Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule...
-
Upload
keyon-bonser -
Category
Documents
-
view
212 -
download
0
Transcript of Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule...
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
1
• Payment schedule• Materials• Mobilization• Monthly payments• Final Payment
Contract Provision that Impact Cash Flow
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
2
Contractor Cash Disbursements
• Labor• Equipment• Materials• Subcontractors• Other
– Insurance,– Permit and mobilization– Overhead items
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
3
Factors That Minimize Contractor's Negative Cash Flow
1. Front end rate loading: – earlier items in bill of quantities carry a higher mark-
up than later items early stages.– This reduces negative cash flows in contract early
stages.
2. Reduction of delays in receiving revenue.
3. Adjustment of work schedule to late start timing.
4. Coinciding the timing of delivery of large materials orders with the submittal of the contractor's monthly pay estimate.
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
4
Factors That Minimize Contractor's Negative Cash Flow
5. Delay in paying labour, plant hirers, materials suppliers, and subcontractors.– This would reduce negative cash flows but undermine
commercial confidence in the company.
6. Increasing the mark-up and reducing the retentions.
7. Increasing mobilization and advance payment.8. Achievement of maximum production in the
field.9. Quick settlement or claims.
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
5
The Cash Flow Analysis
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
6
The Cash Flow Analysis
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
7
Example 4.1
• The mark-up is 10% of tender value and is assumed to be uniformly distributed over the contract.
• The contractor will receive an advanced payment of 10% of tender value. – This will be deducted from each monthly revenue.
Retention is 5% and is paid on contract completion.• Labour cost is assumed to be 30% of total
contract cost and is paid after one week's delay.• The delay for other submitting is one month.• Revenue is received after 4 weeks from
submitting invoices.
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
8
Example 4.1
• Assuming all the activities are scheduled on their early start timings, it is required to derive:– revenue and income curves, – cost and expense curves and– contract cash flow curves.
• Compare contract net cash flows for revenue received after 4 and 6 weeks from submitting invoices.
• Determine the effect on contract cash flow of scheduling the activities on their late start timings while the revenue is received with 4 week’s delay.
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
9
Table 4.3 Date for example 4.1
Activity Duration (weeks)
Preceding activity
Overlap Value (LE)
A 5 30000 B 4 A 20000 C 5 A -1 15000 D 5 A 15000 E 5 B 2 25000 F 4 B,C 16000 G 6 D 18000 H 4 E 1 8000 I 3 F,G 2 with G 9000 J 2 H.I 4000
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
10
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
11
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
12
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
13
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
14
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
15
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
16
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
17
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
18
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
19
Algorithm Calculations1) calculate the net operating cash flow at the end of
period t for t ≥ 0 is given by:
At = Pt Et
– At is positive for a surplus and negative for a shortfall– Et = the contractor's expenses in period t, and – Pt = owner's payments in period t, for t = 0,1,2,...,n.
2) calculate The cumulative operating cash flow at the end of period t just before receiving payment Pt (for t ≥ 1) is:
Ft = Nt-1 Et
– Nt-1 is the cumulative net cash flows from period 0 to period (t-1).
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
20
3) calculate the cumulative net operating cash flow after receiving payment Pt at the end of period t (for t ≥1) is:
Nt = Ft + Pt = Nt-1 + At
4) The gross operating profit G for a n-period project is defined as net operating cash flow at t=n and is given by:
Algorithm Calculations
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
21
Example 1: Contractor's gross profit from a project
The contractor's expenses and owner's payments for a multi-year construction project are given in Columns 2 and 3, respectively, of Table 1. Each time period is represented by one year, and the annual interest rate i is for borrowing 11%. The computation has been carried out in Table 1, and the contractor's gross profit G is found to be N5 = $8.025 million in the last column of the table.
