Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule...

32
Spring 2008, King Saud Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract Provision that Impact Cash Flow

Transcript of Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule...

Page 1: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

1

• Payment schedule• Materials• Mobilization• Monthly payments• Final Payment

Contract Provision that Impact Cash Flow

Page 2: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

2

Contractor Cash Disbursements

• Labor• Equipment• Materials• Subcontractors• Other

– Insurance,– Permit and mobilization– Overhead items

Page 3: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

3

Factors That Minimize Contractor's Negative Cash Flow

1. Front end rate loading: – earlier items in bill of quantities carry a higher mark-

up than later items early stages.– This reduces negative cash flows in contract early

stages.

2. Reduction of delays in receiving revenue.

3. Adjustment of work schedule to late start timing.

4. Coinciding the timing of delivery of large materials orders with the submittal of the contractor's monthly pay estimate.

Page 4: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

4

Factors That Minimize Contractor's Negative Cash Flow

5. Delay in paying labour, plant hirers, materials suppliers, and subcontractors.– This would reduce negative cash flows but undermine

commercial confidence in the company.

6. Increasing the mark-up and reducing the retentions.

7. Increasing mobilization and advance payment.8. Achievement of maximum production in the

field.9. Quick settlement or claims.

Page 5: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

5

The Cash Flow Analysis

Page 6: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

6

The Cash Flow Analysis

Page 7: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

7

Example 4.1

• The mark-up is 10% of tender value and is assumed to be uniformly distributed over the contract.

• The contractor will receive an advanced payment of 10% of tender value. – This will be deducted from each monthly revenue.

Retention is 5% and is paid on contract completion.• Labour cost is assumed to be 30% of total

contract cost and is paid after one week's delay.• The delay for other submitting is one month.• Revenue is received after 4 weeks from

submitting invoices.

Page 8: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

8

Example 4.1

• Assuming all the activities are scheduled on their early start timings, it is required to derive:– revenue and income curves, – cost and expense curves and– contract cash flow curves.

• Compare contract net cash flows for revenue received after 4 and 6 weeks from submitting invoices.

• Determine the effect on contract cash flow of scheduling the activities on their late start timings while the revenue is received with 4 week’s delay.

Page 9: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

9

Table 4.3 Date for example 4.1

Activity Duration (weeks)

Preceding activity

Overlap Value (LE)

A 5 30000 B 4 A 20000 C 5 A -1 15000 D 5 A 15000 E 5 B 2 25000 F 4 B,C 16000 G 6 D 18000 H 4 E 1 8000 I 3 F,G 2 with G 9000 J 2 H.I 4000

Page 10: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

10

Page 11: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

11

Page 12: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

12

Page 13: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

13

Page 14: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

14

Page 15: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

15

Page 16: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

16

Page 17: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

17

Page 18: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

18

Page 19: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

19

Algorithm Calculations1) calculate the net operating cash flow at the end of

period t for t ≥ 0 is given by:

At = Pt Et

– At is positive for a surplus and negative for a shortfall– Et = the contractor's expenses in period t, and – Pt = owner's payments in period t, for t = 0,1,2,...,n.

2) calculate The cumulative operating cash flow at the end of period t just before receiving payment Pt (for t ≥ 1) is:

Ft = Nt-1 Et

– Nt-1 is the cumulative net cash flows from period 0 to period (t-1).

Page 20: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

20

3) calculate the cumulative net operating cash flow after receiving payment Pt at the end of period t (for t ≥1) is:

Nt = Ft + Pt = Nt-1 + At

4) The gross operating profit G for a n-period project is defined as net operating cash flow at t=n and is given by:

Algorithm Calculations

Page 21: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

21

Example 1: Contractor's gross profit from a project

The contractor's expenses and owner's payments for a multi-year construction project are given in Columns 2 and 3, respectively, of Table 1. Each time period is represented by one year, and the annual interest rate i is for borrowing 11%. The computation has been carried out in Table 1, and the contractor's gross profit G is found to be N5 = $8.025 million in the last column of the table.

