutment and Pier 1. Following construction of the bridge, the embankment slope and railroad ditches will be graded to match the existing condition. The substructures will be designed to accommodate a 2:1 slope, in accordance with CSXT standards, as needed for the future condition when railroad construction is completed. The proposed location of Pier 2 will require the existing underground fiber optic cable to be relocated.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

19

Alternate 3A: Full Closure and Detour.

The superstructure consists of six plate girders spaced at 7’-10” with uniform 2’-9” deck slab overhangs, cross frames, and a cast-in-place composite deck slab. The proposed curb to face of railing width is 24’-0” and the out-to-out width is 45’-2”. The deck slab has a minimum thickness of 8.5 inches. The web depth of the plate girder section is 28 inches and the total girder depth is 31⅛ inches.

The estimated time for construction of this alternate is approximately 10-11 months, using normal, routine construction methods.

This alternate is not recommended. The duration increases due to the demolition of the existing piers and construction of the new piers. The proposed location of Pier 2 will also require the relocation of the existing underground fiber optic cable. The advantages of this alternate, which include a less significate raise in profile and a shallower girder depth, likely will not offset required closure time of the bridge for routine, normal construction.

Alternate 3B - Staged Construction: One Lane – Alternating Two-Way Traffic, with Pedestrian Access.

The superstructure consists of six plate girders spaced at 7’-5½” with uniform 2’-4” deck slab overhangs, cross frames, and a cast-in-place composite deck slab. The proposed curb to face of railing width is 39’-8½” and the final out-to-out width is 56’-10½”. The deck slab has a minimum thickness of 8.5 inches. The web depth of the plate girder section is 28 inches and the total girder depth is 31⅛ inches.

This alternate is not recommended. Although staged construction will allow the bridge to remain open to traffic, it will also result in a significantly longer construction duration due to the construction of the piers. The location of the piers will also require the relocation of the existing underground fiber optic cable. The overall cost of the project will also increase when compared to Alternate 3A. Finally, the bridge will remain open to pedestrian use but will require bicycles to use a suitable detour.

Alternate 3C - Staged Construction: Two Lanes, without Pedestrian Access.

The superstructure consists of six plate girders spaced at 7’-10” with uniform 2’-11” deck slab overhangs, cross frames, and a cast-in-place composite deck slab. The proposed curb to face of railing width is 43’-6” and the final out-to-out width is 60’-8”. The web depth of the plate girder section is 28 inches and the total girder depth is 31⅛ inches.

This alternate is not recommended. Although staged construction will allow the bridge to remain open to traffic, it will also result in a significantly longer construction duration due to the construction of the piers. The location of the piers will also require the relocation of the existing underground fiber optic cable. The overall cost of the project will also increase when compared to Alternate 3A. Finally, this alternate will require the use of a detour or construction of a temporary bridge for maintenance of pedestrian/bicycle traffic.

6.4 ALTERNATE 4 – 135’-0” SINGLE SPAN BRIDGE UTILIZING ABC METHODS

The construction of the recommended alternative, Alternate 2A, was evaluated for Accelerated Bridge Construction (ABC) methods to determine how much construction time could be saved to reduce the detour time. The Alternate 2A standard construction of the bridge superstructure consists of a 135’ single span steel plate girder with a cast-in-place reinforced composite concrete deck and cast-in-place reinforced concrete semi-integral abutments. The standard construction of the foundation for the substructures are two rows of steel H-piles driven behind MSE walls. The ABC evaluation examines two types of ABC deck construction options and one type of ABC abutment construction option.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

20

ABC Deck Construction Option 1:

This ABC deck option consists of attaching the stay-in-place (S.I.P.) and deck overhang forms to two girders that are connected and then erected together. After all girder units have been erected and set, the shear studs are attached and pre-tied top and bottom steel reinforcing mat sections are lifted into place. Attaching the deck forms to the girders prior to erection will also reduce the time working over the tracks that requires overhead protection. The estimated construction time is 7 working days, which represents a 13 working day savings over the standard deck construction method.

ABC Deck Construction Option 2:

This ABC deck option consists of using 10-foot long full width precast deck panels with shear key pockets and transverse joint keys between the panels. After all of the girders are set and the cross frames are installed, the precast deck panels will be set in place. The precast deck panels will start four feet from the end of the girders so that the semi-integral abutments can be poured. The required shear studs will be installed and then the shear key pockets and transverse joint keys will be grouted. The semi-integral diaphragms at both abutments will be poured up to top of precast deck. This option will require a 1” wearing surface to be placed. This will require the same construction time as placing a cast-in-place deck. The estimated construction time is 8 working days, which represents a 12 working day savings over the standard deck construction method.

ABC Abutment Construction Option:

This ABC option consists of using precast abutment pile caps with grouted pile pockets. The standard construction method is after the piles are installed, the pile caps are formed, the required reinforcing steel is placed and then cast-in-place concrete is poured. The precast abutment pile caps will be cast with pile pockets that will fit over the piles and then high strength grout placed in the pockets. The estimated construction time for both precast pile caps is 2 working days which would be 8 working day savings over the standard pile cap construction method.

One type of ABC foundation was also explored that compared the standard construction method of driving steel H-piles to using 3’-0 diameter reinforced concrete drilled shafts. It is estimated that it will take five drilled shafts to replace the two rows of H-piles for each abutment. Using drilled shafts will also delay the construction of the MSE wall. The drilled shafts below the existing ground will have to be drilled, reinforcing placed and then concrete placed. Then the part of the drilled shaft above the existing ground will have to be formed as a de-facto column, reinforcing steel installed and concrete placed. This will require additional time before the MSE wall can be constructed because the “column” forms will need to be installed, reinforcing steel placed, cast-in-place concrete poured and then forms removed. With the standard construction the contractor will just have the time driving the steel H-piles and placing plastic or metal pile sleeves over the piles before starting construction of the MSE wall. This is not a good ABC option because of the additional time for constructing the drilled shaft (columns) above the existing ground and the additional cost of hiring a specialty sub-contractor.

Combining either of the ABC Deck Construction with the ABC Abutment Construction will only reduce the detour time by 30 calendar days.

From research, the estimated additional construction cost for any Accelerated Bridge Construction is approximately 20%. The cost estimate will be developed by multiplying the estimated bridge construction cost of Alternate 2A by a factor of 1.20. A detailed cost estimate with line items will not be provided. Sketches are also not provided. The sketches for Alternate 2A are an adequate representation of the type, size, and location for this alternate. The main differences in the sketches will be the possible use of precast deck panels, precast abutments, and drilled shafts.

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

21

The ABC of Alternative 2A is not recommended because the moderate savings of 30 calendar days of detour time does not outweigh the 20% increase in construction cost.

7.0 RECOMMENDED ALTERNATE

Alternate 2A, the 135’ single span alternate requiring a full bridge closure for the duration of construction, is recommended for the structure replacement of the Route 617 Bridge over CSX Railroad. This alternative requires the least cost and shortest construction time. The span length and width of this bridge also represents the smallest footprint of the studied alternates, which results in the least amount of land disturbance to the project site and less potential for right-of-way impacts. Finally, Alternate 2A is less likely to require relocation of the existing underground fiber optic cable when compared to the other structure alternates, and less likely to require relocation of the existing overhead utility line adjacent to the bridge when compared to the other MOT options.

8.0 ENGINEER’S COST ESTIMATE

The cost estimate breakdown for each bridge replacement alternate are provided in Attachment 4 of this report. Preliminary cost estimates were developed based on information gathered from historical bid tab data, discussions with fabricators, and engineering judgment. The cost estimates include complete demolition of the existing structure, construction of the new structure, and approach roadway work, and maintenance of traffic. The construction cost, other associated costs (including estimate contingency, force account estimate for CSX, CEI costs, construction contingency, and preliminary engineering), and total cost for each alternate are summarized in Table 8.1.

Alternate Bridge Construction

Cost

Roadway Construction

Cost

MOT Construction

Cost

Other Costs Total Estimated

Cost

1 $2,891,300 $791,280 $199,445 $3,789,275 $7,671,300

2A $2,839,500 $815,330 $199,445 $3,771,025 $7,625,300

2B $3,325,600 $858,980 $344,625 $4,209,795 $8,739,000

2C $3,394,800 $876,930 $322,325 $4,252,045 $8,846,100

3A $3,067,900 $692,590 $199,445 $3,939,665 $7,899,600

3B $3,619,200 $714,040 $344,625 $4,406,335 $9,084,200

3C $3,729,200 $740,790 $322,325 $4,480,885 $9,273,200

4 $3,407,400 $815,330 $199,445 $4,140,225 $8,562,400

Table 8-1

Stage I Report Route 617 (Backlick Road) over CSX Railroad ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

22

9.0 SCHEDULE

The scope of work for this project provides bridge design and engineering support services from Stage I through Stage II of the Structure and Bridge Division’s design process. Future milestone dates, project progress, and submittals for this task will be assumed as follows:

Scoping for Stage II November 2016 PFI Plans (30% Roadway) December 2016 Final Plans/PAC February 2017 Advertisement May 2017

The above schedule is approximate and may require adjustment as necessary due to any unanticipated delays from reviews by the Department or coordination with DRPT or CSXT. The schedule is based on a 2-week review period by the Department.

A Risk Analysis Matrix will need to be completed for this project after a preferred alternate is selected by the Department

ATTACHMENT 1

PROJECT LOCATION MAP

Project Location Map

ROUTE 617 (BACKLICK ROAD) BRIDGE OVER CSX RAILROAD

FAIRFAX COUNTY, VA

 

Rte. 617 (Backlick Road) 

over CSX Railroad 

ATTACHMENT 2

STAGE I PRELIMINARY ROADWAY SKETCHES

ATTACHMENT 3

STAGE I PRELIMINARY BRIDGE SKETCHES

2.0% 2.0%

BR27C-12

TRANSVERSE SECTION

G1 G2 G3 G4 G5 G6

Scale: 1/8" = 1'-0"

G7

Rte. 617 BL

finished grade

Point of

SBLNBL

1.0%

BR27C-15

TRANSVERSE SECTION

ALTERNATE 1

FULL CLOSURE WITH DETOUR

2'-7"2'-7"6 Spaces @ 6'-8" = 40'-0"

1'-1"

12'-0" 2'-0"15'-6"

2'-0" 12'-0"10"10"

45'-2" Out to Out

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

115 116 117+50+50 +50

PO

E 202+45.4

8

(BA

CKLIC

K R

D.)

= 114+72.4

8

PLANScale: 1" = 40'-0"

Scale: 1" = 40'-0"

ELEVATION

To Rte. 286 To Cinder Bed Road

15'-0

"

Rte. 617 Constr. B

L

L

L

14'-1

„" +

L

135'-0"

Sta. 116+96.99

Abutment B

End of slab

Sta. 115+61.99

Abutment A

End of slab

145.50

Elev.

28'-

0"

10"

typ.

Approach slab

typ.

22'-0"

Fill

typ.

Approach slab

ABUTMENT B

Fill

LLC Future track

L

L

typ.

HP 12x53

1

2

42'-6

†"

35'-2

‚"

Horiz.

Clear

ance

Horiz. Clr.

ABUTMENT A

139.21

Elev.

10"

43'-

6"

15'-

6"

Face of rail

sidewalk curb

Face of

Face of rail

135'-0"

CSXT R/W

CSXT R/WCSXT R/W

Easement

VDOT

RW-A

MSE Wall RW-B

MSE Wall

mile

post 95

0.1

4

mile to

V.C. = 250.0

C.G. Elev. 147.70

C.G. Sta. 115 + 90.63

C Future relocated track

1.0% -7.0%

Future finished grade

Finished Grade

CSX RR track

C Future

22-00'-0

0"

typ.

Existing Grade

Rte. 617 Constr. B

Existing profile along

PLAN AND ELEVATION

FULL CLOSURE WITH DETOUR

ALTERNATE 2A

to be removed

Existing bridge

to be relocated

CSX RR track

C Existing

CSX RR track

C Future reloc.

Future SUP

Potential

Sta. 115+61.99

Beginning of bridge

End of slab

Sta. 116+96.99

End of bridge

End of slab

18'-0"(w) x 24'-3"(h)

CSX Clearance box

L C track

Existing

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

fiber optic cable

Existing underground

optic cable

Existing fiber

Approx. loc. of

proposed grade, typ.

columns to 3'-0" below

Cut and remove pier

Influence Zone

Theoretical Live Load

Influence Zone

Theoretical Live Load

CSXT R/W

clearance provided

25'-5" Min. vert.

clearance required

24'-3" Min. vert.

CSXT R/W

BR27C-12

2.0%2.0%

TRANSVERSE SECTION

G1 G2 G3 G4 G5 G6

Scale: 1/8" = 1'-0"

Rte. 617 BL

finished grade

Point of

BR27C-15

1.0%

SBLNBL

TRANSVERSE SECTION

ALTERNATE 2A

FULL CLOSURE WITH DETOUR

3'-0" 3'-0"

5 Spaces @ 7'-10" = 39'-2"

3'-10"

12'-0" 2'-0"15'-6"

2'-0" 12'-0"10"10"

45'-2" Out to Out

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

115 116 117+50+50 +50

PO

E 202+45.4

8

(BA

CKLIC

K R

D.)

= 114+72.4

8

PLANScale: 1" = 40'-0"

To Rte. 286 To Cinder Bed Road

Rte. 617 Constr. BL

135'-0"

Sta. 116+96.99

Abutment B

End of slab

Sta. 115+61.99

Abutment A

End of slab

145.50

Elev.

10"

typ.

Approach slab

typ.

22'-0"

139.21

Elev.

39'-

8•

"15'-

6"

55'-

2•

"10"

Face of rail

sidewalk curb

Face of

joint

Deck const.

typ.

HP 12x53

LC Future relocated track

Scale: 1" = 40'-0"

ELEVATION

ABUTMENT B

LLC Future track

ABUTMENT A

Fill

Fill

22-00'-0

0"

typ.

CSXT R/W

Face of rail

CSXT R/W

LCSX RR track

C Future

35'-2

‚"

Horiz. Clr.

15'-0

"

mile

post 95

0.1

4

mile to

14'-1

„" +

42'-6

†"

Horiz.

Clear

ance

CSX RR track

C Future reloc.

Easement

VDOT

to be relocated

CSX RR track

C ExistingL

CSXT R/W

MSE Wall RW-B

MSE Wall RW-A

L

V.C. = 250.0

C.G. Elev. 147.70

C.G. Sta. 115 + 90.63

1.0% -7.0%

Existing Grade

PLAN AND ELEVATION

STAGED CONSTRUCTION WITH ONE LANE OPEN

ALTERNATE 2B

1'-

10"

to be removed

Existing bridge

L

Future finished grade

Rte. 617 Constr. B

Existing profile along

1

2

L C track

Existing

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

fiber optic cable

Existing underground

optic cable

existing fiber

Approx. loc. of

proposed grade, typ.

columns to 3'-0" below

Cut and remove pier

typ.

Approach slab

135'-0"

Future SUP

Potential

Sta. 115+61.99

Beginning of bridge

End of slab

Sta. 116+96.99

End of bridge

End of slab

18'-0"(w) x 24'-3"(h)

CSX Clearance box

CSXT R/W

Finished Grade

CSXT R/W

clearance provided

24'-11" Min. vert.

clearance required

24'-3" Min. vert.

TRANSVERSE SECTION

STAGE 3

STAGE 1

STAGE 2

Rte. 617 BL

2.0%

Rte. 617 BL

2.0% 2.0%

BR27C-12

Rte. 617 BL

Face of curb

2.0% 2.0%

BR27C-12

Face of curb

G1 G2 G3 G4 G5 G6 G7 G8

Out to Out

finished grade

Point of

finished grade

Point of

STAGED CONSTRUCTION WITH ONE LANE OPEN

BR27C-15

BR27C-15

1.0%

1.0%

ALTERNATE 2B

bridge

Existing

27'-0"

17'-6"5'-0"

4'-1•"

24'-8•"

10"

2"

24'-8•"29'-6"

14'-0"5'-0"

1'-4•"

1'-10"

10"

1'-4•"

1'-4•"

10"

15'-6" 14'-0" 25'-8•"10"

56'-10•"

10"

7 Spaces @ 7'-5•" = 52'-2•"

2'-1•"

1'-0"

1'-10"

2'-4" 2'-4"

9"

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

115 116 117+50+50 +50

PO

E 202+45.4

8

(BA

CKLIC

K R

D.)

= 114+72.4

8

PLANScale: 1" = 40'-0"

To Rte. 286 To Cinder Bed Road

Rte. 617 Constr. BL

135'-0"

Sta. 116+96.99

Abutment B

End of slab

Sta. 115+61.99

Abutment A

End of slab

145.50

Elev.

typ.

Approach slab

typ.

22'-0"

35'-2

‚"

Horiz. Clr.

139.21

Elev.

59'-

0"

15'-

6"

43'-

6"

Face of rail

sidewalk curb

Face of

joint

Deck const.

3'-

11"

CSXT R/W 22-00'-0

0"

typ.

Easement

VDOT

to be relocated

CSX RR track

C ExistingL

L CSX RR track

C Future reloc.

15'-0

"

mile

post 95

0.1

4

mile to

42'-6

†"

Horiz.

Clear

ance

14'-1

„" +

CSXT R/W

V.C. = 250.0

C.G. Elev. 147.70

C.G. Sta. 115 + 90.63

1.0% -7.0%

typ.

HP 12x53

Fill

LC Future relocated track

ELEVATION

ABUTMENT B

LLC Future track

ABUTMENT A

Scale: 1" = 40'-0"

Fill

10"

10"

MSE Wall RW-A

Face of rail

CSXT R/W

LCSX RR track

C Future

MSE Wall RW-B

Existing Grade

PLAN AND ELEVATION

STAGED CONSTRUCTION WITH TWO LANES OPEN

ALTERNATE 2C

to be removed

Existing bridge

L C track

Existing

1

2

L

Future finished grade

Rte. 617 Constr. B

Existing profile along

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

fiber optic cable

Existing underground

optic cable

existing fiber

Approx. loc. of

proposed grade, typ.

columns to 3'-0" below

Cut and remove pier

Finished Grade

CSXT R/W

typ.

Approach slab

135'-0"

Sta. 115+61.99

Beginning of bridge

End of slab

Sta. 116+96.99

End of bridge

End of slab

Future SUP

Potential 18'-0"(w) x 24'-3"(h)

CSX Clearance box

CSXT R/W

clearance provided

24'-10" Min. vert.

clearance required

24'-3" Min. vert.

STAGE 3

STAGE 2

STAGE 1

Rte. 617 BL

2.0%

2.0%

2.0%2.0%

2.0%

BR27C-12

BR27C-12

G1 G2 G3 G4 G5 G6 G7 G8

Rte. 617 BL

Rte. 617 BL

Out to Out

Face of curb

Face of curb

finished grade

Point of

finished grade

Point of

TRANSVERSE SECTION

STAGED CONSTRUCTION WITH TWO LANES OPEN

BR27C-15

1.0%

1.0%

1'-0"

10"

ALTERNATE 2C

bridge

Existing

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

26'-5"27'-0"

11'-0"11'-0"

11'-0"11'-0"

15'-6" 14'-0" 29'-6"

2"

3'-11"

10"

10"10"

60'-8"

1'-4•"

1'-4•"

1'-4•"

1'-0" 1'-0"

29'-6"3'-11"

26'-5"

10"

1'-0"

7 Spaces @ 7'-10" = 54'-10"2'-11"2'-11"

3"

2•"

115 116 117+50+50 +50

PO

E 202+45.4

8

(BA

CKLIC

K R

D.)