TABLE 1 Example of Contractor's Expenses and Owner's Payments ($ Million)
Period t
Contractor's Expenses
Et
Owner's Payments
Pt
Net Cash Flow
At
Cumulative Cash Before Payments
Ft
Cumulative Net Cash
Nt
0 1 2 3 4 5
Total
$3.782 7.458
10.425 14.736 11.420
5.679 $53.500
$0 6.473 9.334
13.348 16.832
15.538 $61.525
-$3.782 -0.985 -1.091 -1.388 +5.412
+9.859 +$8.025
-$3.782 -11.240 -15.192 -20.594 -18.666 -7.513
-$3.782 -4.767 -5.858 -7.246 -1.834 +8.025
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
22
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
23
Considering the time value of money
1) Compute the interest per period
- If is negative and i is the borrowing rate for the shortfall,
- If is positive and h is the investment rate for the surplus,
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
24
2) calculate the interest accrued in period t, the cumulative cash flow at the end of period t just before receiving payment Pt (for t ≥1) is:
Considering the time value of money
3) calculate the cumulative net cash flow after receiving payment Pt at the end of period t (for t ≥1) is:
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
25
4) calculate the gross operating profit at the end of a n-period project including interest charges is:
Considering the time value of money
where is the cumulative net cash flow for t = n.
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
26
Example 2: Effects of Construction Financing
The computation of the cumulative cash flows including interest charges at i = 11% for Example 1 is shown in Table 2 with gross profit = = $1.384 million. The results of computation are also shown in Figure 2.
TABLE 2 Example Cumulative Cash Flows Including Interests for a Contractor ($ Million)
Period (year)
t
Construction Expenses
Et
Owner's Payments
Pt
Annual Interest
Cumulative Before Payments
Cumulative Net Cash Flow
0 1 2 3 4 5
$3.782 7.458 10.425 14.736 11.420 5.679
0 $6.473 9.334 13.348 16.832 15.538
0 -$0.826 -1.188 -1.676 -1.831 -1.121
-$3.782 -12.066 -17.206 -24.284 -24.187 -14.154
-$3.782 -5.593 -7.872
-10.936 -7.354 +1.384
Example 2
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
27
Example 2
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
28
Example 2
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
29
Example 3: Effects of Inflation Suppose that both expenses and receipts for the construction project in the Example 1 are now expressed in then-current dollars (with annual inflation rate of 4%) in Table 3. The market interest rate reflecting this inflation is now 15%. In considering these expenses and receipts in then-current dollars and using an interest rate of 15% including inflation, we can recompute the cumulative net cash flow (with interest). Thus, the gross profit less financing costs becomes = = $0.4 million. There will be a loss rather than a profit after deducting financing costs and adjusting for the effects of inflation with this project.
TABLE 3 Example of Overdraft Financing Based on Inflated Dollars ($ Million)
Period (year)
t
Construction Expenses
Et
Owner's Payments
Pt
Annual Interest
Cumulative Before
Payments
Cumulative Net Cash
Flow
0 1 2 3 4 5
$3.782 7.756 11.276 16.576 13.360 6.909
0 $6.732 10.096 15.015 16.691 18.904
0 -$1.149 -1.739 -2.574 -2.953 -1.964
-$3.782 -12.687 -18.970 -28.024 -29.322 -18.504
-$3.782 -5.955 -8.874 -13.009 -9.631 +0.400
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
30
Example 4: Effects of Work Stoppage at Periods of Inflation
TABLE 4 Example of the Effects of Work Stoppage and Inflation on a Contractor ($ Million)
Period (year)
t
Construction Expenses
Et
Owner's Payments
Pt
Annual Interest
Cumulative Before
Payments
Cumulative Net Cash
Flow
0 1 2 3 4 5 6
$3.782 7.756 11.276
0 17.239 13.894 7.185
0 $6.732 10.096
0 15.015 16.691 18.904
0 -$1.149 -1.739 -1.331 -2.824 -3.330 -2.457
-$3.782 -12.687 -18.970 -10.205 -30.268 -32.477 22.428
-$3.782 -5.955 -8.874 -10.205 -15.253 -12.786 -3.524
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
31
Example 4: Effects of Work Stoppage at Periods of Inflation
Spring 2008, King Saud University
Cash Flow AnalysisDr. Khalid Al-Gahtani
32
Example 4: Effects of Work Stoppage at Periods of Inflation