TABLE 1 Example of Contractor's Expenses and Owner's Payments ($ Million)

Period t

Contractor's Expenses

Et

Owner's Payments

Pt

Net Cash Flow

At

Cumulative Cash Before Payments

Ft

Cumulative Net Cash

Nt

0 1 2 3 4 5

Total

$3.782 7.458

10.425 14.736 11.420

5.679 $53.500

$0 6.473 9.334

13.348 16.832

15.538 $61.525

-$3.782 -0.985 -1.091 -1.388 +5.412

+9.859 +$8.025

-$3.782 -11.240 -15.192 -20.594 -18.666 -7.513

-$3.782 -4.767 -5.858 -7.246 -1.834 +8.025

Page 22: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

22

Page 23: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

23

Considering the time value of money

1) Compute the interest per period

- If is negative and i is the borrowing rate for the shortfall,

- If is positive and h is the investment rate for the surplus,

Page 24: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

24

2) calculate the interest accrued in period t, the cumulative cash flow at the end of period t just before receiving payment Pt (for t ≥1) is:

Considering the time value of money

3) calculate the cumulative net cash flow after receiving payment Pt at the end of period t (for t ≥1) is:

Page 25: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

25

4) calculate the gross operating profit at the end of a n-period project including interest charges is:

Considering the time value of money

where is the cumulative net cash flow for t = n.

Page 26: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

26

Example 2: Effects of Construction Financing

The computation of the cumulative cash flows including interest charges at i = 11% for Example 1 is shown in Table 2 with gross profit = = $1.384 million. The results of computation are also shown in Figure 2.

TABLE 2 Example Cumulative Cash Flows Including Interests for a Contractor ($ Million)

Period (year)

t

Construction Expenses

Et

Owner's Payments

Pt

Annual Interest

Cumulative Before Payments

Cumulative Net Cash Flow

0 1 2 3 4 5

$3.782 7.458 10.425 14.736 11.420 5.679

0 $6.473 9.334 13.348 16.832 15.538

0 -$0.826 -1.188 -1.676 -1.831 -1.121

-$3.782 -12.066 -17.206 -24.284 -24.187 -14.154

-$3.782 -5.593 -7.872

-10.936 -7.354 +1.384

Example 2

Page 27: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

27

Example 2

Page 28: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

28

Example 2

Page 29: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

29

Example 3: Effects of Inflation Suppose that both expenses and receipts for the construction project in the Example 1 are now expressed in then-current dollars (with annual inflation rate of 4%) in Table 3. The market interest rate reflecting this inflation is now 15%. In considering these expenses and receipts in then-current dollars and using an interest rate of 15% including inflation, we can recompute the cumulative net cash flow (with interest). Thus, the gross profit less financing costs becomes = = $0.4 million. There will be a loss rather than a profit after deducting financing costs and adjusting for the effects of inflation with this project.

TABLE 3 Example of Overdraft Financing Based on Inflated Dollars ($ Million)

Period (year)

t

Construction Expenses

Et

Owner's Payments

Pt

Annual Interest

Cumulative Before

Payments

Cumulative Net Cash

Flow

0 1 2 3 4 5

$3.782 7.756 11.276 16.576 13.360 6.909

0 $6.732 10.096 15.015 16.691 18.904

0 -$1.149 -1.739 -2.574 -2.953 -1.964

-$3.782 -12.687 -18.970 -28.024 -29.322 -18.504

-$3.782 -5.955 -8.874 -13.009 -9.631 +0.400

Page 30: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

30

Example 4: Effects of Work Stoppage at Periods of Inflation

TABLE 4 Example of the Effects of Work Stoppage and Inflation on a Contractor ($ Million)

Period (year)

t

Construction Expenses

Et

Owner's Payments

Pt

Annual Interest

Cumulative Before

Payments

Cumulative Net Cash

Flow

0 1 2 3 4 5 6

$3.782 7.756 11.276

0 17.239 13.894 7.185

0 $6.732 10.096

0 15.015 16.691 18.904

0 -$1.149 -1.739 -1.331 -2.824 -3.330 -2.457

-$3.782 -12.687 -18.970 -10.205 -30.268 -32.477 22.428

-$3.782 -5.955 -8.874 -10.205 -15.253 -12.786 -3.524

Page 31: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

31

Example 4: Effects of Work Stoppage at Periods of Inflation

Page 32: Spring 2008, King Saud University Cash Flow Analysis Dr. Khalid Al-Gahtani 1 Payment schedule Materials Mobilization Monthly payments Final Payment Contract.

Spring 2008, King Saud University

Cash Flow AnalysisDr. Khalid Al-Gahtani

32

Example 4: Effects of Work Stoppage at Periods of Inflation