= 114+72.4

8

PLANScale: 1" = 40'-0"

Scale: 1" = 40'-0"

ELEVATION

To Rte. 286

15'-0

"

L

L

to be relocated

CSX RR track

C Existing

14'-1

„" +

LCSX RR track

C Future

28'-

0"

10"

typ.

Approach slab

ABUTMENT B

Sta. 115+42.61

Abutment A

End of slab

142.62

Elev.

Sta. 117+24.24

Abutment B

End of slab

typ.

22'-0"

136.80

Elev.

LConstr. B

Rte. 617

Bed Road

To Cinder

Horiz.

Clr.

Clr.Ho

riz.

LC Pier 1

ABUTMENT A

92'-0"44'-9ƒ" 44'-9ƒ"

LC Pier 1LC Pier 2

1

2

LLC Future track

2

1

25'-1

1"

25'-1

0‡"

10"

43'-

6"

15'-

6"

Face of rail

sidewalk curb

Face of

CSXT R/W

Easement

VDOT

CSXT R/W

Face of rail

mile

post 95

0.1

4

mile to

typ.

22-00'-0

0"

CSX RR track

relocated

C Future

Rte. 617 Constr. B

Existing profile along

L

Future finished grade

LC Future relocated track

Potential Future SUP

Finished Grade

Existing grade

V.C. = 160.0

C.G. Elev. 141.39

C.G. Sta. 116 + 53.88

-6.5%

CSXT R/W

LC Pier 2

-1.1%

PIER 1 PIER 2

PLAN AND ELEVATION

FULL CLOSURE WITH DETOUR

ALTERNATE 3A

181'-7•"

to be removed

Existing bridge

181'-7•"

Sta. 115+42.61

Beginning of bridge

End of slab

Sta. 117+24.24

End of bridge

End of slab

18'-0"(w) x 24'-3"(h)

CSX Clearance box

L C track

Existing

fiber optic cable

Existing underground

and reused as necessary

removed. Piles to remain

Existing pier to be

Existing HP 12x53 New HP 12x53

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

optic cable

existing fiber

Approx. loc. of

CSXT R/W

typ.

Approach slab

CSXT R/W

clearance provided

25'-4" Min. vert.

clearance required

24'-3" Min. vert.

2.0%

BR27C-12

2.0%

TRANSVERSE SECTION

G1 G2 G3 G4 G5 G6

Scale: 1/8" = 1'-0"

Rte. 617 BL

finished grade

Point of

SBLNBL

1.0%

BR27C-15

TRANSVERSE SECTION

ALTERNATE 3A

FULL CLOSURE WITH DETOUR

3'-0" 3'-0"5 Spaces @ 7'-10" = 39'-2"

3'-10"

12'-0" 2'-0"15'-6"

2'-0" 12'-0"10"10"

45'-2" Out to Out

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

115 116 117+50+50 +50

PO

E 202+45.4

8

(BA

CKLIC

K R

D.)

= 114+72.4

8

Scale: 1" = 40'-0"

ELEVATION

To Rte. 286

L

to be relocated

CSX RR track

C Existing

LCSX RR track

C Future

typ.

Approach slab

Sta. 115+42.61

Abutment A

End of slab

142.62

Elev.

Sta. 117+24.24

Abutment B

End of slab

typ.

22'-0"

136.80

Elev.

LConstr. B

Rte. 617

Bed Road

To Cinder

LC Pier 1

LLC Future track

2

1

25'-1

0‡"

15'-

6"

Face of rail

sidewalk curb

Face of

55'-

2•

"

39'-

8•

"

joint

Deck const.

15'-0

"

mile

post 95

0.1

4

mile to

14'-1

„" +

Horiz.

Clr.25

'-11"

L

CSX RR track

relocated

C Future

Easement

VDOT

CSXT R/W

typ.

22-00'-0

0"CSXT R/W

10"

10"

Existing grade

LC Future relocated track

Finished Grade

92'-0"44'-9ƒ" 44'-9ƒ"

LC Pier 1LC Pier 2

PLANScale: 1" = 40'-0"

1'-

10"

CSXT R/W

LC Pier 2

Face of rail

V.C. = 160.0

C.G. Elev. 141.39

C.G. Sta. 116 + 53.88

-6.5%-1.1%

ABUTMENT BABUTMENT A PIER 1 PIER 2

Potential Future SUP

PLAN AND ELEVATION

STAGED CONSTRUCTION WITH ONE LANE OPEN

ALTERNATE 3B

Horiz. Clr.

181'-7•"

to be removed

Existing bridge

Sta. 115+42.61

Beginning of bridge

End of slab 181'-7•"

Sta. 117+24.24

End of bridge

End of slab

18'-0"(w) x 24'-3"(h)

CSX Clearance box

L C track

Existing

Rte. 617 Constr. B

Existing profile along

Future finished grade

and reused as necessary

removed. Piles to remain

Existing pier to be

Existing HP 12x53

L

1

2New HP 12x53

fiber optic cable

Existing underground

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

optic cable

existing fiber

Approx. loc. of

CSXT R/W

typ.

Approach slab

18'-0"(w) x 24'-3"(h)

CSX Clearance box CSXT R/W

clearance provided

24'-10" Min. vert.

clearance required

24'-3" Min. vert.

TRANSVERSE SECTION

STAGE 3

G1 G2 G3 G4 G5 G6 G7 G8

Out to Out

STAGED CONSTRUCTION WITH ONE LANE OPEN

ALTERNATE 3B

Rte. 617 BL

BR27C-15

1.0%2.0%

Face of curb

finished grade

Point of

2.0%

BR27C-12

Face of curb

STAGE 2

Rte. 617 BL

BR27C-12

2.0%

finished grade

Point of

2.0%

BR27C-15

1.0%

STAGE 1

2.0%

Rte. 617 B

56'-10•"

7 Spaces @ 7'-5•" = 52'-2•"2'-4" 2'-4"

15'-6" 14'-0" 25'-8•"10" 10"

24'-8•"

14'-0"5'-0"

1'-4•"

1'-10"

1'-4•"

2'-1•"

10"

29'-6"10"

24'-8•"

10"

2" 1'-10"

27'-0"

17'-6"5'-0"

1'-4•"1'-4•"

1'-0"

bridge

Existing

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

115 116 117+50+50 +50

PO

E 202+45.4

8

(BA

CKLIC

K R

D.)

= 114+72.4

8

PLANScale: 1" = 40'-0"

To Rte. 286

L

to be relocated

CSX RR track

C Existing

LCSX RR track

C Future

typ.

Approach slab

Sta. 115+42.61

Abutment A

End of slab

142.62

Elev.

Sta. 117+24.24

Abutment B

End of slab

typ.

22'-0"

136.80

Elev.

LConstr. B

Rte. 617

Bed Road

To Cinder

Clr.Ho

riz.

LC Pier 1

2

1

25'-1

0‡"

10"

15'-

6"

Face of rail

Face of rail

sidewalk curb

Face of

59'-

0"

43'-

6"

joint

Deck const.

3'-

11"

10"

typ.

22-00'-0

0"CSXT R/W

CSXT R/W

Easement

VDOT

L

CSX RR track

relocated

C Future

Horiz.

Clr.25

'-11"

15'-0

"

mile

post 95

0.1

4

mile to

14'-1

„" +

Existing grade

Finished Grade

CSXT R/W

LC Pier 2

V.C. = 160.0

C.G. Elev. 141.39

C.G. Sta. 116 + 53.88

-6.5%-1.1%

Potential Future SUP

Scale: 1" = 40'-0"

ELEVATION

ABUTMENT BABUTMENT A PIER 1 PIER 2

PLAN AND ELEVATION

STAGED CONSTRUCTION WITH TWO LANES OPEN

ALTERNATE 3C

181'-7•"

to be removed

Existing bridge

L C track

Existing

Rte. 617 Constr. B

Existing profile along

Future finished grade

and reused as necessary

removed. Piles to remain

Existing pier to be

L

Existing HP 12x53

1

2

LC Future relocated track

LLC Future track

fiber optic cable

Existing underground

New HP 12x53

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

optic cable

existing fiber

Approx. loc. of

92'-0"44'-9ƒ" 44'-9ƒ"

LC Pier 1LC Pier 2

Sta. 115+42.61

Beginning of bridge

End of slab 181'-7•"

Sta. 117+24.24

End of bridge

End of slab

18'-0"(w) x 24'-3"(h)

CSX Clearance box

CSXT R/W

typ.

Approach slab

18'-0"(w) x 24'-3"(h)

CSX Clearance box CSXT R/W

clearance provided

24'-9" Min. vert.

clearance required

24'-3" Min. vert.

STAGE 3

G1 G2 G3 G4 G5 G6 G7 G8

Out to Out

TRANSVERSE SECTION

STAGED CONSTRUCTION WITH TWO LANES OPEN

ALTERNATE 3C

Rte. 617 BL

2.0%

2.0%

finished grade

Point of

1.0%

Rte. 617 BL

2.0%

BR27C-12

1'-0"

10"

STAGE 2

Rte. 617 BL

BR27C-15

1.0%2.0%

Face of curb

finished grade

Point of

2.0%

BR27C-12

Face of curb

G1 G2 G3 G4 G5 G6 G7 G8

60'-8"

7 Spaces @ 7'-10" = 54'-10"2'-11"

26'-5"27'-0"

2"

3'-11"

1'-4…" 1'-4•"

11'-0"11'-0"

1'-0" 1'-0"

10"

29'-6"

10"

11'-0"

1'-4…"

26'-5"

1'-0"

3'-11"

11'-0"

14'-0" 30'-4"15'-6"

10"

10"

2'-11"

bridge

Existing

3"

2•"

PROJ. 0617-029-344, P101, C501, B642

FAIRFAX CO. - 0.1 MI. E. OF RTE. 286

ROUTE 617 OVER CSX RAILROAD

ATTACHMENT 4

ENGINEER’S COST ESTIMATES

Item Code

60409604506045260490617116181262041620436708862534

Item Code

640056401164112647656476865013652006521167900

Item Code

00100001016847668492

====

=====

LFSY

TNCYLFEALFCYLB

INCIDENTAL ITEMS

Item Quantity Unit Unit Cost Total Item Cost

Sub Total = $329,200

Mobilization LSLS

1 $248,100 $248,100Construction Surveying 1 $35,100 $35,100Environmental and Worker Protection 1 LS $6,000 $6,000Material Disposal

$2.30 $18,470Dismantle and Remove Exst. Struct. 1 $510,000 $510,000

Sub Total = $856,370

LBLS

SUBSTRUCTURE

Item Quantity Unit Unit Cost

$2,891,300$990,800

Steel Piles 12" 1120 $65.00 $72,800

Total Item Cost

Select Matl. Ty. 1 Min. CBR30 1696 $35.00 $59,360Structure Excavation 642 $40.00 $25,680

Concrete Class A3 143.9

Corrosion Resistant Reinf. Steel Cl. I 8030

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

State Project 0617-029-344, P101, C501, B642UPC No. 110156

NS Bridge Superstructure Elastic Inclusion 14" 53 $175.00 $9,320

Railing, BR27C 1 Rail 212

Concrete Class A4 Bridge Appr. Slab 119.7 $825 $98,720Reinf. Steel Bridge Appr. Slab 20382

STAGE 1 COST ESTIMATE - TOTALALTERNATE 1 - FULL CLOSURE WITH DETOUR

One Span (168') - Steel Plate Girder with Composite Concrete Deck on Existing Abutments

SUPERSTRUCTURE

Item Quantity Unit Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 264.0 $1,000 $264,000

566 $10.00 $5,660$1.35 $27,520

Bridge Deck Grooving

CYCYLBSY

$95,580

Sub Total = $1,705,720

Railing, BR27C 3 Rails 212 $300.00 $63,600

Str. Steel Plate Girder ASTM A709 Grade 50W 460883 $2.30 $1,060,040$240.00 $50,880

Corrosion Resistant Reinf. Steel Cl. I 41553 $2.30

Pedestrian Fence 8' 380 $80.00 $30,400

LBLBLFLF

$1,000.00 $143,900Reinforcing Steel 13560 $1.15 $15,600

Pile Point for 12" Steel Piles 28 $120.00 $3,360Driving Test for 12" Steel Piles 80 $90.00 $7,200

1 LS $40,000 $40,000

$776,500$4,658,600

$465,600

Subtotal for Bridge

$1,164,700$582,400$800,000

$7,671,300

Subtotal for Roadway & MOTEstimate Contingency (20%)Total

Force Account Estimate - CSXCEI Costs (30%)Construction Contingency (10%)Preliminary Engineering CostTOTAL COST

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 1 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 1 - Higher Profile, MOT Option A - Detour

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,100 CY 35.00$ = 73,500$ 00141 NS Select Borrow 4,100 CY 35.00$ = 143,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,400 LF 30.00$ 72,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,700 TON 35.00$ = 59,500$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 360 TON 120.00$ = 43,200$ 10642 Asphalt Concrete Ty. BM-25.0A 700 TON 100.00$ = 70,000$ 12600 CG-6 Curb 1,200.00 LF 35.00$ = 42,000$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 165 SY 50.00$ = 8,250$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 2.20 AC 25,000.00$ = 55,000$ 27101 Temporary Seed 530 LB 18.00$ = 9,540$ 27102 Regular Seed 530 LB 18.00$ = 9,540$ 27103 Overseeding 270 LB 10.00$ = 2,700$ 27215 Fertilizer (10 20 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 5.0 TON 400.00$ = 2,000$ 27275 SWM and E&S Lump Sum 1 LS 75,000.00$ = 75,000$ 54032 Type B Class I Pavement Line Marking 4" 2,600.00 LF 5.00$ = 13,000$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 212.00 LF 50.00$ = 10,600$

Total for Approach Roadway : 791,280$

DESCRIPTION PRICE

Item Code

60409604506045260490617116181262041620436708862534

Item Code

64005640116411264765647686501365200652111381067900

Item Code

00100001016847668492

====

=====

$1,167,030

INCIDENTAL ITEMS

Item Quantity Unit Unit Cost

$307,920Corrosion Resistant Reinf. Steel Cl. I 4860 $2.30 $11,180

Dismantle and Remove Exst. Struct. 1 $510,000 $510,000

Total Item Cost

SUBSTRUCTURE

Item Quantity Unit Unit Cost

LBSFLS

LS

Retaining Structure (MSE Wall) 3079 $100.00

Sub Total =

1944 $35.00

Reinforcing Steel 10560 $1.15

Total Item Cost

Select Matl. Ty. 1 Min. CBR30

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

State Project 0617-029-344, P101, C501, B642UPC No. 110156

NS Bridge Superstructure Elastic Inclusion 14" 53 $175.00 $9,220

Railing, BR27C 1 Rail 179

Concrete Class A4 Bridge Appr. Slab 119.7 $825 $98,720Reinf. Steel Bridge Appr. Slab 20382

STAGE 1 COST ESTIMATE - TOTAL

Pedestrian Fence 8' 314 $80.00 $25,120

ALTERNATE 2A - FULL CLOSURE WITH DETOUROne Span (135') - Steel Plate Girder with Composite Concrete Deck & MSE Walls

SUPERSTRUCTURE

Item Quantity Unit Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 215.5 $1,000 $215,500

478 $10.00 $4,780$1.35 $27,520

Bridge Deck Grooving

CYCYLBSY

$78,120

Sub Total = $1,345,100

Railing, BR27C 3 Rails 179 $300.00 $53,700

Str. Steel Plate Girder ASTM A709 Grade 50W 343241 $2.30 $789,460$240.00 $42,960

Corrosion Resistant Reinf. Steel Cl. I 33963 $2.30LBLBLFLFLFSY

$68,040Structure Excavation 126 $50.00 $6,300

Concrete Class A3 102.8 $1,000.00 $102,800

TNCYLFEALFCY

Steel Piles 12" 2080 $65.00 $135,200

$12,150

Pile Point for 12" Steel Piles 52 $120.00 $6,240Driving Test for 12" Steel Piles 80 $90.00 $7,200

LB

Sub Total = $327,300

Mobilization 1 $246,500 $246,500Construction Surveying 1 $34,800 $34,800LSEnvironmental and Worker Protection 1 LS $6,000 $6,000Material Disposal 1 LS $40,000 $40,000

$800,000

$1,014,800

$7,625,300

$2,839,500

$770,900$4,625,200

$1,156,300$578,200

Subtotal for Bridge

$465,600

Subtotal for Roadway & MOTEstimate Contingency (20%)Total

Force Account Estimate - CSXCEI Costs (30%)Construction Contingency (10%)Preliminary Engineering CostTOTAL COST

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 2A 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 2 - Higher Profile, MOT Option A - Detour

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,100 CY 35.00$ = 73,500$ 00141 NS Select Borrow 4,700 CY 35.00$ = 164,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,400 LF 30.00$ = 72,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,800 TON 35.00$ = 63,000$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 370 TON 120.00$ = 44,400$ 10642 Asphalt Concrete Ty. BM-25.0A 700 TON 100.00$ = 70,000$ 12600 CG-6 Curb 1,200.00 LF 35.00$ = 42,000$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 165 SY 50.00$ = 8,250$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 2.20 AC 25,000.00$ = 55,000$ 27101 Temporary Seed 530 LB 18.00$ = 9,540$ 27102 Regular Seed 530 LB 18.00$ = 9,540$ 27103 Overseeding 270 LB 10.00$ = 2,700$ 27215 Fertilizer (10 20 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 5.0 TON 400.00$ = 2,000$ 27275 SWM and E&S Lump Sum 1 LS 75,000.00$ = 75,000$ 54032 Type B Class I Pavement Line Marking 4" 2,600.00 LF 5.00$ = 13,000$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 179.00 LF 50.00$ = 8,950$

Total for Approach Roadway 815,330$

DESCRIPTION PRICE

Item Code

60409604506045260490617116181262041620436708862534

Item Code

64005640116411264765647686501365200652111381067900

Item Code

00100001016847668492

=Subtotal for Roadway & MOT =Estimate Contingency (20%) =Total =

Force Account Estimate - CSX =CEI Costs (30%) =Construction Contingency (10%) =Preliminary Engineering Cost =TOTAL COST =

Sub Total =

$679,400

$8,739,000

$3,325,600

$905,900$1,203,700

$5,435,200

$1,358,800

$800,000

$370,400

1 $284,700 $284,700Construction Surveying 1 $39,700 $39,700

LBSFLS

LSLS

Unit Unit Cost Total Item Cost

Mobilization

Reinforcing Steel 13290 $1.15 $15,290

Pile Point for 12" Steel Piles 60 $120.00 $7,200Driving Test for 12" Steel Piles 80 $90.00 $7,200

EALFCYLB

2447 $35.00 $85,650Structure Excavation 156 $50.00 $7,800

Concrete Class A3 129.4 $1,000.00 $129,400

TNCYLFSteel Piles 12" 2400 $65.00 $156,000

$94,450

Sub Total = $1,676,560

Railing, BR27C 3 Rails 179 $300.00 $53,700

Str. Steel Plate Girder ASTM A709 Grade 50W 449104 $2.30 $1,032,940$240.00 $42,960

Corrosion Resistant Reinf. Steel Cl. I 41063 $2.30LBLBLFLFLFSY

792 $10.00 $7,920$1.35 $33,350

Bridge Deck Grooving

CYCYLBSY

ALTERNATE 2B - STAGED CONSTRUCTION W/ ONE LANE OPENOne Span (135') - Steel Plate Girder with Composite Concrete Deck & MSE Walls

