Transcript of SR 1 BLUFFTON Public Hearing September 25, 2012. INDOT Mission: INDOT will plan, build, maintain and...
INDOT Mission: INDOT will plan, build, maintain and operate a
superior transportation system enhancing safety, mobility and economic growth
INDOT Values: Respect Teamwork Accountability Excellence
INDOT
6 district offices 3,722 employees $396 million/annual operating budget $1 billion/annual capital expenditures 28,410 total lane miles
5,098 lane miles of interstate 16,519 lane miles of two-lane roads 5,320 INDOT-owned bridges
INDOT Profile
Comments For The Record
Verbally as a Public Statement Comment Form Mail or Fax Email
Please feel free to use any and all methods.Comment period ending October 10, 2012.
Project History
Environmental Document released for public involvement on December 6, 2011Scope of Environmental Study:
Evaluate impacts to natural and human environments
Social and economic factors Waterways, wetlands, and endangered species Historical properties
Project History continued
Legal Notice of Public Hearing The News Banner September 10th & 17th, 2012
Community Input One of the final steps of the
Environmental process
Real Estate Acquisition Process
http://www.fhwa.dot.gov/realestate/realprop/index.html
http://www.fhwa.dot.gov/realestate/rights/index.html
Real Estate Acquisition Process “Uniform Act” of 1970
All federal, state, and local governments must comply – just compensation
Acquisition Process Appraisals Review appraisals Amount of compensation cannot be less
than fair market value Offer will be made in writing No agreement Mediation Condemnation
Project Need Numerous commercial property
access points and high traffic volumes Lack of access control and turning
lanes impedes traffic operations Poor surface
drainage patterns
SR 1 classified as a principal arterial roadway SR 116 classified as a minor arterial roadway One travel lane in each direction, limited
turn lanes and passing blisters Speed limit: 40 mph,
decreases to 30 at thesouth edge of the WellsCounty 4-H Park
Existing SR 1 south of Spring St.
Existing SR 1 south of Spring St. Asphalt travel lanes 12 ft wide Paved shoulders 3 ft to 6 ft wide Last resurfaced in 2003 Land use is commercial
and light industrial with agricultural at the south end
Existing SR 1 Conditions
Currently in fair condition Ruts and cracks beginning to
show in the wheel paths Tight turn radii at SR 116 and other intersections Few access points
south of 4-H Park North of 4-H Park almost completely paved with few defined driveways
Existing SR 1 Conditions (cont’d) Poorly defined drainage system
Roadside ditches show signs of standing water
Existing discharge points have inadequate capacity for new runoff
Incidental Construction (Blue) Widening and Resurface (Green) Cul-de-sac for Scott Street (Red)
NN
SR 1 Construction Areas
NN
Sta
te
St.
SR
11
6
(Harr
ison
Pla
za)
Harv
est
R
d.
4-H
Park
Rd.
Harv
est
R
d.
Spri
ng S
t.
Scott St.
Delo
ng
Dit
ch
12’-0”2’-7”14’-0”
12’-0”2’-7”
SR 1 Proposed Typical Section
One 12’-wide Lane Each Direction 14’-wide Continuous Two-Way Left-Turn
Lane New Concrete Curb and Gutter Widening with Overlay of Existing
Pavement
Proposed SR 1
Permanent Right-of-Way (Orange) Typical Width – 80’ (40’ each side) Maximum Width – 113’ 5.88 Acres
Temporary Right-of-Way (Green) 0.52 Acre
SR 1 Proposed Right-of-Way
NN
South Half
Sta
te
St.
Harv
est
R
d.
SR
11
6
Permanent Right-of-Way (Orange) One commercial relocation (Pink)
Temporary Right-of-Way (Green)
SR 1 Proposed Right-of-WayNN
North Half4
-H P
ark
R
d.
Spri
ng S
t.
Scott St.
4-H
Park
R
d.
Spri
ng S
t.
Scott St.
Phase 1 One travel lane in each direction Lanes shifted to west and narrowed to 10’ Widening and storm sewers constructed
on east half Access will be maintained to all properties Construction zone speed limit 30 mph
Maintenance of Traffic (MOT)
Phase 2 One 11’ travel lane in each direction Lanes shifted east to new widening Widening and storm sewers constructed
on west half Access will be maintained to all properties Construction zone speed limit 30 mph
Maintenance of Traffic (MOT)
Public Comments
Indiana Department of Transportation Public Hearings Office, Room N642 100 North Senate Avenue
Indianapolis, IN 46204 E-mail: [email protected] INDOT respectfully requests comments
postmarked by October 10, 2012All comments will be reviewed and