SUPERSTRUCTURE

Item Quantity Unit Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 256.4 $1,000 $256,400

Total Item Cost

Select Matl. Ty. 1 Min. CBR30

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

UPC No. 110156State Project 0617-029-344, P101, C501, B642

NS Bridge Superstructure Elastic Inclusion 14" 66 $175.00 $11,610

Railing, BR27C 1 Rail 179

Concrete Class A4 Bridge Appr. Slab 143.2 $825 $118,110Reinf. Steel Bridge Appr. Slab 24702

STAGE 1 COST ESTIMATE - STRUCTURE

Pedestrian Fence 8' 314 $80.00 $25,120

SUBSTRUCTURE

Item Quantity Unit Unit Cost

Subtotal for Bridge

$465,600

Retaining Structure (MSE Wall) 3460 $100.00 $346,000Corrosion Resistant Reinf. Steel Cl. I 6120 $2.30 $14,080

Dismantle and Remove Exst. Struct. 1 $510,000 $510,000Sub Total = $1,278,620

INCIDENTAL ITEMS

Item Quantity

Environmental and Worker Protection 1 LS $6,000 $6,000Material Disposal 1 LS $40,000 $40,000

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 2B 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 2 - Higher Profile, MOT Option B - One Lane, Two way Traffic

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,100 CY 35.00$ = 73,500$ 00141 NS Select Borrow 5,100 CY 35.00$ = 178,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,400 LF 30.00$ = 72,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,900 TON 35.00$ = 66,500$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 390 TON 120.00$ = 46,800$ 10642 Asphalt Concrete Ty. BM-25.0A 700 TON 100.00$ = 70,000$ 12600 CG-6 Curb 1,200.00 LF 35.00$ = 42,000$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 140 SY 50.00$ = 7,000$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 2.20 AC 25,000.00$ = 55,000$ 27101 Temporary Seed 530 LB 18.00$ = 9,540$ 27102 Regular Seed 530 LB 18.00$ = 9,540$ 27103 Overseeding 270 LB 10.00$ = 2,700$ 27215 Fertilizer (10 20 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 5.0 TON 400.00$ = 2,000$ 27275 SWM and E&S Lump Sum 1 LS 100,000.00$ = 100,000$ 54032 Type B Class I Pavement Line Marking 4" 2,600.00 LF 5.00$ = 13,000$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 179.00 LF 50.00$ = 8,950$

Total for Approach Roadway : 858,980$

DESCRIPTION PRICE

Item Code

60409604506045260490617116181262041620436708862534

Item Code

64005640116411264765647686501365200652111381067900

Item Code

00100001016847668492

=Subtotal for Roadway & MOT =Estimate Contingency (20%) =Total =

Force Account Estimate - CSX =CEI Costs (30%) =Construction Contingency (10%) =Preliminary Engineering Cost =TOTAL COST =

$689,200

$8,846,100

$3,394,800

$918,900$1,199,300

$5,513,000

$1,378,300

$800,000

Unit Unit Cost Total Item Cost

Sub Total = $374,900

Subtotal for Bridge

$465,600

Environmental and Worker Protection 1 LS $6,000 $6,000Material Disposal 1 LS $40,000

80 $90.00 $7,200

LB

Mobilization 1 $288,400 $288,400Construction Surveying 1 $40,500 $40,500

Reinforcing Steel 14190 $1.15 $16,320

LS

$362,000$15,050

$510,000$1,310,030

$91,420Structure Excavation 166 $40.00 $6,640

Concrete Class A3 138.2 $1,000.00 $138,200

TNCYLFEALFCY

Steel Piles 12" 2400 $65.00 $156,000Pile Point for 12" Steel Piles 60 $120.00 $7,200Driving Test for 12" Steel Piles

Corrosion Resistant Reinf. Steel Cl. I 45503 $2.30LBLBLFLFLFSY

Sub Total = $1,709,780

Railing, BR27C 3 Rails 179 $300.00 $53,700

Str. Steel Plate Girder ASTM A709 Grade 50W 449104 $2.30 $1,032,940$240.00 $42,960

$25,120$80.00

ALTERNATE 2C - STAGED CONSTRUCTION W/ TWO LANES OPENOne Span (135') - Steel Plate Girder with Composite Concrete Deck & MSE Walls

SUPERSTRUCTURE

Item Quantity Unit Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 269.5 $1,000 $269,500

866 $10.00 $8,660$1.35 $35,400

Bridge Deck Grooving

CYCYLBSY

$104,660

$35.00

Total Item Cost

Select Matl. Ty. 1 Min. CBR30

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

State Project 0617-029-344, P101, C501, B642UPC No. 110156

NS Bridge Superstructure Elastic Inclusion 14" 71 $175.00 $12,380

Railing, BR27C 1 Rail 179

Concrete Class A4 Bridge Appr. Slab 150.9 $825 $124,460Reinf. Steel Bridge Appr. Slab 26222

STAGE 1 COST ESTIMATE - STRUCTURE

Pedestrian Fence 8' 314

$40,000

SUBSTRUCTURE

Item Quantity Unit Unit Cost

LBSFLS

LS

Retaining Structure (MSE Wall) 3620 $100.00Corrosion Resistant Reinf. Steel Cl. I 6540 $2.30

Dismantle and Remove Exst. Struct. 1 $510,000Sub Total =

INCIDENTAL ITEMS

Item Quantity

2612

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 2C 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 2 - Higher Profile, MOT Option C - Two Lane, Two way Traffic

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,200 CY 35.00$ = 77,000$ 00141 NS Select Borrow 5,300 CY 35.00$ = 185,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,400 LF 30.00$ = 72,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,900 TON 35.00$ = 66,500$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 400 TON 120.00$ = 48,000$ 10642 Asphalt Concrete Ty. BM-25.0A 770 TON 100.00$ = 77,000$ 12600 CG-6 Curb 1,200.00 LF 35.00$ = 42,000$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 125 SY 50.00$ = 6,250$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 2.20 AC 25,000.00$ = 55,000$ 27101 Temporary Seed 530 LB 18.00$ = 9,540$ 27102 Regular Seed 530 LB 18.00$ = 9,540$ 27103 Overseeding 270 LB 10.00$ = 2,700$ 27215 Fertilizer (10 20 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 5.0 TON 400.00$ = 2,000$ 27275 SWM and E&S Lump Sum 1 LS 100,000.00$ = 100,000$ 54032 Type B Class I Pavement Line Marking 4" 2,600.00 LF 5.00$ = 13,000$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 179.00 LF 50.00$ = 8,950$

Total for Approach Roadway : 876,930$

DESCRIPTION PRICE

Item Code

60409604506045260490617116181262041620436708862534

Item Code

640056401164112647656476865013652006521167900

Item Code

00100001016847668492

Subtotal for Bridge =Subtotal for Roadway & MOT =Estimate Contingency (20%) =Total =

Force Account Estimate - CSX =CEI Costs (30%) =Construction Contingency (10%) =Preliminary Engineering Cost =TOTAL COST = $7,899,600

$3,067,900

$792,000$892,100

$4,752,000

$1,188,000$594,000$900,000

$465,600

Sub Total = $334,300

Mobilization 1 $252,500 $252,500Construction Surveying 1 $35,800 $35,800

LSLS

Environmental and Worker Protection 1 LS $6,000 $6,000Material Disposal 1 LS $40,000 $40,000

Dismantle and Remove Exst. Struct. 1 $510,000 $510,000Sub Total = $1,176,560

INCIDENTAL ITEMS

Item Quantity Unit Unit Cost Total Item Cost

$40.00 $28,120

Concrete Class A3 297.8 $1,000.00 $297,800Reinforcing Steel 29995 $1.15 $34,500

Pile Point for 12" Steel Piles 68 $120.00 $8,160Driving Test for 12" Steel Piles 210 $90.00 $18,900

$124,690

Sub Total = $1,557,040

Railing, BR27C 3 Rails 226 $300.00 $67,690

Str. Steel Plate Girder ASTM A709 Grade 50W 351340 $2.30 $808,090$240.00 $54,150

Corrosion Resistant Reinf. Steel Cl. I 54211 $2.30LBLBLFLFLFSY

Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 332.5 $1,000 $332,500CY

602 $10.00 $6,020$1.35 $27,520

Bridge Deck Grooving

CYLBSY

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

State Project 0617-029-344, P101, C501, B642UPC No. 110156

NS Bridge Superstructure Elastic Inclusion 14" 29 $175.00 $5,080

Railing, BR27C 1 Rail 226

Concrete Class A4 Bridge Appr. Slab 119.7 $825 $98,720Reinf. Steel Bridge Appr. Slab 20382

STAGE 1 COST ESTIMATE - STRUCTUREALTERNATE 3A - FULL CLOSURE WITH DETOUR

Three Span (45'-92'-45') - Steel Plate Girder with Composite Concrete DeckSUPERSTRUCTURE

Item Quantity Unit

Corrosion Resistant Reinf. Steel Cl. I 37887 $2.30 $87,140

Pedestrian Fence 8' 407 $80.00 $32,580

SUBSTRUCTURE

Item Quantity Unit Unit Cost

Steel Piles 12" 2292 $65.00 $149,000

Total Item Cost

Select Matl. Ty. 1 Min. CBR30 1227 $35.00 $42,940Structure Excavation 703

TNCYLFEALFCYLBLBLS

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 3A 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 3 - Optimum Profile, MOT Option A - Detour

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,200 CY 35.00$ = 77,000$ 00141 NS Select Borrow 2,300 CY 35.00$ = 80,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,200 LF 30.00$ = 66,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,600 TON 35.00$ = 56,000$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 350 TON 120.00$ = 42,000$ 10642 Asphalt Concrete Ty. BM-25.0A 600 TON 100.00$ = 60,000$ 12600 CG-6 Curb 1,100.00 LF 35.00$ = 38,500$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 165 SY 50.00$ = 8,250$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 1.80 AC 25,000.00$ = 45,000$ 27101 Temporary Seed 440 LB 18.00$ = 7,920$ 27102 Regular Seed 440 LB 18.00$ = 7,920$ 27103 Overseeding 220 LB 10.00$ = 2,200$ 27215 Fertilizer (10 20 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 4.0 TON 400.00$ = 1,600$ 27275 SWM and E&S Lump Sum 1 LS 75,000.00$ = 75,000$ 54032 Type B Class I Pavement Line Marking 4" 2,300.00 LF 5.00$ = 11,500$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 225.00 LF 50.00$ = 11,250$

Total for Approach Roadway : 692,590$

DESCRIPTION PRICE

Item Code

60409604506045260490617116181262041620436708862534

Item Code

640056401164112647656476865013652006521167900

Item Code

00100001016847668492

Subtotal for Bridge =Subtotal for Roadway & MOT =Estimate Contingency (20%) =Total =

Force Account Estimate - CSX =CEI Costs (30%) =Construction Contingency (10%) =Preliminary Engineering Cost =TOTAL COST =

$5,613,500

$701,700

$9,084,200

$3,619,200

$935,600$1,058,700

$1,403,400

$900,000

$465,600

Sub Total = $380,200

Mobilization 1 $293,100 $293,100Construction Surveying 1 $41,100 $41,100

LSLS

Environmental and Worker Protection 1 LS $6,000 $6,000Material Disposal 1 LS $40,000 $40,000

Dismantle and Remove Exst. Struct. 1 $510,000 $510,000Sub Total = $1,340,730

INCIDENTAL ITEMS

Item Quantity Unit Unit Cost Total Item Cost

$40.00 $32,920

Concrete Class A3 371.4 $1,000.00 $371,400Reinforcing Steel 36155 $1.15 $41,580

Pile Point for 12" Steel Piles 95 $120.00 $11,400Driving Test for 12" Steel Piles 210 $90.00 $18,900

$146,560

Sub Total = $1,898,240

Railing, BR27C 3 Rails 226 $300.00 $67,690

Str. Steel Plate Girder ASTM A709 Grade 50W 452975 $2.30 $1,041,850$240.00 $54,150

Corrosion Resistant Reinf. Steel Cl. I 63721 $2.30LBLBLFLFLFSY

Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 387.6 $1,000 $387,600

996 $10.00 $9,960$1.35 $33,350

Bridge Deck Grooving

CYCYLBSY

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

UPC No. 110156State Project 0617-029-344, P101, C501, B642

NS Bridge Superstructure Elastic Inclusion 14" 36 $175.00 $6,390

Railing, BR27C 1 Rail 226

Concrete Class A4 Bridge Appr. Slab 143.2 $825 $118,110Reinf. Steel Bridge Appr. Slab 24702

STAGE 1 COST ESTIMATE - STRUCTUREALTERNATE 3B - STAGED CONSTRUCTION W/ ONE LANE OPENThree Span (45'-92'-45') - Steel Plate Girder with Composite Concrete Deck

SUPERSTRUCTURE

Item Quantity Unit

Corrosion Resistant Reinf. Steel Cl. I 45517 $2.30 $104,690

Pedestrian Fence 8' 407 $80.00 $32,580

SUBSTRUCTURE

Item Quantity Unit Unit Cost

Steel Piles 12" 3012 $65.00 $195,800

Total Item Cost

Select Matl. Ty. 1 Min. CBR30 1544 $35.00 $54,040Structure Excavation 823

TNCYLFEALFCYLBLBLS

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 3B 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 3 - Optimum Profile, MOT Option B - One Lane, Two way Traffic

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,100 CY 35.00$ = 73,500$ 00141 NS Select Borrow 2,300 CY 35.00$ = 80,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,200 LF 30.00$ = 66,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,600 TON 35.00$ = 56,000$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 360 TON 120.00$ = 43,200$ 10642 Asphalt Concrete Ty. BM-25.0A 600 TON 100.00$ = 60,000$ 12600 CG-6 Curb 1,100.00 LF 35.00$ = 38,500$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 140 SY 50.00$ = 7,000$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 1.80 AC 25,000.00$ = 45,000$ 27101 Temporary Seed 440 LB 18.00$ = 7,920$ 27102 Regular Seed 440 LB 18.00$ = 7,920$ 27103 Overseeding 220 LB 10.00$ = 2,200$ 27215 Fertilizer (10 20 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 4.0 TON 400.00$ = 1,600$ 27275 SWM and E&S Lump Sum 1 LS 100,000.00$ = 100,000$ 54032 Type B Class I Pavement Line Marking 4" 2,300.00 LF 5.00$ = 11,500$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 225.00 LF 50.00$ = 11,250$

Total for Approach Roadway : 714,040$

DESCRIPTION PRICE

Item Code

60409604506045260490617116181262041620436708862534

Item Code

640056401164112647656476865013652006521167900

Item Code

00100001016847668492

Subtotal for Bridge =Subtotal for Roadway & MOT =Estimate Contingency (20%) =Total =

Force Account Estimate - CSX =CEI Costs (30%) =Construction Contingency (10%) =Preliminary Engineering Cost =TOTAL COST =

Environmental and Worker Protection 1 LS $6,000 $6,000Material Disposal 1 LS $40,000 $40,000

Corrosion Resistant Reinf. Steel Cl. I 46657 $2.30 $107,310

Pedestrian Fence 8' 407 $80.00 $32,580

SUBSTRUCTURE

Item Quantity Unit Unit Cost

Steel Piles 12" 3092 $65.00 $201,000

Total Item Cost

Select Matl. Ty. 1 Min. CBR30 1578 $35.00 $55,230Structure Excavation 866

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

UPC No. 110156State Project 0617-029-344, P101, C501, B642

NS Bridge Superstructure Elastic Inclusion 14" 39 $175.00 $6,820

Railing, BR27C 1 Rail 226

Concrete Class A4 Bridge Appr. Slab 150.9 $825 $124,460Reinf. Steel Bridge Appr. Slab 26222

STAGE 1 COST ESTIMATE - STRUCTUREALTERNATE 3C - STAGED CONSTRUCTION W/ TWO LANES OPEN

Three Span (45'-92'-45') - Steel Plate Girder with Composite Concrete DeckSUPERSTRUCTURE

Item Quantity Unit Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 405.4 $1,000 $405,400

1091 $10.00 $10,910$1.35 $35,400

Bridge Deck Grooving

CYCYLBSY

$153,920

Sub Total = $1,933,180

Railing, BR27C 3 Rails 226 $300.00 $67,690

Str. Steel Plate Girder ASTM A709 Grade 50W 452975 $2.30 $1,041,850$240.00 $54,150

Corrosion Resistant Reinf. Steel Cl. I 66921 $2.30LBLBLFLFLFSY

$40.00 $34,640

Concrete Class A3 427.2 $1,000.00 $427,200

TNCYLF

Reinforcing Steel 36575 $1.15 $42,070

Pile Point for 12" Steel Piles 97 $120.00 $11,640Driving Test for 12" Steel Piles 210 $90.00 $18,900

EALFCYLB

Mobilization 1 $299,600 $299,600Construction Surveying 1 $42,400 $42,400

Dismantle and Remove Exst. Struct. 1 $510,000 $510,000Sub Total = $1,407,990

INCIDENTAL ITEMS

Item Quantity Unit Unit Cost Total Item Cost

LBLS

LSLS

$1,063,200

$1,437,800

$900,000$9,273,200

$5,750,900

$465,600

$718,900

$3,729,200

$958,500

Sub Total = $388,000

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 3C 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 3 - Optimum Profile, MOT Option C - Two Lane, Two Way Traffic

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,200 CY 35.00$ = 77,000$ 00141 NS Select Borrow 2,500 CY 35.00$ = 87,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,200 LF 30.00$ = 66,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,700 TON 35.00$ = 59,500$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 410 TON 120.00$ = 49,200$ 10642 Asphalt Concrete Ty. BM-25.0A 670 TON 100.00$ = 67,000$ 12600 CG-6 Curb 1,100.00 LF 35.00$ = 38,500$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 135 SY 50.00$ = 6,750$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 1.80 AC 25,000.00$ = 45,000$ 27101 Temporary Seed 440 LB 18.00$ = 7,920$ 27102 Regular Seed 440 LB 18.00$ = 7,920$ 27103 Overseeding 220 LB 10.00$ = 2,200$ 27215 Fertilizer (10 30 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 4.0 TON 400.00$ = 1,600$ 27275 SWM and E&S Lump Sum 1 LS 100,000.00$ = 100,000$ 54032 Type B Class I Pavement Line Marking 4" 2,300.00 LF 5.00$ = 11,500$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 225.00 LF 50.00$ = 11,250$

Total for Approach Roadway : 740,790$

DESCRIPTION PRICE

Item Code

60409604506045260490617116181262041620436708862534

Item Code

64005640116411264765647686501365200652111381067900

Item Code

00100001016847668492

=Subtotal for Roadway & MOT =Estimate Contingency (20%) =Total =

Force Account Estimate - CSX =CEI Costs (30%) =Construction Contingency (10%) =Preliminary Engineering Cost =TOTAL COST =

$800,000

$1,014,800

$8,562,400

$3,407,400

$884,500$5,306,700

$1,326,700$663,400

Subtotal for Bridge

$465,600

Sub Total = $327,300

Mobilization 1 $246,500 $246,500Construction Surveying 1 $34,800 $34,800LSEnvironmental and Worker Protection 1 LS $6,000 $6,000Material Disposal 1 LS $40,000 $40,000

$12,150

Pile Point for 12" Steel Piles 52 $120.00 $6,240Driving Test for 12" Steel Piles 80 $90.00 $7,200

LB

$68,040Structure Excavation 126 $50.00 $6,300

Concrete Class A3 102.8 $1,000.00 $102,800

TNCYLFEALFCY

Steel Piles 12" 2080 $65.00 $135,200

$78,120

Sub Total = $1,345,100

Railing, BR27C 3 Rails 179 $300.00 $53,700

Str. Steel Plate Girder ASTM A709 Grade 50W 343241 $2.30 $789,460$240.00 $42,960

Corrosion Resistant Reinf. Steel Cl. I 33963 $2.30LBLBLFLFLFSY

478 $10.00 $4,780$1.35 $27,520

Bridge Deck Grooving

CYCYLBSY

ALTERNATE 4 - FULL CLOSURE WITH DETOUR ACCELERATED BRIDGE CONSTRUCTIONOne Span (135') - Steel Plate Girder with Composite Concrete Deck & MSE Walls

SUPERSTRUCTURE

Item Quantity Unit Unit Cost Total Item Cost

Conc. Class A4 Mod. Low Shrinkage 215.5 $1,000 $215,500

Total Item Cost

Select Matl. Ty. 1 Min. CBR30

ROUTE 617 OVER CSX RAILROADFairfax County, NOVA District

State Project 0617-029-344, P101, C501, B642UPC No. 110156

NS Bridge Superstructure Elastic Inclusion 14" 53 $175.00 $9,220

Railing, BR27C 1 Rail 179

Concrete Class A4 Bridge Appr. Slab 119.7 $825 $98,720Reinf. Steel Bridge Appr. Slab 20382

STAGE 1 COST ESTIMATE - TOTAL

Pedestrian Fence 8' 314 $80.00 $25,120

SUBSTRUCTURE

Item Quantity Unit Unit Cost

LBSFLS

LS

Retaining Structure (MSE Wall) 3079 $100.00

Sub Total =

1944 $35.00

Reinforcing Steel 10560 $1.15

$1,167,030

INCIDENTAL ITEMS

Item Quantity Unit Unit Cost

$307,920Corrosion Resistant Reinf. Steel Cl. I 4860 $2.30 $11,180

Dismantle and Remove Exst. Struct. 1 $510,000 $510,000

Total Item Cost

Rte 617 over CSX ‐ Stage I Quantities ‐ Alternate 4 11/18/2016

Improvement of Backlick RoadROUTE 617 CSX Railroad - ALTERNATE 4 - Higher Profile, ABC Construction using MOT Option A - Detour

Fairfax County, VirginiaVirginia Department of Transportation - NOVA District

State Project 0617-029-344, P101, B642

110156 Project No. 0617-029-344

ENGINEER'S COST ESTIMATE18-Nov-16

Approach Roadway

Item Code QTY UNIT COST00110 Clearing and Grubbing 1 LS 11,000.00$ = 11,000$ 00120 Regular Excavation 2,100 CY 35.00$ = 73,500$ 00141 NS Select Borrow 4,700 CY 35.00$ = 164,500$ 01180 18" Pipe 31 LF 150.00$ = 4,650$ 00588 Underdrain UD-4 2,400 LF 30.00$ = 72,000$ 06820 Drop Inlet DI-3B, L=10' 1 EA 5,000.00$ = 5,000$ 07510 Drop Inlet DI-7A 5 EA 5,000.00$ = 25,000$ 09046 Manhole MH-1 1 EA 7,000.00$ = 7,000$ 10128 Aggregate Base Material Ty. I No.21B 1,800 TON 35.00$ = 63,000$ 10636 Asphalt Concrete Surface Course Ty. SM-9.5D 370 TON 120.00$ = 44,400$ 10642 Asphalt Concrete Ty. BM-25.0A 700 TON 100.00$ = 70,000$ 12600 CG-6 Curb 1,200.00 LF 35.00$ = 42,000$ 13315 GUARDRAIL TERMINAL GR‐11 1.00 EA 1,000.00$ = 1,000$ 13320 Guardrail GR-2 410.00 LF 30.00$ = 12,300$ 13345 Guardrail Terminal GR-9 1.00 EA 3,000.00$ = 3,000$ 13349 Guardrail Terminal Site Preperation 2.00 EA 1,000.00$ = 2,000$ 13392 Fixed Object Attachment GR-FOA-2 Type I 5.00 EA 2,500.00$ = 12,500$ 24430 Demolition of Pavement (Flexible) 165 SY 50.00$ = 8,250$ 24505 NS Relocate Existing StreetLight 1.00 EA 10,000.00$ = 10,000$ 24505 Relocate Existing Sign 12.00 EA 250.00$ = 3,000$ 24600 Remove Exist. Guardrail 400.00 LF 5.00$ = 2,000$ 27012 Topsoil Class A 4" 2.20 AC 25,000.00$ = 55,000$ 27101 Temporary Seed 530 LB 18.00$ = 9,540$ 27102 Regular Seed 530 LB 18.00$ = 9,540$ 27103 Overseeding 270 LB 10.00$ = 2,700$ 27215 Fertilizer (10 20 10) 1.0 TON 1,500.00$ = 1,500$ 27250 Lime 5.0 TON 400.00$ = 2,000$ 27275 SWM and E&S Lump Sum 1 LS 75,000.00$ = 75,000$ 54032 Type B Class I Pavement Line Marking 4" 2,600.00 LF 5.00$ = 13,000$ 67086 PED. FENCE 6' 50.00 LF 40.00$ = 2,000$ 67088 PED. FENCE 8' 179.00 LF 50.00$ = 8,950$

Total for Approach Roadway 815,330$

DESCRIPTION PRICE

MAINTENANCE OF TRAFFIC

COST ESTIMATES

MOT OPTION A ‐ with no Bike/Pedestrian Access

ITEM CODE DESCRIPTION QTY UNIT PRICE  COST

Maintenance of Traffic  270 Day

Maintenance of Traffic Lump Sum MOB 1 LS 40,000.00$    $40,000

Bike / Pedestrian Shuttle 1 LS 10,000.00$    $10,000

10128 Aggregate Base Material Ty. I No.21B  500 TON 33.00$            $16,500

10636 Asphalt Concrete Surface Course Ty. SM‐9.5D  650 TON 113.00$         $73,450

10643 Asphalt Concrete Ty. BM‐25.0D  0 TON 93.00$            $0

24160 Construction Signs  480 SF 21.50$            $10,320

24278 Group 2 Channelizing Devices  270 DAY 65.00$            $17,550

24279 PORTABLE CHANGEABLE MESSAGE SIGN  3240 HR 5.00$              $16,200

24281 ELECTRONIC ARROW  100 HR 2.25$              $225

24282 Flagger Service 50 HR 23.00$            $1,150

24297 TRAF.BARR.SER.CONC.DOUBLE FACE  300 LF 38.00$            $11,400

14260 Crusher Run Aggregate No. 25 or 26‐ 0 TON 24.00$            $0

24288 Warning Light Type B  0 DAY 2.50$              $0

50030 BARRIER DELINEATOR  50 EA 10.50$            $525

51955 Temporary Traffic Control Signal,  0 LS 30,000.00$    $0

54105 Eradication of Existing Pavement Marking 500 LF 2.25$              $1,125

54510 Construction Pavement Marking Type D Class I 500 LF 2.00$              $1,000

54514  Construction Pavement Marking Type D Class I 8"  0 LF 2.28$              $0

54522 Construction Pavement Marking Type D Class I 24"  0 LF 9.00$              $0

54240 Temporary Pavement Marker, 1‐Way  0 EA 8.25$              $0

Total for MOT = $199,445

MOT OPTION B1 ‐ One Lane with Temp Signal

ITEM CODE DESCRIPTION QTY UNIT PRICE  COST

Maintenance of Traffic 270 Day

Maintenance of Traffic Lump Sum MOB 1 LS 50,000.00$    $50,000

Bike / Pedestrian Shuttle 0 LS 10,000.00$    $0

10128 Aggregate Base Material Ty. I No.21B  1000 TON 33.00$            $33,000

10636 Asphalt Concrete Surface Course Ty. SM‐9.5D  1300 TON 113.00$         $146,900

10643 Asphalt Concrete Ty. BM‐25.0D  0 TON 93.00$            $0

24160 Construction Signs  320 SF 21.50$            $6,880

24278 Group 2 Channelizing Devices  270 DAY 65.00$            $17,550

24279 PORTABLE CHANGEABLE MESSAGE SIGN  6480 HR 5.00$              $32,400

24281 ELECTRONIC ARROW  100 HR 2.25$              $225

24282 Flagger Service 200 HR 23.00$            $4,600

24297 TRAF.BARR.SER.CONC.DOUBLE FACE  420 LF 38.00$            $15,960

14260 Crusher Run Aggregate No. 25 or 26‐ 0 TON 24.00$            $0

24288 Warning Light Type B  0 DAY 2.50$              $0

50030 BARRIER DELINEATOR  70 EA 10.50$            $735

51955 Temporary Traffic Control Signal,  1 LS 30,000.00$    $30,000

54105 Eradication of Existing Pavement Marking 1500 LF 2.25$              $3,375

54510 Construction Pavement Marking Type D Class I 1500 LF 2.00$              $3,000

54514  Construction Pavement Marking Type D Class I 8"  0 LF 2.28$              $0

54522 Construction Pavement Marking Type D Class I 24"  0 LF 9.00$              $0

54240 Temporary Pavement Marker, 1‐Way  0 EA 8.25$              $0

Total for MOT = $344,625

MOT OPTION B2 ‐ One Lane by time of day

ITEM CODE DESCRIPTION QTY UNIT PRICE  COST

Maintenance of Traffic  270 Day

Maintenance of Traffic Lump Sum MOB 1 LS 50,000.00$    $50,000

Bike / Pedestrian Shuttle 0 LS 10,000.00$    $0

10128 Aggregate Base Material Ty. I No.21B  1000 TON 33.00$            $33,000

10636 Asphalt Concrete Surface Course Ty. SM‐9.5D  1300 TON 113.00$         $146,900

10643 Asphalt Concrete Ty. BM‐25.0D  0 TON 93.00$            $0

24160 Construction Signs  640 SF 21.50$            $13,760

24278 Group 2 Channelizing Devices  270 DAY 65.00$            $17,550

24279 PORTABLE CHANGEABLE MESSAGE SIGN  6480 HR 5.00$              $32,400

24281 ELECTRONIC ARROW  100 HR 2.25$              $225

24282 Flagger Service 300 HR 23.00$            $6,900

24297 TRAF.BARR.SER.CONC.DOUBLE FACE  420 LF 38.00$            $15,960

14260 Crusher Run Aggregate No. 25 or 26‐ 0 TON 24.00$            $0

24288 Warning Light Type B  0 DAY 2.50$              $0

50030 BARRIER DELINEATOR  70 EA 10.50$            $735

51955 Temporary Traffic Control Signal,  0 LS 30,000.00$    $0

54105 Eradication of Existing Pavement Marking 1500 LF 2.25$              $3,375

54510 Construction Pavement Marking Type D Class I 1500 LF 2.00$              $3,000

54514  Construction Pavement Marking Type D Class I 8"  0 LF 2.28$              $0

54522 Construction Pavement Marking Type D Class I 24"  0 LF 9.00$              $0

54240 Temporary Pavement Marker, 1‐Way  0 EA 8.25$              $0

Total for MOT = $323,805

MOT OPTION C ‐ Two Way Traffic w no Bike Ped Access

ITEM CODE DESCRIPTION QTY UNIT PRICE  COST

Maintenance of Traffic  270 Day

Maintenance of Traffic Lump Sum MOB 1 LS 50,000.00$    $50,000

Bike / Pedestrian Shuttle 1 LS 10,000.00$    $10,000

10128 Aggregate Base Material Ty. I No.21B  1000 TON 33.00$            $33,000

10636 Asphalt Concrete Surface Course Ty. SM‐9.5D  1300 TON 113.00$         $146,900

10643 Asphalt Concrete Ty. BM‐25.0D  0 TON 93.00$            $0

24160 Construction Signs  320 SF 21.50$            $6,880

24278 Group 2 Channelizing Devices  270 DAY 65.00$            $17,550

24279 PORTABLE CHANGEABLE MESSAGE SIGN  6480 HR 5.00$              $32,400

24281 ELECTRONIC ARROW  100 HR 2.25$              $225

24282 Flagger Service 100 HR 23.00$            $2,300

24297 TRAF.BARR.SER.CONC.DOUBLE FACE  420 LF 38.00$            $15,960

14260 Crusher Run Aggregate No. 25 or 26‐ 0 TON 24.00$            $0

24288 Warning Light Type B  0 DAY 2.50$              $0

50030 BARRIER DELINEATOR  70 EA 10.50$            $735

51955 Temporary Traffic Control Signal,  0 LS 30,000.00$    $0

54105 Eradication of Existing Pavement Marking 1500 LF 2.25$              $3,375

54510 Construction Pavement Marking Type D Class I 1500 LF 2.00$              $3,000

54514  Construction Pavement Marking Type D Class I 8"  0 LF 2.28$              $0

54522 Construction Pavement Marking Type D Class I 24"  0 LF 9.00$              $0

54240 Temporary Pavement Marker, 1‐Way  0 EA 8.25$              $0

Total for MOT = $322,325

ATTACHMENT 5

STAGE I PRELIMINARY BRIDGE PLANS FOR RECOMMENDED ALTERNATE

XXX-XXNov. 2016HNT

BSW

STM

617

Date Plan No. Sheet No.Designed: ...........

Drawn: ................

Checked: ............2016, Commonwealth of Virginiac

No. Description Date

STRUCTURE AND BRIDGE DIVISION

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

Revisions

ROUTE

FEDERAL AID

PROJECT ROUTE PROJECT

STATE SHEET

NO.

VA.

STATEROUTE

FEDERAL AID

PROJECT ROUTE PROJECT

STATE SHEET

NO.STATE

Ty

p

Sect-

Alt 2

A - f

ull siz

e.d

gn

STRUCTURAL ENGINEER

FAIRFAX, VA

PRIME ENGINEERING, INC.

0617-029-344, P101, B642

TRANSVERSE SECTION

G1 G2 G3 G4 G5 G6

SBL

finished grade

Point of

NBL

Rte. 617 BL

BR27C-12

2.0% 2.0%

1.0%

BR27C-15

10"15'-6"

2'-0" 12'-0" 12'-0"

45'-2" Out to Out

10"2'-0"

3'-10"

3'-0" 5 Spaces @ 7'-10" = 39'-2"

3'-0"

ALTERNATE 2A

TYPICAL SECTION

2

2 of 3

FOR CONSTRUCTION

THESE PLANS NOT TO BE USED

PRELIMINARY PLANS

Scale: 1/2" = 1'-0"

ATTACHMENT 6

TRAFFIC IMPACT STUDY - EXECUTIVE SUMMARY

 

BACKLICK ROAD 

BRIDGE EVALUATION Route 617 Backlick Road Bridge over 

the CSX Railroad 

ABSTRACT Traffic evaluation to determine impacts of construction on Newington area roadways. Study Intersections shown. 

3201 Jermantown Road Suite 660

Fairfax, VA 22030 Tel: (703) 865-0606

www.primeeng.com

 

Performed for Virginia Department 

of Transportation  

Performed by PRIME AE Group Contract 43280 

Revision 1 18 November, 2016 

Executive Summary  

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT Traffic Study ‐ November 2016 

 

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT 

Traffic Study  

I Background Virginia’s Atlantic Gateway Project is a $1.4 billion series of project to address congestion on the 

I‐95 corridor in Northern Virginia. The project includes 14 miles of new rail track to improve 

capacity for freight, commuter and passenger rail service. 

The Route 617 Bridge over the CSX railroad in the Newington Area currently has insufficient 

horizontal or vertical clearance to accommodate a new rail track. A number of options to 

replace the existing bridge are being investigated by PRIME AE Group in a Stage 1 Bridge Study. 

This Traffic Study has the following 

purposes: 

1) determine the relative traffic 

impacts of staged versus full 

closure during construction; 

2) develop traffic estimates to 

inform area businesses and 

residences; 

3) determine mitigation that can 

be performed during 

construction. 

The traffic impact of the proposed full 

closure was evaluated for seven 

intersections. Existing intersection 

traffic counts were developed using 

the NOVA Signal Files (Synchro files) 

and updated with new 24 hour 

counts. The volume of strictly external 

traffic – that is “cut through” traffic – was 

estimated using Bluetooth readers. Existing traffic volumes on Backlick Bridge was reassigned to 

Newington Road. The seven study intersections:  

1. Newington Road and Loisdale Road; 

2. Newington Road Underpass of CSX Railroad; 

3. Intersection of Newington Road and Cinder Bed Road;  

4. Telegraph Road and Newington Road; 

5. Intersection of Backlick Road and Fairfax County Parkway spur, 

6. Backlick Road Spur and Fairfax County Parkway. 

7. Loisdale Road and Fairfax County Parkway.    

Executive Summary  

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT Traffic Study ‐ November 2016 

 

II Existing Traffic and Level of Service Traffic volumes on the Backlick Road bridge 

over the CSX Railroad are relatively light when 

compared with the surrounding road network. 

The Average Daily Traffic (ADT) for Backlick 

Road is 2,100 vpd. The Average Daily Traffic 

(ADT) for Fairfax County Parkway is 40,000 

vpd.  

The figure to the right shows peak hour 

vehicles per hour. These peak hour volumes are 

based on VDOT Synchro files and recent September 2016 24 hour tube counts. Peak hour 

volumes less than 200 are considered light. 

The intersection that is most likely to have be affected by a full closure is Intersection 2 – 

Newington Road Underpass.  This intersection is not a true intersection, rather it is a one‐way 

segment of roadway. Small platoons of three or four vehicles take turns going through the 

underpass. This results in a low capacity segment of roadway. This operation was simulated with 

a single phase signal with a short maximum green split. 

Queues from the Newington Road 

CSX Underpass vary as shown in 

the table on the following page. 

The distance between the 

Underpass and Loisdale Road is 

approximately 450 feet. The 

queues shown are the result of 

traffic simulation using 

SIMTRAFFIC, and are similar to 

queues observed in the field. 

The highest volume in the Study 

Area is Intersection 7 ‐ Loisdale 

Road and Fairfax County Parkway. 

The LOS observed at this 

intersection is worse than LOS 

calculated by Synchro. Loisdale 

Road and Fairfax County Parkway 

is LOS F in the AM, and this is due 

to a very heavy eastbound 

movement. 

   

Intersection Level of Service  

AM Peak 

PM Peak 

MD1 Period 

Off‐Peak 

1.  Newington Road and Loisdale Road 

B 15.4 

C 30.9 

B 16.5 

C 30.3 

2.  Newington Road Underpass of CSX Railroad (E/W) 

F/F 122/ 118 

C/F 32.0/ 335 

D/D 44.8/ 45.6 

D/F 51.0/ 154 

3.  Newington Road and Cinder Bed Road 

‐  ‐  ‐  ‐ 

4.  Telegraph Road and Newington Road 

B 17.6 

C 34.2 

B 16.0 

B 11.6 

5.  Backlick Road and Fairfax County Parkway Spur 

A 9.5 

B 10.2 

B 12.2 

A 9.0 

6.  Backlick Road Spur and Fairfax County Parkway 

B 19.9 

B 15.5 

B 12.0 

A 8.2 

7.  Loisdale Road and Fairfax County Parkway 

F 96.5 

D 35.7 

D 37.5 

B 17.6 

Executive Summary  

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT Traffic Study ‐ November 2016 

 

 

 

The traffic internal to the study area – that is along Backlick Road, Cinder Bed Road and 

Newington Road is commercial and industrial. There is a high percentage of heavy vehicles, 

especially during the day, and for analysis purposes 25% heavy vehicles was assumed. Fairfax 

County Connector Route 334 uses Cinder Bed Road and the underpass as well as Backlick Road. 

The proposed detour route has a height restriction of 13’ 11”. Area businesses were contacted 

to determine if they operate oversized vehicles. None were discovered. 

III External Through Traffic There are currently 192 southbound vehicles per hour in the AM and 157 northbound vehicles 

per hour in the PM traveling over the Backlick Road /CSC Railroad bridge. During the full closure 

these vehicles will either: 

Divert via the Underpass and Loisdale Road; 

Divert via Newington Road via Telegraph Road; 

Avoid the area (External – External Traffic). 

 

We conducted an Origin / Destination Study using Bluetooth readers and found 38% of the PM 

vehicles pass through the area; that is they do not have a destination in the study area. Of the 

eastbound traffic over the bridge 33% was found to be pass through traffic. In calculating the 

new traffic volumes on Newington Road and at the Newington Road Underpass, 33% of 

eastbound bridge traffic was assumed to avoid Newington Road and the proposed detour. 

 

The external traffic in the AM is less. In the AM only 5% of the total traffic is passing through the 

area. Of the eastbound traffic over the bridge 5% was found to be pass through traffic. A 

summary of the pass through PM traffic on the following page. 

The Fairfax County Parkway between Telegraph Road and Loisdale Road is a congested segment 

of roadway. The external traffic is avoiding congestion on the Fairfax County Parkway. Some of 

the external traffic may divert to use the detour, which uses the Newington Road underpass. 

However, there are nearly 400 external vehicles per peak period (2 to 3) using the underpass. 

During construction many external vehicles will avoid the underpass as traffic from Cinder Bed 

Road, Backlick Road or Newington Road detour to the underpass.   

Roadway Queue  95th Percentile Queue (ft) 

  AM  PM  Midday  Off Peak 

Newington Road at CSX Underpass 

Eastbound  318  197  159  301 

Westbound  236  234  269  192 

Executive Summary  

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT Traffic Study ‐ November 2016 

 

Injury 35,712 35.70% 13 35.10%

K 232 0.20% 0 0.00%

PDO 64,134 64.10% 24 64.90%

Total 100,078 37

NOVA District Study Area

Table ES – 4: Crash Comparison – NOVA District vs Study 

Area, Years: 2013 ‐ 2016 

The table below shows the share of traffic that is External / External during the AM and PM peak 

periods. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Crash History  The study intersections and the Newington area roadways have light traffic and few crashes 

over the past 3 1/2 years. The higher volume intersections at Loisdale Road and Telegraph Road 

had eight and seven crashes respectively. Neither have been identified as high Potential Safety 

Improvement (PSI) intersections by VDOT Traffic Engineering Division. Overall the study 

intersections and Newington area roadways had 37 crashes over the 3 1/2‐year period. The 

share of Injury vs Property Damage Only (PDO) crashes is consistent with NOVA District for the 

same period: 

 

 

   

 Table ES – 3: PM Peak Period (3 hour) Origin‐Destination Table 

   Destinations     

  PM  1  2  3  4  Total  EXTERNAL

Origins 

1    35  70  210  316  33.4% 

2  39    399  1,041  1,479  29.6% 

3  46  381    293  720  59.4% 

4  283  423  329    1,035   

  Total  368  839  799  1,544    EXTERNAL 23.2% 49.6%  58.8%    37.7%  1. Backlick Bridge 

2. Newington Road vic Telegraph Road 3. Newington Underpass 4. Internal to study area 

 

Executive Summary  

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT Traffic Study ‐ November 2016 

 

IV Change in LOS Due to Construction  

The bridge construction and detour of traffic will change travel patterns in the area. Generally, 

slight changes in study intersection average delay and LOS is expected to occur. A comparison of 

before and after average delay is shown in the table below. 

Newington Road underpass traffic volumes are projected to increase slightly, resulting in an 

increase in average delay from 435 seconds to 439 seconds (PM westbound). Also critical to 

traffic flow is the length of 95% queue; which increases slightly from 234 feet to 239 feet (PM 

westbound) and from 307 feet to 337 feet (AM eastbound). The AM queue length of 

approximately 18 vehicles does not extend into the downstream Loisdale/Newington 

intersection. As such it is not projected to interfere with operations and create gridlock. 

Fairfax County Parkway at Loisdale Road is a congested intersection with unstable conditions. 

The addition of approximately 100 vehicles leads to a slight increase in average delay and a 

change in LOS. However, conditions are not expected to be appreciably worse.  

 

Table ES – 5: Level of Service and Queue Comparison 

Intersection Level of Service   

AM Exist 

AM Cons. 

PM Exist 

PM Cons. 

MD1 Exist 

MD Cons. 

Off‐Peak 

Off Cons. 

1.  Newington Road and Loisdale Road 

B 15.4 

B 13.3 

C 30.9 

D 35.4 

B 16.5 

B 18.9 

C 30.3 

C 34.0 

2.  Newington Road Underpass of CSX Railroad (EB/WB) 

F/F 122/ 118 

F/F 141/128 

C/F 32.0/335 

D/F 39.5/ 439 

D/D 44.8/ 45.6 

F/D 107/ 53 

D/F 51.0/ 154 

E/F 65/ 235 

4.  Telegraph Road and Newington Road 

B 17.6 

B 15.4 

C 34.2 

D 39.6 

B 16.0 

B 19.0 

B 11.6 

B 14.0 

5.  Backlick Road and FCP  Spur 

A 9.5 

A 8.2 

B 10.2 

A 8.7 

B 12.2 

A 4.8 

A 9.0 

A 8.4 

6.  Backlick Road Spur and Fairfax County Parkway 

B 19.9 

B 15.8 

B 15.5 

B 11.0 

B 12.0 

A 7.0 

A 8.2 

A 6.3 

7.  Loisdale Road and Fairfax County Parkway 

F 96.5 

F 106.0

D 35.7 

D 41.2 

D 37.5 

E 48.2 

B 17.6 

C 23.5 

Roadway Queue  95th Percentile Queue (ft) 

 

  AM Exist 

AM Cons. 

PM Exist 

PM Cons. 

MD1 Exist 

MD Cons. 

Off‐Peak 

Off Cons. 

Newington Road at CSX Underpass 

Eastbound  307  337  184  223  227  321  263  299 

Westbound  277  251  234  239  251  272  234  238 

Executive Summary  

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT Traffic Study ‐ November 2016 

 

 

IV Traffic Impacts Due to Staged Construction Three alternatives are possible to stage construction for the purpose of keeping traffic on the 

bridge. (Alternative A is full closure with detour): 

Alternative B1: One Lane ‐Alternating Two Way Traffic, with pedestrian access. One lane 

of traffic will be maintained with northbound and southbound traffic alternating over 

the bridge. Traffic will be controlled with a temporary signal. 

Alternative B2: One Lane – Two Way Traffic by time of day, with pedestrian access. 

Alternative C: Two Lanes without pedestrian access.  

Two lanes with pedestrian access will have nearly the same width as the existing and proposed 

bridge typical section. This alternative is not feasible as the number of phases and complexity of 

construction would greatly increase the cost of the bridge. 

Alternative B1 has sufficient capacity to pass the traffic, however queues on the north end of the bridge will interfere with operations on the Fairfax County Parkway. There is approximately 

100 feet of staging on the Fairfax County Parkway spur to Backlick Bridge; enough for a single 

large truck but little additional traffic. Turning vehicles waiting for northbound traffic to 

conclude will interfere with Fairfax County Parkway through lanes. 

Alternative B2 will operate southbound during the AM peak period and northbound during 

PM peak period. Without the alternating traffic, the queue from Staged Alternative 1 will be 

eliminated. 

24 hour counts conducted indicate that traffic is generally heavier southbound between 5:00 

AM and 2:00 PM.  Between 6:30 PM and 5:00 AM traffic is light and there is no pronounced 

direction. In order to provide emergency egress during night time hours, northbound traffic 

should be maintained between 6:30 PM and 5:00 AM. As such, the bridge would be open for 

southbound traffic between 5:00 AM and 2:00 PM and the remainder of day the bridge would 

be open for northbound traffic. 

Another variation of this alternative is to maintain northbound traffic only. The advantage to 

this variation is that there would be no confusion as to which direction the bridge would be 

open and when. Egress from the Newington area would be maintained throughout the project. 

Alternative C has the principal disadvantage to traffic in that bike and pedestrian traffic is not maintained on the trail system. Bike and pedestrian traffic is very light and there are no 

residential traffic generators in the area. 

Staged Alternative B2 and C will maintain the current traffic flow to, from and through the 

Newington enclave. The impacts will be similar to any construction project along a roadway, 

capacity will be reduced and short term closures will be normal.   

Executive Summary  

ROUTE 617 BACKLICK ROAD BRIDGE REPLACEMENT Traffic Study ‐ November 2016 

 

V Findings and Conclusions  

Findings 

Traffic Volumes over the Backlick Bridge are relatively light, especially when compared with 

the surrounding road‐network. 

The Newington commercial area has a high volume of heavy vehicles, estimated to be 25% 

of total traffic, 

The Newington Road underpass of the CSX railroad has a height restriction of 13’ 11”. 

However, no business was discovered that operates vehicles in excess of 13’11”. 

A significant portion of traffic on Newington Road and Backlick Road is external “cut‐

through” traffic. In the PM, 33% of the traffic to the bridge is external traffic. 

With the closure of the Backlick Bridge, origin and destinations in the study area will be 

forced to use the underpass, however, 

Many current external trips will avoid the underpass. 

Newington Road Underpass of the CSC Railroad currently is LOS F and the AM 95% queue is 

307 feet. 

With addition of detour trips and the reduction in external trips the longest 95% queue will 

grow slightly to 337 feet. 

Average vehicle delay at the Loisdale / Fairfax County Parkway interchange is calculated to 

change in the PM peak hour from 35.7 sec per vehicle (LOS ) to 41.2 sec per vehicle. 

Three Alternatives are available for staged construction. Alternative B2: One Lane 

Alternating by Time of Day and Alternative C: Two‐way Operations, will have minor impacts 

to traffic flow. However, 

Alternative C: Two Way Operations does not include bike or pedestrian access. 

Conclusion 

Backlick Road at the bridge over CSX railroad is a lightly used local roadway. In addition, a large 

portion of the traffic on Backlick Road and Newington Road is external “cut through” traffic; 

some of this traffic will divert to other roadways during bridge construction.  

Staged construction will allow traffic to continue over the CSX Railroad during construction. Two 

alternatives are possible with only minor impacts to traffic flow. However, staged construction 

will either necessitate one way operations or removing pedestrian access. Two way operations 

with pedestrian access is not feasible. 

A full closure of the bridge is not expected to create significant congestion along the proposed 

detour route. Furthermore, conditions on Fairfax County Parkway and other primary routes are 

not expected to be significantly affected. 

ATTACHMENT 7

ABC CONSTRUCTION TIME ESTIMATE OF ALTERNATE 4

ROUTE 617 (BACKLICK ROAD) OVER CSX RAILROAD

 PROPOSED BRIDGE REPLACEMENT 

Fairfax County, Virginia

Virginia Department of Transportation – Northern Virginia District

Abutment Construction

Abutment Construction ‐ Standard Construction

This abutment construction option is based on the standard practice of after the piles are placed and the MSE wall is built up to the bottom of

pile cap elevation the pile cap & stem wall is formed and reinforcing steel placed. Then the concrete pile cap poured.

Time required =   10 Days

ABC Abutment Construction Option 1

This abutment construction option is based on after the piles are placed and the MSE wall is built up to the bottom of pile cap elevation 

that a precast reinforced concrete pile cap & stem wall is placed over the piles and then the pile pockets are grouted.

Time required =   2 Days

Cure time for both options would be the same.

Superstructure Construction

Because of train traffic at the site, CSXT has stated that the construction window work over the tracks is just 2 hours . All deck construction 

options are base on the erection of 2 girders connected together with cross frames.

Description of Deck Construction Options

Deck Construction ‐ Standard Construction 

This deck construction is based on the standard practice of placing S.I.P. forms and overhang brackets with building overhang forms. 

The required shear studs are then attached and the reinforcing steel placed in the regular construction method.  The screed setup and 

the deck poured. The parapets reinforcing steel tied and parapets shall be poured using the slip formed method. 

ABC Deck Construction Option 1 ‐ S.I.P. and Overhang Forms are attached to Girders and Using Pre‐Tied Reinforcing Steel Mats

This deck construction is base on attaching the S.I.P. forms and overhang brackets with building overhang forms to the girders before erection. 

The required shear studs are then attached and the pre‐tied reinforcing steel mats are place.  The screed setup and deck pour. The parapets

 reinforcing steel tied and parapets shall be poured using the slipped formed method. 

ABC Deck Construction Option 2 ‐ Using Precast Deck Panels with a Overlay

This deck construction is base on using full width precast deck panels 10' long. The required shear studs are then attached and the 

reinforcing steel place in the regular construction method.  The screed setup and deck poured. The parapets reinforcing steel tied and parapets 

shall be poured using the slipped formed method. 

Setting up screed machine, pouring Deck or Overlay, Placing Parapet Reinforcing Steel and Pouring Parapet for all 3 Options would be the same. 

Deck Construction Standard

Install Stay‐in‐Place Forms Studs & Reinforcing Steel Total Days

10 10 20

Deck Construction Option 1Finalize Forms Studs & Pre‐Tied Rebar Mats Total Days

2 5 7

Deck Construction Option 2

Install Deck Precast Panels Studs, Grout Joints and Keys Total Days

3 5 8

Total time to construct  Days

Standard construction of Abutments and Deck  30

9

 Option 2 ‐ Using Precast Abutment Pile Cap & Stem Wall and Precast Deck Panels with an Overlay   10

Alternative #4 ‐ABC of Alternative #2 ‐ Single Span 135' Steel Girder on Semi‐Integral Abutments on 2 Rows of Steel H‐Piles

Cast‐in‐Place Deck ‐ Pre‐Installed 

S.I.P. & Pre‐Tied Rebar Mats

Cast‐in‐Place Deck ‐ Standard

Precast Deck Panels 

Option 1 ‐ Using Precast Abutment Pile Cap & Stem Wall, Pre‐Installed S.I.P and Overhang Forms with Pre‐Tied Reinforcing Steel Mats  

Evaluation of Standard Construction Time and ABC Construction Time of Abutment Pile Cap and Deck 

ATTACHMENT 8

STORMWATER COMPUTATIONS

Design 

AlternateMOT Option

Total Land 

Disturbance

Qualified for 

Nutrient Credits

Nutrient Credits 

Required 

(Phophorous 

Reduction 

(Lb/Year)

Remarks

1 Detour 1.90 Yes 0.49

2 Detour 1.96 Yes 0.50

One‐Lane / Two‐

Way2.07 Yes 0.60

Two‐Lane / Two‐

Way2.08 Yes 0.65

3 Detour 1.74 Yes 0.48

One‐Lane / Two‐

Way1.72 Yes 0.60

Two‐Lane / Two‐

Way1.73 Yes 0.65

4 Detour 1.96 Yes 0.50

Project Name: Date:

Linear Development Project? No

Site Information

Post-Development Project (Treatment Volume and Loads)1.90 ####

20% Linear project? NoThe site's net increase in impervious cover (acres) is: 0.03 ✔

Post-Development TP Load Reduction for Site (lb/yr): 0.49 ✔

Pre-ReDevelopment Land Cover (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) -- undisturbed, protected forest/open space or reforested land

0.00

Managed Turf (acres) -- disturbed, graded for yards or other turf to be mowed/managed 1.16 1.16

Impervious Cover (acres) 0.74 0.74

1.90

Post-Development Land Cover (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) -- undisturbed, protected forest/open space or reforested land

0.00

Managed Turf (acres) -- disturbed, graded for yards or other turf to be mowed/managed 1.13 1.13

Impervious Cover (acres) 0.77 0.77

Area Check OK. OK. OK. OK. 1.90

Constants Runoff Coefficients (Rv)Annual Rainfall (inches) 43 A Soils B Soils C Soils D SoilsTarget Rainfall Event (inches) 1.00 Forest/Open Space 0.02 0.03 0.04 0.05Total Phosphorus (TP) EMC (mg/L) 0.26 Managed Turf 0.15 0.20 0.22 0.25Total Nitrogen (TN) EMC (mg/L) 1.86 Impervious Cover 0.95 0.95 0.95 0.95Target TP Load (lb/acre/yr) 0.41Pj (unitless correction factor) 0.90

Pre-ReDevelopment Listed Adjusted1

Forest/Open Space Cover (acres) 0.00 0.00 Forest/Open Space Cover (acres)

0.00 Forest/Open Space Cover (acres)

0.00

Weighted Rv(forest) 0.00 0.00 Weighted Rv(forest) 0.00 Weighted Rv(forest) 0.00% Forest 0% 0% % Forest 0% % Forest 0%

Managed Turf Cover (acres) 1.16 1.13 Managed Turf Cover (acres)

1.13 Managed Turf Cover (acres)

1.13

Weighted Rv(turf) 0.22 0.22 Weighted Rv (turf) 0.22 Weighted Rv (turf) 0.22

% Managed Turf 61% 60% % Managed Turf 59% % Managed Turf 60%

Impervious Cover (acres) 0.74 0.74 Impervious Cover (acres)

0.77 ReDev. Impervious Cover (acres)

0.74 New Impervious Cover (acres)

0.03

Rv(impervious) 0.95 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95

% Impervious 39% 40% % Impervious 41% % Impervious 40%

Total Site Area (acres) 1.90 1.87 Final Site Area (acres) 1.90 Total ReDev. Site Area (acres)

1.87

Site Rv 0.50 0.51 Final Post Dev Site Rv 0.52 ReDev Site Rv 0.51

Pre-ReDevelopment Treatment Volume (acre-ft)

0.0799 0.0793Final Post-Development

Treatment Volume (acre-ft)

0.0817Post-ReDevelopment

Treatment Volume (acre-ft)

0.0793Post-Development Treatment Volume

(acre-ft) 0.0024

Pre-ReDevelopment Treatment Volume (cubic feet)

3,478 3,454Final Post-Development

Treatment Volume (cubic feet)

3,558Post-ReDevelopment

Treatment Volume (cubic feet)

3,454Post-Development

Treatment Volume (cubic feet)

103

Pre-ReDevelopment TP Load (lb/yr) 2.19 2.17

Final Post-Development TP Load

(lb/yr)2.24

Post-ReDevelopment Load (TP) (lb/yr)*

2.17Post-Development TP

Load (lb/yr) 0.07

Pre-ReDevelopment TP Load per acre(lb/acre/yr)

1.15 1.16Final Post-Development TP

Load per acre (lb/acre/yr)

1.18Post-ReDevelopment TP

Load per acre (lb/acre/yr)

1.16

0.77Max. Reduction Required

(Below Pre-ReDevelopment Load)

20%

TP Load Reduction Required for

Redeveloped Area (lb/yr)

0.43TP Load Reduction Required for New

Impervious Area (lb/yr)0.05

0.49

N/A

15.63

Backlick Road -Detour Option Alternate 110/11/2016

LAND COVER SUMMARY -- POST DEVELOPMENTLAND COVER SUMMARY -- PRE-REDEVELOPMENT

Maximum reduction required:

Enter Total Disturbed Area (acres) → Check:

Land cover areas entered correctly?Total disturbed area entered?

BMP Design Specifications List:

Linear Project TP Load Reduction Required (lb/yr):

Treatment Volume and Nutrient Load

Land Cover Summary-Post (Final)

2013 Draft Stds & Specs

Land Cover Summary-Pre

Pre-ReDevelopment TN Load (lb/yr)Final Post-Development TN Load

(Post-ReDevelopment & New Impervious) (lb/yr)

15.99

Land Cover Summary-Post

Post-ReDevelopment

TP Load Reduction Required (lb/yr)

Post-Development Requirement for Site Area

Nitrogen Loads (Informational Purposes Only)

Baseline TP Load (lb/yr)(0.41 lbs/acre/yr applied to pre-redevelopment area excluding pervious

land proposed for new impervious cover)

1 Adjusted Land Cover Summary: Pre ReDevelopment land cover minus pervious land cover (forest/open space or managed turf) acreage proposed for new impervious cover.

Adjusted total acreage is consistent with Post-ReDevelopment acreage (minus acreage of new impervious cover).

Column I shows load reduction requriement for new impervious cover (based on new development load limit, 0.41 lbs/acre/year).

Post ReDev. & New Impervious

Treatment Volume and Nutrient Load

Land Cover Summary-Post

Post-Development New Impervious

CLEAR ALL data input cells

constant values

calculation cells

final results

Project Name: 

Date: 

Linear Development Project? No

Site Information

Post‐Development Project (Treatment Volume and Loads)

1.96 ####

20% Linear project? No

The site's net increase in impervious cover (acres) is: 0.03 ✔Post‐Development TP Load Reduction for Site (lb/yr): 0.50 ✔

Pre‐ReDevelopment Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 1.201.20

Impervious Cover (acres)0.76

0.76

1.96

Post‐Development Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 1.171.17

Impervious Cover (acres)0.79

0.79

Area Check OK. OK. OK. OK. 1.96

Constants Runoff Coefficients (Rv)Annual Rainfall (inches) 43 A Soils B Soils C Soils D Soils

Target Rainfall Event (inches) 1.00 Forest/Open Space 0.02 0.03 0.04 0.05

Total Phosphorus (TP) EMC (mg/L) 0.26 Managed Turf 0.15 0.20 0.22 0.25

Total Nitrogen (TN) EMC (mg/L) 1.86 Impervious Cover 0.95 0.95 0.95 0.95

Target TP Load (lb/acre/yr) 0.41

Pj (unitless correction factor) 0.90

Pre‐ReDevelopment Listed Adjusted1

Forest/Open Space Cover (acres) 0.00 0.00Forest/Open Space 

Cover (acres)0.00

Forest/Open Space 

Cover (acres)0.00

Weighted Rv(forest) 0.00 0.00 Weighted Rv(forest) 0.00 Weighted Rv(forest) 0.00

% Forest 0% 0% % Forest 0% % Forest 0%

Managed Turf Cover (acres) 1.20 1.17Managed Turf Cover 

(acres)1.17

Managed Turf Cover 

(acres)1.17

Weighted Rv(turf) 0.22 0.22 Weighted Rv (turf) 0.22 Weighted Rv (turf) 0.22

% Managed Turf 61% 61% % Managed Turf 60% % Managed Turf 61%

Impervious Cover (acres) 0.76 0.76Impervious Cover 

(acres)0.79

ReDev. Impervious 

Cover (acres)0.76

New Impervious Cover 

(acres)0.03

Rv(impervious) 0.95 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95

% Impervious 39% 39% % Impervious 40% % Impervious 39%

Total Site Area (acres) 1.96 1.93 Final Site Area (acres) 1.96Total ReDev. Site Area 

(acres)1.93

Site Rv 0.50 0.51 Final Post Dev Site Rv 0.51 ReDev Site Rv 0.51

Pre‐ReDevelopment Treatment Volume 

(acre‐ft) 0.0822 0.0816

Final Post‐

Development 

Treatment Volume      

(acre‐ft) 

0.0840Post‐ReDevelopment 

Treatment Volume     

(acre‐ft) 

0.0816Post‐Development 

Treatment Volume 

(acre‐ft) 

0.0024

Pre‐ReDevelopment Treatment Volume 

(cubic feet) 3,579 3,555

Final Post‐

Development 

Treatment Volume 

(cubic feet) 

3,659Post‐ReDevelopment 

Treatment Volume     

(cubic feet) 

3,555Post‐Development 

Treatment Volume (cubic 

feet) 

103

Pre‐ReDevelopment TP Load              

(lb/yr)2.25 2.23

Final Post‐

Development TP 

Load                 

(lb/yr)

2.30Post‐ReDevelopment 

Load (TP)              

(lb/yr)*

2.23Post‐Development TP 

Load (lb/yr)0.07

Pre‐ReDevelopment TP Load per acre

(lb/acre/yr)1.15 1.16

Final Post‐Development TP 

Load per acre 

(lb/acre/yr)

1.17

Post‐ReDevelopment TP 

Load per acre 

(lb/acre/yr)

1.16

0.79Max. Reduction Required 

(Below Pre‐

ReDevelopment Load)

20%

TP Load Reduction 

Required for 

Redeveloped Area 

(lb/yr)

0.45TP Load Reduction 

Required for New 

Impervious Area (lb/yr)0.05

0.50

N/A

16.09Pre‐ReDevelopment TN Load (lb/yr)

Final Post‐Development TN Load

(Post‐ReDevelopment & New 

Impervious)  (lb/yr)

16.44

Land Cover Summary‐Post

Post‐ReDevelopment

TP Load Reduction Required (lb/yr)

Post‐Development Requirement for Site Area

Nitrogen Loads (Informational Purposes Only)

Baseline TP Load (lb/yr)(0.41 lbs/acre/yr applied to pre‐redevelopment area excluding pervious 

land proposed for new impervious cover)

1 Adjusted Land Cover Summary: 

Pre ReDevelopment land cover minus pervious land cover (forest/open space or 

managed turf) acreage proposed for new impervious cover.  

Adjusted total acreage is consistent with Post‐ReDevelopment acreage (minus  

acreage of new impervious cover).  

Column I shows load reduction requriement for new impervious cover (based on new 

development load limit, 0.41 lbs/acre/year). 

Post ReDev. & New Impervious

Treatment Volume and Nutrient Load

Land Cover Summary‐Post

Post‐Development New Impervious

Linear Project TP Load Reduction Required (lb/yr): 

Treatment Volume and Nutrient Load

Land Cover Summary‐Post (Final)

2013 Draft Stds & Specs

Land Cover Summary‐Pre

Backlick Road ‐Detour Option Alternate 2

10/11/2016

LAND COVER SUMMARY -- POST DEVELOPMENTLAND COVER SUMMARY -- PRE-REDEVELOPMENT

 Maximum reduction required:

Enter Total Disturbed Area (acres) → Check:

Land cover areas entered correctly?

Total disturbed area entered?

BMP Design Specifications List:

CLEAR  ALL(Ctrl+Shift+R)

data input cells

constant values

calculation cells

final results

Project Name: 

Date: 

Linear Development Project? No

Site Information

Post‐Development Project (Treatment Volume and Loads)

2.07 ####

20% Linear project? No

The site's net increase in impervious cover (acres) is: 0.09 ✔Post‐Development TP Load Reduction for Site (lb/yr): 0.60 ✔

Pre‐ReDevelopment Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 1.331.33

Impervious Cover (acres)0.74

0.74

2.07

Post‐Development Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 1.241.24

Impervious Cover (acres)0.83

0.83

Area Check OK. OK. OK. OK. 2.07

Constants Runoff Coefficients (Rv)Annual Rainfall (inches) 43 A Soils B Soils C Soils D Soils

Target Rainfall Event (inches) 1.00 Forest/Open Space 0.02 0.03 0.04 0.05

Total Phosphorus (TP) EMC (mg/L) 0.26 Managed Turf 0.15 0.20 0.22 0.25

Total Nitrogen (TN) EMC (mg/L) 1.86 Impervious Cover 0.95 0.95 0.95 0.95

Target TP Load (lb/acre/yr) 0.41

Pj (unitless correction factor) 0.90

Pre‐ReDevelopment Listed Adjusted1

Forest/Open Space Cover (acres) 0.00 0.00Forest/Open Space 

Cover (acres)0.00

Forest/Open Space 

Cover (acres)0.00

Weighted Rv(forest) 0.00 0.00 Weighted Rv(forest) 0.00 Weighted Rv(forest) 0.00

% Forest 0% 0% % Forest 0% % Forest 0%

Managed Turf Cover (acres) 1.33 1.24Managed Turf Cover 

(acres)1.24

Managed Turf Cover 

(acres)1.24

Weighted Rv(turf) 0.22 0.22 Weighted Rv (turf) 0.22 Weighted Rv (turf) 0.22

% Managed Turf 64% 63% % Managed Turf 60% % Managed Turf 63%

Impervious Cover (acres) 0.74 0.74Impervious Cover 

(acres)0.83

ReDev. Impervious 

Cover (acres)0.74

New Impervious Cover 

(acres)0.09

Rv(impervious) 0.95 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95

% Impervious 36% 37% % Impervious 40% % Impervious 37%

Total Site Area (acres) 2.07 1.98 Final Site Area (acres) 2.07Total ReDev. Site Area 

(acres)1.98

Site Rv 0.48 0.49 Final Post Dev Site Rv 0.51 ReDev Site Rv 0.49

Pre‐ReDevelopment Treatment Volume 

(acre‐ft) 0.0830 0.0813

Final Post‐

Development 

Treatment Volume      

(acre‐ft) 

0.0884Post‐ReDevelopment 

Treatment Volume     

(acre‐ft) 

0.0813Post‐Development 

Treatment Volume 

(acre‐ft) 

0.0071

Pre‐ReDevelopment Treatment Volume 

(cubic feet) 3,614 3,542

Final Post‐

Development 

Treatment Volume 

(cubic feet) 

3,853Post‐ReDevelopment 

Treatment Volume     

(cubic feet) 

3,542Post‐Development 

Treatment Volume (cubic 

feet) 

310

Pre‐ReDevelopment TP Load              

(lb/yr)2.27 2.23

Final Post‐

Development TP 

Load                 

(lb/yr)

2.42Post‐ReDevelopment 

Load (TP)              

(lb/yr)*

2.23Post‐Development TP 

Load (lb/yr)0.20

Pre‐ReDevelopment TP Load per acre

(lb/acre/yr)1.10 1.12

Final Post‐Development TP 

Load per acre 

(lb/acre/yr)

1.17

Post‐ReDevelopment TP 

Load per acre 

(lb/acre/yr)

1.12

0.81Max. Reduction Required 

(Below Pre‐

ReDevelopment Load)

20%

TP Load Reduction 

Required for 

Redeveloped Area 

(lb/yr)

0.45TP Load Reduction 

Required for New 

Impervious Area (lb/yr)0.16

0.60

N/A

16.24Pre‐ReDevelopment TN Load (lb/yr)

Final Post‐Development TN Load

(Post‐ReDevelopment & New 

Impervious)  (lb/yr)

17.32

Land Cover Summary‐Post

Post‐ReDevelopment

TP Load Reduction Required (lb/yr)

Post‐Development Requirement for Site Area

Nitrogen Loads (Informational Purposes Only)

Baseline TP Load (lb/yr)(0.41 lbs/acre/yr applied to pre‐redevelopment area excluding pervious 

land proposed for new impervious cover)

1 Adjusted Land Cover Summary: 

Pre ReDevelopment land cover minus pervious land cover (forest/open space or 

managed turf) acreage proposed for new impervious cover.  

Adjusted total acreage is consistent with Post‐ReDevelopment acreage (minus  

acreage of new impervious cover).  

Column I shows load reduction requriement for new impervious cover (based on new 

development load limit, 0.41 lbs/acre/year). 

Post ReDev. & New Impervious

Treatment Volume and Nutrient Load

Land Cover Summary‐Post

Post‐Development New Impervious

Linear Project TP Load Reduction Required (lb/yr): 

Treatment Volume and Nutrient Load

Land Cover Summary‐Post (Final)

2013 Draft Stds & Specs

Land Cover Summary‐Pre

Backlick Road ‐One Lane Option Alternate 2

10/11/2016

LAND COVER SUMMARY -- POST DEVELOPMENTLAND COVER SUMMARY -- PRE-REDEVELOPMENT

 Maximum reduction required:

Enter Total Disturbed Area (acres) → Check:

Land cover areas entered correctly?

Total disturbed area entered?

BMP Design Specifications List:

CLEAR  ALL(Ctrl+Shift+R)

data input cells

constant values

calculation cells

final results

Project Name: 

Date: 

Linear Development Project? No

Site Information

Post‐Development Project (Treatment Volume and Loads)

2.08 ####

20% Linear project? No

The site's net increase in impervious cover (acres) is: 0.11 ✔Post‐Development TP Load Reduction for Site (lb/yr): 0.65 ✔

Pre‐ReDevelopment Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 1.301.30

Impervious Cover (acres)0.78

0.78

2.08

Post‐Development Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 1.191.19

Impervious Cover (acres)0.89

0.89

Area Check OK. OK. OK. OK. 2.08

Constants Runoff Coefficients (Rv)Annual Rainfall (inches) 43 A Soils B Soils C Soils D Soils

Target Rainfall Event (inches) 1.00 Forest/Open Space 0.02 0.03 0.04 0.05

Total Phosphorus (TP) EMC (mg/L) 0.26 Managed Turf 0.15 0.20 0.22 0.25

Total Nitrogen (TN) EMC (mg/L) 1.86 Impervious Cover 0.95 0.95 0.95 0.95

Target TP Load (lb/acre/yr) 0.41

Pj (unitless correction factor) 0.90

Pre‐ReDevelopment Listed Adjusted1

Forest/Open Space Cover (acres) 0.00 0.00Forest/Open Space 

Cover (acres)0.00

Forest/Open Space 

Cover (acres)0.00

Weighted Rv(forest) 0.00 0.00 Weighted Rv(forest) 0.00 Weighted Rv(forest) 0.00

% Forest 0% 0% % Forest 0% % Forest 0%

Managed Turf Cover (acres) 1.30 1.19Managed Turf Cover 

(acres)1.19

Managed Turf Cover 

(acres)1.19

Weighted Rv(turf) 0.22 0.22 Weighted Rv (turf) 0.22 Weighted Rv (turf) 0.22

% Managed Turf 63% 60% % Managed Turf 57% % Managed Turf 60%

Impervious Cover (acres) 0.78 0.78Impervious Cover 

(acres)0.89

ReDev. Impervious 

Cover (acres)0.78

New Impervious Cover 

(acres)0.11

Rv(impervious) 0.95 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95

% Impervious 38% 40% % Impervious 43% % Impervious 40%

Total Site Area (acres) 2.08 1.97 Final Site Area (acres) 2.08Total ReDev. Site Area 

(acres)1.97

Site Rv 0.49 0.51 Final Post Dev Site Rv 0.53 ReDev Site Rv 0.51

Pre‐ReDevelopment Treatment Volume 

(acre‐ft) 0.0856 0.0836

Final Post‐

Development 

Treatment Volume      

(acre‐ft) 

0.0923Post‐ReDevelopment 

Treatment Volume     

(acre‐ft) 

0.0836Post‐Development 

Treatment Volume 

(acre‐ft) 

0.0087

Pre‐ReDevelopment Treatment Volume 

(cubic feet) 3,728 3,640

Final Post‐

Development 

Treatment Volume 

(cubic feet) 

4,019Post‐ReDevelopment 

Treatment Volume     

(cubic feet) 

3,640Post‐Development 

Treatment Volume (cubic 

feet) 

379

Pre‐ReDevelopment TP Load              

(lb/yr)2.34 2.29

Final Post‐

Development TP 

Load                 

(lb/yr)

2.53Post‐ReDevelopment 

Load (TP)              

(lb/yr)*

2.29Post‐Development TP 

Load (lb/yr)0.24

Pre‐ReDevelopment TP Load per acre

(lb/acre/yr)1.13 1.16

Final Post‐Development TP 

Load per acre 

(lb/acre/yr)

1.21

Post‐ReDevelopment TP 

Load per acre 

(lb/acre/yr)

1.16

0.81Max. Reduction Required 

(Below Pre‐

ReDevelopment Load)

20%

TP Load Reduction 

Required for 

Redeveloped Area 

(lb/yr)

0.46TP Load Reduction 

Required for New 

Impervious Area (lb/yr)0.19

0.65

N/A

16.76

Backlick Road ‐Two Lane Option Alt 2

10/11/2016

LAND COVER SUMMARY -- POST DEVELOPMENTLAND COVER SUMMARY -- PRE-REDEVELOPMENT

 Maximum reduction required:

Enter Total Disturbed Area (acres) → Check:

Land cover areas entered correctly?

Total disturbed area entered?

BMP Design Specifications List:

Linear Project TP Load Reduction Required (lb/yr): 

Treatment Volume and Nutrient Load

Land Cover Summary‐Post (Final)

2013 Draft Stds & Specs

Land Cover Summary‐Pre

Pre‐ReDevelopment TN Load (lb/yr)

Final Post‐Development TN Load

(Post‐ReDevelopment & New 

Impervious)  (lb/yr)

18.07

Land Cover Summary‐Post

Post‐ReDevelopment

TP Load Reduction Required (lb/yr)

Post‐Development Requirement for Site Area

Nitrogen Loads (Informational Purposes Only)

Baseline TP Load (lb/yr)(0.41 lbs/acre/yr applied to pre‐redevelopment area excluding pervious 

land proposed for new impervious cover)

1 Adjusted Land Cover Summary: 

Pre ReDevelopment land cover minus pervious land cover (forest/open space or 

managed turf) acreage proposed for new impervious cover.  

Adjusted total acreage is consistent with Post‐ReDevelopment acreage (minus  

acreage of new impervious cover).  

Column I shows load reduction requriement for new impervious cover (based on new 

development load limit, 0.41 lbs/acre/year). 

Post ReDev. & New Impervious

Treatment Volume and Nutrient Load

Land Cover Summary‐Post

Post‐Development New Impervious

CLEAR  ALL(Ctrl+Shift+R)

data input cells

constant values

calculation cells

final results

Project Name: Date:

Linear Development Project? No

Site Information

Post-Development Project (Treatment Volume and Loads)1.74 ####

20% Linear project? NoThe site's net increase in impervious cover (acres) is: 0.03 ✔

Post-Development TP Load Reduction for Site (lb/yr): 0.48 ✔

Pre-ReDevelopment Land Cover (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) -- undisturbed, protected forest/open space or reforested land

0.00

Managed Turf (acres) -- disturbed, graded for yards or other turf to be mowed/managed 0.98 0.98

Impervious Cover (acres) 0.76 0.76

1.74

Post-Development Land Cover (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) -- undisturbed, protected forest/open space or reforested land

0.00

Managed Turf (acres) -- disturbed, graded for yards or other turf to be mowed/managed 0.95 0.95

Impervious Cover (acres) 0.79 0.79

Area Check OK. OK. OK. OK. 1.74

Constants Runoff Coefficients (Rv)Annual Rainfall (inches) 43 A Soils B Soils C Soils D SoilsTarget Rainfall Event (inches) 1.00 Forest/Open Space 0.02 0.03 0.04 0.05Total Phosphorus (TP) EMC (mg/L) 0.26 Managed Turf 0.15 0.20 0.22 0.25Total Nitrogen (TN) EMC (mg/L) 1.86 Impervious Cover 0.95 0.95 0.95 0.95Target TP Load (lb/acre/yr) 0.41Pj (unitless correction factor) 0.90

Pre-ReDevelopment Listed Adjusted1

Forest/Open Space Cover (acres) 0.00 0.00 Forest/Open Space Cover (acres)

0.00 Forest/Open Space Cover (acres)

0.00

Weighted Rv(forest) 0.00 0.00 Weighted Rv(forest) 0.00 Weighted Rv(forest) 0.00% Forest 0% 0% % Forest 0% % Forest 0%

Managed Turf Cover (acres) 0.98 0.95 Managed Turf Cover (acres)

0.95 Managed Turf Cover (acres)

0.95

Weighted Rv(turf) 0.22 0.22 Weighted Rv (turf) 0.22 Weighted Rv (turf) 0.22

% Managed Turf 56% 56% % Managed Turf 55% % Managed Turf 56%

Impervious Cover (acres) 0.76 0.76 Impervious Cover (acres)

0.79 ReDev. Impervious Cover (acres)

0.76 New Impervious Cover (acres)

0.03

Rv(impervious) 0.95 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95

% Impervious 44% 44% % Impervious 45% % Impervious 44%

Total Site Area (acres) 1.74 1.71 Final Site Area (acres) 1.74 Total ReDev. Site Area (acres)

1.71

Site Rv 0.54 0.54 Final Post Dev Site Rv 0.55 ReDev Site Rv 0.54

Pre-ReDevelopment Treatment Volume (acre-ft)

0.0781 0.0776Final Post-Development

Treatment Volume (acre-ft)

0.0800Post-ReDevelopment

Treatment Volume (acre-ft)

0.0776Post-Development Treatment Volume

(acre-ft) 0.0024

Pre-ReDevelopment Treatment Volume (cubic feet)

3,403 3,380Final Post-Development

Treatment Volume (cubic feet)

3,483Post-ReDevelopment

Treatment Volume (cubic feet)

3,380Post-Development

Treatment Volume (cubic feet)

103

Pre-ReDevelopment TP Load (lb/yr) 2.14 2.12

Final Post-Development TP Load

(lb/yr)2.19

Post-ReDevelopment Load (TP) (lb/yr)*

2.12Post-Development TP

Load (lb/yr) 0.07

Pre-ReDevelopment TP Load per acre(lb/acre/yr)

1.23 1.24Final Post-Development TP

Load per acre (lb/acre/yr)

1.26Post-ReDevelopment TP

Load per acre (lb/acre/yr)

1.24

0.70Max. Reduction Required

(Below Pre-ReDevelopment Load)

20%

TP Load Reduction Required for

Redeveloped Area (lb/yr)

0.42TP Load Reduction Required for New

Impervious Area (lb/yr)0.05

0.48

N/A

15.30

Backlick Road -Detour Option Alt 310/11/2016

LAND COVER SUMMARY -- POST DEVELOPMENTLAND COVER SUMMARY -- PRE-REDEVELOPMENT

Maximum reduction required:

Enter Total Disturbed Area (acres) → Check:

Land cover areas entered correctly?Total disturbed area entered?

BMP Design Specifications List:

Linear Project TP Load Reduction Required (lb/yr):

Treatment Volume and Nutrient Load

Land Cover Summary-Post (Final)

2013 Draft Stds & Specs

Land Cover Summary-Pre

Pre-ReDevelopment TN Load (lb/yr)Final Post-Development TN Load

(Post-ReDevelopment & New Impervious) (lb/yr)

15.66

Land Cover Summary-Post

Post-ReDevelopment

TP Load Reduction Required (lb/yr)

Post-Development Requirement for Site Area

Nitrogen Loads (Informational Purposes Only)

Baseline TP Load (lb/yr)(0.41 lbs/acre/yr applied to pre-redevelopment area excluding pervious

land proposed for new impervious cover)

1 Adjusted Land Cover Summary: Pre ReDevelopment land cover minus pervious land cover (forest/open space or managed turf) acreage proposed for new impervious cover.

Adjusted total acreage is consistent with Post-ReDevelopment acreage (minus acreage of new impervious cover).

Column I shows load reduction requriement for new impervious cover (based on new development load limit, 0.41 lbs/acre/year).

Post ReDev. & New Impervious

Treatment Volume and Nutrient Load

Land Cover Summary-Post

Post-Development New Impervious

CLEAR ALL data input cells

constant values

calculation cells

final results

Project Name: 

Date: 

Linear Development Project? No

Site Information

Post‐Development Project (Treatment Volume and Loads)

1.72 ####

20% Linear project? No

The site's net increase in impervious cover (acres) is: 0.1 ✔Post‐Development TP Load Reduction for Site (lb/yr): 0.60 ✔

Pre‐ReDevelopment Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 0.930.93

Impervious Cover (acres)0.79

0.79

1.72

Post‐Development Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 0.830.83

Impervious Cover (acres)0.89

0.89

Area Check OK. OK. OK. OK. 1.72

Constants Runoff Coefficients (Rv)Annual Rainfall (inches) 43 A Soils B Soils C Soils D Soils

Target Rainfall Event (inches) 1.00 Forest/Open Space 0.02 0.03 0.04 0.05

Total Phosphorus (TP) EMC (mg/L) 0.26 Managed Turf 0.15 0.20 0.22 0.25

Total Nitrogen (TN) EMC (mg/L) 1.86 Impervious Cover 0.95 0.95 0.95 0.95

Target TP Load (lb/acre/yr) 0.41

Pj (unitless correction factor) 0.90

Pre‐ReDevelopment Listed Adjusted1

Forest/Open Space Cover (acres) 0.00 0.00Forest/Open Space 

Cover (acres)0.00

Forest/Open Space 

Cover (acres)0.00

Weighted Rv(forest) 0.00 0.00 Weighted Rv(forest) 0.00 Weighted Rv(forest) 0.00

% Forest 0% 0% % Forest 0% % Forest 0%

Managed Turf Cover (acres) 0.93 0.83Managed Turf Cover 

(acres)0.83

Managed Turf Cover 

(acres)0.83

Weighted Rv(turf) 0.22 0.22 Weighted Rv (turf) 0.22 Weighted Rv (turf) 0.22

% Managed Turf 54% 51% % Managed Turf 48% % Managed Turf 51%

Impervious Cover (acres) 0.79 0.79Impervious Cover 

(acres)0.89

ReDev. Impervious 

Cover (acres)0.79

New Impervious Cover 

(acres)0.10

Rv(impervious) 0.95 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95

% Impervious 46% 49% % Impervious 52% % Impervious 49%

Total Site Area (acres) 1.72 1.62 Final Site Area (acres) 1.72Total ReDev. Site Area 

(acres)1.62

Site Rv 0.56 0.58 Final Post Dev Site Rv 0.60 ReDev Site Rv 0.58

Pre‐ReDevelopment Treatment Volume 

(acre‐ft) 0.0796 0.0778

Final Post‐

Development 

Treatment Volume      

(acre‐ft) 

0.0857Post‐ReDevelopment 

Treatment Volume     

(acre‐ft) 

0.0778Post‐Development 

Treatment Volume 

(acre‐ft) 

0.0079

Pre‐ReDevelopment Treatment Volume 

(cubic feet) 3,467 3,387

Final Post‐

Development 

Treatment Volume 

(cubic feet) 

3,732Post‐ReDevelopment 

Treatment Volume     

(cubic feet) 

3,387Post‐Development 

Treatment Volume (cubic 

feet) 

345

Pre‐ReDevelopment TP Load              

(lb/yr)2.18 2.13

Final Post‐

Development TP 

Load                 

(lb/yr)

2.34Post‐ReDevelopment 

Load (TP)              

(lb/yr)*

2.13Post‐Development TP 

Load (lb/yr)0.22

Pre‐ReDevelopment TP Load per acre

(lb/acre/yr)1.27 1.31

Final Post‐Development TP 

Load per acre 

(lb/acre/yr)

1.36

Post‐ReDevelopment TP 

Load per acre 

(lb/acre/yr)

1.31

0.66Max. Reduction Required 

(Below Pre‐

ReDevelopment Load)

20%

TP Load Reduction 

Required for 

Redeveloped Area 

(lb/yr)

0.43TP Load Reduction 

Required for New 

Impervious Area (lb/yr)0.18

0.60

N/A

15.58

Backlick Road ‐One Lane Option Alt 3

10/11/2016

LAND COVER SUMMARY -- POST DEVELOPMENTLAND COVER SUMMARY -- PRE-REDEVELOPMENT

 Maximum reduction required:

Enter Total Disturbed Area (acres) → Check:

Land cover areas entered correctly?

Total disturbed area entered?

BMP Design Specifications List:

Linear Project TP Load Reduction Required (lb/yr): 

Treatment Volume and Nutrient Load

Land Cover Summary‐Post (Final)

2013 Draft Stds & Specs

Land Cover Summary‐Pre

Pre‐ReDevelopment TN Load (lb/yr)

Final Post‐Development TN Load

(Post‐ReDevelopment & New 

Impervious)  (lb/yr)

16.77

Land Cover Summary‐Post

Post‐ReDevelopment

TP Load Reduction Required (lb/yr)

Post‐Development Requirement for Site Area

Nitrogen Loads (Informational Purposes Only)

Baseline TP Load (lb/yr)(0.41 lbs/acre/yr applied to pre‐redevelopment area excluding pervious 

land proposed for new impervious cover)

1 Adjusted Land Cover Summary: 

Pre ReDevelopment land cover minus pervious land cover (forest/open space or 

managed turf) acreage proposed for new impervious cover.  

Adjusted total acreage is consistent with Post‐ReDevelopment acreage (minus  

acreage of new impervious cover).  

Column I shows load reduction requriement for new impervious cover (based on new 

development load limit, 0.41 lbs/acre/year). 

Post ReDev. & New Impervious

Treatment Volume and Nutrient Load

Land Cover Summary‐Post

Post‐Development New Impervious

CLEAR  ALL(Ctrl+Shift+R)

data input cells

constant values

calculation cells

final results

Project Name: 

Date: 

Linear Development Project? No

Site Information

Post‐Development Project (Treatment Volume and Loads)

1.73 ####

20% Linear project? No

The site's net increase in impervious cover (acres) is: 0.13 ✔Post‐Development TP Load Reduction for Site (lb/yr): 0.65 ✔

Pre‐ReDevelopment Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 0.940.94

Impervious Cover (acres)0.79

0.79

1.73

Post‐Development Land Cover  (acres)A Soils B Soils C Soils D Soils Totals

Forest/Open Space (acres) ‐‐ undisturbed, 

protected forest/open space or reforested land0.00

Managed Turf (acres) ‐‐ disturbed, graded for 

yards or other turf to be mowed/managed 0.810.81

Impervious Cover (acres)0.92

0.92

Area Check OK. OK. OK. OK. 1.73

Constants Runoff Coefficients (Rv)Annual Rainfall (inches) 43 A Soils B Soils C Soils D Soils

Target Rainfall Event (inches) 1.00 Forest/Open Space 0.02 0.03 0.04 0.05

Total Phosphorus (TP) EMC (mg/L) 0.26 Managed Turf 0.15 0.20 0.22 0.25

Total Nitrogen (TN) EMC (mg/L) 1.86 Impervious Cover 0.95 0.95 0.95 0.95

Target TP Load (lb/acre/yr) 0.41

Pj (unitless correction factor) 0.90

Pre‐ReDevelopment Listed Adjusted1

Forest/Open Space Cover (acres) 0.00 0.00Forest/Open Space 

Cover (acres)0.00

Forest/Open Space 

Cover (acres)0.00

Weighted Rv(forest) 0.00 0.00 Weighted Rv(forest) 0.00 Weighted Rv(forest) 0.00

% Forest 0% 0% % Forest 0% % Forest 0%

Managed Turf Cover (acres) 0.94 0.81Managed Turf Cover 

(acres)0.81

Managed Turf Cover 

(acres)0.81

Weighted Rv(turf) 0.22 0.22 Weighted Rv (turf) 0.22 Weighted Rv (turf) 0.22

% Managed Turf 54% 51% % Managed Turf 47% % Managed Turf 51%

Impervious Cover (acres) 0.79 0.79Impervious Cover 

(acres)0.92

ReDev. Impervious 

Cover (acres)0.79

New Impervious Cover 

(acres)0.13

Rv(impervious) 0.95 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95 Rv(impervious) 0.95

% Impervious 46% 49% % Impervious 53% % Impervious 49%

Total Site Area (acres) 1.73 1.60 Final Site Area (acres) 1.73Total ReDev. Site Area 

(acres)1.60

Site Rv 0.55 0.58 Final Post Dev Site Rv 0.61 ReDev Site Rv 0.58

Pre‐ReDevelopment Treatment Volume 

(acre‐ft) 0.0798 0.0774

Final Post‐

Development 

Treatment Volume      

(acre‐ft) 

0.0877Post‐ReDevelopment 

Treatment Volume     

(acre‐ft) 

0.0774Post‐Development 

Treatment Volume 

(acre‐ft) 

0.0103

Pre‐ReDevelopment Treatment Volume 

(cubic feet) 3,475 3,371

Final Post‐

Development 

Treatment Volume 

(cubic feet) 

3,819Post‐ReDevelopment 

Treatment Volume     

(cubic feet) 

3,371Post‐Development 

Treatment Volume (cubic 

feet) 

448

Pre‐ReDevelopment TP Load              

(lb/yr)2.18 2.12

Final Post‐

Development TP 

Load                 

(lb/yr)

2.40Post‐ReDevelopment 

Load (TP)              

(lb/yr)*

2.12Post‐Development TP 

Load (lb/yr)0.28

Pre‐ReDevelopment TP Load per acre

(lb/acre/yr)1.26 1.32

Final Post‐Development TP 

Load per acre 

(lb/acre/yr)

1.39

Post‐ReDevelopment TP 

Load per acre 

(lb/acre/yr)

1.32

0.66Max. Reduction Required 

(Below Pre‐

ReDevelopment Load)

20%

TP Load Reduction 

Required for 

Redeveloped Area 

(lb/yr)

0.42TP Load Reduction 

Required for New 

Impervious Area (lb/yr)0.23

0.65

N/A

15.62

Backlick Road ‐Two Lane Option Alt 3

10/11/2016

LAND COVER SUMMARY -- POST DEVELOPMENTLAND COVER SUMMARY -- PRE-REDEVELOPMENT

 Maximum reduction required:

Enter Total Disturbed Area (acres) → Check:

Land cover areas entered correctly?

Total disturbed area entered?

BMP Design Specifications List:

Linear Project TP Load Reduction Required (lb/yr): 

Treatment Volume and Nutrient Load

Land Cover Summary‐Post (Final)

2013 Draft Stds & Specs

Land Cover Summary‐Pre

Pre‐ReDevelopment TN Load (lb/yr)

Final Post‐Development TN Load

(Post‐ReDevelopment & New 

Impervious)  (lb/yr)

17.17

Land Cover Summary‐Post

Post‐ReDevelopment

TP Load Reduction Required (lb/yr)

Post‐Development Requirement for Site Area

Nitrogen Loads (Informational Purposes Only)

Baseline TP Load (lb/yr)(0.41 lbs/acre/yr applied to pre‐redevelopment area excluding pervious 

land proposed for new impervious cover)

1 Adjusted Land Cover Summary: 

Pre ReDevelopment land cover minus pervious land cover (forest/open space or 

managed turf) acreage proposed for new impervious cover.  

Adjusted total acreage is consistent with Post‐ReDevelopment acreage (minus  

acreage of new impervious cover).  

Column I shows load reduction requriement for new impervious cover (based on new 

development load limit, 0.41 lbs/acre/year). 

Post ReDev. & New Impervious

Treatment Volume and Nutrient Load

Land Cover Summary‐Post

Post‐Development New Impervious

CLEAR  ALL(Ctrl+Shift+R)

data input cells

constant values

calculation cells

final results

ATTACHMENT 9

BRIDGE ALTERNATES MATRIX AND MOT OPTIONS MATRIX

Alt.Span 

Arrangement

Construction 

Method

Superstructure 

TypeAbutment Type Pier Type

Horiz./vert. 

alignment shift 

(II&M 227.9)

Minimum Tie‐Ins 

and Minimum 

Approach Work

Vertical 

Profile 

Rise

Construction within 

Existing ROW

Storm Water 

Management NeedBridge DE/DW

Rails with Trails 

Compatability

Construction 

DurationAdvantages Disadvantages

Total Cost

(See Attachment 4 of 

Stage I Report for 

Breakdown)

11‐Span

168'Detour

Steel Plate Girder 

with Reinforced 

Concrete Deck

Semi‐Integral w/ 

modifications 

(Existing 

abutments to 

remain)

N/AVertical 

alignmentNo 6‐0" ± Yes

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits

 

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes:

DE/DW needed due to 

the relaxation of span‐to‐

depth ratio needed to 

decrease the 

superstructure depth 

enough to provide 

sufficient vertical 

clearance

DW needed for 15'‐6" 

SUP on the bridge

Yes, there is 

sufficient 

clearance to the 

East of the future 

3rd railroad track 

for a future SUP

7‐8 months

‐ Construction cost savings by utilizing exist. 

abutments

‐ Piers removed as obstructions

‐ Construction within existing ROW

‐ Longer horizontal clearance

‐ No impact to fiber optic line along RR

‐ Utilization of exist. abutments may reduce 

construction duration and need for large 

quantities of cut/fill

‐ Bridge will be closed for duration of construction

‐ Requires deep superstructure and significant profile 

raise

‐ Relaxed span‐to‐depth ratio requires waiver

‐ Relaxed S‐to‐D ratio may result in uncomfortable ride 

for bikes adjacent to large trucks

‐ Modifications to Integral Abutment

‐ Impacts to grade of trail (ADA)

‐ Long roadway construction length

$7,671,300 

2A1‐Span

135'Detour

Steel Plate Girder 

with Reinforced 

Concrete Deck

Semi‐Integral,

adjacent to MSE 

walls

N/AVertical 

alignmentNo 6‐0" ± Yes

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits 

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes: 

DW needed for 15'‐6" 

SUP on the bridge

Yes, there is 

sufficient 

clearance to the 

East of the future 

3rd railroad track 

for a future SUP

8‐9 months

‐ Location of MSE walls and abutments will 

reduce the demo costs of the exist. bridge

‐ Less likely impact to fiber optic line along 

railroad 

‐ Construction within existing ROW

‐ MSE Wall can be constructed quickly

‐ Shorter duration than staged construction

‐ Bridge will be closed for duration of construction

‐ High cost of fill required for MSE wall construction

‐ Requires raise in profile

‐ Impacts to grade of trail (ADA)

‐ Long roadway construction length

$7,625,300 

2B1‐Span

135'

Staged 

Construction ‐ 

One two‐way 

traffic lane 

open during 

construction

Steel Plate Girder 

with Reinforced 

Concrete Deck

Semi‐Integral,

adjacent to MSE 

walls

N/A

Vertical 

alignment

&

Temporary 

horizontal 

alignment shift 

for staged 

construction

No 6‐0" ± Yes

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes: 

DW needed for 15'‐6" 

SUP on the bridge

Yes, there is 

sufficient 

clearance to the 

East of the future 

3rd railroad track 

for a future SUP

13‐15 months

‐ Location of MSE walls and abutments will 

reduce the demolition costs of the existing 

bridge

‐ Unlikely impact to fiber optic line along 

railroad 

‐ Construction within existing ROW

‐ MSE Wall can be constructed quickly

‐ Bridge remains open to vehicular and 

pedestrian traffic

‐ High cost of fill required for MSE wall construction

‐ Impacts to grade of trail (ADA)

‐ Long roadway construction length

‐ Requires temporary shift in horizontal alignment.

‐ Final transverse section 13' wider than detour option, 

which increases construction cost

$8,739,000 

2C1‐Span

135'

Staged 

Construction ‐ 

Two traffic 

lanes open 

during 

construction

Steel Plate Girder 

with Reinforced 

Concrete Deck

Semi‐Integral,

adjacent to MSE 

walls

N/A

Vertical 

alignment

&

Temporary 

horizontal 

alignment shift 

for staged 

construction

No 6‐0" ±

Yes, however there 

isn't sufficient ROW to 

the North  for 

construction of a 

temporary bridge for 

pedestrians and 

bicycles

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes: 

DW needed for 15'‐6" 

SUP on the bridge

Yes, there is 

sufficient 

clearance to the 

East of the future 

3rd railroad track 

for a future SUP

13‐15 months

‐ Location of MSE walls and abutments will 

reduce the demolition costs of the exist. 

bridge

‐ Unlikely impact to fiber optic line along 

railroad 

‐ Construction within existing ROW

‐ MSE Wall can be constructed quickly

‐ Bridge remains open to vehicular traffic

‐ High cost of fill required for MSE wall construction

‐ Impacts to grade of trail (ADA)

‐ Long roadway construction length

‐ Requires temporary shift in horiz. alignment.

‐ Final transverse section 14' wider than detour option, 

which increases construction cost

‐ Pedestrian access not provided on bridge

‐ Construction of temporary pedestrian bridge may 

require ROW

$8,846,100 

Rte. 617 (Backlick Road) over CSX Railroad

Fairfax County, Virginia

Project No. 0617‐029‐344, P101, C501, B642

UPC No. 110156

BRIDGE ALTERNATES MATRIX

Rte 617 over CSX ‐ Matrix ‐‐ Bridge Alternates Page 1

Alt.Span 

Arrangement

Construction 

Method

Superstructure 

TypeAbutment Type Pier Type

Horiz./vert. 

alignment shift 

(II&M 227.9)

Minimum Tie‐Ins 

and Minimum 

Approach Work

Vertical 

Profile 

Rise

Construction within 

Existing ROW

Storm Water 

Management NeedBridge DE/DW

Rails with Trails 

Compatability

Construction 

DurationAdvantages Disadvantages

Total Cost

(See Attachment 4 of 

Stage I Report for 

Breakdown)

Rte. 617 (Backlick Road) over CSX Railroad

Fairfax County, Virginia

Project No. 0617‐029‐344, P101, C501, B642

UPC No. 110156

BRIDGE ALTERNATES MATRIX

3A

3‐Span

45' ‐ 92' ‐ 45', 

continuous

Detour

Steel Plate Girder 

with Reinforced 

Concrete Deck

IntegralMulti‐

ColumnNo Yes 3'‐6" ± Yes

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits

 

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes: 

DW needed for 15'‐6" 

SUP on the bridge

Girder uplift condition 

possible at abutments 

but will be mitigated by 

the DL of the 

diaprhragm and 

superstructure

Yes, there is 

sufficient 

clearance to the 

East of the future 

3rd railroad track 

for a future SUP

10‐11 months

‐ Shallowest girder depth

‐ Least significant profile raise

‐ Construction within existing ROW

‐ Less impact to approach roadway and trail 

than other alternates

‐ Shortest roadway construction length

‐ Bridge will be closed for duration of construction

‐ Conflict between exist. and prop. foundations

‐ Construction of pier will require the relocation of the 

fiber optic line along the railroad

‐ Longer construction duration for CIP pier and 

abutment

$7,899,600 

3B

3‐Span

45' ‐ 92' ‐ 45', 

continuous

Staged 

Construction ‐ 

One two‐way 

traffic lane 

open during 

construction

Steel Plate Girder 

with Reinforced 

Concrete Deck

IntegralMulti‐

Column

Temporary 

horizontal 

alignment shift 

for staged 

construction

No 3'‐6" ± Yes

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits 

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes: 

DW needed for 15'‐6" 

SUP on the bridge

Girder uplift condition 

possible at abutments 

but will be mitigated by 

the DL of the 

diaprhragm and 

superstructure

Yes, there is 

sufficient 

clearance to the 

East of the 

railroad tracks for 

a future SUP

14‐16 months

‐ Shallowest girder depth

‐ Least significant profile raise

‐ Construction within existing ROW

‐ Less impact to approach roadway and trail 

than other alternates

‐ Shortest roadway construction length

‐ Bridge remains open to vehicular and 

pedestrian traffic

‐ Conflict between exist. and prop. foundations

‐ Construction of pier will require the relocation of the 

fiber optic line along the railroad

‐ Longer construction duration due to CIP pier

‐ Requires temporary shift in horiz. alignment.

‐ Final transverse section 13' wider than detour option, 

which increases construction cost

$9,084,200 

3C

3‐Span

45' ‐ 92' ‐ 45', 

continuous

Staged 

Construction ‐ 

Two traffic 

lanes open 

during 

construction

Steel Plate Girder 

with Reinforced 

Concrete Deck

IntegralMulti‐

Column

Temporary 

horizontal 

alignment shift 

for staged 

construction

No 3'‐6" ±

Yes, however there 

isn't sufficient ROW to 

the North  for 

construction of a 

temporary bridge for 

pedestrians and 

bicycles

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes: 

DW needed for 15'‐6" 

SUP on the bridge

Girder uplift condition 

possible at abutments 

but will be mitigated by 

the DL of the 

diaprhragm and 

superstructure

Yes, there is 

sufficient 

clearance to the 

East of the 

railroad tracks for 

a future SUP

14‐16 months

‐ Shallowest girder depth

‐ Least significant profile raise

‐ Construction within existing ROW

‐ Least impact to appr. roadway and trail

‐ Shortest roadway construction length

‐ Bridge remains open to vehicular traffic

‐ Conflict between exist. and prop. foundations

‐ Construction of pier will require the relocation of the 

fiber optic line along the railroad

‐ Longer construction duration due to CIP pier

‐ Requires temporary shift in horiz. alignment

‐ Final transverse section 14' wider than detour option, 

which increases constuction cost

‐ Pedestrian access not provided on bridge typical 

section

‐ Construction of temporary pedestrian bridge may 

require ROW

$9,273,200 

41‐Span

135'

Detour with 

Accelerated 

Bridge 

Construction 

Methods

Steel Plate Girder 

with Reinforced 

Concrete Deck

Semi‐Integral 

using precast 

footing and stem 

on steel 

H‐piles

N/AVertical 

alignmentNo 6‐0" ± Yes

1. Water quality will be 

addressed by 

purchasing Nutrient 

credits

2. Water Quantity will 

be addressed 

attenuating 10‐yr peak 

discharge to existing 

conditions

Yes: 

DW needed for 15'‐6" 

SUP on the bridge

Yes, there is 

sufficient 

clearance to the 

East of the future 

3rd railroad track 

for a future SUP

7‐8 months

‐ Location of MSE walls and abutments will 

reduce the demo costs of the exist. bridge

‐ Unlikely impact to fiber optic line along 

railroad 

‐ Construction within existing ROW

‐ MSE Wall can be constructed quickly

‐ Shortest construction duration

‐ Bridge will be closed for duration of construction

‐ High construction cost of fill likely for MSE wall

‐ Requires raise in profile

‐ Impacts to grade of trail (ADA)

‐ Long roadway construction length

‐ Increased construction cost for ABC method

‐ Potential for higher long‐term maintenance if precast 

deck panels are used

$8,562,400 

Rte 617 over CSX ‐ Matrix ‐‐ Bridge Alternates Page 2

Option Maintenance of TrafficConstruction within Existing 

ROWConstruction Duration Advantages Disadvantages Estimated Cost

MOT A Detour

Yes.

Minimal need for 

construction easements

No time added.

• Reduced project duration and construction cost.

• Reduce risk and improved safety to construction workers 

and motorists.

• Reduced environmental impacts from less complicated 

construction and fewer vehicles in construction area.

• Reduced construction cost due to reduced bridge width. 

Final bridge width will be 45 feet.

• Detour will have modest effect on area congestion (see 

Traffic Study).

• Lack of egress from Newington area. Egress will be limited 

to the CSX underpass or the Newington residential area.

• Special provisions will be needed for bike / pedestrian 

access.

MOT Total: 

$199,445

MOT B1Staged with One‐Lane One‐

Way with Temporary Signal

Yes.

Minimal need for 

construction easements

4‐6 months longer than 

MOT Option A

• Maintains bike and pedestrian access.

• No detour of traffic.

• Increased risk to workers and motorists than detour.

• Longer project duration and greater construction cost 

than detour.

• Temporary traffic signal needed.

• Traffic heading southbound is expected to create queues 

that will block through traffic on Fairfax County Parkway.

• Wider bridge width. Final bridge width will be 57 feet.

MOT Total: 

$344,625

MOT B2Staged with One‐Lane One‐

Way by Time of Day

Yes.

Minimal need for 

construction easements

4‐6 months longer than 

MOT Option A

• Maintains bike and pedestrian access.

• Traffic heading SB not expected to queue or block Fairfax 

County Parkway traffic.

• No need for temporary traffic signal.

• Detour by time of day necessary. Potentially confusing 

signing and marketing necessary.

• Increased risk to workers and motorists than detour.

• Longer project duration and greater construction cost 

than detour.

• Wider bridge width. Final bridge width will be 57 feet.

MOT Total: 

$323,805

MOT C

Staged with Two‐Lane Two‐

Way

and no Bike or Pedestrian 

Access

Yes.

Minimal need for 

construction easements

4‐6 months longer than 

MOT Option A

• Best vehicular capacity over bridge; most similar to 

current conditions.

• Signing and marking less complicated.

• Increased risk to workers and motorists than detour.

• Longer project duration and greater construction cost 

than detour.

• No access for bike or pedestrians.

• Widest bridge width. Final bridge width will be 61 feet.

MOT Total: 

$322,325

MOT OPTIONS MATRIX

Rte. 617 (Backlick Road) over CSX Railroad

Fairfax County, Virginia

Project No. 0617‐029‐344, P101, C501, B642

UPC No. 110156

Rte 617 over CSX ‐ Matrix ‐‐ MOT Options Page 1

ATTACHMENT 10

UTILITY CONFLICT MATRIX

Utility Conflict Matrix

Project Owner:  Utility Conflict Matrix Developed/Revised By: 

Project No. : Date:

Project Description: Reviewed By:

Highway or Route: Date:

Utility Owner and/or Contact 

Name

Drawing or 

Sheet No. Utility Type Size and/or Material Utility Conflict Description

Start 

Station

Start 

Offset

End 

Station

End 

Offset

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, Full Depth Asphalt Pavement, and Pavement Removal 113+50 22' RT 115+32 26' RT

VDOT PS‐02 Signal Traffic Handbox Grading 114+09 96' RT

VDOT PS‐02 Signal Traffic Control Cabinet Grading 114+21 83' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+42 53' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Verizon PS‐02 Communications Multiple, Unknown Grading and Ditch 117+47 25' RT 118+50 27' RT

Verizon PS‐02 Communications Handbox Grading 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

Alexander Bratchie

November 17, 2016

Kurt Miller

17‐Nov‐16

Alternate 1 ‐ Higher Profile, MOT Option A Detour

Virginia Department of Transportation ‐ Northern District

0617‐029‐344

Backlick Road over CSX Railroad

617

1

Utility Conflict Matrix

Project Owner:  Utility Conflict Matrix Developed/Revised By: 

Project No. : Date:

Project Description: Reviewed By:

Highway or Route: Date:

Utility Owner and/or Contact 

Name

Drawing or 

Sheet No. Utility Type Size and/or Material Utility Conflict Description

Start 

Station

Start 

Offset

End 

Station

End 

Offset

Alexander Bratchie

November 17, 2016

Kurt Miller

17‐Nov‐16

Virginia Department of Transportation ‐ Northern District

0617‐029‐344

Backlick Road over CSX Railroad

617

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, Full Depth Asphalt Pavement, and Pavement Removal 113+50 22' RT 115+32 26' RT

VDOT PS‐02 Signal Traffic Handbox Grading 114+09 96' RT

VDOT PS‐02 Signal Traffic Control Cabinet Grading 114+21 83' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+42 53' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Verizon PS‐02 Communications Multiple, Unknown Grading and Ditch 117+47 25' RT 118+50 27' RT

Verizon PS‐02 Communications Handbox Grading and Ditch 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, and Full Depth Asphalt Pavement 113+50 22' RT 115+32 26' RT

VDOT PS‐02 Signal Traffic Handbox Grading 114+09 96' RT

Alternate 2 ‐ Higher Profile, MOT Option B 1 Lane

Alternate 2 ‐ Higher Profile, MOT Option A Detour

2

Utility Conflict Matrix

Project Owner:  Utility Conflict Matrix Developed/Revised By: 

Project No. : Date:

Project Description: Reviewed By:

Highway or Route: Date:

Utility Owner and/or Contact 

Name

Drawing or 

Sheet No. Utility Type Size and/or Material Utility Conflict Description

Start 

Station

Start 

Offset

End 

Station

End 

Offset

Alexander Bratchie

November 17, 2016

Kurt Miller

17‐Nov‐16

Virginia Department of Transportation ‐ Northern District

0617‐029‐344

Backlick Road over CSX Railroad

617

VDOT PS‐02 Signal Traffic Control Cabinet Grading 114+21 83' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+42 53' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Verizon PS‐02 Communications Multiple, Unknown Grading and Ditch 117+47 25' RT 118+50 27' RT

Verizon PS‐02 Communications Handbox Grading 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, and Full Depth Asphalt Pavement 113+50 22' RT 115+32 26' RT

VDOT PS‐02 Signal Traffic Handbox Grading 114+09 96' RT

VDOT PS‐02 Signal Traffic Control Cabinet Grading 114+21 83' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+42 53' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Verizon PS‐02 Communications Multiple, Unknown Grading 117+47 25' RT 118+50 27' RT

Alternate 2 ‐ Higher Profile, MOT Option C 2 Lane

3

Utility Conflict Matrix

Project Owner:  Utility Conflict Matrix Developed/Revised By: 

Project No. : Date:

Project Description: Reviewed By:

Highway or Route: Date:

Utility Owner and/or Contact 

Name

Drawing or 

Sheet No. Utility Type Size and/or Material Utility Conflict Description

Start 

Station

Start 

Offset

End 

Station

End 

Offset

Alexander Bratchie

November 17, 2016

Kurt Miller

17‐Nov‐16

Virginia Department of Transportation ‐ Northern District

0617‐029‐344

Backlick Road over CSX Railroad

617

Verizon PS‐02 Communications Handbox Grading 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

4

Utility Conflict Matrix

Project Owner:  Utility Conflict Matrix Developed/Revised By: 

Project No. : Date:

Project Description: Reviewed By:

Highway or Route: Date:

Utility Owner and/or Contact 

Name

Drawing or 

Sheet No. Utility Type Size and/or Material Utility Conflict Description

Start 

Station

Start 

Offset

End 

Station

End 

Offset

Alexander Bratchie

November 17, 2016

Kurt Miller

17‐Nov‐16

Virginia Department of Transportation ‐ Northern District

0617‐029‐344

Backlick Road over CSX Railroad

617

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, Full Depth Asphalt Pavement, and Pavement Removal 113+50 22' RT 115+30 27' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+45 45' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Verizon PS‐02 Communications Multiple, Unknown Grading 117+47 25' RT 118+50 27' RT

Verizon PS‐02 Communications Handbox Grading 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, Full Depth Asphalt Pavement, and Bridge Construction 113+50 22' RT 115+32 26' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+45 45' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Alternate 3 ‐ Optimum Profile, MOT Option A Detour

Alternate 3 ‐ Optimum Profile, MOT Option B 1 Lane

5

Utility Conflict Matrix

Project Owner:  Utility Conflict Matrix Developed/Revised By: 

Project No. : Date:

Project Description: Reviewed By:

Highway or Route: Date:

Utility Owner and/or Contact 

Name

Drawing or 

Sheet No. Utility Type Size and/or Material Utility Conflict Description

Start 

Station

Start 

Offset

End 

Station

End 

Offset

Alexander Bratchie

November 17, 2016

Kurt Miller

17‐Nov‐16

Virginia Department of Transportation ‐ Northern District

0617‐029‐344

Backlick Road over CSX Railroad

617

Verizon PS‐02 Communications Multiple, Unknown Grading, Bridge Construction, Ditch, and Full Depth Asphalt Pavement 117+47 25' RT 118+50 27' RT

Verizon PS‐02 Communications Handbox Grading and Bridge Construction 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, Full Depth Asphalt Pavement, and Bridge Construction 113+50 22' RT 115+32 26' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+45 45' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Verizon PS‐02 Communications Multiple, Unknown Grading, Bridge Construction, Pavement Removal, and Full Depth Asphalt Pavement 117+47 25' RT 118+50 27' RT

Verizon PS‐02 Communications Handbox Grading and Bridge Construction 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

Alternate 3 ‐ Optimum Profile, MOT Option C 2 Lane

6

Utility Conflict Matrix

Project Owner:  Utility Conflict Matrix Developed/Revised By: 

Project No. : Date:

Project Description: Reviewed By:

Highway or Route: Date:

Utility Owner and/or Contact 

Name

Drawing or 

Sheet No. Utility Type Size and/or Material Utility Conflict Description

Start 

Station

Start 

Offset

End 

Station

End 

Offset

Alexander Bratchie

November 17, 2016

Kurt Miller

17‐Nov‐16

Virginia Department of Transportation ‐ Northern District

0617‐029‐344

Backlick Road over CSX Railroad

617

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, Full Depth Asphalt Pavement, and Pavement Removal 113+50 22' RT 115+32 26' RT

VDOT PS‐02 Signal Traffic Handbox Grading 114+09 96' RT

VDOT PS‐02 Signal Traffic Control Cabinet Grading 114+21 83' RT

Verizon PS‐02 Communications Handbox Grading 115+32 26' RT

Quest or MCI PS‐02 Communications Fiber Optic Bridge Construction 116+42 53' LT 116+78 35' RT

Dominion Virginia Power PS‐02 Electric Light Pole Grading and Full Depth Shared Use Path 177+44 28' LT

Verizon PS‐02 Communications Multiple, Unknown Grading and Ditch 117+47 25' RT 118+50 27' RT

Verizon PS‐02 Communications Handbox Grading and Ditch 117+47 25' RT

Verizon PS‐03 Communications Multiple, Unknown Grading, Pavement Removal, and Ditch 118+50 27' RT 121+15 33' RT

Dominion Virginia Power PS‐03 Electric Light Pole Grading 119+84 29' LT

Verizon PS‐01 Communications Multiple, Unknown Grading 113+03 20' RT 113+50 22' RT

Verizon PS‐01 Communications Handbox Grading 113+14 26' RT

Verizon PS‐02 Communications Multiple, Unknown Grading, Riprap, and Full Depth Asphalt Pavement 113+50 22' RT 115+32 26' RT

VDOT PS‐02 Signal Traffic Handbox Grading 114+09 96' RT

Alternate 4 ‐ Higher Profile, MOT Option A Detour

Alternate 4 ‐ Higher Profile, MOT Option B 1 Lane

7

bwilson
Text Box